Flange joint preload optimization comprehensive test device and method

The comprehensive testing device is optimized through flange joint pre-tightening, and the flange joint sealing performance is detected and evaluated, which solves the flange connection leakage problem and improves the sealing performance and safety.

CN110864896BActive Publication Date: 2024-11-01CHINA SPECIAL EQUIP INSPECTION & RES INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911335456.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-23
Publication Date
2024-11-01
Estimated Expiration
2039-12-23

AI Technical Summary

Technical Problem

The prior art lacks special equipment for detecting and evaluating the sealing performance of flange joints, which leads to leakage in flange connections in actual use, affecting sealing performance and safety.

Method used

Provide a comprehensive test device for pre-tightening optimization of flange joints, including flange installation procedure testing module, lubricant test module and leakage rate testing module, through which the leakage rate of gaskets, flange installation procedures and lubricant pairs can be tested. The influence of bolt preload improves sealing performance.

Benefits of technology

It realizes convenient inspection and evaluation of flange joint sealing performance, improves testing work efficiency, and ensures the sealing performance and safety of flange connections.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110864896B_ABST
    Figure CN110864896B_ABST
Patent Text Reader

Abstract

The present invention discloses a comprehensive test device for optimizing the preload of a flange joint, comprising a flange installation procedure test module, a lubricant test module, a leakage rate test module and a test platform. The flange installation procedure test module, the lubricant test module and the leakage rate test module are all arranged on the test platform. The test platform provides support for each test module, thereby improving the structural stability of the device. A controller is arranged on the test platform, which is convenient for an operator to control each test module and obtain the test results in real time. The present invention also provides a comprehensive test method for optimizing the preload of a flange joint, wherein the flange installation procedure can be tested by the flange installation procedure test module, the influence of the lubricant on the bolt preload can be tested by the lubricant test module, the leakage rate of the gasket can be tested by the leakage rate test module, and a joint test of the installation procedure and the leakage rate can be performed, thereby improving the efficiency of the test work.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of connection and fastening device detection, and in particular to a flange joint pre-tightening optimization comprehensive testing device and method. Background Art

[0002] There are many forms of detachable sealing connections for pressure-bearing equipment, such as threaded connection, socket connection and flange connection, among which flange connection is the most commonly used in industry due to its simple structure and convenient assembly and disassembly. However, in actual use, under the influence of medium pressure, temperature, additional bending moment and additional axial force of the pipe system, leakage is prone to occur at the connection joint, resulting in sealing failure, which not only wastes energy, causes serious pollution to the environment, harms human health, but also even causes catastrophic accidents such as explosions.

[0003] The flange connection structure is mainly composed of flanges, bolts and gaskets. It relies on the bolt preload to connect the flange rings of equipment or pipelines together, compress the gaskets, and achieve sealing at the connection. As an important form of sealing connection, flange connection requires reliable tightness and sufficient strength. Engineering practice shows that bolt flange connections rarely fail in strength, and most failures are caused by leakage due to insufficient sealing performance. Statistics show that the main reasons for the leakage failure of flange joints are poor gasket quality and insufficient bolt preload. Under normal circumstances, the compression rebound performance of the gasket is its main technical indicator, but this indicator does not reflect the leakage performance of the gasket, that is, its leakage rate level is unknown, and gaskets with excessive leakage rates may also be used in industrial sites, causing leakage in flange joints. In addition, the installation quality of the flange connection will directly affect the bolt preload. If the installation quality is not good, it will lead to uneven bolt forces in the flange joint. In the later use process, weak points will inevitably occur, causing leakage failure. Among them, the key link in the installation quality is the pre-tightening sequence of the bolt group. Different pre-tightening sequences will affect the installation efficiency, the size of the final bolt force, and the uniformity of the force distribution in the bolt group. In summary, detecting gasket leakage performance and evaluating and optimizing the installation sequence of bolt groups are of great practical significance for improving the sealing performance of bolt flange joints and conducting related scientific research. However, in the existing technology, there is a lack of special equipment for detecting, evaluating and optimizing the sealing performance of flange joints.

