Humidification, drying and cooling integrated pelletizing machine

By integrating a steam generator and a burner in the rocker, combining airflow circulation and waste heat recovery, the problem of steam supply dependence in the existing technology is solved, self-supply steam and efficient drying are achieved, adapting to different fabric temperature needs, and reducing the Production cost and equipment volume.

CN112853666BActive Publication Date: 2024-12-24LIANYUNGANG LIANXU MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110173589.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-02-09
Publication Date
2024-12-24
Estimated Expiration
2041-02-09

AI Technical Summary

Technical Problem

The existing rocker relies on steam supply during humidification and drying, resulting in high usage costs, large equipment volume and unsafe, and cannot be used in places without steam supply, which limits the manufacturer's site selection.

Method used

A humidification, drying and cooling integrated rocker is designed, using a built-in steam generator and burner to achieve self-supply of steam and drying through airflow circulation and heat exchange components. Combined with waste heat recovery and intelligent wind speed control, the temperature is increased Regulation and energy efficiency.

Benefits of technology

It realizes self-supply of steam, reduces production costs, improves equipment compactness and safety, adapts to the temperature needs of different fabrics, and enhances drying and cooling efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112853666B_ABST
    Figure CN112853666B_ABST
Patent Text Reader

Abstract

The present invention relates to an integrated humidifying, drying and cooling grain shaker, comprising a grain shaker arranged in a housing, partition plates wrapping the roller are arranged on both sides of the grain shaker, a ventilation cavity is arranged between the upper parts of the two partition plates, an independent hot air generating chamber is formed between the partition plate on one side and the housing, an air inlet connected to the ventilation cavity is arranged on the upper part of the hot air generating chamber, an air flow drying system and a steam humidifying system are arranged in the hot air generating chamber; an air flow circulation chamber is formed between the partition plate on the other side and the housing, a centrifugal fan is arranged on one side of the bottom of the air flow circulation chamber, the centrifugal fan is connected to the hot air generating chamber through a circulation duct, an air outlet is arranged on the circulation duct, and a damper for controlling the air flow is arranged in the circulation duct. The overall structure of the device is compact, and it can produce steam by itself, and perform humidification process on fabrics, thereby reducing production costs, improving production efficiency, and meeting the production process requirements of different fabrics.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a pellet machine, in particular to a humidifying, drying and cooling integrated pellet machine. Background Art

[0002] In the textile industry, fabrics are subjected to processes such as napping, combing and shearing, and then are subjected to pilling to make the disordered fluff on the surface of the fabric curl into granules. Currently, the most commonly used pilling machine is a pilling machine, which is mainly used for pilling treatment of fabrics such as artificial fur, acrylic, and blankets. After high-temperature friction, the shrinkage fibers of the fabric are deformed, and the fluff on the surface of the fabric curls naturally, giving it a natural wool style, making it soft and elastic, thereby improving the quality of the product itself.

[0003] However, when using the existing pelletizer, the fabric must first be rolled at a certain humidity and temperature. The traditional humidification method is to spray steam. The steam has a certain temperature, so the fabric can be directly rolled. After rolling, it is dried. The drying process is done through a steam radiator, and then cooled down. The existing steam is provided by a thermal power plant, which has a high cost. At the same time, the transmission pipeline is long, and the steam temperature will be lost, generally about 100°C, which cannot meet the use temperature of various fabrics. In addition, the pelletizer cannot be used in places without steam supply, which brings limitations to the site selection of manufacturers.

[0004] The existing drying method uses natural gas to heat the air, such as patent No. 201821833035, named natural gas granulator. It can be seen from the disclosed technical solution that it has low energy consumption cost and can control the drying temperature. However, it still uses steam provided by the thermal power plant during the humidification process. In addition, the heater is located outside, its size is large, and the external temperature is high, which brings harm to the operator. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a humidifying, drying and cooling integrated granulator with reasonable structure, self-steam supply and self-drying in view of the deficiencies in the prior art.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] A humidifying, drying and cooling integrated shaker comprises a box body and a door. The front of the box body is provided with an opening. A shaker drum is provided in the box body. The barrel mouth of the shaker drum is connected with the opening. The door can cover the opening. The characteristics are:

[0008] Separation plates wrapping the roller are provided on both sides of the shaking roller, a ventilation cavity is provided between the upper parts of the two separation plates, an independent hot air generating chamber is formed between the separation plate on one side and the box body, an air inlet communicating with the ventilation cavity is provided on the upper part of the hot air generating chamber, and an airflow drying system and a steam humidification system are provided in the hot air generating chamber;

[0009] An air circulation chamber is formed between the partition plate on the other side and the box body. An air outlet connected to the shaking drum is arranged on the partition plate at the bottom of the air circulation chamber. A centrifugal fan is arranged on one side of the bottom of the air circulation chamber. The centrifugal fan is connected to the hot air generating chamber through a circulation duct. An air outlet is arranged on the circulation duct. A damper for controlling the air flow is arranged in the circulation duct.

[0010] The airflow drying system includes a first burner installed on the back of the box body and used to heat the air at the bottom of the hot air generating chamber. The heated hot air enters the particle shaking drum from the air inlet at the upper part of the hot air generating chamber for drying. Under the guidance of the centrifugal fan, part of the air is discharged into the airflow circulation chamber through the air outlet at the bottom of the drum, and then enters the hot air generating chamber again through the circulation pipe for heating, and the cycle continues.

[0011] The steam humidification system includes a steam generator arranged at the upper part of the hot air generating chamber, a steam outlet pipe connected to the steam generator is arranged at the ventilation cavity, the steam outlet pipe is arranged along the length direction of the grain shaking drum, and the steam outlet pipe is provided with a plurality of steam outlets arranged toward the grain shaking drum.

[0012] As a further scheme of the present invention: the steam generator is provided with a rectangular furnace body, a combustion chamber is provided at the lower part of the furnace body, a second burner is provided in the combustion chamber, a water storage tank is provided outside the combustion chamber, a water level gauge is connected to one side of the water storage tank, a water inlet is provided at the bottom of the water storage tank, a steam outlet is provided at the top, heat exchange channels are respectively provided between the two sides of the water storage tank and the outer wall of the furnace body, an exhaust port is provided at the top of the heat exchange channel, an exhaust pipe extending from the box body is connected to the exhaust port, the inner end of the combustion chamber is connected with the heat exchange channel, a plurality of groups of heat exchange components are arranged side by side from bottom to top on the water storage tank, each group of heat exchange components is provided with a plurality of heat exchange tubes with both ends passing through, the two ends of the heat exchange tubes are respectively connected with the heat exchange channels on both sides, a plurality of partitions are respectively provided in the heat exchange channels on both sides, so that every two adjacent groups of heat exchange components on this side are connected with the heat exchange channel between the two adjacent partitions, and the partitions in the heat exchange channels on both sides are staggered so that the plurality of groups of heat exchange components are connected in series from bottom to top at both ends.

[0013] As a further solution of the present invention, the heat exchange assembly is provided with 6 groups arranged side by side from bottom to top, each group is provided with 12 heat exchange tubes with both ends connected, and the total heat exchange area of ​​the heat exchange assembly is 3.0 m 2 -4.0m 2; Three partitions are provided in the heat exchange channel connected to the combustion chamber, and two partitions are provided in another corresponding heat exchange channel, so that the combustion chamber is connected to one end of the first group of heat exchange components, the other end of the first group of heat exchange components is connected to one end of the second group of heat exchange components, the other end of the second group of heat exchange components is connected to one end of the third group of heat exchange components, and so on.

[0014] As a further solution of the present invention: the steam outlet is connected to a condensate return pipe, the condensate return pipe is arranged on the top of the pelletizer casing, a pressure gauge and a pressure relief valve are installed on the condensate return pipe, a steam delivery pipe is connected to one side of the condensate return pipe, and the steam delivery pipe is connected to a steam outlet pipe arranged in the casing.

[0015] As a further solution of the present invention: the water inlet at the bottom of the water storage tank is connected to the water inlet pipe, the water inlet pipe is provided with a water pump, and the bottom of the water storage tank is also connected to a sewage pipe.

