Tool-type self-lifting construction site gate and method thereof

By adopting standard section structures and anti-collision guide devices without welding and full bolts, the existing construction site doors are solved by the problems of heavy weight, installation difficulties and waste of steel, which is light, easy to install and detachable in construction site doors, saving materials and improving applicability.

CN112554770BActive Publication Date: 2025-03-25GUANGXI CONSTR ENG GRP UNITED CONSTR CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202011563820.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-25
Publication Date
2025-03-25
Estimated Expiration
2040-12-25

AI Technical Summary

Technical Problem

The existing construction site gates are heavy, difficult to install due to the welded structure, and cannot be disassembled without loss, resulting in waste of steel and inapplicable size.

Method used

The door beam and door post are connected by multiple sections of standard sections, and the electric hoist and rope are used to achieve self-lifting installation, and the door beam size is reduced through anti-collision guide devices.

Benefits of technology

It realizes the lightness, easy installation and detachability of the construction site door, saves materials, reduces steel waste, and improves the applicability and operational convenience of the door.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112554770B_ABST
    Figure CN112554770B_ABST
Patent Text Reader

Abstract

The present invention discloses a tool-type self-lifting construction site gate and method, comprising a gate beam and gate posts supporting both ends of the gate beam, wherein the gate beam and the gate posts are respectively connected by multiple standard sections, an electric hoist is fixed to the upper end of the gate post, and the standard section is assembled into a cubic structure by angle steel, a connecting plate, and a locking bolt; a lifting rope is provided on the standard section of the gate beam and is directly below the electric hoist; and a lifting hook of the electric hoist hooks the lifting rope. The present invention has the advantages of fully bolted detachable assembly, reusability, and material saving.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of assembled construction site gates, and in particular to a tool-type self-lifting construction site gate and a method thereof. Background Art

[0002] Regarding the requirements of closed management at the construction site of the construction project, a construction site gate should be set up at the entrance and exit of the construction site. Vehicles and personnel must enter and exit from the construction site gate, which is conducive to the safe and civilized management of the construction site and ensures the safety of the construction site. At present, the most commonly used construction site gate is a full steel structure construction site gate. The material is mainly angle steel. The door posts and door crossbeams on both sides are assembled and welded with angle steel, and finally hoisted by a crane. The existing construction site gates are welded and spliced ​​with door posts and door crossbeams. They are heavy and must be installed with the help of a crane during the installation process, which is difficult to install. Moreover, the welded door posts and door crossbeams cannot be disassembled without loss. After use, they are generally treated as waste. The door cannot be reused after disassembly, which greatly reduces the service life of the steel and causes waste of steel. After the door is fixed by welding, the size of the door cannot be changed, and its applicability is limited. The door is closed by welding iron sheets, which is inconvenient to operate and the iron sheets cannot be reused.

[0003] The disclosure of the above background technology content is only used to assist in understanding the concept and technical solution of the present invention. It does not necessarily belong to the prior art of this patent application. In the absence of clear evidence that the above content has been disclosed on the filing date of this patent application, the above background technology should not be used to evaluate the novelty and creativity of the present application. Summary of the invention

[0004] The invention aims to provide a construction site gate which is non-welded and fully bolt-assembled and can be disassembled.

[0005] To this end, the present invention provides a tool-type self-lifting construction site gate and a method thereof.

[0006] Preferably, the present invention may also have the following technical features:

[0007] The tool-type self-lifting construction site gate includes a door beam and door posts supporting both ends of the door beam, wherein the door beam and door posts are respectively connected by multiple standard sections, an electric hoist is fixed to the upper end of the door post, and the standard section is assembled into a cubic structure by angle steel, connecting plates, and locking bolts; a lifting rope is provided on the standard section of the door beam and is directly below the electric hoist; the lifting rope is hooked by the lifting hook of the electric hoist.

