Method, device, electronic device and medium for determining power supply voltage data

By processing power supply voltage simulation data in multiple simulation cycles, determining the target voltage data of each logic unit and configuring it into a static timing analysis tool, the problem of insufficient accuracy of power supply voltage data in integrated circuits is solved, and static timing analysis is improved accuracy.

CN113627107BActive Publication Date: 2024-12-06HYGON INFORMATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110917357.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-11
Publication Date
2024-12-06
Estimated Expiration
2041-08-11

AI Technical Summary

Technical Problem

In the static timing analysis of integrated circuits, it is difficult for the prior art to accurately determine the power supply voltage data, resulting in the timing analysis results being too pessimistic and lacking accuracy.

Method used

By obtaining the power supply voltage simulation data in multiple simulation cycles, the power supply voltage simulation sub-data for each logic unit in the timing path is determined, and the data is processed to obtain the target voltage data for each logic unit and configure it to a static timing In the analysis tool, it is used for static timing analysis of each timing path.

Benefits of technology

It improves the accuracy of power supply voltage data, reduces the pessimism of the analysis results, and makes static timing analysis more accurate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113627107B_ABST
    Figure CN113627107B_ABST
Patent Text Reader

Abstract

A method for determining power supply voltage data in static timing analysis of an integrated circuit, a static timing analysis method, a device, an electronic device and a medium. The method comprises: obtaining power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles; determining at least one timing path in the integrated circuit; processing the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain the target voltage data of at least one logic unit; and using the target voltage data of at least one logic unit as the power supply voltage data of at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of at least one logic unit to perform static timing analysis on each timing path. The method can reduce the pessimism of the power supply voltage data used for static timing analysis, thereby making the result of static timing analysis more accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Embodiments of the present disclosure relate to a method for determining power supply voltage data in static timing analysis of an integrated circuit, a static timing analysis method of an integrated circuit, an apparatus for determining power supply voltage data in static timing analysis of an integrated circuit, a static timing analysis apparatus of an integrated circuit, an electronic device, and a computer-readable storage medium. Background Art

[0002] As integrated circuit design becomes larger, the process becomes more advanced, and the frequency becomes higher, the standard requirements for high-accuracy timing signoff are getting higher and higher. For high-performance CPUs and GPUs, the impact of voltage drop on timing is particularly important because the chip area is large and the entire power supply network is complex and large. Summary of the invention

[0003] At least one embodiment of the present disclosure provides a method for determining power supply voltage data in static timing analysis of an integrated circuit, the integrated circuit including multiple logic units, the method including: acquiring power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, the power supply voltage simulation data including power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; determining at least one timing path in the integrated circuit, each timing path in the at least one timing path including at least one logic unit in the multiple logic units; processing the power supply voltage simulation sub-data corresponding to each of the at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and using the target voltage data of the at least one logic unit as the power supply voltage data of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of the at least one logic unit to perform static timing analysis on each timing path.

[0004] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, power supply voltage simulation sub-data corresponding to each of at least one logic unit in each timing path are processed to obtain target voltage data of at least one logic unit, including: for each timing path, processing the power supply voltage simulation sub-data of each logic unit in at least one logic unit in each two adjacent simulation cycles in multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and determining the target voltage data of each logic unit based on the voltage fluctuation characterization parameters.

[0005] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, the timing path includes a clock path, and for each timing path, power supply voltage simulation sub-data of each logic unit in at least one logic unit in each two adjacent simulation cycles in multiple simulation cycles are processed, including: determining at least one clock path logic unit in each timing path that is located on the clock path; and processing the power supply voltage simulation sub-data of each clock path logic unit in at least one clock path logic unit in each two adjacent simulation cycles in multiple simulation cycles.

[0006] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, the multiple simulation cycles are N simulation cycles, N is an integer greater than 0, and for each timing path, the power supply voltage simulation sub-data of each logic unit in at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles are processed to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles, including: for each timing path, determining the first voltage value of each logic unit in at least one logic unit in each simulation cycle in N simulation cycles; taking the difference between the first voltage values ​​of each logic unit in each two adjacent simulation cycles in N simulation cycles to obtain N-1 differences, and taking the absolute values ​​of the N-1 differences to obtain N-1 voltage difference absolute values; and calculating the N-1 voltage difference absolute values ​​to obtain the voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0007] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, every two adjacent simulation cycles include a first simulation cycle and a second simulation cycle, and determining the first voltage value of each logic unit in each simulation cycle of N simulation cycles includes: taking the maximum value in the power supply voltage simulation sub-data in the first simulation cycle as the first voltage value of the first simulation cycle; and taking the minimum value in the power supply voltage simulation sub-data in the second simulation cycle as the first voltage value of the second simulation cycle.

[0008] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, N-1 absolute values ​​of voltage differences are calculated to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles, including: calculating the average value and / or standard deviation of the N-1 absolute values ​​of voltage differences to obtain the voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0009] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, target voltage data of each logic unit is determined based on voltage fluctuation characterization parameters, including: determining an average voltage value of each logic unit in multiple simulation cycles based on power supply voltage simulation sub-data of each logic unit; and determining the target voltage data of each logic unit based on the average voltage value and the voltage fluctuation characterization parameters.