[0016] As a further solution of the present invention: the exhaust pipe is equipped with an exhaust valve, a waste heat recovery pipe is connected to the exhaust pipe below the exhaust valve, the end of the waste heat recovery pipe is arranged at the ventilation cavity of the two partition plates, and a control valve is installed on the waste heat recovery pipe. When the fabric is humidified, the exhaust valve is closed and the control valve is opened, so that the exhaust gas generated by the steam generator can pass through the waste heat recovery pipe and return to the pelletizing drum, thereby further quickly increasing the temperature in the drum to adapt to the processing temperature requirements of different varieties.

[0017] As a further solution of the present invention: the first burner and the second burner are both connected to the gas supply system; the first burner and the second burner are both provided with a flame detection device, an ignition electrode, an air inlet and a gas inlet, the gas supply system is provided with an air main pipeline, a gas inlet pipe and a combustion controller, the air main pipeline is connected to the fan, an air valve is installed on the air main pipeline connected to the fan, the fan is connected to an intelligent frequency converter for controlling its air intake, the frequency converter is connected to a temperature control meter via a signal line, and a temperature measuring probe is connected to the temperature control meter; the air inlets of the first burner and the second burner are respectively connected to air branch pipelines, the air branch pipelines are connected to the air main pipeline, and the air branch pipelines are both provided with electric air valves;

[0018] The gas inlets of the first burner and the second burner are respectively connected to gas branch pipelines, which are connected to the gas inlet pipe. Solenoid valves are respectively installed on the gas branch pipelines connected to the first burner and the second burner. A pressure regulating valve, a gas solenoid valve, an air-fuel ratio valve and a ball valve are sequentially arranged on the gas inlet pipe along the inlet direction. The air inlet of the air-fuel ratio valve is connected to an air inlet pipeline, which is connected to the main air pipeline.

[0019] The ignition electrode is connected to the igniter, and the combustion controller is connected to a flame detection control line and an ignition control line. Intermediate relays are respectively installed on the flame detection control line and the ignition control line. The flame detection devices and igniters of the first burner and the second burner are respectively connected to their respective intermediate relays through signal lines.

[0020] The two burners are controlled by a gas supply system at the same time, so that the gas supply systems of the two burners are integrated, and the components of the burners are reduced. It not only meets the operational requirements of the humidification and drying of the granulator, but also can control the combustion temperature as needed, reducing equipment investment and production costs.

[0021] As a further solution of the present invention: a dust cleaning chamber is provided below the shaking drum, the dust cleaning chamber is provided between two partition plates, an integrated drawer is installed in the dust cleaning chamber, the dust cleaning chamber is connected with the air circulation chamber through the air outlet on the partition plate, and a filter screen is provided on the air outlet.

[0022] As a further solution of the present invention: a cooling air port connected to the ventilation cavity is provided on the upper part of the partition plate of the air circulation chamber, a cooling air door opened outward is hinged on the cooling air port, and a cylinder driving the opening and closing of the cooling air door is provided on the back of the cooling air door. When the cooling operation is performed, the cooling air door is fully opened so that the drum can quickly dissipate heat and cool the fabric. When drying, the opening can be adjusted to discharge the water vapor in the drum and improve the drying efficiency.

[0023] As a further solution of the present invention: the centrifugal fan is connected to an intelligent frequency converter for controlling its air intake, so that the wind speed can be adjusted at any time during the three process steps of humidification, drying and cooling of the fabric. The centrifugal fan includes a fan blade and a motor for driving the fan blade to rotate. A circle of ridges is provided on the fan blade installation end face close to the motor. When the centrifugal fan is working, the ridges rotate to suck cold air from around the motor into the fan blade, so that the cold air wraps the motor, the motor is cooled, the service life of the motor is increased, and the high temperature damage phenomenon is reduced.

[0024] Compared with the prior art, the present invention has the following beneficial effects:

[0025] 1. This system sets a steam generator in the hot air generating room, which occupies a small space and makes the pellet machine compact. At the same time, it can realize self-sufficient steam for humidification. The steam output of this steam generator can reach 50Kg / h, with small gas consumption and high heat exchange efficiency. The steam temperature can be adjusted as needed, and the temperature control is precise, so as to adapt to the use of different fabrics; in addition, due to the high air temperature in the hot air generating room, the water in the steam generator can be kept warm, thereby increasing the basic temperature of heating, reducing energy consumption and saving costs.

