Method for checking pipeline consistency records in planning system, planning system and control program

By determining the main path and secondary path of the pipeline in the planning system, inconsistent objects are eliminated, the problem of consistency inspection of the two-dimensional and three-dimensional records of the pipeline is solved, fast and reliable inspection and operation instructions are achieved, and the integrity of the records is ensured sex and connectivity.

CN113366397BActive Publication Date: 2024-10-22SIEMENS AG
View PDF 14 Cites 0 Cited by

Patent Information

Application Number
CN202080012217.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Priority Date
2019-02-04
Filing Date
2020-01-07
Publication Date
2024-10-22
Estimated Expiration
2040-01-07

AI Technical Summary

Technical Problem

Existing technology makes it difficult to quickly and reliably check the consistency of two-dimensional and three-dimensional records of pipelines in the planning system, resulting in possible inconsistencies in sequence, completeness and connectivity.

Method used

By determining the primary path and secondary path of the pipeline in the planning system, eliminating objects that do not have mutual correspondence, and iteratively identifying and classifying objects with different orders until all objects have no difference in order, and finally in the graphical user interface Allocations in the correct order are shown above to indicate inconsistency elimination operations.

Benefits of technology

It enables quick and reliable checking of the consistency of pipeline two-dimensional and three-dimensional records in the planning system, provides operation instructions for exporting and eliminating inconsistencies, and ensures the integrity and connectivity of pipeline records.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113366397B_ABST
    Figure CN113366397B_ABST
Patent Text Reader

Abstract

In order to check the consistent recording of pipelines (10, 20) recorded two-dimensionally in a first plan (1) and recorded three-dimensionally in a second plan (2), at least one main path in the respective plan is determined for the pipelines recorded in both plans. Sequences of objects to be compared, including line components (11, 21), branches (12, 22) and / or interfaces, are determined for the main paths recorded in the two plans. Objects that do not have a mutual correspondence are eliminated from the sequence to be compared, which objects are recorded only in one of the two plans and / or only in the main path of one of the two plans. Thereafter, objects with different orders are iteratively determined and classified in the sequence to be compared, which objects have the greatest order difference in terms of the order of the objects in the sequence to be compared. This step is continued until all objects remaining after the classification have no order difference in terms of the order of the objects in the sequence to be compared.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Industrial automation systems are used to monitor, control and regulate technological processes, in particular in the fields of manufacturing, process and building automation, and enable largely independent operation of control devices, sensors, machines and technical systems. The fundamental basis for the reliable provision of monitoring, control and regulation functions by process automation systems is that the components of the industrial process automation system are fully and correctly documented and reflected in the engineering or planning system. Background Art

[0002] The engineering system can be used to configure, in particular, control programs for automation devices, which provide for visualization of images of technical installations or complex machines and their control or regulation. While the control program is running or working at run time, the technological process is controlled or regulated by an automation device such as a programmable logic controller. As part of process monitoring during operation, the operator can call up the process image to obtain an overview of the current system status and gain insight into process control and operation.

[0003] EP 1 166 215 B1 describes a method for automatically obtaining engineering data from a technical system, wherein engineering and runtime objects are described by a unified object model. This creates a direct correspondence between engineering objects and runtime objects at the object level, so that no information is lost due to the mapping of system components on the object model. In addition, direct communication between engineering and runtime objects is possible.

[0004] EP 2 808 749 B1 discloses a method for exchanging control information between operating and monitoring devices of an industrial automation system. Based on the control information, at least a segmented image of a technical device regulated or controlled by an automation device is visualized on a graphical user interface of the corresponding operating and monitoring device. Computer-based objects representing elements of the technical system are assigned to the visualization image, which are provided by a runtime environment provided on the corresponding operating and monitoring device. Based on a uniform addressing scheme, all object types provided on different operating and monitoring devices can be used for cross-device access.