[0008] Furthermore, the standard section connecting the door crossbeam and the door post is the standard section at the end of the door crossbeam; the upper and lower surfaces of the standard section at the end of the door crossbeam are provided with installation openings for assembling the door post, and installation holes are provided at positions opposite to the installation openings of the standard section at the end of the door crossbeam; the standard section connecting the door post and the door crossbeam is the standard section at the top of the door post; the upper parts of the two standard sections at the top of the door post are provided with the electric hoist, and the electric hoist is arranged on the opposite side of the door post; the size of the installation opening is larger than the combined size of the standard section at the top of the door post and the electric hoist; the upper end of the standard section at the top of the door post is provided with a connecting hole corresponding to the position of the installing hole of the installing opening of the standard section at the end of the door crossbeam; and the positions of the door crossbeam and the door post are fixed by passing round steel through the installing hole and the connecting hole.

[0009] Furthermore, it also includes an anti-collision guide device, which is installed on the front and rear sides of the door cross beam and corresponds to the front and rear sides of the door post.

[0010] Furthermore, the anti-collision guide device includes an angle plate, a spring, and a clip mechanism. The angle plate is fixed into an angle by two flat plates, and the angle is 120 to 160°; the clip mechanism is an η-shaped structure, which includes a fixed plate, a movable plate, and a locking bolt. The upper end of the fixed plate is a hook, and the upper end of the movable plate is hinged to the hook end of the fixed plate, and the upper part of the movable plate and the fixed plate are provided with positioning holes corresponding to each other; the locking bolt is passed through the two positioning holes and fixed by screwing on nuts; there are two springs, one end of the two springs is respectively fixed to the lower end of the fixed plate and the lower end of the movable plate; the other ends of the two springs are respectively fixed to the two flat plates of the angle plate; the arc transition surface of the angle plate points to the door post; an anti-collision guide device is provided on each side of the door post.

[0011] Furthermore, the joint of the two flat sheets is an arc transition surface.

[0012] Furthermore, a horizontal connecting shaft is provided at the hook end of the fixed plate, and a radial limiting surface is provided at the end of the connecting shaft; the upper end of the movable plate is a hook, and is hooked on the connecting shaft.

[0013] Furthermore, a plurality of bolt holes are provided on the connection surface of each standard section, and an inclined rod is provided on the side of the standard section, and two adjacent inclined rods are arranged in a V-shaped structure.

[0014] Furthermore, the connecting plate includes a three-hole connecting plate, a four-hole connecting plate, and a six-hole connecting plate, and the corresponding connecting plate is used for fixing according to the connection situation.

[0015] A method for assembling a tool-type self-lifting construction site gate comprises the following steps: firstly, a concrete foundation is cast in situ at the installation position of the gate, and anchor bolts for connecting standard sections of door posts are also pre-buried in the cast-in-situ concrete foundation; a corresponding number of standard sections of door posts are stacked according to the design height of the gate, and the standard section at the top of the door posts is arranged at the uppermost end; then, a standard section at the end of a door beam is assembled at the bottom of the door post, and two standard sections at the end of the door beam are connected by using the standard section of the door beam; the hook of an electric hoist is lowered and the rope of the standard section at the end of the door beam is hooked; then, the electric hoist is started to lift the door beam, and after lifting into place, the position of the door beam and the door post is fixed by using round steel to pass through the installation hole and the connection hole; finally, panels are attached to the outer surfaces of the door post and the door beam to close them; and the installation of the construction site gate is completed.

[0016] Compared with the prior art, the beneficial effects of the present invention include: the standard section is fixed with bolts, which can be disassembled, replaced and reused, thus saving materials; in the process of lifting the door beam, when the door post collides with the door beam, the angle plate first hits the door post, and can pass smoothly by utilizing the elastic deformation of the spring and the arc transition surface of the angle plate, without causing the door beam to stop momentarily; by arranging an anti-collision guide device, the size of the door beam can be further reduced, saving steel. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a three-dimensional structural diagram of the present invention.

