Sunken integrated pipeline corridor

By designing double-layer space and natural vents in the urban comprehensive pipeline corridor, the problem of difficulty in passage and lighting in the closed pipeline corridor is solved, natural underground lighting and ventilation are achieved, and traffic convenience and resource utilization efficiency are improved.

CN112031022BActive Publication Date: 2024-11-22CHINA ENFI ENG CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010884556.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-28
Publication Date
2024-11-22
Estimated Expiration
2040-08-28

AI Technical Summary

Technical Problem

Most of the existing urban comprehensive pipeline corridors are closed structures, which are difficult to achieve underground traffic and driving, lighting and ventilation are difficult, and confined spaces lead to waste of resources and maintenance problems.

Method used

Design a sunken integrated pipe corridor, divide the double-layer space through structural beams, set up lighting roofs, ventilation ducts and natural vents, hang large drainage pipes, arrange cable trays and gas pipelines, realize the integration of human-vehicle diversion and multiple pipelines Laying.

Benefits of technology

It realizes natural underground lighting and ventilation, improves traffic convenience, saves resources, solves the lighting and ventilation problems of closed pipe corridors, and enhances the comfort and maintenance convenience of pipe corridors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112031022B_ABST
    Figure CN112031022B_ABST
Patent Text Reader

Abstract

The present invention provides a sunken integrated pipe gallery, comprising a wall, a structural column, and a structural beam arranged in the middle of the structural column to divide the pipe gallery into a double-layer space, a skylight is arranged on the top of the structural beam to provide rain protection and lighting for the double-layer space; the double-layer space comprises an upper space and a lower space; a ventilation duct and a smoke pipe are arranged in the upper space; and an opening is arranged on one side of the upper space to serve as a natural vent; a road and a drainage pipe are arranged in the lower space; the drainage pipe comprises a small drainage pipe and a large drainage pipe, and the large drainage pipe is hung on the structural beam, and the small drainage pipe is fixed on a side wall of the wall, thereby solving the problem that the small drainage pipe itself has insufficient rigidity to support and suspend the structural beam over a long distance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of urban construction, and more specifically, to a sunken integrated pipe gallery. Background Art

[0002] The urban integrated pipeline corridor came into being to solve the "road zipper" problem caused by repeated ground excavation and the spider-web-like overhead lines on main streets. A tunnel space is built underground in the city to integrate various engineering pipelines such as electricity, communications, gas, heating, water supply and drainage. It is an underground integrated pipeline corridor with special inspection ports, lifting ports and monitoring systems.

[0003] Most of the existing pipe corridors are closed corridors, and different types of pipelines are arranged in compartments, making it difficult to pass pedestrians and vehicles in the underground integrated pipe corridor. If there is a need for pedestrians and vehicles, it is often necessary to separate the integrated pipe corridor from the integrated pipe corridor and re-plan the cabins for pedestrians and vehicles. In addition, since this integrated pipe corridor is a closed layout, its lighting and ventilation are difficult to solve. Usually, natural lighting cannot be achieved in the corridor, and lighting equipment is required. In addition, a separate ventilation shaft is usually required in the integrated pipe corridor. Moreover, since it is a confined space, fire doors need to be installed at intervals along the length of the cabin in the integrated pipe corridor according to fire protection needs, which not only wastes resources but is also difficult to maintain.

[0004] Therefore, there is an urgent need for a sunken comprehensive pipeline corridor that can realize the comprehensive laying of various pipelines such as electricity, communications, gas, heating, water supply and drainage, ventilation, smoke exhaust, etc. according to different media, fully consider the flow lines of pedestrians and vehicles in the pipeline corridor, realize the separation of people and vehicles, and realize lighting and ventilation. Summary of the invention

[0005] In view of the above problems, the purpose of the present invention is to provide a sunken integrated pipe corridor to solve the problem that most of the existing pipe corridors are closed pipe corridors, and it is difficult to realize the passage of pedestrians and vehicles in the underground integrated pipe corridor. If there is a need for pedestrians and vehicles, it is often necessary to separate the integrated pipe corridor from the integrated pipe corridor and re-plan the cabins for pedestrians and vehicles. In addition, since this integrated pipe corridor is a closed layout, its lighting and ventilation are difficult problems to solve. Usually, natural lighting cannot be achieved in the corridor, and lighting equipment is required, and a separate ventilation shaft needs to be set up in the integrated pipe corridor. Moreover, since it is a confined space, fire doors need to be set at intervals along the length of the cabin in the integrated pipe corridor according to fire protection needs, which not only wastes resources but is also difficult to maintain.