[0026] 2. The first burner is arranged in the hot air generating chamber. Since the burner is arranged inside the pelletizer, the volume of the machine is greatly reduced. Meanwhile, the heat utilization rate is improved, the heat loss is reduced, and the safety factor of the operator is increased.

[0027] 3. The first burner and the second burner of the steam generator are controlled by a gas supply system to simultaneously control the operation of the two burners, so that the gas supply systems of the two burners are integrated, which not only meets the operating requirements of the humidification and drying of the granulator, but also can control the combustion temperature as needed, reducing equipment investment and production costs.

[0028] 4. A special cooling air door is set up. When cooling, the cooling air door is fully opened to allow the drum to quickly dissipate heat and cool the fabric. When drying, the opening can be adjusted to discharge the water vapor in the drum and improve the drying efficiency.

[0029] 5. Reuse the exhaust gas of the steam generator. When humidifying the fabric, close the exhaust valve and open the control valve so that the exhaust gas generated by the steam generator can pass through the waste heat recovery pipe and return to the pelletizing drum, thereby further quickly increasing the temperature in the drum to adapt to the processing temperature requirements of different varieties.

[0030] 6. The overall structure of this device is compact, and it can produce steam by itself to perform humidification process on the fabric, thereby reducing production costs, improving production efficiency, and meeting the production process requirements of different fabrics. The burner is used to heat the air for drying operations. The burner is located inside the box, so the heat utilization rate is high. A special cooling damper is set to improve the cooling efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A three-dimensional structural schematic diagram of the present invention;

[0032] Figure 2 A three-dimensional structural schematic diagram of the present invention;

[0033] Figure 3 for Figure 1 A right view structural diagram of ;

[0034] Figure 4 for Figure 1 A cross-sectional view of

[0035] Figure 5 for Figure 1 A schematic diagram of a top view structure;

[0036] Figure 6 A structural schematic diagram of a steam generator;

[0037] Figure 7 for Figure 6A right view structural diagram of ;

[0038] Figure 8 A structural diagram of a gas supply system. DETAILED DESCRIPTION

[0039] See also Figures 1 to 8 In an embodiment of the present invention, a humidifying, drying and cooling integrated grain shaker comprises a box body 1 and a box door 4, wherein a heat preservation layer is provided on the inner wall of the box body 1, an opening 2 is provided on the front of the box body 1, a grain shaker drum is provided in the box body 1, the barrel mouth of the grain shaker drum is connected to the opening 2, and the box door 4 can cover the opening 2.

[0040] Separation plates 11 wrapping the drum 12 are provided on both sides of the shaking drum, respectively. The separation plates 11 are made of stainless steel plates, and their upper ends are connected to the top of the box body 1, and their lower ends are connected to the bottom of the box body 1. A ventilation cavity 16 is provided between the upper parts of the two separation plates 11, and an independent hot air generating chamber 13 is formed between the separation plate 11 on one side and the box body 1. An air inlet communicating with the ventilation cavity 16 is provided on the upper part of the hot air generating chamber 13, and an airflow drying system and a steam humidification system are provided in the hot air generating chamber 13.

[0041] An air circulation chamber 15 is formed between the corresponding partition plate 11 on the other side and the box body 1. An air outlet connected to the particle shaking drum is provided on the partition plate 11 at the lower part of the air circulation chamber 15. A centrifugal fan 6 is provided on one side of the bottom of the air circulation chamber 15. The centrifugal fan 6 is connected to the hot air generating chamber 13 through a circulation duct 14. An air outlet is provided on the circulation duct 14. A damper 7 for controlling the airflow volume is installed in the circulation duct 14.

[0042] A dust cleaning chamber is provided below the shaking drum, and the dust cleaning chamber is provided between two partition plates 11. An integrated drawer 3 is installed in the dust cleaning chamber, and the dust cleaning chamber is connected to the air circulation chamber 15 through the air outlet on the partition plate 11, and a filter screen is provided on the air outlet. During the hot air circulation process, the lint of the fabric stays in the dust cleaning chamber and will not be sucked into the air circulation chamber 15, and is cleaned by cleaning the integrated drawer 3.

