Prefabricated staircase stacking rack and use method
By designing a prefabricated staircase stacking frame that includes side steel plates, bottom steel plates, and multiple groups of staircases, the problem of hidden safety hazards and space waste during the existing technologies has been solved. Standing and transportation of stairs.
Patent Information
- Application Number
- CN202011406101.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-03
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2040-12-03
AI Technical Summary
Existing prefabricated stairs are prone to cracks and safety hazards during stacking and transportation, and the lack of standard stacking racks leads to waste and restriction of space.
A prefabricated staircase stacking frame is designed, including the left and right symmetrical side steel plates, bottom steel plates, and multiple groups of staircase stress platforms. Through the structure of the stringing platform of oblique and level, ensure the stability and safety of the stacking and transportation of stacks and transportation. sex.
Effectively solve the cracks and safety problems that prefabricated stairs may occur during stacking and transportation, and achieve a more standardized, safe and efficient staircase stacking, saving space, and suitable for factories and transportation scenarios.
Smart Images

Figure CN112660672B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a stacking rack and a use method, in particular to a prefabricated staircase stacking rack suitable for storage of assembled components and a use method. Background Art
[0002] At present, prefabricated stairs are usually placed in layers on the square timber on the ground. This method has great disadvantages. Stairs are bending components. The stacked stairs transfer the load to the lower stairs layer by layer. Therefore, the lower stairs are prone to cracks at the bottom of the stair treads, especially at the junction of the stair treads and the platform. In addition, if the bearing capacity of the foundation is poor, the safety awareness of the factory construction workers and the management staff are negligent in management, it is easy to collapse due to uneven settlement of the foundation, causing safety problems. At the same time, since there is no standard stacking rack, the prefabricated stairs are only placed on the square timber, and the number of stairs that can be placed at the same position is limited. If a large number of stairs are produced in one batch, more space is needed to stack the stairs, resulting in a waste of space. Summary of the invention
[0003] In view of the shortcomings of the above-mentioned technology, a prefabricated staircase stacking rack with a simple structure and easy use and a method of use are provided, which effectively solve the problems of cracks and easy collapse and insecurity during the stacking and transportation of prefabricated stairs, thereby making the stacking of prefabricated stairs more standardized, safer and more efficient, thereby avoiding unnecessary expenses or losses.
[0004] In order to solve the above technical problems, the prefabricated staircase stacking frame of the present invention comprises two side steel plates arranged symmetrically on the left and right, the bottom of the two side steel plates is provided with a bottom steel plate connecting the two side steel plates, the two side steel plates and the bottom steel plate constitute an external support frame, the two side steel plates are arranged inclined to both sides, and the two sides of the two side steel plates are respectively provided with a support structure, and the stability is ensured by the support structure, the support structure comprises a channel steel diagonal brace a and a channel steel diagonal brace b, wherein the acute angle structure formed by one end of the channel steel diagonal brace a and the channel steel diagonal brace b contacts the ground, and the other ends of the two sides are in contact with the ground. It is connected to the outer side of the side steel plate, the channel steel diagonal brace b is arranged on the outer side, the channel steel diagonal brace a is arranged on the inner side, a round steel pipe for fixing the two transversely arranged is arranged between the channel steel diagonal brace a and the channel steel diagonal brace b, and multiple groups of stair force-bearing platforms for placing prefabricated stairs are arranged between the two side steel plates. The stair force-bearing platforms include multiple upper stair force-bearing platforms for placing prefabricated stairs arranged on the left side steel plate, and multiple lower stair force-bearing platforms arranged on the right steel plate. The multiple upper stair force platforms and the multiple lower stair force platforms are highly matched and arranged in pairs.
[0005] The multiple upper stress-bearing platforms of the stairs include an oblique stress-bearing platform steel plate, both ends of which are connected at an angle to the side steel plate 1, and the top surface is processed into a horizontal structure to support the placement of prefabricated stairs, and a steel wire rope is provided on the inner side of the angle of the oblique stress-bearing platform steel plate to connect and reinforce the oblique stress-bearing platform steel plate with the side steel plate on the left, and a steel rib is provided on the outer side of the angle to support the oblique stress-bearing platform steel plate to prevent local damage to the root of the oblique stress-bearing steel plate; no steel rib is provided at the outer angle of the lowest oblique stress-bearing platform steel plate, and a vertical support channel steel a is provided on the outer side of the angle between the oblique stress-bearing platform steel plate and the bottom steel plate, and an oblique brace steel pipe a is provided between the connection point of the vertical support channel steel a with the bottom steel plate and the connection point of the oblique stress-bearing platform steel plate with the side steel plate on the left to provide triangular support.