[0006] The present invention provides a sunken integrated pipe gallery, characterized in that it comprises a wall constituting the exterior of the pipe gallery, a structural column arranged in the wall, and a structural beam arranged in the middle of the structural column to divide the pipe gallery into a double-layer space, wherein:

[0007] A skylight is provided on the top of the structural beam, and the skylight is used for rain protection and lighting of the double-layer space;

[0008] The double-layer space includes an upper space and a lower space; wherein,

[0009] A ventilation duct and a smoke pipe are arranged in the upper space; and an opening is arranged on one side of the upper space to serve as a natural ventilation opening;

[0010] Roads and drainage pipes are arranged in the lower space; the drainage pipes include small drainage pipes and large drainage pipes, and,

[0011] The large drainage pipe is hung on the structural beam, and the small drainage pipe is fixed on the inner wall of the wall.

[0012] Preferably, a power cable tray and a communication cable tray are hung below the structural beam; wherein,

[0013] The horizontal spacing between the power cable tray and the communication cable tray is not less than the minimum spacing for preventing electromagnetic interference.

[0014] Preferably, a gas pipeline is also provided in the lower space, and the gas pipeline is suspended below the structural beam.

[0015] Preferably, the distance between the power cable tray, communication cable tray and gas pipeline and the bottom surface of the lower space is not less than 5 meters.

[0016] Preferably, a thermal pipeline is also provided in the upper space.

[0017] Preferably, the ventilation duct, the smoke duct and the thermal pipeline are supported and laid on the structural beam.

[0018] Preferably, the external ground is used as the calibration line;

[0019] The elevation of the structural beam is not less than 1 meter;

[0020] The bottom elevation of the lower space is not higher than -6 meters.

[0021] Preferably, the road includes a carriageway and a sidewalk,

[0022] The sidewalk is arranged on the side of the carriageway, and

[0023] The width of the carriageway is not less than 4 meters;

[0024] The width of the sidewalk is not less than 0.8 meters.

[0025] Preferably, the large drainage pipe is a pipe with a diameter of DN300 or above;

[0026] The small drainage pipe is a pipe with a diameter below DN300, and is fixed to the inner wall of the wall through cantilever brackets at equal intervals, and the length of the cantilever bracket is not more than 1 meter.

[0027] Preferably, the opening is the entire surface opposite to the structural column, and the height of the opening is not less than two meters.

[0028] From the above description, it can be seen that the sunken integrated pipe corridor provided by the present invention includes walls and structural columns constituting the exterior of the pipe corridor, and structural beams arranged in the middle of the structural columns to divide the pipe corridor into a double-layer space, and a skylight is arranged on the top of the structural beam to provide rain protection and lighting for the double-layer space; the double-layer space includes an upper space and a lower space; ventilation ducts and smoke pipes are arranged in the upper space; and an opening is arranged on one side of the upper space to serve as a natural ventilation port; roads and drainage pipes are arranged in the lower space; the drainage pipes include small drainage pipes and large drainage pipes, and the large drainage pipes are hung on the structural beams, and the small drainage pipes are fixed on the inner wall of the wall, thereby solving the problem that the small drainage pipes themselves are unable to cross the supports and suspensions arranged on the structural beams over a long distance due to their own rigidity. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] By referring to the following description and claims in conjunction with the accompanying drawings, and with a more comprehensive understanding of the invention, other objects and results of the present invention will become more apparent and easier to understand. In the accompanying drawings:

[0030] Figure 1 A schematic diagram of the cross-sectional structure of a sunken integrated pipe gallery according to an embodiment of the present invention;

[0031] The reference numerals include: 1. structural column; 2. structural beam; 3. skylight; 4. large drainage pipe; 5. power cable tray; 6. communication cable tray; 7. ventilation duct; 8. smoke pipe; 9. thermal pipe; 10. small drainage pipe; 11. gas pipeline; 12. driveway; 13. sidewalk; 14. natural vent. DETAILED DESCRIPTION

[0032] Most of the existing pipe corridors are closed corridors, and different types of pipelines are arranged in compartments, making it difficult to pass pedestrians and vehicles in the underground integrated pipe corridor. If there is a need for pedestrians and vehicles, it is often necessary to separate the integrated pipe corridor from the integrated pipe corridor and re-plan the cabins for pedestrians and vehicles. In addition, since this integrated pipe corridor is a closed layout, its lighting and ventilation are difficult to solve. Usually, natural lighting cannot be achieved in the corridor, and lighting equipment is required. In addition, a separate ventilation shaft needs to be set up in the integrated pipe corridor. Moreover, since it is a confined space, fire doors need to be set at intervals along the length of the cabin in the integrated pipe corridor according to fire protection needs, which not only wastes resources but is also difficult to maintain.