[0018] Figure 2 It is a three-dimensional view of a standard section of a door cross beam end of the present invention.

[0019] Figure 3 It is a three-dimensional diagram of a standard section at the top of a door post of the present invention.

[0020] Figure 4 It is an installation diagram of the anti-collision guide device of the present invention.

[0021] Figure 5 It is a front view of the movable plate of the anti-collision guide device of the present invention.

[0022] Figure 6 It is a three-dimensional diagram of a doorpost standard section of the present invention.

[0023] Figure 7 It is a three-dimensional diagram of a standard section of a door beam of the present invention.

[0024] Figure 8 It is a packaging diagram of the present invention. DETAILED DESCRIPTION

[0025] The present invention will be further described in detail below in conjunction with specific implementations and with reference to the accompanying drawings. It should be emphasized that the following description is merely exemplary and is not intended to limit the scope of the present invention and its application.

[0026] Non-limiting and non-exclusive embodiments will be described with reference to the following figures, wherein like reference numerals refer to like parts unless otherwise specifically stated.

[0027] like Figure 1 The tool-type self-lifting construction site gate shown includes a door crossbeam 300 and door posts 100 supporting both ends of the door crossbeam 300, and the door crossbeam 300 and the door posts 100 are respectively connected by multiple sections of standard sections. The mating surfaces between the standard sections are provided with bolt holes and are fixed by bolt connection. The lower end of the door post 100 is connected to the cast-in-place concrete foundation 1, and the cast-in-place concrete foundation 1 is pre-set with anchor bolts 2 for installing the door post 100. The door crossbeam 300 is inserted into the door post 100, so that the door crossbeam 300 is guided by the door post 100 to move the door crossbeam 300 along the length direction of the door post 100, thereby adjusting the height of the door crossbeam 300. The connection between the door crossbeam 300 and the door post 100 is achieved in this way, refer to Figure 2 The standard section for connecting the door cross beam 300 and the door post 100 is the door cross beam end standard section 400; the door cross beam end standard section 400 is provided with an installation opening 401 on the upper and lower sides. When pre-installing the construction site gate, firstly, the lower end of the door post 100 is threadedly connected to the cast-in-place concrete foundation 1, and then the installation opening 401 of the door cross beam end standard section 400 is installed, and two door cross beam end standard sections 400 are connected to form a complete door cross beam 300 by using multiple door cross beam standard sections, and the door cross beam 300 is lifted by a lifting device, and fixed after it is raised to the position. The installation opening 401 of the door cross beam end standard section 400 is provided with installation holes on the opposite sides, and corresponding round steel 19 is arranged in the installation holes. The round steel 19 passes through the two installation holes arranged oppositely on the installation opening along the length direction of the door cross beam end standard section 400, and is used to fix the door cross beam 300 and the door post 100, and the round steel 19 is in the same direction as the door cross beam 300. The material used for the door post 100 and the door cross beam 300 is angle steel.

[0028] Reference Figure 3The standard section connecting the door post 100 and the door cross beam 300 is the door post top standard section 200. The upper part of the door post top standard section 200 of the two door posts is provided with an electric hoist 12, and the electric hoist 12 is fixedly connected to the upper part of the door post top standard section 200 through two channel steels 11, and the electric hoist 12 is arranged on the opposite side of the two door posts 100. The size of the installation opening 401 is larger than the combined size of the door post top standard section 200 and the electric hoist 12, so that the door cross beam 300 can move along the length direction of the door post 100 through its installation opening 401. In order to strengthen the connection between the door post 100 and the door cross beam 300, a connection hole 131 corresponding to the installation hole position of the installation opening 401 of the door cross beam end standard section 400 is arranged at the upper end of the door post top standard section 200. After the door cross beam 300 is lifted into place along the door post 100 by the electric hoist 12, the round steel 19 is passed through the mounting hole and the connecting hole 131 to fix the position of the door cross beam 300 and the door post 100. Lifting rings are set on both sides of the width direction of the standard section 400 at the end of the door cross beam, and the two ends of the lifting rope 600 are connected to the two lifting rings 24, and then the lifting rope 600 is hooked with the hook of the electric hoist 12. When lifting the door cross beam 300, the electric hoist 12 can quickly slide to the middle of the lifting rope 600. During the lifting process, the door cross beam 300 swings left and right, and it is easy to collide with the bolt head on the door post 100, which makes lifting inconvenient.