[0005] US 6 063 128 relates to a system comprising a storage device, a first and a second hardware or software platform, a persistent portable data model, and a computer-based modeling system dependent on the first and the second platform. Each platform has an interface to the storage device and provides system-dependent services. A first operating system type and a first computer hardware type are assigned to the first platform, while a second operating system type and a second computer hardware type are assigned to the second platform. The portable data model is stored in a platform-independent format in the storage device and includes persistent component objects. In addition, the computer-based modeling system for the first platform is stored in a first storage area of ​​the storage device, while the computer-based modeling system for the second platform is stored in a second storage area of ​​the storage device. Each computer-based modeling system provides services for retrieving the portable data model from the storage device, changing the data model by adding and deleting component objects, and permanently storing the data model in the storage device. In addition, each computer-based modeling system includes a static kernel and a dynamic software framework. The kernel runs on the corresponding platform and forms an interface to the specified operating system and to the corresponding computer hardware. The software framework runs on the corresponding platform, forms an interface to the specified kernel and accordingly provides a platform-independent graphical user interface.

[0006] A method for managing process control in a computer system is described in WO 2010 / 037145 A2, and the computer system is provided for configuring and monitoring process facilities. The computer system provides an interactive user interface for managing multiple objects in a process facility. Here, each of the multiple objects corresponds to a physical or logical unit in the process facility. In addition, a navigation area is created to display a set of optional items. Each item in a set of optional items corresponds to a corresponding one from multiple objects. In addition, a command area is created for displaying a set of optional control items. Each control item in a set of optional control items corresponds to a task to be performed on at least one of the multiple objects in the process facility. A selection of an item from the optional item group is received via the navigation area, and a selection of a control item from the optional control item is received via the command area. An operating environment is determined based on the obtained selection. If the selection is an item selection, the operating environment corresponds to a set of actions applicable to the selection, and if the selection is a control item selection, it corresponds to a set of items used by the selection. The navigation area or the command area is adjusted according to the operating environment.

[0007] An engineering system for an industrial process automation system is known from EP 3 364 257 A1, wherein the components of the industrial process automation system are respectively represented by computer-based objects and are persistently stored in at least one server-side database. Objects selected and specified by a user are loaded into at least one processing storage area for processing from the database. When the user release of the object to be released loaded into the selected processing storage area is initiated, a check is performed to determine whether the direct priority processing storage area is available. For the releasable object loaded into the selected processing storage area, if the check result is positive, the direct predecessor in the priority processing storage area is determined and added to the releasable object. Objects that belong hierarchically to the object to be released are identified in the releasable object and marked as released. The object marked as released is moved from the selected user storage area to the priority user storage area by changing its allocation.

[0008] A 3D CAD method for laying pipes, channels, supply lines and HVAC (heating, ventilation and cooling) lines is known from US 2006 / 247902 A1. Router software and a graphical user interface for 2D real-time applications are combined to create a processing environment in which designers can quickly create fully valid 3D routes for pipes, HVAC lines, cable cars and other curved 3D objects.

[0009] In its construction, the pipeline is first created schematically and two-dimensionally in a piping and instrumentation diagram (P&ID) with the aid of a planning system. The three-dimensional construction of the pipeline is then created. Components and branches must exist in both the two-dimensional and three-dimensional representations and must match in terms of their order. Furthermore, the pipelines in both representations must match in terms of their connections or interfaces to external devices or pipelines. Summary of the invention

[0010] The object of the present invention is to provide a method for reliably and quickly checking the consistent two-dimensional and three-dimensional recording of pipelines in a planning system and to specify a suitable device for carrying out the method.

[0011] According to the method for checking the consistent recording of pipelines in a planning system according to the present invention, wherein the pipeline is recorded in a two-dimensional manner in a first plan and in a three-dimensional manner in a second plan, at least one main path in the corresponding plan is determined for the pipelines recorded in the two plans. Preferably, the main path is determined as a path that does not intersect with other paths in the corresponding pipeline, as an interface of other paths in the branch and / or in the direction of the tributary. Here, each branch has exactly one input interface in the direction of the main flow, exactly one output interface in the direction of the main flow, and at least one input or output interface in the direction of the tributary. In principle, the main path is determined by eliminating the path leading to the loop and / or parallel branch in the pipeline.