[0004] Therefore, how to provide a comprehensive device that can detect and evaluate the sealing performance of flange joints has become an urgent problem to be solved by technical personnel in this field. Summary of the invention

[0005] The purpose of the present invention is to provide a flange joint preload optimization comprehensive testing device and method to solve the problems existing in the above-mentioned prior art, so that the operator can conveniently perform tests on the leakage rate of the gasket, the flange installation procedures and the evaluation of the lubricant's effect on the bolt preload.

[0006] To achieve the above object, the present invention provides the following solution: The present invention provides a flange joint preload optimization comprehensive test device, comprising:

[0007] A flange installation procedure test module, wherein the flange installation procedure test module comprises a flat welding flange, a first bolt and nut set and a first flange plate, wherein the flat welding flange can be connected to the first flange plate through the first bolt and nut set, and a gasket is arranged between the flat welding flange and the first flange plate;

[0008] a lubricant testing module, the lubricant testing module comprising a second bolt and nut set;

[0009] A leakage rate testing module, wherein the leakage rate testing module comprises a third bolt and nut group and two second flanges, wherein the two second flanges are connected via the third bolt and nut group, a gasket is arranged between the two second flanges, a leakage detection cavity is formed between the two second flanges, one end of the leakage detection cavity is connected to a high-pressure gas cylinder, and the high-pressure gas cylinder can transport gas into the leakage detection cavity, a standard container is arranged between the leakage detection cavity and the high-pressure gas cylinder, and the standard container can store gas, the other end of the leakage detection cavity is connected to the external environment, and the leakage detection cavity is also connected to a pressure transmitter and a thermocouple;

[0010] The first bolt and nut group, the second bolt and nut group, and the third bolt and nut group are all provided with a gasket-type pressure sensor;

[0011] A test platform, the flange installation procedure test module, the lubricant test module and the leakage rate test module are all arranged on the test platform, a controller is arranged on the test platform, and the pressure transmitter, the thermocouple and the gasket pressure sensor are all connected to the controller.

[0012] Preferably, the test platform includes a first column and a second column arranged in parallel, the number of the flange installation procedure test modules is two sets, the two sets of flange installation procedure test modules are respectively arranged on the first column and the second column, a connecting plate is arranged between the first column and the second column, the axes of the first column and the second column are perpendicular to the connecting plate, and the lubricant test module is arranged on the connecting plate.

[0013] Preferably, the height of the first column is higher than that of the second column, one set of the flange installation procedure test modules is connected to the top of the first column through an elbow, and the axis of the flange installation procedure test modules is perpendicular to the axis of the first column, and another set of the flange installation procedure test modules is connected to the second column through a support frame, and the axis of the flange installation procedure test modules is perpendicular to the axis of the second column.

[0014] Preferably, the elbow and the first column, the support frame and the second column are all detachably connected, and the installation positions of the support frame and the second column are adjustable.

[0015] Preferably, the connecting plate includes an upper connecting plate and a lower connecting plate arranged in parallel, the upper connecting plate is located on the top of the lower connecting plate, and there is a gap between the upper connecting plate and the lower connecting plate, the two ends of the upper connecting plate and the lower connecting plate are respectively connected to the first column and the second column, the upper connecting plate has a through hole that can accommodate the second bolt and nut group to pass through, and the bottom of the second bolt and nut group abuts against the lower connecting plate.

[0016] Preferably, the leakage rate testing module further comprises a buffer tank, and the buffer tank is located between the standard container and the high-pressure gas cylinder.

[0017] Preferably, flow regulating valves are provided between the leak detection cavity and the high-pressure gas cylinder and between the leak detection cavity and the external environment, a pressure reducing valve is provided between the high-pressure gas cylinder and the leak detection cavity, and valves are provided for the standard container, the buffer tank and the high-pressure gas cylinder.

[0018] Preferably, the leak detection cavity is connected to the high-pressure gas cylinder via a hose, and both the standard container and the buffer tank are connected to the hose.

