An Optimal Configuration Method for Voltage Sag Monitoring Points Based on Probabilistic Observability

Through the probability observable method, the voltage drop monitoring point is optimized, the probability observable matrix is ​​extracted, and the objective function and constraints are established, which solves the economic and observability problems of the configuration of power grid monitoring point, and realizes observability and cost optimization of the entire network .

CN110795867BInactive Publication Date: 2024-11-22CHINA UNIV OF PETROLEUM (EAST CHINA)
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911132722.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-11-19
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The prior art is difficult to effectively optimize the configuration of voltage drop monitoring points, resulting in the installation of too many monitoring devices, which increases economic costs and makes it difficult to achieve observability across the entire network.

Method used

Using a probabilistic observability method, the installation location and number of monitoring points are optimized by extracting the probability observable matrix, establishing the objective function of the minimum installation cost and cost loss, and the constraints of the probability observable grid.

Benefits of technology

The number of monitoring devices installed is reduced, the entire network observability of the power grid is realized, the requirements of different voltage drop monitoring accuracy are met, and the economic cost is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure BDA0002278767000000011
    Figure BDA0002278767000000011
  • Figure BDA0002278767000000021
    Figure BDA0002278767000000021
  • Figure BDA0002278767000000022
    Figure BDA0002278767000000022
Patent Text Reader

Abstract

The present invention discloses a method for optimizing the configuration of voltage sag monitoring points based on probability observability. The method is characterized by including three contents: extracting a probability observable matrix, establishing an objective function with minimum installation cost and price loss, and establishing constraints with probability observability of the power grid when a short circuit fault occurs at a certain point. The present invention proposes a method for optimizing the configuration of voltage sag monitoring points based on probability observability. For some lines in the system with low voltage levels or low failure rates, probability observability replaces traditional full observability, greatly reducing the number of installations. From an economic point of view, it meets the requirements of different voltage sag monitoring accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of electric power systems, and in particular relates to a method for optimizing configuration of voltage sag monitoring points. Background Art

[0002] With the application of power electronic equipment and the investment of sensitive equipment in power grids, power quality issues are increasingly receiving widespread attention. Voltage sag, as one of the important power quality issues, accounts for more than 80% of all power quality issues. Therefore, it is of great significance to establish a complete and reliable voltage sag monitoring system to realize the monitoring of voltage sag. How to reasonably optimize the configuration of voltage sag monitoring points and install the least monitoring devices to achieve the observability of voltage sag in the entire network has become an important issue. It is the basis for the subsequent extraction and analysis of voltage sag characteristic quantities, and the location and control of voltage sag sources. The present invention proposes an optimization configuration method for voltage sag monitoring points based on probabilistic observability. For some lines with low voltage levels or low failure rates in the system, probabilistic observability is used instead of traditional full observability, reducing the number of installations. From an economic point of view, it meets the requirements of different voltage sag monitoring accuracy. Summary of the invention

[0003] The technical solution of the present invention is a method for optimizing the configuration of voltage sag monitoring points based on probability observability. The method is characterized in that the method includes three contents: extraction of probability observability matrix, establishment of objective function with minimum installation cost and cost loss, and establishment of constraint conditions with probability observability of power grid when short circuit fault occurs at a certain point. The specific implementation steps of the method are as follows:

[0004] Step 1: Use the node voltage when a short circuit fault occurs at a certain point in the power grid to extract the probability observable matrix;

[0005] Define the probability observable matrix M P,ij The expression is shown in formula (1):

[0006]

[0007] Where i = 1, 2, ..., N, j = 1, 2, ..., 4F; N is the number of nodes; F is the number of fault points; 4F is the total number of fault points under the four short-circuit fault types; V ij It represents the voltage value of node i when a short circuit occurs at point j in the power grid; V th.max Represents the upper limit of the voltage threshold; V th.min Represents the lower bound of the voltage threshold.

[0008] Step 2: Establish the objective function with minimum installation cost and price loss;

[0009] First, define the observable probability y jas follows:

[0010]

[0011] Where, X i represents the monitoring point installation vector, which is recorded as 1 when a monitoring device is installed at the i node, and recorded as 0 when no monitoring device is installed at the i node; j It means that when a fault occurs at point j, i =The probability that the power grid is observable when a monitoring device is installed at 1 location.

[0012] Define the objective function:

[0013]

[0014] In the formula, C i represents the cost of installing a monitoring device at the i-node; D j represents the unobservable loss when a failure occurs at point j; y j represents the probability of an observation.