[0012] According to the present invention, for the main path recorded in two plans, the sequences to be compared of the objects including line components, branches and / or interfaces are determined respectively. Objects that do not have a mutual correspondence relationship are correspondingly eliminated from the sequence to be compared, which are only recorded in one of the two plans or only recorded in the main path of one of the two plans. After eliminating the objects that do not have a mutual correspondence relationship, objects with different orders are iteratively determined and classified in the sequence to be compared, which have the largest order difference in the order of the object in the sequence to be compared. Objects with different orders are continued to be determined until all objects remaining after classification do not have order differences in the order of the object in the sequence to be compared. Finally, a distribution with the correct order is created between the corresponding objects recorded in the first plan and the second plan, and the distribution is displayed on a graphical user interface. In this way, the inconsistency between the two plans in terms of order, integrity and connectivity can be displayed so as to derive an operation instruction for eliminating the inconsistency.

[0013] According to a preferred design of the present invention, in addition to the determined main path representing the first-order main path, a secondary path that does not intersect with the determined main path is also determined. If necessary, a second-order and / or higher-order main path that is processed similarly to the first-order main path is iteratively determined within the secondary path. The processing of the second-order and / or higher-order main paths includes: determining a sequence of objects to be compared with each other, eliminating objects that do not have a mutual correspondence, and iteratively determining and eliminating objects with different orders within the sequence to be compared. Therefore, inconsistencies in the secondary paths can also be reliably determined.

[0014] For example, the object comprising pipeline assembly, branch or interface can be identified according to identification, component type, nominal diameter or nominal diameter combination. In addition, the mutual correspondence of the object from the sequence to be compared can be advantageously determined according to the identification or mark of the object. The objects with the same or assigned identification or mark are linked to each other. Preferably, in the sequence to be compared, after linking the object with the same or assigned identification or mark, iteratively determine the object to be linked to each other with the object type of matching in the unlinked object, the object has the minimum difference in the order difference between them and / or in the sequence to be compared, the distance between this object and the neighbors of the same type. The determined object to be linked is processed as the object with the mutual correspondence. Especially can correspondingly determine the object to be linked to each other with the object type of matching, the object has the minimum difference in the order difference between them and the weighted distance between the neighbors of the same type of the first and second levels in the sequence to be compared.

[0015] According to an advantageous development of the invention, objects recorded in the primary path of the first plan or the second plan and in the secondary path of the respective other plan and not corresponding to each other are classified as unfamiliar objects, while objects recorded in only one of the two plans and not corresponding to each other are classified as missing objects. In addition, objects with different orders are classified as objects with wrong orders, while objects remaining after the classification of objects with different orders are classified as objects with the correct order. For example, the classification of the objects is displayed on a graphical user interface as a result of a consistency check between pipelines recorded in two dimensions and three dimensions.

[0016] The planning system according to the invention is used to carry out the method according to the foregoing description and is designed and arranged to record the pipeline in a two-dimensional manner in a first plan and to record the pipeline in a three-dimensional manner in a second plan. In addition, the planning system is designed and arranged to determine at least one main path in the corresponding plan for the pipelines recorded in the two plans, and to determine a sequence of objects including line components, branches and / or interfaces to be compared with each other for the main paths recorded in the two plans. In addition, the planning system is designed and arranged to eliminate objects that do not have a mutual correspondence from the sequence to be compared, which objects are recorded only in one of the two plans and / or only in the main path of one of the two plans.

[0017] Furthermore, the planning system according to the present invention is designed and arranged to iteratively determine and classify objects with different orders within the sequence to be compared, which objects have the greatest order difference in the order of the objects within the sequence to be compared, after eliminating objects that do not have a mutual correspondence. Furthermore, the planning system is designed and arranged to continue determining objects with different orders until all objects remaining after the classification have no order difference in the order of the objects within the sequence to be compared, and finally to create an order-corrected assignment between the corresponding objects recorded in the first plan and the second plan, and to display the assignment on a graphical user interface.