[0019] The present invention also provides a flange joint preload optimization comprehensive test method, comprising the following steps:

[0020] Step 1: Determine the tightening procedure of the flange structure to be tested, loosen the first bolt and nut group in the flange installation procedure test module, start the gasket pressure sensor, rotate the first bolt and nut group to a tightened state, set the gasket pressure sensor to zero, and apply torque to the first bolt and nut group according to the tightening procedure of the flange structure to be tested until the tightening procedure is set. During the loading process, the controller can obtain the load value of the bolt in the first bolt and nut group to evaluate the rationality of the tightening procedure;

[0021] Step 2: Use the lubricant test module to select a test bolt and a reference bolt in the second bolt and nut group, evenly apply the lubricant to be tested on the thread of the test bolt and the inner side of the nut that matches it, manually install the nut without tightening it, and the reference bolt and reference nut do not need to be lubricated. Start the gasket pressure sensor, tighten the bolt, set the gasket pressure sensor to zero, start the test, apply torque to the second bolt and nut group until the target preload force is reached, and the controller can obtain the load values ​​of the test bolt and the reference bolt to evaluate the effect of the lubricant.

[0022] Step 3: Use the leak rate test module

[0023] Apply gasket preload stress to the gasket between the two second flanges and maintain it for a certain period of time after reaching the specified value;

[0024] Determine the cavity volume between the two second flanges

[0025] Let the high pressure gas cylinder introduce pressure p into the leak detection cavity s Close the high-pressure gas cylinder, connect the leak detection cavity with the standard container, and measure the equilibrium pressure p after the leak detection cavity and the standard container are connected. ε , the cavity volume of the two second flanges is calculated as follows:

[0026]

[0027] Where:

[0028] V s —The volume of the leak detection chamber, in cubic centimeters

[0029] V B —The volume of a standard container in cubic centimeters

[0030] p B —The initial absolute pressure in the standard container, in Pa

[0031] p s —Absolute pressure of the test medium introduced into the leak detection chamber, in Pa

[0032] p e —The absolute pressure after the standard container is connected to the leak detection cavity, in Pa

[0033] Measuring gasket leakage rate

[0034] Introduce the test medium into the leak detection cavity. When the medium pressure reaches the specified value and remains for a period of time, start leak detection. Record the pressure p3 and temperature T3 of the leak detection cavity at the beginning of leak detection, and start timing. Record and measure the pressure p4 and temperature T4 in the leak detection cavity at the end of the measurement. The leakage rate of the gasket is calculated as follows:

[0035]

[0036] Where:

[0037] L v —Volume leakage rate, N·cm 3 / s

[0038] p st —Atmospheric pressure under standard conditions is 101325Pa

[0039] T st — Absolute atmospheric temperature under standard conditions, 273.15K

[0040] p3—absolute pressure in the leak detection chamber at the beginning of leak detection, in Pa

[0041] p4—absolute pressure in the leak detection chamber at the end of the leak detection, in Pascals

[0042] T3—absolute temperature in the leak detection chamber at the beginning of leak detection, in K

[0043] T4—Absolute temperature in the leak detection chamber at the end of the leak detection, unit: K

[0044] V s —The volume of the leak detection chamber, in cubic centimeters

[0045] t—leak detection time, in seconds.

[0046] Preferably, in step three, a gasket pre-tightening stress is applied to the gasket between the two second flanges, and maintained for 15 minutes after reaching a specified value; when measuring the leakage rate of the gasket, a test medium is introduced into the leak detection cavity, and when the medium pressure reaches a specified value, it is maintained for 10 minutes, and the measuring time is 2-10 minutes.

[0047] Compared with the prior art, the present invention has achieved the following technical effects: the flange joint pre-tightening optimization comprehensive test device provided by the present invention includes a flange installation procedure test module, a lubricant test module, a leakage rate test module and a test platform. The flange installation procedure test module, the lubricant test module and the leakage rate test module are all arranged on the test platform. The test platform provides support for each test module, improves the structural stability of the device, and is provided with a controller on the test platform, which is convenient for the operator to control each test module and obtain the test results in real time. The present invention also provides a flange joint pre-tightening optimization comprehensive test method, which can test the flange installation procedure by using the flange installation procedure test module, test the influence of lubricant on bolt pre-tightening force by using the lubricant test module, test the leakage rate of the gasket by using the leakage rate test module, and can also perform installation procedure and leakage rate joint test to improve the test work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0049] Figure 1 It is a structural schematic diagram of the flange joint preload optimization comprehensive test device of the present invention;