[0006] The multiple lower stress-bearing platforms of the stairs include a horizontal stress-bearing steel plate arranged on the side steel plate on the right side and flush with the horizontal structural height of the oblique stress-bearing platform steel plate. A plurality of oblique bracing steel pipes b are arranged between the bottom of the horizontal stress-bearing steel plate and the side steel plate on the right side to increase the supporting force. A vertical supporting channel steel b is also vertically arranged between the lowest horizontal stress-bearing steel plate and the bottom steel plate.
[0007] The horizontal length of the stair force-bearing platform increases from top to bottom and is used to place stairs with different stair lengths.
[0008] Four diagonal bracing steel pipes b of the horizontal stress-bearing steel plate are symmetrically welded on both sides to support the horizontal stress-bearing steel plate.
[0009] A pull ring for connecting with a crane is welded on the left side steel plate between the multiple upper stress-bearing platforms of the stairs, and a pull ring for connecting with a crane is welded on the right side steel plate between the multiple lower stress-bearing platforms of the stairs, and the pull ring on the left side steel plate matches the pull ring on the right side steel plate in horizontal height.
[0010] A method for using a prefabricated staircase stacking rack, the steps are as follows:
[0011] aFirstly, use the pull ring to connect with the crane, place the stacking racks of corresponding sizes processed in batches according to the specifications of the prefabricated stairs in the component stacking site and arrange them neatly, and then number the load-bearing platform of each staircase on each stacking rack;
[0012] b. Paste the QR code with complete information on the prefabricated stairs that need to be stacked and stored and mark the corresponding position. Hang the prefabricated stair components on the stair bearing platform of the stair stacking rack according to the production date and the length of the stair section, and place them from low to high. Each stair bearing platform can stack up to two prefabricated stairs, of which the lower part of the prefabricated stair is placed on the lower bearing platform of the stair, and the upper part is placed on the upper bearing platform of the stair;
[0013] c. After the prefabricated stairs are transported away from the rack, repeat step b to stack the prefabricated stairs produced in the first step;
[0014] d. When the prefabricated stairs need to be transported by a transport vehicle, connect the pull ring to the crane, move the prefabricated staircase stacking rack to the transport vehicle, and then use a steel wire rope to pass through the pull ring to tie the prefabricated staircase stacking rack and the transport vehicle together to prevent the stairs from sliding during transportation. Finally, place the stairs on the rack and fix them.
[0015] Beneficial effects: The device of the present application has a simple structure and is easy to use. The prefabricated stairs are reasonably stressed, which reduces damage to the stairs during placement and solves the problem of cracks easily appearing when stacking prefabricated staircase components. It can realize vertical stacking of multiple staircase components at the same time, saving space. It can be used not only to stack prefabricated stairs in factories, but also to stack stairs on transport vehicles during transportation. It is highly practical and worthy of promotion and use. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a front view of the prefabricated staircase stacking rack of the present invention;
[0017] Figure 2 It is a side view of the prefabricated staircase stacking rack of the present invention;
[0018] Figure 3 for Figure 1 1-1 cross-sectional view.
[0019] In the figure: 1-side steel plate; 2-bottom steel plate; 3-channel steel diagonal brace a; 4-channel steel diagonal brace b; 5-round steel pipe; 6-diagonal force-bearing steel plate; 7-steel rib plate; 8-steel wire rope; 9-vertical support channel steel a; 10-diagonal brace steel pipe a; 11-horizontal force-bearing steel plate; 12-diagonal brace steel pipe b; 13-vertical support channel steel b; 14-prefabricated stairs; 15-pull ring. DETAILED DESCRIPTION
[0020] The present invention is further described below in conjunction with the embodiments, but it should not be understood that the above subject matter of the present invention is limited to the following embodiments. Without departing from the above technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the art, which should all be included in the protection scope of the present invention.