[0010] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, the voltage fluctuation characterization parameters include an average value and a standard deviation of N-1 absolute values ​​of voltage differences, and the target voltage data of each logic unit is determined based on the average voltage value and the voltage fluctuation characterization parameters, including: determining a confidence interval based on the average value and the standard deviation of the absolute values ​​of N-1 voltage differences; and determining the target voltage data of each logic unit based on the average voltage value and the confidence interval.

[0011] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, the timing path includes a clock path, the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives a data signal, and the target voltage data of each logic unit is determined based on an average voltage value and a confidence interval, including: determining the larger endpoint value of two endpoint values ​​in the confidence interval as a fluctuation value; taking the difference between the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the sending clock path; and taking the sum of the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the receiving clock path.

[0012] For example, in the method for determining power supply voltage data provided in an embodiment of the present disclosure, the confidence interval is [μ-3×σ, μ+3×σ], where μ is the average value of the absolute value of the voltage difference, and σ is the standard deviation.

[0013] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, for each timing path, power supply voltage simulation sub-data of each logic unit in at least one logic unit in each two adjacent simulation cycles in multiple simulation cycles are processed to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles, including: for each timing path, determining the maximum value of the voltage difference between each two adjacent simulation cycles of each logic unit in at least one logic unit in multiple simulation cycles; determining the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value; and using the minimum voltage value and the maximum voltage value as voltage fluctuation characterization parameters.

[0014] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, the timing path includes a clock path, the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives a data signal, and based on the voltage fluctuation characterization parameters, the target voltage data of each logic unit is determined, including: using the minimum voltage value as the target voltage data of each logic unit on the sending clock path; and using the maximum voltage value as the target voltage data of each logic unit on the receiving clock path.

[0015] For example, in a method for determining power supply voltage data provided in an embodiment of the present disclosure, power supply voltage simulation data obtained by simulating an integrated circuit in multiple simulation cycles is obtained, including: obtaining a simulation netlist and a simulation stimulus file corresponding to the integrated circuit, the simulation stimulus file including signal information of the circuit; and performing power supply voltage fluctuation simulation on the integrated circuit based on the simulation netlist and the simulation stimulus file to obtain power supply voltage simulation data.

[0016] At least one embodiment of the present disclosure provides a static timing analysis method for an integrated circuit, wherein the integrated circuit includes multiple logic units, and the method includes: obtaining power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, the power supply voltage simulation data including power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; determining at least one timing path in the integrated circuit, each timing path in the at least one timing path including at least one logic unit in the multiple logic units; processing the power supply voltage simulation sub-data corresponding to each of the at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and configuring the target voltage data of the at least one logic unit into a static timing analysis tool as the power supply voltage data of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of the at least one logic unit to perform static timing analysis on each timing path.

[0017] For example, in a static timing analysis method provided in an embodiment of the present disclosure, a timing path includes a clock path and a data path, and at least one logic unit in each timing path includes at least one clock path logic unit located in the clock path and at least one data path logic unit located in the data path, and processing power supply voltage simulation sub-data corresponding to each of the at least one logic unit in each timing path to obtain target voltage data of each of the at least one logic unit includes: processing power supply voltage simulation sub-data corresponding to each of the at least one clock path logic unit in each timing path to obtain target voltage data of each of the at least one clock path logic unit; and processing power supply voltage simulation sub-data corresponding to each of the at least one data path logic unit in each timing path to obtain target voltage data of each of the at least one data path logic unit.

[0018] For example, in the static timing analysis method provided in an embodiment of the present disclosure, the power supply voltage simulation sub-data corresponding to each of at least one clock path logic unit in each timing path is processed to obtain the target voltage data of at least one clock path logic unit, including: for each clock path logic unit in the at least one clock path logic unit, the power supply voltage simulation sub-data of each clock path logic unit in each two adjacent simulation cycles in multiple simulation cycles are processed to obtain the voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each clock path logic unit in adjacent cycles; and based on the voltage fluctuation characterization parameters, the target voltage data of each clock path logic unit is determined.

[0019] For example, in a static timing analysis method provided in an embodiment of the present disclosure, the power supply voltage simulation sub-data corresponding to each of at least one data path logic unit in each timing path is processed to obtain target voltage data of each of the at least one data path logic unit, including: for each data path logic unit in each timing path, determining the minimum value of the power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles, and using the minimum value as the target voltage data of each data path logic unit; or for each data path logic unit in each timing path, calculating the average value of the power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles, and using the average value as the target voltage data of each data path logic unit.

[0020] At least one embodiment of the present disclosure provides an apparatus for determining power supply voltage data in static timing analysis of an integrated circuit, comprising: a first acquisition module, configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, the power supply voltage simulation data including power supply voltage simulation sub-data of each logic unit in multiple simulation cycles of multiple logic units; a first determination module, configured to determine at least one timing path in the integrated circuit, each timing path in at least one timing path including at least one logic unit in the multiple logic units; a first processing module, configured to process the power supply voltage simulation sub-data corresponding to each of at least one logic unit in each timing path to obtain target voltage data of each of the at least one logic unit; and a second determination module, configured to use the target voltage data of each of the at least one logic unit as the power supply voltage data of each of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of each of the at least one logic unit to perform static timing analysis on each timing path.