[0050] Figure 2 It is a schematic diagram of the front view of the comprehensive testing device for optimizing the preload of flange joints of the present invention;

[0051] Figure 3 It is a schematic diagram of the right side view of the flange joint preload optimization comprehensive test device of the present invention;

[0052] Figure 4 It is a schematic diagram of a top view of a comprehensive test device for optimizing preload of a flange joint according to the present invention;

[0053] Figure 5 It is a schematic diagram of the axial direction of a part of the structure of the comprehensive test device for optimizing the preload of a flange joint of the present invention;

[0054] Figure 6 A disassembly schematic diagram of a flange installation procedure test module of the flange joint preload optimization comprehensive test device of the present invention;

[0055] Figure 7 A schematic diagram of the working principle of the gas circuit of the leakage rate test module of the flange joint pre-tightening optimization comprehensive test device of the present invention;

[0056] Among them, 1 is the flange installation procedure test module, 2 is the lubricant test module, 3 is the leakage rate test module, 4 is the test platform, 5 is the flat welding flange, 6 is the first bolt and nut group, 7 is the first flange, 8 is the gasket, 9 is the second bolt and nut group, 10 is the third bolt and nut group, 11 is the second flange, 12 is the high-pressure gas cylinder, 13 is the standard container, 14 is the pressure transmitter, 15 is the thermocouple, 16 is the gasket type pressure sensor, 17 is the first column, 18 is the second column, 19 is the elbow, 20 is the support frame, 21 is the upper connecting plate, 22 is the lower connecting plate, and 23 is the buffer tank. DETAILED DESCRIPTION

[0057] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0058] The purpose of the present invention is to provide a flange joint preload optimization comprehensive testing device and method to solve the problems existing in the above-mentioned prior art, so that the operator can conveniently perform tests on the leakage rate of the gasket, the flange installation procedures and the evaluation of the lubricant's effect on the bolt preload.

[0059] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0060] Please refer to Figure 1-7 ,in, Figure 1 This is a schematic diagram of the structure of the flange joint preload optimization comprehensive test device of the present invention. Figure 2 This is a schematic diagram of the front view of the flange joint preload optimization comprehensive test device of the present invention, Figure 3 This is a schematic diagram of the flange joint preload optimization comprehensive test device of the present invention from the right side. Figure 4 This is a schematic diagram of a top view of the flange joint preload optimization comprehensive test device of the present invention, Figure 5 This is a schematic diagram of the axial structure of a partial structure of the flange joint preload optimization comprehensive test device of the present invention. Figure 6 This is a disassembly diagram of the flange installation procedure test module of the flange joint preload optimization comprehensive test device of the present invention, Figure 7 It is a schematic diagram of the gas circuit working principle of the leakage rate test module of the flange joint pre-tightening optimization comprehensive test device of the present invention.

[0061] The present invention provides a flange joint preload optimization comprehensive test device, comprising:

[0062] The flange installation procedure test module 1 includes a flat welding flange 5, a first bolt and nut group 6 and a first flange plate 7. The flat welding flange 5 can be connected to the first flange plate 7 through the first bolt and nut group 6. A gasket 8 is arranged between the flat welding flange 5 and the first flange plate 7.

[0063] The lubricant testing module 2 comprises a second bolt and nut set 9 .

[0064] The leakage rate testing module 3 comprises a third bolt and nut group 10 and two second flanges 11, the two second flanges 11 are connected via the third bolt and nut group 10, a gasket 8 is arranged between the two second flanges 11, a leakage detection cavity is formed between the two second flanges 11, one end of the leakage detection cavity is connected with a high-pressure gas cylinder 12, the high-pressure gas cylinder 12 can transport gas into the leakage detection cavity, a standard container 13 is arranged between the leakage detection cavity and the high-pressure gas cylinder 12, the standard container 13 can store gas, the other end of the leakage detection cavity is connected with the external environment, the leakage detection cavity is also connected with a pressure transmitter 14 and a thermocouple 15, the pressure transmitter 14 can test the pressure in the leakage detection cavity, and the thermocouple 15 can test the temperature in the leakage detection cavity.

[0065] Gasket-type pressure sensors 16 are provided at the first bolt-nut group 6 , the second bolt-nut group 9 and the third bolt-nut group 10 . The number of gasket-type pressure sensors 16 is consistent with the number of bolts and nuts specifically used in the test, thereby improving the accuracy of the test results.