[0021] like Figure 1 and Figure 2As shown, the prefabricated staircase stacking frame includes two side steel plates 1 symmetrically arranged on the left and right, and the bottom of the two side steel plates 1 is provided with a bottom steel plate 2 connecting the two together, and the two side steel plates 1 and the bottom steel plate 2 constitute an external support frame, and the two side steel plates 1 are inclined to both sides, and support structures are respectively provided on both sides of the two side steel plates 1, and the stability is ensured by the support structure, and the support structure includes a channel steel diagonal brace a3 and a channel steel diagonal brace b4, wherein the acute angle structure formed by one end of the channel steel diagonal brace a3 and the channel steel diagonal brace b4 contacts the bottom steel plate, and the two side steel plates 1 are inclined to both sides ... The other end is connected to the outside of the side steel plate 1, the channel steel diagonal brace b4 is arranged on the outside, the channel steel diagonal brace a3 is arranged on the inside, and a round steel pipe 5 is arranged between the channel steel diagonal brace a3 and the channel steel diagonal brace b4 to fix the two horizontally arranged round steel pipes 5, and multiple groups of stair force platforms are arranged between the two side steel plates 1, and the stair force platforms include multiple upper stair force platforms arranged on the left side steel plate 1, and multiple lower stair force platforms arranged on the right side steel plate 1, and the multiple upper stair force platforms and multiple lower stair force platforms are highly matched and arranged in pairs. The horizontal length of the stair force platform increases from top to bottom, and is used to place stairs with different stair lengths.
[0022] The multiple upper stress-bearing platforms of the stairs include an oblique stress-bearing platform steel plate 6, both ends of which are connected at an angle to the side steel plate 1, and the top surface is processed into a horizontal structure to support the placement of the prefabricated stairs 14. A steel wire rope 8 is provided on the inner side of the angle of the oblique stress-bearing platform steel plate 6 to connect and reinforce the oblique stress-bearing platform steel plate 6 and a steel rib plate 7 is provided on the outer side of the angle to support the oblique stress-bearing platform steel plate 6 to prevent local damage to the root of the oblique stress-bearing steel plate 6; no steel rib plate 7 is provided at the outer angle of the lowest oblique stress-bearing platform steel plate 6, and a vertical support channel steel a9 is provided on the outer side of the angle between the oblique stress-bearing platform steel plate 6 and the bottom steel plate 2, and an oblique bracing steel pipe a10 is provided between the connection point of the vertical support channel steel a9 and the bottom steel plate 2 and the connection point of the oblique stress-bearing platform steel plate 6 and the side steel plate 1 on the left to form a triangular support. Multiple stair lower stress platforms include a horizontal stress steel plate 11 which is arranged on the side steel plate 1 on the right and is flush with the horizontal structural height of the oblique stress platform steel plate 6. A plurality of oblique bracing steel pipes b12 are arranged below the horizontal stress steel plate 11 and between the side steel plate 1 on the right to increase the supporting force. Four oblique bracing steel pipes b12 of the horizontal stress steel plate 11 are symmetrically welded on the left and right sides to support the horizontal stress steel plate 11. A vertical supporting channel steel b13 is also vertically arranged between the lowest horizontal stress steel plate 11 and the bottom steel plate 2. A pull ring 15 for connecting to a crane is welded on the side steel plate 1 on the left between multiple stair upper stress platforms. A pull ring 15 for connecting to a crane is welded on the side steel plate 1 on the right between multiple stair lower stress platforms. The pull ring 15 on the left side steel plate 1 matches the pull ring 15 on the right side steel plate 1 in horizontal height.
[0023] A method for using a prefabricated staircase stacking rack, the steps are as follows:
[0024] a First, use the pull ring 15 to connect with the crane, place the stacking racks of corresponding sizes processed in batches according to the specifications of the prefabricated staircases in the component stacking site and arrange them neatly, and then mark the load-bearing platform of each staircase on each stacking rack;
[0025] b. Paste the QR code with complete information on the prefabricated stairs that need to be stacked and stored and mark the corresponding position. Hang the prefabricated stair components on the stair bearing platform of the stair stacking rack according to the production date and the length of the stair section, and place them from low to high. Each stair bearing platform can stack up to two prefabricated stairs, of which the lower part of the prefabricated stair is placed on the lower bearing platform of the stair, and the upper part is placed on the upper bearing platform of the stair;