[0018] The control program according to the invention can be stored in a main memory of a computer and has at least one code section which, when it is run in the computer, carries out the above-described steps of the method according to the invention when the control program is executed. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The present invention will be described in more detail below with reference to the accompanying drawings with the aid of an embodiment. The accompanying drawings show:

[0020] Figure 1 shows a diagram with a first plan of a pipeline recorded in two dimensions and a corresponding second plan of the pipeline recorded in three dimensions,

[0021] Figure 2 A schematic diagram showing a method flow for determining unfamiliar objects and missing objects within paths to be compared with each other is shown,

[0022] Figure 3 A schematic diagram of the process flow for subsequently determining objects with an incorrect order and objects with a correct order is shown. DETAILED DESCRIPTION

[0023] according to Figure 1 In a computer-based planning system comprising at least one computer 100 and a control program, pipes 10, 20 are recorded two-dimensionally in a first plan 1 and three-dimensionally in a second plan 2. The control program is permanently stored in a non-volatile memory 103 of the computer 100 and can be loaded into its working memory 102 and has at least one code segment which, when the control program is run on the computer 100, performs the steps described below during its processing by a processor 101 of the computer 100.

[0024] For pipelines 10 and 20 recorded in the two plans 1 and 2, according to Figure 2 In step 201 of the method flow shown in , at least one main path is determined in the corresponding plan 1, 2. Here, the main path is determined as a path that does not intersect with other paths in the corresponding pipeline 10, 20 as an interface of another path in the branch or in the direction of the tributary. Here, each branch 12, 22 has exactly one input interface in the direction of the main flow, exactly one output interface in the direction of the main flow and at least one input or output interface in the direction of the tributary. In principle, the main path can be determined by eliminating the path leading to the loop or parallel branch in the pipeline 10, 20.

[0025] Furthermore, according to step 202, a sequence of objects to be compared with each other, including pipeline components 11, 21, branches 12, 22 or interfaces, is determined for the main path recorded in the plan 1, 2. The objects including pipeline components 11, 21, branches 12, 22 or interfaces are preferably identified based on a label, component type, nominal diameter or nominal diameter combination. Then, in step 203, the mutual correspondence of objects from the sequence to be compared is determined based on the identification or label of the object. Objects with the same or assigned identification or label are linked to each other.

[0026] Objects that do not have a mutual correspondence are eliminated from the sequences to be compared that are recorded only in one of the two plans 1, 2 or only in the main path of one of the two plans (step 204). Objects that do not have a mutual correspondence and are recorded in the main path of the first plan 1 or the second plan 2 and the secondary path of the respective other plan are classified as unfamiliar objects. On the contrary, objects that are known to have no mutual correspondence and are recorded only in one of the two plans are classified as missing objects.

[0027] After linking the object with the same or assigned identification or mark according to step 204 and eliminating these objects, iteratively determine in the unlinked object the object to be linked to each other with the object type of matching, which has the minimum difference in its order difference and / or in the sequence to be compared, the distance of this object and the neighbor of the same type. For this reason, check whether there is an object that has not been linked so far according to step 205. If there is an unlinked object, then check whether there is at least one object that is the same or of the same type for the selected object according to step 206 subsequently. If there is at least one object of the same type, then determine to have the object to be linked (step 207) with minimum distance or difference relative to the selected object in the sequence to be compared. Then the object selected is connected with the determined object (step 208), and turns back to step 205. The determined objects to be linked to each other are processed as the object with a mutual corresponding relationship.

[0028] If there are no more unlinked objects according to step 205, the process proceeds to determining the objects in the correct order that have a mutual correspondence within the sequence to be compared (step 301, see Figure 3 ). If there is no object of the same type as the object selected according to step 206, the selected object is eliminated and classified as a missing object according to step 209. Then return to step 205.

[0029] Preferably, according to steps 205-208, objects to be linked to each other with matching object types are determined, which have the smallest difference in their order difference with each other and in their weighted distances with the same type of neighbors of the first and second levels in the sequence to be compared. For example, two can be used as the weighting factor for the first-level neighbors, while the weighting factor for the second-level neighbors is set to one.