[0043] The airflow drying system includes a first burner 9 installed on the back of the box 1 for heating the air at the bottom of the hot air generating chamber 13. The heated hot air enters the particle shaking drum from the air inlet at the top of the hot air generating chamber 13 for drying operation. Under the guidance of the centrifugal fan 6, part of the air is discharged into the airflow circulation chamber 15 through the air outlet at the bottom of the drum 12, and then enters the hot air generating chamber 13 again through the circulation pipe 14 for heating, and the cycle continues.

[0044] The steam humidification system includes a steam generator 10 arranged at the upper part of the hot air generating chamber 13, and a steam outlet pipe 17 connected to the steam generator 10 is provided at the ventilation cavity 16. The steam outlet pipe 17 is arranged along the length direction of the grain shaking drum, and the steam outlet pipe 17 is provided with a plurality of steam outlets arranged toward the grain shaking drum.

[0045] Specific references Figure 6 and 7 The steam generator 10 is provided with a rectangular parallelepiped furnace body 101, and a combustion chamber 111 is provided at the lower part of the furnace body 101. The combustion chamber 111 can be made of a round tube with a diameter of 150 mm. A second burner 811 is provided in the combustion chamber 111, and the second burner 811 is connected to the gas supply system 8. A water storage tank 102 is provided outside the combustion chamber 111, and a water inlet is provided at the bottom of the water storage tank 102, and a steam outlet is provided at the top. The water inlet at the bottom of the water storage tank 102 is connected to a water inlet pipe 110, and a water pump is provided on the water inlet pipe 110. A sewage pipe 109 is also connected to the bottom of the water storage tank 102, and a water level gauge 113 is connected to one side of the water storage tank 102, so that the water volume in the water storage tank 102 can be observed at any time. The steam outlet is connected to a condensate return pipe, which is arranged on the top of the pelletizing machine housing 1. A pressure gauge 103 and a pressure relief valve 104 are installed on the condensate return pipe. A steam delivery pipe 105 is connected to one side of the condensate return pipe, and the steam delivery pipe 105 is connected to a steam outlet pipe 17 arranged in the housing 1.

[0046] Heat exchange channels 108 are provided between the two sides of the water storage tank 102 and the inner wall of the furnace body 101. The heat exchange channels 108 are symmetrically arranged on both sides of the furnace body 101. An exhaust port 106 is provided on the top of the heat exchange channel 108. The exhaust port 106 is connected to an exhaust pipe extending out of the box body 1. The exhaust pipe is equipped with an exhaust valve. A waste heat recovery pipe 114 is connected to the exhaust pipe below the exhaust valve. The end of the waste heat recovery pipe 114 is arranged at the ventilation cavity 16 of the two partition plates 11. A control valve is installed on the waste heat recovery pipe 114. When the fabric is humidified, the exhaust valve is closed and the control valve is opened so that the exhaust gas generated by the steam generator 10 can be returned to the shaking drum through the waste heat recovery pipe 114, thereby further quickly increasing the temperature in the drum 12 to adapt to the processing temperature requirements of different varieties.

[0047] The inner end of the combustion chamber 111 is connected to the heat exchange channel 108. Six groups of heat exchange components are arranged side by side from bottom to top on the water storage tank 102. Each group of heat exchange components is provided with 12 heat exchange tubes 112 with both ends connected. The heat exchange tubes 112 can be selected from DN25 round tubes with a length of 60 cm. The total heat exchange area of ​​the heat exchange components is 3.5 m 2The two ends of the heat exchange tube 112 are respectively connected to the heat exchange channels 108 on both sides, and a plurality of partitions 107 are respectively provided in the heat exchange channels 108 on both sides, so that each two adjacent groups of heat exchange components on this side are connected to the heat exchange channel 108 between the two adjacent partitions 107, and the partitions 107 in the heat exchange channels 108 on both sides are staggered so that the plurality of groups of heat exchange components are connected in series from bottom to top. Specifically, three partitions 107 are provided in the heat exchange channel 108 connected to the combustion chamber 111, and two partitions 107 are provided in the corresponding other heat exchange channel 108, so that the combustion chamber 111 is connected to one end of the first group of heat exchange components, the other end of the first group of heat exchange components is connected to one end of the second group of heat exchange components, the other end of the second group of heat exchange components is connected to one end of the third group of heat exchange components, and so on.