[0026] c. After the prefabricated stairs are transported away from the rack, repeat step b to stack the prefabricated stairs produced in the first step;
[0027] d. When the prefabricated staircase needs to be transported by a transport vehicle, the pull ring 15 is connected to the crane, and the prefabricated staircase stacking rack is moved and hoisted onto the transport vehicle. Then, a steel wire rope is passed through the pull ring 15 to tie the prefabricated staircase stacking rack and the transport vehicle together to prevent the staircase from sliding during transportation. Finally, the staircase is placed on the rack and fixed. Example
[0028] A prefabricated staircase stacking rack and a method of use, the specific steps of use are as follows:
[0029] 1) Processing and manufacturing of steel plates, channel steels and steel pipes;
[0030] 2) Weld the two inclined steel plates to the bottom steel plate, and then weld the two ends of the channel steel diagonal brace to the bottom steel plate and the inclined steel plate respectively;
[0031] 3) Weld the internal load-bearing platform steel plate to the side steel plate according to the position designed in the drawing, and then weld the corresponding steel ribs, steel pipes 4) diagonal braces and bottom vertical support channel steel to the left and right load-bearing steel plates; pass the steel wire rope through the reserved holes on the side steel plates and the diagonal load-bearing steel plates and fix them; batch process the stacking racks of corresponding sizes according to the specifications of the prefabricated stairs, place the stacking racks in the component stacking site, and number each layer of all the stacking racks;
[0032] 5) Paste the QR code with complete information on the prefabricated staircase and mark the corresponding position. Hang the prefabricated staircase components on the bottom stacking rack according to the production date and the length of the staircase, and then hang them on the stacking racks on the second floor and other levels upwards. Note that at most 2 staircases can be stacked on each floor;
[0033] 6) The stacking rack has high strength, rigidity and stability and can be recycled. After a batch of prefabricated components are transported from the rack, the newly produced prefabricated stairs can be stacked on the rack. Example
[0034] A prefabricated staircase stacking rack and a method of use, the specific steps of use are as follows:
[0035] 1) According to the specifications of the prefabricated staircase, stacking racks of corresponding sizes are batch-processed, and a total of four pull rings 15 are welded on the inner side of each side steel plate 1 of the stacking rack; numbers are marked on the outer side of each layer of the side steel plate 1 of all the stacking racks, and the lifting wire rope is passed through the pull ring (15) of the stacking rack, and the wire rope is hooked with a crane hook to lift the stacking rack onto a flatbed truck;
[0036] 2) Paste the QR code with complete information on the prefabricated staircase and mark the corresponding position. Hang the prefabricated staircase components on the bottom stacking rack according to the production date and the length of the staircase, and then hang them on the stacking racks on the second floor and other levels upwards. Note that at most 2 staircases can be stacked on each floor;
[0037] 3) Pass the wire rope through the pull ring and securely fix it on the pallet truck to prevent the stacking rack from moving. Pass the wire rope through the pull ring and tie the prefabricated stairs to the side steel plates to prevent the stairs from sliding during transportation.
[0038] The present invention has the following innovative features:
[0039] The present invention is composed of two parts: an external support frame and an internal force-bearing platform. The resting platforms at both ends of the prefabricated staircase are placed on the left and right force-bearing platforms. The force state is close to the force state in normal use. Therefore, the present invention can also be used to check whether the safety and applicability of the staircase can be guaranteed during the stacking stage. The deadweight of the staircase is transmitted to the external support frame through the internal force-bearing platform, and then to the foundation through the bottom steel plate. The force is clear and reasonable.
[0040] The same stacking rack is divided into multiple layers, and multiple staircase components of different sizes can be placed vertically at the same time, saving space;
[0041] The rack is recyclable and does not require any foundation treatment, so it can be used on general sites.
[0042] It can not only be used for stacking prefabricated stairs, but also for transportation. You only need to lift the entire rack onto the transport vehicle, and then place the stairs on the rack and fix them.