[0030] After eliminating the objects that do not have a corresponding relationship in the sequence to be compared, according to Figure 3Iteratively determine and classify objects with different orders, which have the largest order difference in their order in the sequence to be compared. Continue to determine objects with different orders until all objects remaining after classification do not have order differences in their order in the sequence to be compared. For this reason, after starting to determine objects with correct order that have a mutual correspondence according to step 302 (step 301), check whether there are only objects with a mutual correspondence, which do not have order differences in the sequence to be compared. If there are objects with order differences, then determine objects with a mutual correspondence according to step 303, which have the largest order difference in their order in the sequence to be compared. According to step 304, these objects are classified as objects with a wrong order. Then return to step 302.

[0031] If there are no objects with order differences according to the check in step 302, the objects remaining after the classification of the objects with different orders are classified as objects with correct order. Finally, a correct order assignment between the corresponding objects recorded in the first plan and the second plan is created (step 305) and displayed on the graphical user interface 104 of the computer (step 306). In addition, as a result of the consistency check between the pipelines recorded in a two-dimensional manner and in a three-dimensional manner, strange objects, missing objects, or objects with wrong orders can be selectively displayed on the graphical user interface 104 with their corresponding classifications.

[0032] In addition to determining the determined main path representing the main path of the first order, a secondary path that does not intersect therewith is also determined. A second-order or higher-order main path that is processed similarly to the first-order main path is determined within the secondary path. In particular, the processing of the second-order or higher-order main path includes: determining a sequence of objects to be compared with each other, eliminating objects that do not have a mutual correspondence, and iteratively determining and eliminating objects with different orders within the sequence to be compared.

Claims

1. A method for checking the consistent recording of pipelines in a planning system, wherein: - the conduits (10, 20) are recorded in two dimensions in the first plan (1) and in three dimensions in the second plan (2); - for the pipelines (10, 20) recorded in the first plan (1) and the second plan (2), at least one main path is determined in the respective plan, the main path being determined by eliminating paths leading to loops and / or parallel branches in the pipeline; - for the main paths recorded in the first plan (1) and the second plan (2), respectively determining a sequence of objects including line components (11, 21), branches (12, 22) and / or interfaces to be compared with each other; - correspondingly eliminating objects that do not have a mutual correspondence from the sequences to be compared, the objects that do not have a mutual correspondence being recorded only in one of the first plan and the second plan and / or only in a main path of one of the first plan and the second plan; - after eliminating objects that do not have a mutual correspondence, iteratively determining and classifying objects with different orders within the sequence to be compared, the objects with different orders having the greatest order difference in terms of the order of the objects with different orders within the sequence to be compared; - continuing to determine objects with different orders until all objects remaining after the classification have no order differences with respect to the order of the objects remaining within the sequence to be compared; - finally creating a correctly ordered assignment between the corresponding objects recorded in the first plan and the second plan and displaying the assignment on a graphical user interface.

2. The method according to claim 1, wherein: The main path is defined as a path that does not intersect with another path within the corresponding pipeline (10, 20) and serves as an interface for another path that branches and / or flows in a tributary direction, wherein each branch (12, 22) has exactly one input interface in the mainstream direction, exactly one output interface in the mainstream direction, and at least one input or output interface in the tributary direction.

3. The method according to claim 1 or 2, wherein: The objects, including pipe components (11, 21), branches (12, 22) and / or interfaces, are identified based on markings, component types, nominal diameters and / or nominal diameter combinations.

4. The method according to claim 3, wherein: The mutual correspondence of the objects from the sequence to be compared is determined based on the identification and / or marking of the objects, and objects having the same or assigned identification and / or marking are linked to one another.

5. The method according to claim 4, wherein: Within the sequence to be compared, after linking objects with the same or assigned identification and / or marking, objects with matching object types to be linked to each other are iteratively determined among the unlinked objects, the determined objects having the smallest degree of difference in terms of the order differences of the determined objects relative to each other and / or in terms of the distances of the determined objects from neighbors of the same type within the sequence to be compared, and wherein the determined objects to be linked to each other are processed as objects having a mutual correspondence.