[0033] In view of the above problems, the present invention provides a sunken integrated pipe gallery, and the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0034] The following description of exemplary embodiments is merely illustrative in nature and is not intended to limit the invention and its application or use. Technologies and devices known to ordinary technicians in the relevant field may not be discussed in detail, but in appropriate cases, technologies and devices should be considered as part of the specification.

[0035] like Figure 1 As shown, the present invention provides a sunken integrated pipe gallery, including a wall constituting the exterior of the pipe gallery (not marked in the figure), a structural column 1 arranged in the wall, and a structural beam 2 arranged in the middle of the structural column to divide the pipe gallery into a double-layer space, wherein a skylight 3 is arranged on the top of the structural beam 2, and the skylight 3 is used for rain protection and lighting of the double-layer space, that is, rain protection and lighting of the double-layer space. Specifically, in the present embodiment, the side of the skylight away from the structural column 1 has a downward slope, so that in rainy weather, rain and snow slide to this side to prevent water or snow from accumulating on the skylight. The material of the skylight 3 is not specifically limited, and any material with support, lighting and waterproof properties can be used to benefit the lighting in the pipe gallery, so as to overcome the disadvantage that the traditional closed pipe gallery can only be illuminated by lighting equipment.

[0036] exist Figure 1 In the embodiment shown, if the external ground is used as the reference line (reference object), the elevation of the structural beam 2 is not less than 1 meter, that is, the height of the structural beam above the ground is not less than 1 meter, so that the maintenance platform connected to the external building can perform local maintenance on the pipes arranged on the structural beam 2 in the pipe gallery; the bottom elevation of the lower space is not higher than -6 meters, that is, relative to the external ground, the depth of the lower space should be greater than six meters to ensure that there is sufficient space underground in the pipe gallery to facilitate the layout of pipes and facilitate the entry of large fire trucks.

[0037] like Figure 1The sunken integrated pipe gallery shown in the figure has a double-layer space including an upper space and a lower space; the upper structure is used to support the laying of airflow-type pipes such as ventilation and smoke exhaust, and the lower structure is used to suspend pipes with strong rigidity. Specifically, ventilation ducts 7 and smoke pipes 8 are arranged in the upper space to ventilate and exhaust the pipe gallery; and an opening is arranged on one side of the upper space to serve as a natural ventilation hole 14. The size of the opening is not specifically limited and can be any opening with a ventilation effect. In the present embodiment, the opening is the entire surface opposite to the structural column 1, and the height of the natural ventilation hole is not less than two meters, that is, the natural ventilation hole 14 is the entire surface opposite to the structural column 1. In other words, the entire surface opposite to the structural column 1 is open and not completely closed to achieve sufficient ventilation.

[0038] exist Figure 1 In the illustrated embodiment, the upper space is further provided with a thermal pipe 9, which is consistent with the above-mentioned ventilation pipe 7 and smoke pipe 8, and is supported and laid on the structural beam 2, so as to realize the comprehensive laying of various pipes such as heating, ventilation, and smoke exhaust in the pipe gallery according to different media.

[0039] exist Figure 1 In the shown embodiment, roads and drainage pipes are provided in the lower space, and the drainage pipes include a small drainage pipe 10 and a large drainage pipe 4. The large drainage pipe is hung on the structural beam, and the small drainage pipe is fixed on the inner wall of the wall. Specifically, the large drainage pipe 4 is a pipe with a diameter of DN300 or above; the small drainage pipe 10 is a pipe with a diameter of DN300 or below, and the small drainage pipe 10 is fixed to the inner wall of the wall by cantilever brackets at equal intervals, and the length of the cantilever bracket is not more than 1 meter, and the vertical distance between the bottom of the cantilever bracket and the driving lane 12 is not less than 4m to prevent the cantilever bracket from affecting road traffic.

[0040] exist Figure 1 In the shown embodiment, a power cable tray 5 and a communication cable tray 6 are suspended under the structural beam 2, wherein the power cable tray 5 is used to place power cables, and the communication cable tray 6 is used to place communication cables, wherein the horizontal spacing between the power cable tray 5 and the communication cable tray 6 is not less than the minimum spacing for preventing electromagnetic interference. In the present embodiment, the horizontal spacing between the power cable tray 5 and the communication cable tray 6 is not less than 0.5 meters to prevent communication signals from being electromagnetically interfered.