Claims
1. A prefabricated staircase stacking rack, characterized in that: The invention comprises two side steel plates (1) arranged symmetrically on both sides, a bottom steel plate (2) connecting the two side steel plates (1) is provided at the bottom of the two side steel plates (1), the two side steel plates (1) and the bottom steel plate (2) form an external support frame, the two side steel plates (1) are arranged to be inclined to both sides, and support structures are provided on both sides of the two side steel plates (1), and stability is ensured by the support structures, wherein the support structures comprise a channel steel diagonal brace a (3) and a channel steel diagonal brace b (4), wherein the acute angle structure formed by one end of the channel steel diagonal brace a (3) and the channel steel diagonal brace b (4) contacts the bottom steel plate (2), and the other ends of the two are in contact with the side steel The outer side of the plate (1) is connected, the channel steel diagonal brace b (4) is arranged on the outer side, the channel steel diagonal brace a (3) is arranged on the inner side, and a round steel pipe (5) is arranged between the channel steel diagonal brace a (3) and the channel steel diagonal brace b (4) for fixing the two transversely arranged round steel pipes, and a plurality of stair bearing platforms for placing prefabricated stairs are arranged between the two side steel plates (1), and the stair bearing platforms include a plurality of stair upper bearing platforms arranged on the side steel plate (1) on the left side, and a plurality of stair lower bearing platforms arranged on the side steel plate (1) on the right side, and the plurality of stair upper bearing platforms and the plurality of stair lower bearing platforms are highly matched and arranged in pairs; The multiple upper stress-bearing platforms of the stairs include an oblique stress-bearing platform steel plate (6), the two ends of the oblique stress-bearing platform steel plate (6) are connected to the side steel plate (1) at an angle, and the top surface is processed into a horizontal structure for supporting the placement of the prefabricated stairs (14). A steel wire rope (8) is provided on the inner side of the angle of the oblique stress-bearing platform steel plate (6) to connect and reinforce the oblique stress-bearing platform steel plate (6) and the side steel plate (1) on the left side, and a steel rib plate (7) is provided on the outer side of the angle to support the oblique stress-bearing platform steel plate (6). To prevent local damage to the root of the oblique force-bearing platform steel plate (6); the outer angle of the lowest oblique force-bearing platform steel plate (6) is not provided with a steel rib plate (7); a vertical support channel steel a (9) is provided on the outer side of the angle between the oblique force-bearing platform steel plate (6) and the bottom steel plate (2); and an oblique bracing steel pipe a (10) is provided between the connection point between the vertical support channel steel a (9) and the bottom steel plate (2) and the connection point between the oblique force-bearing platform steel plate (6) and the left side steel plate (1) to provide triangular support.
2. The prefabricated staircase stacking rack according to claim 1, characterized in that: The multiple stair lower load-bearing platforms include a horizontal load-bearing steel plate (11) arranged on the right side steel plate (1) and flush with the horizontal structural height of the inclined load-bearing platform steel plate (6); a plurality of inclined bracing steel pipes b (12) for increasing the supporting force are arranged between the lower portion of the horizontal load-bearing steel plate (11) and the right side steel plate (1); and a vertical supporting channel steel b (13) is also vertically arranged between the lowest horizontal load-bearing steel plate (11) and the bottom steel plate (2).
3. The prefabricated staircase stacking rack according to claim 2, characterized in that: The horizontal length of the stair force-bearing platform increases from top to bottom and is used to place stairs with different stair lengths.
4. The prefabricated staircase stacking rack according to claim 2, characterized in that: Four diagonal bracing steel pipes b (12) are symmetrically welded on the left and right sides of the horizontal force-bearing steel plate (11) to support the horizontal force-bearing steel plate (11).
5. The prefabricated staircase stacking rack according to claim 1, characterized in that: A pull ring (15) for connecting to a crane is welded on the left side steel plate (1) between the plurality of upper staircase load-bearing platforms, and a pull ring (15) for connecting to a crane is welded on the right side steel plate (1) between the plurality of lower staircase load-bearing platforms, wherein the pull ring (15) on the left side steel plate (1) matches the pull ring (15) on the right side steel plate (1) in horizontal height.
6. A method for using the prefabricated staircase stacking rack according to any one of claims 1 to 5, characterized in that Here are the steps: a. First, the pull ring (15) is used to connect with the crane, and the stacking racks of corresponding sizes processed in batches according to the specifications of the prefabricated staircase are placed in the component stacking site and arranged neatly, and then the load-bearing platform of each staircase layer of each stacking rack is numbered; b. Paste the QR code with complete information on the prefabricated stairs that need to be stacked and stored and mark the corresponding position. Hang the prefabricated stair components on the stair bearing platform of the stair stacking rack according to the production date and the length of the stair section, and place them from low to high. Each stair bearing platform can stack up to two prefabricated stairs, of which the lower part of the prefabricated stair is placed on the lower bearing platform of the stair, and the upper part is placed on the upper bearing platform of the stair; c. After the prefabricated stairs are transported away from the rack, repeat step b to stack the newly produced prefabricated stairs; d. When the prefabricated staircase needs to be transported by a transport vehicle, the pull ring (15) is connected to the crane, and the prefabricated staircase stacking rack is moved and hoisted onto the transport vehicle. Then, a steel wire rope is passed through the pull ring (15) to tie the prefabricated staircase stacking rack and the transport vehicle together to prevent the staircase from sliding during transportation. Finally, the staircase is placed on the rack and fixed.
Citation Information
Patent Citations
Improved combined adjustable prefabricated stair showing stand
CN210067478U
And bracket is used for storing vertical plate prefabricated parts
CN211845639U
Precast stair stacking frame
CN215438087U
Cited By
Prefabricated stair stacking structure
CN224662070U