[0066] The test platform 4, the flange installation procedure test module 1, the lubricant test module 2 and the leakage rate test module 3 are all arranged on the test platform 4. The test platform 4 is provided with a controller, and the pressure transmitter 14, the thermocouple 15 and the gasket pressure sensor 16 are all connected to the controller.

[0067] The flange joint pre-tightening optimization comprehensive test device provided by the present invention includes a flange installation procedure test module 1, a lubricant test module 2, a leakage rate test module 3 and a test platform 4. The flange installation procedure test module 1, the lubricant test module 2 and the leakage rate test module 3 are all arranged on the test platform 4. The test platform 4 provides support for each test module, improves the structural stability of the device, and is provided with a controller on the test platform 4, which is convenient for the operator to control each test module and obtain the test results in real time. The flange installation procedure test module 1 can be used to test the flange installation procedure, the lubricant test module 2 can be used to test the influence of the lubricant on the bolt pre-tightening force, the leakage rate test module 3 can be used to test the leakage rate of the gasket 8, and the installation procedure and leakage rate joint test can also be performed to improve the test work efficiency.

[0068] Among them, the test platform 4 includes a first column 17 and a first column 18 arranged in parallel, the number of flange installation specification test modules 1 is two sets, and the two sets of flange installation specification test modules 1 can test flanges of DN125 specifications and flanges of DN250 specifications, so as to realize the testing of flange installation specifications of different specifications, and the two sets of flange installation specification test modules 1 are respectively arranged on the first column 17 and the first column 18, and a connecting plate is arranged between the first column 17 and the first column 18, and the axes of the first column 17 and the first column 18 are perpendicular to the connecting plate, and the lubricant test module 2 is arranged on the connecting plate, and the connecting plate connects the first column 17 and the first column 18 to enhance the structural stability, and the lubricant test module 2 is arranged on the connecting plate to save space. In this specific embodiment, the first column 17 and the second column 18 are respectively connected with the base bolts of the test platform 4, which is convenient for disassembly and assembly, and can ensure the stability and rigidity of the test platform.

[0069] Specifically, the height of the first column 17 is higher than that of the first column 18. One set of flange installation procedure test modules 1 is connected to the top of the first column 17 through the elbow 19, and the axis of the flange installation procedure test module 1 is perpendicular to the axis of the first column 17. Another set of flange installation procedure test modules 1 is connected to the first column 18 through the support frame 20, and the axis of the flange installation procedure test module 1 is perpendicular to the axis of the first column 17 / first column 18, which is convenient for operators to perform testing operations.

[0070] At the same time, the elbow 19 and the first column 17, the support frame 20 and the first column 18 can be detachably connected, which is convenient for disassembly and assembly. The installation position of the support frame 20 and the first column 18 can be adjusted, which is convenient for the operator to adjust the relative positions of the elbow 19 and the first column 17, the support frame 20 and the first column 18 according to the test needs, thereby improving the convenience of the test operation.

[0071] More specifically, the connecting plate includes an upper connecting plate 21 and a lower connecting plate 22 which are arranged in parallel. The upper connecting plate 21 is located on the top of the lower connecting plate 22. There is a gap between the upper connecting plate 21 and the lower connecting plate 22. The two ends of the upper connecting plate 21 and the lower connecting plate 22 are respectively connected to the first column 17 and the first column 18. The upper connecting plate 21 has a through hole that can accommodate the second bolt and nut group 9 to pass through. The bottom of the second bolt and nut group 9 abuts against the lower connecting plate 22. The lower connecting plate 22 can provide support for the second bolt and nut group 9. In this specific embodiment, the number of through holes in the upper connecting plate 21 is three, and the three through holes are arranged at equal intervals to improve the structural stability of the connecting plate.

[0072] In addition, the leakage rate test module 3 also includes a buffer tank 23, which is located between the standard container 13 and the high-pressure gas cylinder 12. The buffer tank 23 can buffer the pipeline pressure during the test to protect the pipeline safety.