[0021] At least one embodiment of the present disclosure provides a static timing analysis device for an integrated circuit, wherein the integrated circuit includes multiple logic units, and the device includes: a second acquisition module, configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, the power supply voltage simulation data including power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; a third determination module, configured to determine at least one timing path in the integrated circuit, each timing path in the at least one timing path includes at least one logic unit in the multiple logic units; a second processing module, configured to process the power supply voltage simulation sub-data corresponding to each of the at least one logic unit in each timing path to obtain target voltage data of each of the at least one logic unit; and a fourth determination module, configured to configure the target voltage data of each of the at least one logic unit into a static timing analysis tool as the power supply voltage data of each of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of each of the at least one logic unit to perform static timing analysis on each timing path.

[0022] At least one embodiment of the present disclosure provides an electronic device, comprising a processor; a memory, comprising one or more computer program modules; the one or more computer program modules are stored in the memory and configured to be executed by the processor, and the one or more computer program modules include instructions for implementing the method for determining power supply voltage data in static timing analysis of an integrated circuit or the static timing analysis method of an integrated circuit provided by any embodiment of the present disclosure.

[0023] At least one embodiment of the present disclosure provides a computer-readable storage medium for storing non-temporary computer-readable instructions. When the non-temporary computer-readable instructions are executed by a computer, the method for determining power supply voltage data in static timing analysis of an integrated circuit or the static timing analysis method of an integrated circuit provided in any embodiment of the present disclosure can be implemented. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present disclosure, the drawings of the embodiments will be briefly introduced below. Obviously, the drawings in the following description only relate to some embodiments of the present disclosure, but are not intended to limit the present disclosure.

[0025] Figure 1A A flow chart of a method for determining power supply voltage data in static timing analysis of an integrated circuit provided by at least one embodiment of the present disclosure is shown;

[0026] Figure 1B A schematic diagram showing a timing path provided by at least one embodiment of the present disclosure is shown;

[0027] Figure 2A It shows that at least one embodiment of the present disclosure provides Figure 1A The method flow chart of step S30 in FIG.

[0028] Figure 2B It shows that at least one embodiment of the present disclosure provides Figure 1B A schematic diagram of power supply voltage simulation sub-data of the standard cell 202;

[0029] Figure 3 It shows that at least one embodiment of the present disclosure provides Figure 2A The method flow chart of step S31 in FIG.

[0030] Figure 4 It shows that at least one embodiment of the present disclosure provides Figure 2A The method flow chart of step S32 in FIG.

[0031] Figure 5 A flow chart of a method for determining target voltage data of each logic unit based on an average voltage value and a confidence interval provided by at least one embodiment of the present disclosure is shown;

[0032] Figure 6 It shows that at least one embodiment of the present disclosure provides Figure 2A Another method flow chart of step S31 in FIG.

[0033] Fig. 7A A flowchart of a static timing analysis method for an integrated circuit provided by at least one embodiment of the present disclosure is shown;

[0034] Figure 7BIt shows that at least one embodiment of the present disclosure provides Fig. 7A Schematic diagram of the method of step S730;

[0035] Figure 8 A flowchart of another static timing analysis method provided by at least one embodiment of the present disclosure is shown;

[0036] Fig.9A A schematic block diagram of an apparatus 900 for determining power supply voltage data in static timing analysis of an integrated circuit provided by at least one embodiment of the present disclosure is shown;

[0037] Fig. 9B A schematic block diagram of a static timing analysis device 1000 for an integrated circuit provided by at least one embodiment of the present disclosure is shown;

[0038] Fig.10 A schematic block diagram of an electronic device provided by at least one embodiment of the present disclosure is shown;

[0039] Fig.11 A schematic block diagram showing another electronic device provided by at least one embodiment of the present disclosure; and

[0040] Fig.12 A schematic diagram of a computer-readable storage medium provided by at least one embodiment of the present disclosure is shown. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solution and advantages of the embodiments of the present disclosure clearer, the technical solution of the embodiments of the present disclosure will be clearly and completely described below in conjunction with the drawings of the embodiments of the present disclosure. Obviously, the described embodiments are part of the embodiments of the present disclosure, not all of the embodiments. Based on the described embodiments of the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present disclosure.

[0042] Unless otherwise defined, the technical terms or scientific terms used in the present disclosure should be understood by people with ordinary skills in the field to which the present disclosure belongs. The "first", "second" and similar words used in the present disclosure do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, similar words such as "one", "one" or "the" do not indicate quantity restrictions, but indicate that there is at least one. Similar words such as "include" or "comprise" mean that the elements or objects appearing before the word cover the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Similar words such as "connect" or "connected" are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0043] Static Timing Analysis (STA) is an important part of integrated circuit design. The main purpose of STA is to calculate the various timing performance indicators of the integrated circuit design by analyzing the delay of the timing path, and to promptly discover the paths that violate the timing requirements. For high-performance CPUs and GPUs, the impact of voltage drop on timing is particularly important due to the large chip area and the complex and large power supply network. Therefore, it is usually necessary to simulate the voltage drop of the integrated circuit, and then use the power supply voltage data obtained by simulation to perform STA to determine whether the design of the integrated circuit meets the timing performance indicators.

