Rubble stone stack and reinforced soil composite embankment culvert pipe structure
A technology for reinforcing embankments and rubble piles, which is applied to the bottom layer of roads, buildings, etc., can solve problems such as difficulty in installing culverts on rubble embankments, reduce construction costs, and fall deformation, and achieve coordination of uneven settlement, improved stress state, and cost low effect
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2014-07-02
Smart Images
Figure 1
Abstract
Description
Technical field
[0001] The invention relates to an embankment culvert pipe structure, in particular to a composite embankment culvert pipe structure reinforced by rubble piles. Background technique
[0002] Radar base stations are often built on the top of small hills, and simple roads to the top are often needed for this. When the simple road to the top meets a mountain stream, it cannot be crossed by the construction of a small bridge due to road construction cost restrictions. The most economical method is to use the construction of rubble retaining walls and embankment culverts. Due to the scouring effect of the stream in the mountain stream, the base part of the stone retaining wall to be built is often soft soil. After the soft soil is removed, the site of the stone retaining wall to be built is usually a height of more than 10 meters. For steep slope sections with narrow toe, construction of rubble retaining walls and embankment culvert pipes in this case will not only gr...
Examples
Embodiment Construction
[0012] The present invention will be further described below with reference to the drawings and specific embodiments.
[0013] See figure 1 , The rubble embankment 3 shall be constructed according to the conventional rubble embankment, the height 1 of the rubble embankment 3 is not more than 8 meters, the top width 13 is greater than 7 meters, and the embankment surface of the rubble embankment 3 maintains an inwardly inverted embankment greater than 5% The slope rate, the upper part of the rubble embankment 3 is provided with the first impervious geotextile 4, the upper part of the first impervious geotextile 4 is provided with a cushion layer 5 made of sand and gravel, and a culvert pipe 6 is arranged on the cushion layer 5. A sinkhole 12 is provided on the side close to the natural slope, and the culvert pipe 6 is connected to the sinkhole 12. Above the culvert pipe 6 is provided a set of gravel soil 17 and a soft permeable pipe 16 placed on the side close to the natural slope...