[0029] To solve this problem, the current choice is to increase the size of the installation opening 401, but this will increase the manufacturing cost of the door beam 300. To this end, an anti-collision guide device is designed, referring to Figure 4The anti-collision guide device includes an angle plate 3, a spring 4, and a clip mechanism. The angle plate 3 is welded into an angle by two flat plates, and its angle is 120-160°. The joint of the two flat plates is a circular arc transition surface. The clip mechanism is an η-shaped structure, which includes a fixed plate 5, a movable plate 51, and a locking bolt 6. The upper end of the fixed plate 5 is a hook 52. The upper end of the movable plate 51 is plugged into the end of the hook 52 of the fixed plate 5, and the upper part of the movable plate 51 and the fixed plate 5 are provided with positioning holes 510 corresponding to each other. The locking bolt 6 is inserted into the two positioning holes 510 and screwed with nuts to fix. There are two springs 4, one end of the two springs 4 is respectively fixed to the lower end of the fixed plate 5 and the lower end of the movable plate 51; the other ends of the two springs 4 are respectively fixed to the two flat plates of the angle plate 3. In this way, when in use, first separate the movable plate 51 and the fixed plate 5, and then hang the entire anti-collision guide device on the angle steel 23 (cross bar of the standard section at the end of the door beam) at the bottom of the standard section 400 at the end of the door beam, and clamp the vertical surface of the angle steel 23 between the fixed plate 5 and the movable plate 51, and the horizontal surface of the angle steel 23 is located between the two springs 4; insert the movable plate 51 into the hook 52 end of the fixed plate 5, tighten the nut on the locking bolt 6, and the anti-collision guide device can be clamped on the angle steel 23; at this time, the arc transition surface of the angle plate 3 points to the door post 100. An anti-collision guide device is provided on each side of the door post 100, and the door post 100 is located between the two anti-collision guide devices; in the process of lifting the door cross beam 300, when the door post 100 collides with the door cross beam 300, the angle plate 3 first hits the door post 100, and can pass smoothly by utilizing the elastic deformation of the spring 4 and the arc transition surface of the angle plate 3, without causing the door cross beam 300 to stop instantly. By providing an anti-collision guide device, the size of the door cross beam 300 can be further reduced, saving steel. In a preferred embodiment, a horizontal connecting shaft 7 is provided at the end of the hook portion 52 of the fixed plate 5, and a radial limiting surface is provided at the end of the connecting shaft; the upper end of the movable plate 51 is a hook portion, and is hooked on the connecting shaft 7, thereby strengthening the connection between the movable plate 51 and the fixed plate 5.