[0044] In the related art, EDA tools are usually used to simulate the dynamic voltage drop of the power supply, and then the EDA tools are used to simulate the clock jitter of the simulation results of the dynamic voltage drop simulation to obtain the uncertainty of the clock. Then the STA tool uses the uncertainty of the clock to perform static timing analysis. In the related art, the same clock domain often contains multiple timing paths. For the same clock domain, the maximum value of the clock jitter in all the timing paths in the clock domain is usually used as the uncertainty of the clock in the clock domain and back-annotated to the STA tool, which makes the result of the static timing analysis too pessimistic and inaccurate.

[0045] At least one embodiment of the present disclosure provides a method for determining power supply voltage data in static timing analysis of an integrated circuit, a static timing analysis method, an apparatus, an electronic device, and a computer-readable storage medium for an integrated circuit. The method includes: obtaining power supply voltage simulation data obtained by simulating an integrated circuit in multiple simulation cycles, the power supply voltage simulation data including power supply voltage simulation sub-data of each logic unit in multiple simulation cycles of multiple logic units; determining at least one timing path in the integrated circuit, each timing path in at least one timing path including at least one logic unit in multiple logic units; processing the power supply voltage simulation sub-data corresponding to each of at least one logic unit in each timing path to obtain target voltage data of at least one logic unit; and using the target voltage data of at least one logic unit as the power supply voltage data of at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of at least one logic unit to perform static timing analysis on each timing path. The method can obtain power supply voltage data for each logic unit, so that the pessimism of the power supply voltage data can be reduced, so that the result obtained by using the power supply voltage data for static timing analysis will not be too pessimistic, so that the result of static timing analysis is more accurate.

[0046] Figure 1A A flow chart of a method for determining power supply voltage data in static timing analysis of an integrated circuit provided by at least one embodiment of the present disclosure is shown.

[0047] like Figure 1A As shown, the method may include steps S10 to S40.

[0048] Step S10: Acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles.

[0049] Step S20: determining at least one timing path in the integrated circuit, each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units.

[0050] Step S30: Processing the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of at least one logic unit.

[0051] Step S40: using the target voltage data of at least one logic unit as the power supply voltage data of at least one logic unit, so that the static timing analysis tool performs static timing analysis on each timing path using the power supply voltage data of at least one logic unit.

[0052] The method can obtain the power supply voltage data for each logic unit according to the power supply voltage simulation data, so that the power supply voltage data of each logic unit can be used for static timing analysis, instead of, for example, using the maximum value of the clock jitter as the uncertainty of the clock in the clock domain for all timing paths in the same clock domain to perform static timing analysis in the related art. Therefore, the method can improve the accuracy of the power supply voltage data used for STA, reduce the pessimism of static timing analysis, and thus improve the accuracy of STA.

[0053] For step S10 , the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in a plurality of logic units in a plurality of simulation cycles.

[0054] In some embodiments of the present disclosure, step S10 may include obtaining a simulation netlist and a simulation stimulus file corresponding to the integrated circuit, the simulation stimulus file including signal information of the integrated circuit, and performing a power supply voltage fluctuation simulation on the integrated circuit based on the simulation netlist and the simulation stimulus file to obtain power supply voltage simulation data.

[0055] In some embodiments of the present disclosure, for example, the simulation netlist corresponding to the integrated circuit records the connection relationship between various logic units of the integrated circuit at a certain logic level (for example, gate-level circuit). For example, the simulation stimulus file can record the signal information generated by the EDA simulation tool simulating the integrated circuit. In some embodiments of the present disclosure, the simulation stimulus file can be, for example, a Value change dump (abbreviated as "VCD") file.

[0056] In some embodiments of the present disclosure, for example, the simulation netlist and the simulation stimulus file may be pre-stored in a storage medium (memory). For example, the storage medium is directly accessed to obtain the simulation netlist and the simulation stimulus file corresponding to the integrated circuit.

[0057] In some embodiments of the present disclosure, for example, a simulator can be used to simulate power supply voltage fluctuations on an integrated circuit. For example, a simulation netlist and a simulation stimulus file (for example, a VCD file) are input into the simulator, and a parasitic parameter file corresponding to the integrated circuit (for example, a standard parasitic exchange format file, including power supply network data) is also input into the simulator, so that the simulator is used to simulate power supply voltage fluctuations on the integrated circuit to obtain power supply voltage simulation data.

[0058] The simulator performs power supply voltage fluctuation simulation on the integrated circuit to obtain the power supply voltage simulation value of each logic unit in each simulation cycle. Here, the power supply voltage simulation value of a logic unit in each simulation cycle is called the power supply voltage simulation sub-data corresponding to the logic unit, and the set of power supply voltage simulation sub-data corresponding to multiple logic units in the integrated circuit is the power supply voltage simulation data of the integrated circuit.