[0073] In this specific embodiment, flow regulating valves are arranged between the leak detection cavity and the high-pressure gas cylinder 12, and between the leak detection cavity and the external environment, a pressure reducing valve is arranged between the high-pressure gas cylinder 12 and the leak detection cavity, and valves are arranged on the standard container 13, the buffer tank 23 and the high-pressure gas cylinder 12 to facilitate control and adjustment to ensure the smooth progress of the test.

[0074] The leak detection cavity is connected to the high-pressure gas cylinder 12 through a hose, and the standard container 13 and the buffer tank 23 are both connected to the hose.

[0075] The present invention also provides a flange joint preload optimization comprehensive test method, comprising the following steps:

[0076] Step 1, determine the tightening procedure of the flange structure to be tested, including the target preload, tightening mode, tightening rounds and load application ratio. The target preload needs to be determined in combination with the size of the first bolt and nut group 6 and cannot exceed the bolt bearing range. Loosen the first bolt and nut group 6 in the flange installation procedure test module 1, start the gasket pressure sensor 16, turn the first bolt and nut group 6 to a tightened state, set the gasket pressure sensor 16 to zero, and apply torque to the first bolt and nut group 6 through a torque wrench according to the tightening procedure of the flange structure to be tested until the tightening procedure is set. During the loading process, the controller can obtain the load value of the bolts in the first bolt and nut group 6 to evaluate the rationality of the tightening procedure.

[0077] Step 2: Use the lubricant testing module 2 to select a test bolt and a reference bolt in the second bolt and nut group 9, evenly apply the lubricant to be tested on the thread of the test bolt and the inside of the nut that matches it, manually install the nut without tightening it, and the reference bolt and reference nut do not need to be lubricated. Start the gasket pressure sensor 16, tighten the bolt, set the gasket pressure sensor 16 to zero, start the test, apply torque to the second bolt and nut group 9 until the target preload force is reached, and the controller can obtain the load values ​​of the test bolt and the reference bolt to evaluate the effect of the lubricant.

[0078] Step 3: Use the leak rate test module 3

[0079] Before the test, clean the sealing surface of the second flange 11 with a solvent (such as acetone), apply a gasket preload stress to the gasket 8 between the two second flanges 11, and the preload stress of the gasket 8 of different materials is as shown in the following table. After reaching the specified value, maintain it for a period of time;

[0080] Testable gaskets and experimental conditions

[0081]

[0082] Determine the cavity volume between the two second flanges 11

[0083] The high pressure gas cylinder 12 is set to introduce a pressure of p into the leak detection cavity. s The test medium is closed, the high pressure gas cylinder 12 is closed, the leak detection cavity is connected to the standard container 13, and the equilibrium pressure p after the leak detection cavity and the standard container 13 are connected is measured. ε The cavity volume of the two second flanges 11 is calculated as follows:

[0084]

[0085] Where:

[0086] V s —The volume of the leak detection chamber, in cubic centimeters

[0087] V B —The volume of the standard container 13 in cubic centimeters

[0088] p B —The initial absolute pressure in the standard container 13, in Pa

[0089] p s —Absolute pressure of the test medium introduced into the leak detection chamber, in Pa

[0090] p e —The absolute pressure after the standard container 13 is connected to the leak detection cavity, in Pascals

[0091] The calibration process is repeated three times, and the arithmetic mean of the volumes measured three times is taken as the cavity volume between the two second flanges 11. The deviation between the volume value measured each time and the mean value should not be greater than 3%.

[0092] Measuring the leakage rate of gasket 8

[0093] Introduce the test medium into the leak detection cavity. When the medium pressure reaches the specified value and is maintained for a period of time, start leak detection. Record the pressure p3 and temperature T3 of the leak detection cavity at the beginning of leak detection, and start timing. Record and measure the pressure p4 and temperature T4 in the leak detection cavity at the end of the measurement. The leakage rate of gasket 8 is calculated according to the following formula:

[0094]

[0095] Where:

[0096] L v —Volume leakage rate, Ncm 3 / s

[0097] pst —Atmospheric pressure under standard conditions is 101325Pa

[0098] T st — Absolute atmospheric temperature under standard conditions, 273.15K

[0099] p3—absolute pressure in the leak detection chamber at the beginning of leak detection, in Pa

[0100] p4—absolute pressure in the leak detection chamber at the end of the leak detection, in Pascals

[0101] T3—absolute temperature in the leak detection chamber at the beginning of leak detection, in K

[0102] T4—Absolute temperature in the leak detection chamber at the end of the leak detection, unit: K

[0103] V s —The volume of the leak detection chamber, in cubic centimeters

[0104] t—leak detection time, in seconds.

