Steel reinforced concrete column-beam joint concrete pouring construction method
A construction method and concrete technology are applied in the field of concrete pouring construction of section steel concrete column and beam joints to achieve the effects of improving sealing effect, effective sealing and continuous pouring process.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2021-04-23
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention relates to the technical field of concrete pouring for house construction, in particular to a concrete pouring construction method for steel concrete column and beam joints. Background technique
[0002] At present, the steel-concrete composite structure has the advantages of high bearing capacity, significantly higher ductility than the reinforced concrete structure, durability, fire resistance, etc., so it is widely used in housing construction projects; but the steel structure beams and columns in the steel-concrete composite structure Occupying part of the space, there are many steel bars at the beam-column joints, and ordinary concrete is used for pouring. Not only is the aggregate particle size in the concrete strictly required, but the pouring process is also difficult. Because the steel bars at the beam-column joints are arranged vertically and horizontally, the vibrating equipment cannot Vibration is carried out, even if the pour...
Examples
Embodiment Construction
[0034] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided for more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art. It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and examples.
[0035] refer to figure 1 As shown, this embodiment provides a concrete pouring construction method for steel concrete column and beam joints, including:
[...