[0059] In some embodiments of the present disclosure, the simulator may be any tool that can simulate power supply voltage fluctuations on an integrated circuit, and the present disclosure does not limit the simulator. For example, the simulator may be a Redhawk tool or a Voltus voltage drop simulation tool from Cadance.

[0060] For step S20, for example, a static timing analysis tool (e.g., Tempus or Primetime) is used to obtain at least one timing path of the integrated circuit. For example, a static timing analysis tool is used to read in a netlist file, a parasitic parameter file, and a timing constraint file, and then the timing path of the integrated circuit is determined according to the netlist file, the parasitic parameter file, and the timing constraint file.

[0061] Figure 1B A schematic diagram of a timing path provided by at least one embodiment of the present disclosure is shown.

[0062] like Figure 1B As shown, the timing path may include a clock source 201 and multiple logic units, which may include, for example, a standard cell 202 , a standard cell 203 , a first flip-flop 204 , a combinational logic cell 205 , a standard cell 206 , and a second flip-flop 207 .

[0063] For example, the first trigger 204 may be a trigger for sending data, and the second trigger 207 may be a trigger for receiving data.

[0064] In some embodiments of the present disclosure, the timing path includes a clock path and a data path, the clock path is used to transmit a clock signal, and the data path is used to transmit a data signal. The clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a trigger for sending data, and the receiving clock path is a clock path of a trigger for receiving data.

[0065] For example, in Figure 1B In the illustrated scenario, the transmission clock path may be clock source 201 - standard cell 202 - standard cell 203, and the reception clock path may be clock source 201 - standard cell 202 - standard cell 206. The data path may include first flip-flop 204 - combinational logic unit 205 - second flip-flop 207.

[0066] For step S30, for example, Figure 1B In the illustrated scenario, the power supply voltage simulation sub-data of the standard cell 202 is processed to obtain the target voltage data of the standard cell 202, and the power supply voltage simulation sub-data of the standard cell 203 is processed to obtain the target voltage data of the standard cell 203. Similarly, the power supply voltage simulation sub-data corresponding to each of the logic cells other than the standard cell 202 and the standard cell 203 in the timing path are processed, which will not be described in detail here.

[0067] For step S40, for example, the target voltage data of at least one logic unit is used as the power supply voltage data, and the power supply voltage data of each logic unit is configured into the static timing analysis tool, so that the static timing analysis tool uses the power supply voltage data of each logic unit to perform static timing analysis on each timing path.

[0068] Figure 2A It shows that at least one embodiment of the present disclosure provides Figure 1A Flow chart of the method of step S30 in FIG.

[0069] like Figure 2A As shown, step S30 may include step S31 and step S32.

[0070] Step S31: for each timing path, processing the power supply voltage simulation sub-data of each logic unit in at least one logic unit in every two adjacent simulation cycles in multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0071] In some embodiments of the present disclosure, the timing path includes a clock path, and step S31 may include: determining at least one clock path logic unit located on the clock path in each timing path, and processing power supply voltage simulation sub-data of each clock logic unit in at least one clock path logic unit in every two adjacent simulation cycles in multiple simulation cycles.

[0072] In some other embodiments of the present disclosure, the timing path may also include a data path. In addition to the above-mentioned power supply voltage simulation sub-data processing for each clock logic unit in each two adjacent simulation cycles in multiple simulation cycles, step S31 may also include determining at least one data path logic unit located on the data path in each timing path, and power supply voltage simulation sub-data processing for each data logic unit in at least one data path logic unit in each two adjacent simulation cycles in multiple simulation cycles.

[0073] Since the clock path is more important for static timing analysis, while the data path is less important for static timing analysis, step S31 can only process the power supply voltage simulation sub-data of each clock logic unit in every two adjacent simulation cycles in multiple simulation cycles to save resources and improve efficiency.

[0074] In some embodiments of the present disclosure, for example, at least one clock path logic unit on a clock path may be acquired using an EDA tool. Figure 1B In the timing path shown, at least one clock path logic unit may include a standard cell 202 , a standard cell 203 , and a standard cell 206 .

[0075] Figure 2B It shows that at least one embodiment of the present disclosure provides Figure 1B Schematic diagram of power supply voltage simulation sub-data of standard cell 202. Figure 2B An embodiment of power supply voltage simulation sub-data processing for a logic unit in every two adjacent simulation cycles in a plurality of simulation cycles is exemplified.

[0076] like Figure 2B As shown, the schematic diagram includes a clock signal 301 and a waveform 302. For example, the waveform 302 may be formed by the power supply voltage simulation sub-data of the standard cell 202 changing with the clock. That is, the waveform 302 reflects the fluctuation of the power supply voltage simulation sub-data of the standard cell 202 with the clock.