[0105] The average value of all tests is taken as the final test result.

[0106] In step three, a gasket pre-tightening stress is applied to the gasket 8 between the two second flanges 11, and maintained for 15 minutes after reaching the specified value; when measuring the leakage rate of the gasket 8, a test medium is introduced into the leak detection cavity, and when the medium pressure reaches the specified value, it is maintained for 10 minutes, and the measuring time is 2-10 minutes.

[0107] By utilizing the comprehensive test device for optimizing the preload of flange joints of the present invention, it is possible to simultaneously measure the leakage rate of gasket seals, flange installation procedures, tests for evaluating the effect of lubricants on bolt preload, and installation procedure-leakage rate joint tests; it is possible to implement preload force tests on bolt groups with different flange specifications and different installation positions; at the same time, the device of the present invention can also be directly applied to industrial sites to test and verify whether the preload force of the flange sealing structure meets the standards.

[0108] The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A comprehensive test device for optimizing flange joint preload, characterized in that: include: A flange installation procedure test module, wherein the flange installation procedure test module comprises a flat welding flange, a first bolt and nut set and a first flange plate, wherein the flat welding flange can be connected to the first flange plate through the first bolt and nut set, and a gasket is arranged between the flat welding flange and the first flange plate; a lubricant testing module, the lubricant testing module comprising a second bolt and nut set; A leakage rate testing module, wherein the leakage rate testing module comprises a third bolt and nut group and two second flanges, wherein the two second flanges are connected via the third bolt and nut group, a gasket is arranged between the two second flanges, a leakage detection cavity is formed between the two second flanges, one end of the leakage detection cavity is connected to a high-pressure gas cylinder, and the high-pressure gas cylinder can transport gas into the leakage detection cavity, a standard container is arranged between the leakage detection cavity and the high-pressure gas cylinder, and the standard container can store gas, the other end of the leakage detection cavity is connected to the external environment, and the leakage detection cavity is also connected to a pressure transmitter and a thermocouple; The first bolt and nut group, the second bolt and nut group, and the third bolt and nut group are all provided with a gasket-type pressure sensor; A test platform, the flange installation procedure test module, the lubricant test module and the leakage rate test module are all arranged on the test platform, a controller is arranged on the test platform, and the pressure transmitter, the thermocouple and the gasket pressure sensor are all connected to the controller; When the above-mentioned flange joint preload optimization comprehensive test device is used for testing, the following steps are included: Step 1: Determine the tightening procedure of the flange structure to be tested, loosen the first bolt and nut group in the flange installation procedure test module, start the gasket pressure sensor, rotate the first bolt and nut group to a tightened state, set the gasket pressure sensor to zero, and apply torque to the first bolt and nut group according to the tightening procedure of the flange structure to be tested until the tightening procedure is set. During the loading process, the controller can obtain the load value of the bolt in the first bolt and nut group to evaluate the rationality of the tightening procedure; Step 2: Use the lubricant test module to select a test bolt and a reference bolt in the second bolt and nut group, evenly apply the lubricant to be tested on the thread of the test bolt and the inner side of the nut that matches it, manually install the nut without tightening it, and the reference bolt and reference nut do not need to be lubricated. Start the gasket pressure sensor, tighten the bolt, set the gasket pressure sensor to zero, start the test, apply torque to the second bolt and nut group until the target preload force is reached, and the controller can obtain the load values ​​of the test bolt and the reference bolt to evaluate the effect of the lubricant. Step 3: Use the leak rate test module Apply gasket preload stress to the gasket between the two second flanges and maintain it for a certain period of time after reaching the specified value; Determine the cavity volume between the two second flanges Let the high pressure gas cylinder introduce pressure p into the leak detection cavity s Close the high-pressure gas cylinder, connect the leak detection cavity with the standard container, and measure the equilibrium pressure p after the leak detection cavity and the standard container are connected. ε , the cavity volume of the two second flanges is calculated as follows: Where: V s —The volume of the leak detection chamber, in cubic centimeters V B —The volume of a standard container in cubic centimeters p B —The initial absolute pressure in the standard container, in Pa p s —Absolute pressure of the test medium introduced into the leak detection chamber, in Pa p e —The absolute pressure after the standard container is connected to the leak detection cavity, in Pa Measuring gasket leakage rate Introduce the test medium into the leak detection cavity. When the medium pressure reaches the specified value and remains for a period of time, start leak detection. Record the pressure p3 and temperature T3 of the leak detection cavity at the beginning of leak detection, and start timing. Record and measure the pressure p4 and temperature T4 in the leak detection cavity at the end of the measurement. The leakage rate of the gasket is calculated as follows: Where: L v —Volume leakage rate, N·cm 3 / s p st —Atmospheric pressure under standard conditions is 101325Pa T st — Absolute atmospheric temperature under standard conditions, 273.15K p3—absolute pressure in the leak detection chamber at the beginning of leak detection, in Pa p4—absolute pressure in the leak detection chamber at the end of the leak detection, in Pascals T3—absolute temperature in the leak detection chamber at the beginning of leak detection, in K T4—Absolute temperature in the leak detection chamber at the end of the leak detection, unit: K V s —The volume of the leak detection chamber, in cubic centimeters t—leak detection time, in seconds.