6. The method according to claim 5, wherein: Objects to be linked to each other with matching object types are determined, the determined objects having a minimum degree of difference in the order difference of the determined objects relative to each other and in the weighted distance of the determined objects from first-order and second-order neighbors of the same type in the sequence to be compared.

7. The method according to claim 1 or 2, wherein: Objects recorded in the main path of the first plan or the second plan and in the secondary path of the respective other plan and having no mutual correspondence are classified as unfamiliar objects, and objects recorded in only one of the first plan and the second plan and having no mutual correspondence are classified as missing objects.

8. The method according to claim 1 or 2, wherein: The objects having different orders are classified as objects having wrong orders, and wherein objects remaining after the objects having different orders are classified as objects having correct orders.

9. The method according to claim 7, wherein: The classification of the objects is displayed on a graphical user interface as a result of a consistency check between the pipelines recorded in two dimensions and three dimensions.

10. The method according to claim 1 or 2, wherein: In addition to a determined main path representing a first-order main path, secondary paths are determined which do not intersect the determined main path, and wherein second-order and / or higher-order main paths are determined within the secondary paths and are processed in a similar manner to the first-order main paths.

11. The method according to claim 10, wherein: Processing of the second order and / or higher order main paths includes determining a sequence of objects to be compared with each other, eliminating objects that do not have a mutual correspondence, and iteratively determining and eliminating objects with different orders within the sequence to be compared.

12. A planning system for executing the method according to any one of claims 1 to 11, wherein: The planning system is designed and configured to: - the conduit is recorded in two dimensions in the first plan and in three dimensions in the second plan; - for the pipelines recorded in the first plan and the second plan, respectively determining at least one main path in the corresponding plan; - for the main paths recorded in the first plan and the second plan, respectively determining a sequence of objects including line components, branches and / or interfaces to be compared with one another; - correspondingly eliminating objects that do not have a mutual correspondence from the sequences to be compared, the objects that do not have a mutual correspondence being recorded only in one of the first plan and the second plan and / or only in a main path of one of the first plan and the second plan; - after eliminating objects that do not have a mutual correspondence, iteratively determining and classifying objects with different orders within the sequence to be compared, the objects with different orders having the greatest order difference in terms of the order of the objects with different orders within the sequence to be compared; - continuing to determine objects with different orders until all objects remaining after the classification have no order differences with respect to the order of the objects remaining within the sequence to be compared; - finally creating a correctly ordered assignment between the corresponding objects recorded in the first plan and the second plan and displaying the assignment on a graphical user interface.

13. A computer-readable storage medium, on which a control program that can be loaded into a working memory of a computer and has at least one code segment is stored, and when the control program is run on the computer, when the control program is implemented, - the conduit is recorded in two dimensions in the first plan and in three dimensions in the second plan; - for the pipelines recorded in the first plan and the second plan, respectively determining at least one main path in the corresponding plan; - for the main paths recorded in the first plan and the second plan, respectively determining a sequence of objects including line components, branches and / or interfaces to be compared with one another; - correspondingly eliminating objects that do not have a mutual correspondence from the sequences to be compared, the objects that do not have a mutual correspondence being recorded only in one of the first plan and the second plan and / or only in a main path of one of the first plan and the second plan; - after eliminating objects that do not have a mutual correspondence, iteratively determining and classifying objects with different orders within the sequence to be compared, the objects with different orders having the greatest order difference in terms of the order of the objects with different orders within the sequence to be compared; - continuing to determine objects with different orders until all objects remaining after the classification have no order differences with respect to the order of the objects remaining within the sequence to be compared; - finally creating a correctly ordered assignment between the corresponding objects recorded in the first plan and the second plan and displaying the assignment on a graphical user interface, and executing the method according to any one of claims 1 to 11 when the control program is run in the computer.

Citation Information

Patent Citations

  • Method for the automatic retrieval of engineering data of systems

    EP1166215B1

  • Method for the exchange of control information between operating and observation devices of an industrial automation system and industrial automation system

    EP2808749B1

  • Method for operating an engineering system for an industrial process automation system and control program

    EP3364257A1

  • Hybride 3D path router

    US20060247902A1

  • Object-oriented computerized modeling system

    US6063128A