[0077] For example, the scenario includes at least the first clock cycle 311 to the fourth clock cycle 314. Of course, in practice, the clock cycle is not necessarily 4 clock cycles, for example, it can be less than 4 clock cycles, or it can be more than 4 clock cycles. The present disclosure only takes 4 clock cycles as an example to illustrate the implementation of the present disclosure, but it does not limit the present disclosure.

[0078] For example, in step S31, the power supply voltage simulation sub-data of the first clock cycle 311 and the second clock cycle 312 are processed, the power supply voltage simulation sub-data of the second clock cycle 312 and the third clock cycle 313 are processed, and the power supply voltage simulation sub-data of the third clock cycle 313 and the fourth clock cycle 314 are processed, so as to obtain the voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of the standard unit 202 in adjacent cycles.

[0079] References below Figure 3 An embodiment of step S31 provided by at least one embodiment of the present disclosure is shown, and the following reference Figure 6 Another embodiment of step S31 provided by at least one embodiment of the present disclosure is shown and will not be described in detail here.

[0080] Continue to refer Figure 2A , step S32: determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter.

[0081] For example, the target voltage data of the standard cell 202 can be determined according to the voltage fluctuation characterization parameters of the standard cell 202. Similarly, the target voltage data of the logic cells other than the standard cell 202 in the timing path can also be determined according to the voltage fluctuation characterization parameters, which will not be described in detail here.

[0082] In the following, at least reference Figure 4 An embodiment of step S32 provided by at least one embodiment of the present disclosure is shown and will not be described in detail here.

[0083] In actual static timing analysis, for example, in setup time analysis, clock jitter caused by voltage changes in adjacent cycles often has a greater impact on setup time. Figure 2A In the described embodiment, the power supply voltage simulation sub-data in each two adjacent simulation cycles in multiple simulation cycles are processed to obtain the voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles, so as to determine the target voltage data of each logic unit according to the voltage fluctuation characterization parameters, so that the target voltage data can reflect the correlation between adjacent simulation cycles and make the results of static timing analysis more in line with the actual situation.

[0084] Figure 3 It shows that at least one embodiment of the present disclosure provides Figure 2A Flow chart of the method for step S31 in FIG.

[0085] like Figure 3 As shown, step S31 may include steps S301 to S303.

[0086] Step S301: for each timing path, determining a first voltage value of each logic unit in at least one logic unit in each simulation cycle of N simulation cycles.

[0087] In some embodiments of the present disclosure, the plurality of simulation cycles is N simulation cycles, where N is an integer greater than 0.

[0088] For example, for Figure 1BIn the timing path shown, at least one logic unit may include, for example, a standard unit 202, a standard unit 203, and a standard unit 206. For each logic unit in the standard unit 202, the standard unit 203, and the standard unit 206, a first voltage value in each simulation cycle in N simulation cycles is determined. For example, the first voltage value of the standard unit 202 in each simulation cycle in N simulation cycles is determined, the first voltage value of the standard unit 203 in each simulation cycle in N simulation cycles is determined, and so on.

[0089] In some embodiments of the present disclosure, for example, the first voltage value may be a maximum value of the power supply voltage simulation sub-data in each simulation cycle, or a minimum value of the power supply voltage simulation sub-data in each simulation cycle.

[0090] In some embodiments of the present disclosure, every two adjacent simulation cycles include a first simulation cycle and a second simulation cycle. Step S301 includes taking the maximum value in the power supply voltage simulation sub-data in the first simulation cycle as the first voltage value of the first simulation cycle, and taking the minimum value in the power supply voltage simulation sub-data in the second simulation cycle as the first voltage value of the second simulation cycle.

[0091] For example, in every two adjacent simulation cycles, the maximum value of the power supply voltage simulation sub-data in one simulation cycle is used as the first voltage value, and the minimum value of the power supply voltage simulation sub-data in another simulation cycle is used as the first voltage value.

[0092] For example, in Figure 2B In the power supply voltage simulation sub-data of the standard cell 202 shown in the figure, simulation cycle 311 and simulation cycle 312 are two adjacent simulation cycles, simulation cycle 312 and simulation cycle 313 are two adjacent simulation cycles, and simulation cycle 313 and simulation cycle 314 are two adjacent simulation cycles. Figure 2B As shown, the maximum value of the power supply voltage simulation sub-data in simulation cycle 311 is 0.99V, and the minimum value is 0.90V. The maximum value of the power supply voltage simulation sub-data in simulation cycle 312 is 0.98V, and the minimum value is 0.86V. The maximum value of the power supply voltage simulation sub-data in simulation cycle 313 is 0.91V, and the minimum value is 0.80V. The maximum value of the power supply voltage simulation sub-data in simulation cycle 314 is 0.98, and the minimum value is 0.85V. For example, the maximum value of the power supply voltage simulation sub-data in simulation cycle 311 is used as the first voltage value, that is, the first voltage value V in simulation cycle 311 202 (311) is 0.99 V. The minimum value in the power supply voltage simulation sub-data in the simulation cycle 312 is taken as the first voltage value, that is, the first voltage value V in the simulation cycle 312 202(312) is 0.86 V. The maximum value in the power supply voltage simulation sub-data in the simulation cycle 313 is taken as the first voltage value, that is, the first voltage value V in the simulation cycle 313 202 (313) is 0.91 V. The minimum value in the power supply voltage simulation sub-data in the simulation cycle 314 is taken as the first voltage value, that is, the first voltage value V in the simulation cycle 314 202 (314) is 0.85 V. Alternatively, the minimum value in the power supply voltage simulation sub-data in the simulation cycle 311 is used as the first voltage value, the maximum value in the power supply voltage simulation sub-data in the simulation cycle 312 is used as the first voltage value, the minimum value in the power supply voltage simulation sub-data in the simulation cycle 313 is used as the first voltage value, and the maximum value in the power supply voltage simulation sub-data in the simulation cycle 314 is used as the first voltage value.