[0030] The standard section is a cubic structure, and its components are connected and fixed by bolts. The upper and lower end faces of the standard section are provided with the bolt holes, and the side faces are fixed with connecting plates by bolts. The side faces of the standard section are provided with reinforcing diagonal bars, and the two adjacent diagonal bars are arranged in a V-shaped structure. The connecting plates include three-hole connecting plates 8, four-hole connecting plates 9, and six-hole connecting plates 22. The corresponding connecting plates are used for fixing according to the connection conditions. For details, refer to Figure 6The standard door post section includes 4 standard door post section uprights 10, 8 standard door post section cross bars 101, 4 standard door post section diagonal bars 103, and a number of connecting plates and bolts that connect and fix the standard door post section uprights 10, the standard door post section cross bars 101, and the standard door post section diagonal bars 103. The two ends of the standard door post section uprights 10 are respectively connected to the 4 standard door post section cross bars 101 to form a cubic structure, and one standard door post section diagonal bar 103 is respectively fixed on the four sides of the cube, and the adjacent standard door post section diagonal bars are arranged in a V shape. The standard door post section cross bars 101 are also provided with a number of bolt holes 102 for connecting two standard door post sections. Figure 7 The door cross beam standard section includes 4 door cross beam standard section horizontal bars 16, 8 door cross beam standard section vertical bars 17, 4 door cross beam standard section diagonal bars 21, and a number of connecting plates and bolts that connect and fix the door cross beam standard section horizontal bars 16, the door cross beam standard section vertical bars 17, and the door cross beam standard section diagonal bars 21. The two ends of the door cross beam standard section horizontal bars 16 are respectively connected to the 4 door cross beam standard section vertical bars 17 to form a cubic structure. One door cross beam standard section diagonal bar 21 is fixed to each of the four sides of the cube, and the adjacent door cross beam standard section diagonal bars 21 are arranged in a V-shaped layer. The door cross beam standard section vertical bars 17 are also provided with a number of bolt holes 171 for connecting two door cross beam standard sections.

[0031] Reference Figure 8 After the door cross beam 300 is hoisted and fixed in place, a panel 30 is attached to the outer surface of the door post 100 and the door cross beam 300 to close them.

[0032] The assembly method of a tool-type self-lifting construction site gate comprises the following steps: first, a concrete foundation 1 is cast in place at the installation position of the gate, and the cast-in-place concrete foundation 1 is also pre-buried with anchor bolts 2 for connecting the standard sections of the door posts; a corresponding number of standard sections of the door posts are stacked according to the design height of the gate, and the standard section 200 at the top of the door posts is arranged at the uppermost end; then, a standard section 400 at the end of the door beam is assembled at the bottom of the door post 100, and two standard sections at the end of the door beam are connected by using the standard section of the door beam; the hook of the electric hoist 12 is lowered and the rope 600 of the standard section 400 at the end of the door beam is hooked; the electric hoist 12 is then started to lift the door beam 300, and after the door beam 300 is lifted into place, the position of the door beam 300 and the door post 100 is fixed by using the round steel 19 through the installation hole and the connection hole; finally, the panel 30 is affixed to the outer surface of the door post 100 and the door beam 300 to close; and the installation of the construction site gate is completed.

[0033] Those skilled in the art will appreciate that numerous variations to the above description are possible, and that the examples and figures are intended only to describe one or more specific implementations.

[0034] Although what is considered as exemplary embodiments of the present invention has been described and described, it will be understood by those skilled in the art that various changes and substitutions may be made thereto without departing from the spirit of the present invention. In addition, many modifications may be made to adapt specific situations to the teachings of the present invention without departing from the central concept of the present invention described herein. Therefore, the present invention is not limited to the specific embodiments disclosed herein, but the present invention may also include all embodiments and their equivalents that fall within the scope of the present invention.