[0048] When in use, fill the water tank 102 with water, heat the air in the combustion chamber 111 through the second burner 811, and the hot air enters the first group of heat exchange components and the second group of heat exchange components in turn through the heat exchange channel 108. In this way, the cycle finally comes out from the sixth group of heat exchange components and is discharged from the exhaust port 106. The heat exchange tube 112 heated by the hot air exchanges heat with the water in the water tank 102, and the steam generated after the water is heated comes out through the steam outlet and is used. The furnace body 101 of this device is a rectangular parallelepiped and can be directly placed in the granulator for use. It occupies a small space. The steam output of this device can reach 50Kg / h, the gas consumption is small, the heat exchange efficiency is high, the steam temperature can be adjusted arbitrarily as needed, and the temperature control is accurate.

[0049] Reference Figure 8 , the first burner 9 and the second burner 811 are both connected to the gas supply system 8; the first burner 9 and the second burner 811 are both provided with a flame detection device, an ignition electrode, an air inlet and a gas inlet, and the flame detection device is a UV detector. The gas supply system 8 is provided with an air main pipeline 809, a gas inlet pipe 805 and a combustion controller 814, the air main pipeline 809 is connected to a fan 808, and an air valve is installed on the air main pipeline 809 connected to the fan 808, and the fan 808 is connected to an intelligent frequency converter 806 for controlling its air intake, and the frequency converter 806 is connected to a temperature control meter 807 through a signal line, and a temperature measuring probe is connected to the temperature control meter 807. The air inlets of the first burner 9 and the second burner 811 are respectively connected to air branch pipelines 812, and the air branch pipelines 812 are connected to the air main pipeline 809, and the air branch pipelines 812 are both provided with electric air valves 810.

[0050] The gas inlets of the first burner 9 and the second burner 811 are respectively connected to gas branch pipelines 815, which are connected to the gas inlet pipe 805. The gas branch pipelines 815 connected to the first burner 9 and the second burner 811 are respectively equipped with solenoid valves 816. A pressure regulating valve 801, a gas solenoid valve 802, an air-fuel ratio valve 803 and a ball valve 804 are sequentially provided on the gas inlet pipe 805 along the air inlet direction. The air inlet of the air-fuel ratio valve 803 is connected to an air inlet pipeline, which is communicated with the main air pipeline 809.

[0051] The ignition electrode is connected to the igniter, and the combustion controller 814 is connected to a flame detection control line and an ignition control line. Intermediate relays 813 are respectively installed on the flame detection control line and the ignition control line. The flame detection devices and igniters of the first burner 9 and the second burner 811 are respectively connected to their respective intermediate relays 813 through signal lines.

[0052] The combustion controller 814 controls the electric air valve 810 to realize the air supply of the burner. When in use, the electric air valve 810 for controlling the air supply of the first burner 9 and / or the second burner 811 is opened as needed, and the opening is controlled according to the set temperature. The gas supply of the burner is controlled by controlling the opening and closing of the solenoid valve 816. The two burners are controlled to work at the same time through a gas supply system 8, so that the gas supply systems of the two burners are integrated, reducing the components of the burner, so that it not only meets the operating requirements of the humidification and drying of the granulator, but also can control the combustion temperature as needed, reducing equipment investment and production costs.

[0053] The partition plate 11 of the air circulation chamber 15 is provided with a cooling air port connected to the ventilation cavity 16. The cooling air port is hinged with a cooling air door 5 opened outward. The back of the cooling air door 5 is provided with a cylinder for driving the opening and closing thereof. When the cooling operation is performed, the cooling air door 5 is fully opened so that the drum 12 can quickly dissipate heat and cool the fabric. When drying, the opening degree can be adjusted to discharge the water vapor in the drum 12 and improve the drying efficiency.

[0054] The centrifugal fan 6 is connected to an intelligent frequency converter for controlling the air intake, so that the wind speed can be adjusted at any time in the three process steps of humidification, drying and cooling of the fabric. The centrifugal fan 6 includes a fan blade and a motor for driving the fan blade to rotate. A circle of convex ridges is arranged on the fan blade installation end face close to the motor. When the centrifugal fan 6 is working, the convex ridges rotate to suck cold air from around the motor into the fan blade, so that the cold air wraps the motor, the motor is cooled, the service life of the motor is increased, and the high temperature damage phenomenon is reduced.