[0093] Step S302: calculating the difference of the first voltage values ​​of each logic unit in each two adjacent simulation cycles of N simulation cycles to obtain N-1 difference values, and taking absolute values ​​of the N-1 difference values ​​to obtain N-1 voltage difference absolute values.

[0094] For example, in the scenario described in the above step S301 using the standard cell 202 as an example, the first voltage values ​​of the standard cell 202 in each two adjacent simulation cycles are calculated to obtain N-1 differences. 202 (311)-V 202 (312), V 202 (312)-V 202 (313) and V 202 (313)-V 202 (314). Then, in the case of V 202 (311)-V 202 (312), V 202 (312)-V 202 (313) and V 202 (313)-V 202 (314) respectively take the absolute value to obtain the three voltage difference absolute values. Figure 2B In the scenario described as an example of standard cell 202, the absolute values ​​of the three voltage differences are |V 202 (311)-V 202 (312)|、|V 202 (312)-V 202 (313)| and|V 202 (313)-V 202 (314)|.

[0095] The same processing operation as that for the power supply voltage simulation sub-data of the logic unit 202 is performed on the power supply voltage simulation sub-data of the logic unit 202 in the timing path, and will not be repeated here.

[0096] Step S303: Calculate the absolute values ​​of N-1 voltage differences to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0097] In some embodiments of the present disclosure, for example, the voltage fluctuation characterization parameter of the power supply voltage simulation sub-data of each logic unit in adjacent cycles is obtained by calculating the average value and / or standard deviation of N-1 voltage difference absolute values.

[0098] For example, the average value μ of N-1 absolute values ​​of voltage differences is used as the voltage fluctuation characterization parameter of the logic unit, or the standard deviation σ of the absolute values ​​of N-1 voltage differences is used as the voltage fluctuation characterization parameter of the logic unit, or the average value μ and the standard deviation σ of the absolute values ​​of N-1 voltage differences are used as the voltage fluctuation characterization parameter of the logic unit.

[0099] Those skilled in the art may also obtain the voltage fluctuation characterization parameter of the power supply voltage simulation sub-data of each logic unit in adjacent cycles by other calculation methods. For example, the N-1 voltage difference absolute values ​​may be sorted to obtain the median, and the median may be used as the voltage fluctuation characterization parameter.

[0100] Figure 4 It shows that at least one embodiment of the present disclosure provides Figure 2A Flow chart of the method for step S32 in FIG.

[0101] like Figure 4 As shown, step S32 includes step S321 and step S322.

[0102] Step S321: determining an average voltage value of each logic unit in a plurality of simulation cycles based on the power supply voltage simulation sub-data of each logic unit.

[0103] In some embodiments of the present disclosure, the average voltage value of each logic unit in multiple simulation cycles is The average value of all power supply voltage simulation sub-data of the logic unit in multiple simulation cycles may be calculated.

[0104] In some other embodiments of the present disclosure, for each logic unit, for example, the average value of the power supply voltage simulation sub-data of the logic unit in each simulation cycle can be first calculated, and then the average value of the average values ​​of the power supply voltage simulation sub-data corresponding to multiple simulation cycles can be calculated to obtain the average voltage value of the logic unit in multiple simulation cycles. .

[0105] Step S322: Determine target voltage data of each logic unit based on the average voltage value and the voltage fluctuation characterization parameter.

[0106] In some embodiments of the present disclosure, the voltage fluctuation characterization parameter includes an average value and a standard deviation of N-1 voltage difference absolute values. Step S322 may include: determining a confidence interval based on the average value and the standard deviation of the N-1 voltage difference absolute values, and determining target voltage data for each logic unit based on the average voltage value and the confidence interval.

[0107] In the embodiments of the present disclosure, for example, the confidence interval may be [μ-σ, μ+σ], [μ-2×σ, μ+2×σ], or [μ-3×σ, μ+3×σ], etc. Those skilled in the art may set the confidence interval according to the requirements for the confidence level. For example, if the confidence level is required to be 99.7%, the confidence interval may be set to [μ-3×σ, μ+3×σ].

[0108] Figure 5 A flow chart of a method for determining target voltage data of each logic unit based on an average voltage value and a confidence interval provided by at least one embodiment of the present disclosure is shown.

[0109] like Figure 5 As shown, the method may include steps S510 to S530.

[0110] Step S510: Determine the larger endpoint value of the two endpoint values ​​in the confidence interval as the fluctuation value.