2. The flange joint preload optimization comprehensive test device according to claim 1 is characterized in that: The test platform includes a first column and a second column arranged in parallel, the number of the flange installation procedure test modules is two sets, the two sets of the flange installation procedure test modules are respectively arranged on the first column and the second column, a connecting plate is arranged between the first column and the second column, the axes of the first column and the second column are perpendicular to the connecting plate, and the lubricant test module is arranged on the connecting plate.

3. The flange joint preload optimization comprehensive test device according to claim 2 is characterized in that: The height of the first column is higher than that of the second column. One set of the flange installation procedure test modules is connected to the top of the first column through an elbow, and the axis of the flange installation procedure test module is perpendicular to the axis of the first column. Another set of the flange installation procedure test modules is connected to the second column through a support frame, and the axis of the flange installation procedure test module is perpendicular to the axis of the second column.

4. The flange joint preload optimization comprehensive test device according to claim 3 is characterized in that: The elbow and the first column, the support frame and the second column are all detachably connected, and the installation positions of the support frame and the second column are adjustable.

5. The flange joint preload optimization comprehensive test device according to claim 3 is characterized in that: The connecting plate includes an upper connecting plate and a lower connecting plate arranged in parallel, the upper connecting plate is located on the top of the lower connecting plate, and there is a gap between the upper connecting plate and the lower connecting plate. The two ends of the upper connecting plate and the lower connecting plate are respectively connected to the first column and the second column. The upper connecting plate has a through hole that can accommodate the second bolt and nut group to pass through, and the bottom of the second bolt and nut group abuts against the lower connecting plate.

6. The flange joint preload optimization comprehensive test device according to claim 1 is characterized in that: The leakage rate testing module further includes a buffer tank, which is located between the standard container and the high-pressure gas cylinder.

7. The flange joint preload optimization comprehensive test device according to claim 6 is characterized in that: A flow regulating valve is arranged between the leak detection cavity and the high-pressure gas cylinder, and between the leak detection cavity and the external environment. A pressure reducing valve is arranged between the high-pressure gas cylinder and the leak detection cavity. Valves are arranged on the standard container, the buffer tank and the high-pressure gas cylinder.

8. The flange joint preload optimization comprehensive test device according to claim 7 is characterized in that: The leak detection cavity is connected to the high-pressure gas cylinder via a hose, and both the standard container and the buffer tank are connected to the hose.

9. The flange joint preload optimization comprehensive test device according to claim 1 is characterized in that: In step three, apply gasket pre-tightening stress to the gasket between the two second flanges, and maintain it for 15 minutes after reaching the specified value; when measuring the leakage rate of the gasket, introduce the test medium into the leak detection cavity, and maintain it for 10 minutes after the medium pressure reaches the specified value. The measuring time is 2-10 minutes.