Ultra-thick wide cement stabilized macadam base construction process
A cement-stabilized crushed stone and construction technology technology, which is applied in the direction of roads, road repairs, on-site paved coagulation pavements, etc., can solve the problems of unfavorable crushed stone base overall strength, base bearing capacity decline, and affecting the base overall strength, etc. Achieve the effects of improving impermeability and compactness, improving overall strength and promoting contact
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2021-06-11
Abstract
Description
technical field
[0001] The invention relates to the technical field of cement construction, in particular to a super-thick and wide-width cement-stabilized gravel base construction technology. Background technique
[0002] Cement is a powdery hydraulic inorganic gelling material, which forms a slurry after being stirred with water, and can firmly bond sand, stone and other materials together after hardening, while cement-stabilized gravel is cement and graded crushed Stone blending, paving and compaction, embedding and locking, the layer structure formed is suitable as the base material of high-grade pavement. However, in the existing base construction technology, the demand for the thickness of the base is increased. The overall paving will lead to more pores in the lower base, and the difference in density between the upper part and the lower part of the base is large, resulting in dense top and sparse bottom, which is not conducive to the stability of cement-stabilized gr...
Examples
Embodiment 1
[0034] (1) mixing: get cement, aggregate, mixing water and mix, carry out mixing, make the first mixing material and the second mixing material, the moisture content of the first mixing material is higher than the moisture content of the second mixing material by 2 %;
[0035] (2) Paving:
[0036] (2.1) One-time paving: the water-absorbing agent is sprayed on the road surface to be paved, and a cushion is arranged on the road surface, and the consumption of the water agent is 0.3kg / m 2 , use a 20t road roller for static pressure, take the first mixture for paving, and lay the first layer of cement stabilized gravel base;
[0037] (2.2) Primary compaction: use a 20t road roller for static pressure, the number of times of static pressure is 2, and the rolling speed is 25m / min; use a 32t vibratory road roller for vibration compaction, after weak vibration once, strong vibration once, and rolling The pressing speed is 60m / min, and the water agent is sprayed on the upper surface ...
Embodiment 2
[0047] (1) Mixing: Get cement, aggregate, mixing water and mix, carry out mixing, make the first mixing material and the second mixing material, the moisture content of the first mixing material is higher than the moisture content of the second mixing material by 2 %;
[0048] (2) Paving:
[0049] (2.1) One-time paving: the water-absorbing agent is sprayed on the road surface to be paved, and a cushion is arranged on the road surface, and the consumption of the water agent is 0.3kg / m 2 , using a 20t road roller for static pressure, taking the first mixture for paving, and paving to form the first layer of cement-stabilized gravel base;
[0050] (2.2) Primary compaction: use a 20t road roller for static pressure, the number of times of static pressure is 2, and the rolling speed is 25m / min; use a 32t vibratory road roller for vibration compaction, after weak vibration once, strong vibration once, rolling The pressing speed is 60m / min, and the water agent is sprayed on the upp...
Embodiment 3
[0060] (1) Mixing: Get cement, aggregate, mixing water and mix, carry out mixing, make the first mixing material and the second mixing material, the moisture content of the first mixing material is higher than the moisture content of the second mixing material by 2 %;
[0061] (2) Paving:
[0062] (2.1) One-time paving: the water-absorbing agent is sprayed on the road surface to be paved, and a cushion is arranged on the road surface, and the consumption of the water agent is 0.3kg / m 2 , using a 20t road roller for static pressure, taking the first mixture for paving, and paving to form the first layer of cement-stabilized gravel base;
[0063] (2.2) Primary compaction: use a 20t road roller for static pressure, the number of times of static pressure is 2, and the rolling speed is 25m / min; use a 32t vibratory road roller for vibration compaction, after weak vibration once, strong vibration once, rolling The pressing speed is 60m / min, and the water agent is sprayed on the upp...