Claims

1. A tool-type self-lifting construction site gate, comprising a gate beam and gate posts supporting both ends of the gate beam, wherein the gate beam and the gate posts are respectively formed by connecting a plurality of standard sections, and are characterized by: An electric hoist is fixed to the upper end of the door post, and the standard section is assembled into a cubic structure by angle steel, connecting plate, and locking bolts; a hanging rope is provided at the standard section of the door beam, and is directly below the electric hoist; the hook of the electric hoist hooks the hanging rope; It also includes an anti-collision guide device, which is installed on the front and rear sides of the door beam and corresponds to the front and rear sides of the door post; The anti-collision guide device includes an angle plate, a spring, and a clip mechanism. The angle plate is fixed into an angle by two flat plates, and its angle is 120~160°; the clip mechanism is an η-shaped structure, which includes a fixed plate, a movable plate, and a locking bolt. The upper end of the fixed plate is a hook, and the upper end of the movable plate is hinged to the hook end of the fixed plate, and the upper part of the movable plate and the fixed plate are provided with positioning holes corresponding to each other; the locking bolt is passed through the two positioning holes and is screwed on with a nut to fix; there are two springs, one end of the two springs is fixed to the lower end and The lower end of the movable plate; the other ends of the two springs are respectively fixed on the two flat plates of the angle plate; when in use, first separate the movable plate and the fixed plate, then hang the entire anti-collision guide device on the angle steel at the bottom of the standard section at the end of the door beam, clamp the vertical surface of the angle steel between the fixed plate and the movable plate, and the horizontal surface of the angle steel is located between the two springs; insert the movable plate into the hook end of the fixed plate, tighten the nut on the locking bolt, and the anti-collision guide device can be clamped on the angle steel; the arc transition surface of the angle plate points to the door post; an anti-collision guide device is provided on each side of the door post.

2. The tool-type self-lifting construction site gate according to claim 1, characterized in that: The standard section connecting the door cross beam and the door post is the standard section at the end of the door cross beam; the upper and lower surfaces of the standard section at the end of the door cross beam are provided with installation openings for assembling the door post, and installation holes are provided at positions opposite to the installation openings of the standard section at the end of the door cross beam; the standard section connecting the door post and the door cross beam is the standard section at the top of the door post; the upper parts of the two standard sections at the top of the door post are provided with the electric hoist, and the electric hoist is arranged on the opposite side of the door post; the size of the installation opening is larger than the combined size of the standard section at the top of the door post and the electric hoist; the upper end of the standard section at the top of the door post is provided with a connecting hole corresponding to the position of the installing hole of the installing opening of the standard section at the end of the door cross beam; the positions of the door cross beam and the door post are fixed by passing round steel through the installing hole and the connecting hole.

3. The tool-type self-lifting construction site gate according to claim 1, characterized in that: The joint of the two flat sheets is an arc transition surface.

4. The tool-type self-lifting construction site gate according to claim 1, characterized in that: The hook end of the fixed plate is provided with a horizontal connecting shaft, and the end of the connecting shaft is provided with a radial limiting surface; the upper end of the movable plate is a hook, and is hooked on the connecting shaft.

5. The tool-type self-lifting construction site gate according to claim 1, characterized in that: The connection surface of each standard section is provided with a plurality of bolt holes, and the side surface of the standard section is provided with an inclined rod, and two adjacent inclined rods are arranged in a V-shaped structure.

6. The tool-type self-lifting construction site gate according to claim 1, characterized in that: The connecting plates include three-hole connecting plates, four-hole connecting plates, and six-hole connecting plates, and corresponding connecting plates are used for fixing according to the connection conditions.

7. A method for assembling the tool-type self-lifting construction site door according to claim 1, characterized in that: The method comprises the following steps: firstly, a concrete foundation is cast at the installation position of the gate, and anchor bolts for connecting the standard sections of the gate posts are also pre-buried on the cast-in-place concrete foundation; a corresponding number of standard sections of the gate posts are stacked according to the design height of the gate, and the standard section at the top of the gate posts is arranged at the uppermost end; then, the standard section at the end of the gate beam is assembled at the bottom of the gate post, and two standard sections at the end of the gate beam are connected by using the standard section of the gate beam; the hook of the electric hoist is lowered and the rope of the standard section at the end of the gate beam is hooked; then, the electric hoist is started to lift the gate beam, and after lifting into place, the position of the gate beam and the gate post is fixed by using round steel through the installation hole and the connection hole; finally, panels are affixed to the outer surfaces of the gate post and the gate beam to close them; and the installation of the construction site gate is completed.

Citation Information

Patent Citations

  • Recyclable standard knot type construction site bar

    CN108035436A

  • Tool type self-lifting construction site gate

    CN214532738U