[0055] When the fabric is humidified, the steam generator 10 is started. When the steam temperature reaches the set temperature, the steam is transported to the steam outlet pipe 17 through the steam delivery pipe 105, and the steam is sprayed into the grain-forming drum, thereby realizing the humidification process operation. After the humidification operation is completed, the fabric needs to be dried. At this time, the first burner 9 of the airflow drying system is started to heat the air at the bottom of the hot air generating chamber 13. The heated hot air passes through the ventilation cavity 16 from the air inlet at the top of the hot air generating chamber 13 and enters the grain-forming drum for drying. At the same time, the centrifugal fan 6 is started. Under the guidance of the centrifugal fan 6, part of the hot air is discharged into the air circulation chamber 15 through the air outlet at the bottom of the drum 12. The damper 7 controlling the airflow volume in the circulation pipe 14 is opened to a certain degree. Part of the moisture is directly discharged through the damper, and part of the air enters the hot air generating chamber 13 again through the circulation pipe 14 for heating. In this cycle, because the heated air has a certain basic temperature, the heat utilization rate is high, thereby improving the drying efficiency.

[0056] When the cooling process is performed, the damper 7 for controlling the air flow in the circulation duct 14 is opened, the cooling damper 5 is fully opened, the centrifugal fan 6 is started, and the cold air enters the drum 12 from the cooling damper 5 and is discharged from the damper 7 in the circulation duct 14, so that the drum 12 can quickly dissipate heat and the fabric is cooled.

[0057] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A humidifying, drying and cooling integrated shaker, comprising a box body and a door, the front of the box body is provided with an opening, a shaker drum is provided in the box body, the mouth of the shaker drum is connected to the opening, and the door can cover the opening, characterized in that: Separation plates wrapping the roller are provided on both sides of the shaking roller, a ventilation cavity is provided between the upper parts of the two separation plates, an independent hot air generating chamber is formed between the separation plate on one side and the box body, an air inlet communicating with the ventilation cavity is provided on the upper part of the hot air generating chamber, and an airflow drying system and a steam humidification system are provided in the hot air generating chamber; An air circulation chamber is formed between the partition plate on the other side and the box body. An air outlet connected to the shaking drum is arranged on the partition plate at the bottom of the air circulation chamber. A centrifugal fan is arranged on one side of the bottom of the air circulation chamber. The centrifugal fan is connected to the hot air generating chamber through a circulation duct. An air outlet is arranged on the circulation duct. A damper for controlling the air flow is arranged in the circulation duct. The airflow drying system includes a first burner installed on the back of the box body and used to heat the air at the bottom of the hot air generating chamber. The heated hot air enters the particle shaking drum from the air inlet at the upper part of the hot air generating chamber for drying. Under the guidance of the centrifugal fan, part of the air is discharged into the airflow circulation chamber through the air outlet at the bottom of the drum, and then enters the hot air generating chamber again through the circulation pipe for heating, and the cycle continues. The steam humidification system comprises a steam generator disposed at the upper part of the hot air generating chamber, a steam outlet pipe connected to the steam generator is disposed at the ventilation cavity, the steam outlet pipe is disposed along the length direction of the grain shaking drum, and a plurality of steam outlets disposed toward the grain shaking drum are disposed on the steam outlet pipe; The steam generator is provided with a rectangular furnace body, a combustion chamber is provided at the lower part of the furnace body, a second burner is provided in the combustion chamber, a water storage tank is provided outside the combustion chamber, a water level gauge is connected to one side of the water storage tank, a water inlet is provided at the bottom of the water storage tank, a steam outlet is provided at the top, heat exchange channels are provided between the two sides of the water storage tank and the inner wall of the furnace body, an exhaust port is provided at the top of the heat exchange channel, an exhaust pipe extending from the box body is connected to the exhaust port, the inner end of the combustion chamber is connected with the heat exchange channel, a plurality of groups of heat exchange components are arranged side by side from bottom to top on the water storage tank, each group of heat exchange components is provided with a plurality of heat exchange tubes with both ends connected, the two ends of the heat exchange tubes are respectively connected with the heat exchange channels on both sides, a plurality of partitions are provided in the heat exchange channels on both sides, so that every two adjacent groups of heat exchange components on this side are connected with the heat exchange channel between the two adjacent partitions, and the partitions in the heat exchange channels on both sides are staggered so that the plurality of groups of heat exchange components are connected in series from bottom to top at both ends; A dust cleaning chamber is provided below the shaking drum. The dust cleaning chamber is provided between two partition plates. An integrated drawer is installed in the dust cleaning chamber. The dust cleaning chamber is connected with the air circulation chamber through an air outlet on the partition plate. A filter screen is provided on the air outlet.

2. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The heat exchange assembly is provided with 6 groups arranged side by side from bottom to top, each group is provided with 12 heat exchange tubes with both ends connected, and the total heat exchange area of ​​the heat exchange assembly is 3.0 m 2 -4.0m 2 ; Three partitions are provided in the heat exchange channel connected to the combustion chamber, and two partitions are provided in another corresponding heat exchange channel, so that the combustion chamber is connected to one end of the first group of heat exchange components, the other end of the first group of heat exchange components is connected to one end of the second group of heat exchange components, the other end of the second group of heat exchange components is connected to one end of the third group of heat exchange components, and so on.

3. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The steam outlet is connected to a condensate return pipe, which is arranged on the top of the pelletizer casing. A pressure gauge and a pressure relief valve are installed on the condensate return pipe. A steam delivery pipe is connected to one side of the condensate return pipe, and the steam delivery pipe is connected to a steam outlet pipe arranged in the casing.

4. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The water inlet at the bottom of the water storage tank is connected to a water inlet pipe, a water pump is arranged on the water inlet pipe, and a sewage pipe is also connected to the bottom of the water storage tank.

5. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The exhaust pipe is equipped with an exhaust valve, a waste heat recovery pipe is connected to the exhaust pipe below the exhaust valve, the end of the waste heat recovery pipe is arranged at the ventilation cavity of the two partition plates, and a control valve is installed on the waste heat recovery pipe.

6. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The first burner and the second burner are both connected to the gas supply system; the first burner and the second burner are both provided with a flame detection device, an ignition electrode, an air inlet and a gas inlet; the gas supply system is provided with an air main pipeline, a gas inlet pipe and a combustion controller; the air main pipeline is connected to the fan; an air valve is installed on the air main pipeline connected to the fan; the fan is connected to an intelligent frequency converter for controlling its air intake; the frequency converter is connected to a temperature control meter via a signal line; the temperature control meter is connected to a temperature measuring probe; the air inlets of the first burner and the second burner are respectively connected to air branch pipelines, the air branch pipelines are connected to the air main pipeline, and the air branch pipelines are both provided with electric air valves; The gas inlets of the first burner and the second burner are respectively connected to gas branch pipelines, which are connected to the gas inlet pipe. Solenoid valves are respectively installed on the gas branch pipelines connected to the first burner and the second burner. A pressure regulating valve, a gas solenoid valve, an air-fuel ratio valve and a ball valve are sequentially arranged on the gas inlet pipe along the inlet direction. The air inlet of the air-fuel ratio valve is connected to an air inlet pipeline, which is connected to the main air pipeline. The ignition electrode is connected to the igniter, and the combustion controller is connected to a flame detection control line and an ignition control line. Intermediate relays are respectively installed on the flame detection control line and the ignition control line. The flame detection devices and igniters of the first burner and the second burner are respectively connected to their respective intermediate relays through signal lines.

7. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: A cooling air port connected to the ventilation cavity is provided on the upper part of the partition plate of the air circulation chamber, a cooling air door opened outward is hinged on the cooling air port, and a cylinder for driving the opening and closing of the cooling air door is provided on the back side of the cooling air door.

8. The humidifying, drying and cooling integrated pelletizing machine according to claim 1, characterized in that: The centrifugal fan is connected to an intelligent frequency converter for controlling its air intake; the centrifugal fan comprises a fan blade and a motor for driving the fan blade to rotate, and a circle of ridges is arranged on the fan blade installation end surface close to the motor.