[0041] In addition, Figure 1In the shown embodiment, a gas pipeline 11 is also provided in the lower space, and the gas pipeline 11 is suspended below the structural beam 2. It should be noted that the specific suspension method of the large drainage pipeline 4, the power cable bridge 5, the communication cable bridge 6 and the gas pipeline 11 on the structural beam 2 is not specifically limited. In the present embodiment, they are fixed to the upper structural beam 2 by means of supports (not shown in the figure), and the large drainage pipeline 4, the power cable bridge 5, the communication cable bridge 6 and the gas pipeline 11 suspended below the structural beam are at a distance of not less than 5 meters from the bottom surface of the lower space to meet the needs of large fire trucks passing through.

[0042] exist Figure 1 In the illustrated embodiment, the road includes a carriageway 12 and a sidewalk 13. The carriageway 12 may be a one-way street or a two-way street. The sidewalk 13 is arranged on the side of the carriageway 12. The sidewalk 12 may be arranged on one side of the carriageway 12 or on both sides of the carriageway 12. Railings are used to enclose the carriageway 12 and the sidewalk 13. In addition, the width of the carriageway 12 is not less than 4 meters; the width of the sidewalk is not less than 0.8 meters, so as to improve the adaptability of the road.

[0043] The sunken integrated pipe gallery of the present invention is different from the traditional closed pipe gallery. It is a sunken building body, which contains various pipes such as electricity, communication, gas, heating, water supply and drainage, ventilation, smoke exhaust, etc., and is comprehensively laid according to different media. The pedestrian and vehicle flow lines in the pipe gallery are fully considered to achieve the separation of people and vehicles. The semi-open design of the sunken integrated pipe gallery is also more beneficial to the lighting and ventilation in the pipe gallery, which completely solves the inconvenience of lighting, ventilation and other inconveniences of the existing closed pipe gallery, as well as the drawbacks of wasting resources, greatly improves the convenience of people and vehicles passing through the pipe gallery, and natural lighting can be achieved without lighting devices, thereby improving the overall comfort and saving resources.

[0044] As described above, the sunken integrated pipe gallery according to the present invention is described by way of example with reference to the accompanying drawings. However, those skilled in the art should understand that various improvements can be made to the sunken integrated pipe gallery proposed by the present invention without departing from the content of the present invention. Therefore, the protection scope of the present invention should be determined by the content of the attached claims.

Claims

1. A sunken integrated pipe gallery, characterized in that: It includes a wall constituting the exterior of the pipe gallery, a structural column arranged in the wall, and a structural beam arranged in the middle of the structural column to divide the pipe gallery into a double-layer space, wherein: A skylight is provided on the top of the structural beam, and the skylight is used for rain protection and lighting of the double-layer space; A power cable tray and a communication cable tray are hung below the structural beam; wherein, The horizontal spacing between the power cable tray and the communication cable tray is not less than the minimum spacing for electromagnetic interference prevention; The double-layer space includes an upper space and a lower space; wherein, A ventilation duct and a smoke pipe are arranged in the upper space; and an opening is arranged on one side of the upper space as a natural ventilation opening; the opening is the entire surface opposite to the structural column, and the height of the opening is not less than two meters; A thermal pipeline is also arranged in the upper space; the ventilation pipeline, the smoke pipe and the thermal pipeline are supported and laid on the structural beam; Roads and drainage pipes are arranged in the lower space; the drainage pipes include small drainage pipes and large drainage pipes, and, The road includes a carriageway and a sidewalk, and the sidewalk is arranged on the side of the carriageway; The large drainage pipe is hung on the structural beam, and the small drainage pipe is fixed on the inner wall of the wall; A gas pipeline is also provided in the lower space, and the gas pipeline is suspended below the structural beam; the distance between the power cable tray, the communication cable tray and the gas pipeline and the bottom surface of the lower space is not less than 5 meters; The external ground is used as the reference line; The elevation of the structural beam is not less than 1 meter; The bottom elevation of the lower space is not higher than -6 meters.

2. The sunken integrated pipe gallery according to claim 1 is characterized in that: The width of the carriageway is not less than 4 meters; The width of the sidewalk is not less than 0.8 meters.

3. The sunken integrated pipe gallery according to claim 2 is characterized in that: The large drainage pipe is a pipe with a diameter of DN300 or above; The small drainage pipe is a pipe with a diameter below DN300, and is fixed to the inner wall of the wall through cantilever brackets at equal intervals, and the length of the cantilever bracket is not more than 1 meter.