[0015] Step 3: Establish constraint conditions based on the observable probability of the power grid when a short circuit fault occurs at a certain point in the power grid;

[0016] The constraint conditions are defined as shown in formula (4):

[0017]

[0018] In the formula, p j represents the observable probability of the power grid when a short circuit fault occurs at point j, p j ∈[0,1].

[0019] Step 4: Use the optimization algorithm to solve the installation vector and obtain the number and location of the monitoring points; DETAILED DESCRIPTION

[0020] The preferred embodiments are described in detail below in conjunction with the specification. It should be emphasized that the following description is only exemplary and is not intended to limit the scope of the present invention and its application.

[0021] The present invention provides an optimization configuration method for voltage sag monitoring points based on probability observability, and performs programming simulation on the IEEE39 node system, assuming that each node is a fault point, and there are 3 fault points on each line except the first and last nodes; the fault types are set as three-phase short circuit, single-phase short circuit, two-phase short circuit, and two-phase ground short circuit faults. There are a total of 141 fault points and 564 fault types in the entire network. The specific implementation of this method is as follows:

[0022] 1. Calculate the node voltage when a short circuit occurs at a certain point in the power grid and extract the probabilistic observable matrix;

[0023] Calculate the voltage at each bus node when different short-circuit faults occur at each fault point. Suppose V th.max =0.92, V th.min =0.88, and establish the probability observable matrix M according to formula (1) P,ij . Due to M P,ij The matrix dimension is too large to be fully presented, so the following only gives the M when a short circuit occurs at some points in the power grid. P,ij The matrix is ​​as follows. When a three-phase short circuit occurs at node 1, the corresponding M P,ij The first column: M P,i1 =[1,1,1,0.9549,0.8654,0.7543,1,1,1,0.3367,0.4777,0.4370,0.3963,0.5269,0.08657,0,0.4985,0.9989,0,0,0,0,0,0,1,0.7145,0.6144,0,0,0,0,0,0,0,0,0,0,0.2329,0,1] T ; When a three-phase short circuit fault occurs at 1 / 4 of line 1-2, the corresponding M P,ij The second column: M P,i2 =[1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,1,0.9952,0.7916,0.6281,0.3482,1,1,1];

[0024] 2. Establish the objective function with minimum installation cost and price loss;

[0025] Using formula (2), multiple objective functions are established as follows:

[0026] Let C i =1,D j =1000, that is, when the installation cost is low but the incompletely observable cost is high, the objective function is: The above objective function is optimized and solved, and the installation results under the objective function are analyzed.

[0027] 3. Establish constraint conditions based on the observable probability of a short circuit fault occurring at a certain point in the power grid;

[0028] The constraint condition is established by formula (3), where p j Set all to 1.

[0029] 4. Use the optimization algorithm to solve the installation vector and obtain the number and location of the monitoring points;

[0030] When f1 is used as the objective function, since the installation cost is low but the incomplete observability cost is high, in order to ensure the complete observability of the entire network, one set of installation nodes is obtained as: 2, 12, 19, 24, 27. It can be obtained that in order to achieve complete observability of the entire network, the minimum number of monitoring points to be installed is 5.

[0031] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A method for optimizing the configuration of voltage sag monitoring points based on probability observability is characterized by The method consists of the following three steps: Step 1: Calculate the node voltage when a short circuit occurs at a certain point in the power grid and extract the probabilistic observable matrix: The characteristic of this step is to extract the probability observable matrix M P,ij The way is as follows: Where i = 1, 2, ..., N, j = 1, 2, ..., 4F; N is the number of nodes; F is the number of fault points; 4F is the total number of fault points under the four short-circuit fault types; V ij It represents the voltage value of node i when a short circuit occurs at point j in the power grid; V th.max Represents the upper limit of the voltage threshold; V th.min represents the lower bound of the voltage threshold; Step 2: Establish the objective function with the minimum installation cost and price loss: The characteristic of this step is to establish the objective function f, first define the observable probability y j : In the above formula, X i represents the monitoring point installation vector, which is recorded as 1 when a monitoring device is installed at the i node, and recorded as 0 when no monitoring device is installed at the i node; j It means that when a fault occurs at point j, i = The probability of the power grid being observable when a monitoring device is installed at 1 location, Then, the objective function is defined as: In the above formula, C i represents the cost of installing a monitoring device at the i-node; D j represents the unobservable loss when a failure occurs at point j. Step 3: Establish the observable constraints of the power grid probability when a short circuit occurs at a certain point in the power grid as follows: The characteristic of this step is the establishment of constraints, as shown in the following formula: In the formula, p j represents the observable probability of the power grid when a short circuit fault occurs at point j; Step 4: Use the optimization algorithm to solve the above model and obtain the number and location of the monitoring points.