[0111] For example, the confidence interval is [μ-3×σ, μ+3×σ], μ is the average value of the absolute value of the voltage difference, σ is the standard deviation, and the fluctuation value is determined to be μ+3×σ.

[0112] Step S520: taking the difference between the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the sending clock path.

[0113] In some embodiments of the present disclosure, the timing path includes a clock path, and the clock path includes a sending clock path and a receiving clock path. The sending clock path is the clock path of the device that sends the data signal, and the receiving clock path is the clock path of the device that receives the data signal.

[0114] like Figure 1B As shown, the clock path includes a sending clock path: clock source 201-standard cell 202-standard cell 203. The difference between the average voltage value of the standard cell 202 and the 1 / 2 times fluctuation value is used as the target voltage data of the standard cell 202 on the sending clock path (clock source 201-standard cell 202-standard cell 203). The calculation result is used as the target voltage data of the standard cell 202 on the sending clock path.

[0115] Step S530: taking the sum of the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the receiving clock path.

[0116] like Figure 1B As shown, the clock path includes a receiving clock path: clock source 201-standard cell 202-standard cell 206. The sum of the average voltage value of the standard cell 202 and the 1 / 2 times fluctuation value is used as the target voltage data of the standard cell 202 on the receiving clock path (clock source 201-standard cell 202-standard cell 206). The calculation result is used as the target voltage data of the standard cell 202 on the receiving clock path.

[0117] In some embodiments of the present disclosure, some logic units are located only on the transmit clock path (e.g. Figure 1B standard cell 203 in the receiving clock path (e.g. Figure 1B For the standard cell 206 in the clock path, the target voltage data is calculated according to step S520 for the logic cell located only on the sending clock path, and the target voltage data is calculated according to step S530 for the logic cell located only on the receiving clock path. That is, the target voltage data of the logic cell on the sending clock path is calculated according to step S520, and the target voltage data of the logic cell on the receiving clock path is calculated according to step S530.

[0118] In some embodiments of the present disclosure, the greater the voltage on the logic unit, the smaller the clock delay, and the smaller the voltage, the greater the clock delay. Therefore, the target voltage data of the logic unit in the sending clock path takes a smaller value, and the target voltage data of the logic unit in the receiving clock path takes a larger value, which can make the static timing analysis more rigorous. Therefore, this method can at least partially avoid the power supply voltage data used for static timing analysis from being too pessimistic, while making the results of static timing analysis more comprehensive and reliable.

[0119] Figure 6 It shows that at least one embodiment of the present disclosure provides Figure 2A Another method flow chart of step S31 in FIG.

[0120] like Figure 6 As shown, step S31 may include steps S304 to S306.

[0121] Step S304: for each timing path, determining a maximum value of a voltage difference between every two adjacent simulation cycles in each logic unit in at least one logic unit in a plurality of simulation cycles.

[0122] For example, step S304 may be to find out which two adjacent cycles have the largest voltage difference. Figure 1B In the scenario shown, a first initial value of the voltage difference between simulation cycle 311 and simulation cycle 312 is determined (for example, 0.99-0.86=0.13), a second initial value of the voltage difference between simulation cycle 312 and simulation cycle 313 is determined (for example, 0.98-0.80=0.18), a third initial value of the voltage difference between simulation cycle 313 and simulation cycle 314 is determined (for example, 0.98-0.80=0.18), and then the first initial value, the second initial value and the third initial value are compared to determine the maximum value of the voltage difference (for example, 0.18).

[0123] Step S305: Determine the minimum voltage value and the maximum voltage value in two simulation cycles corresponding to the maximum value.

[0124] For example, if the first initial value of the voltage difference between the simulation cycle 312 and the simulation cycle 313 is the maximum value, it can be determined that the maximum voltage value in the simulation cycle 312 and the simulation cycle 313 is 0.98 and the minimum voltage value is 0.80.

[0125] Step S306: taking the minimum voltage value and the maximum voltage value as voltage fluctuation characterization parameters.

[0126] For example, the minimum voltage value of 0.80 and the maximum voltage value of 0.98 are used as voltage fluctuation characterization parameters.

[0127] In some embodiments of the present disclosure, the timing path includes a clock path, the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives a data signal. Figure 6 In the illustrated embodiment, step S32 determines the target voltage data of each logic unit based on the voltage fluctuation characterization parameter, including: using the minimum voltage value as the target voltage data of each logic unit on the sending clock path, and using the maximum voltage value as the target voltage data of each logic unit on the receiving clock path.

[0128] For example, the minimum voltage value is used as the target voltage data of the logic unit on the sending clock path, and the maximum voltage value is used as the target voltage data of the logic unit on the receiving clock path. In other words, the target voltage data of each logic unit on the sending clock path is the above minimum voltage value, and the target voltage data of each logic unit on the receiving clock path is the above maximum voltage value.

[0129] For example, in Figure 1B and Figure 2BIn the illustrated scenario, for the standard cell 202, the maximum voltage value 0.98 is used as the target voltage data of the standard cell 202 on the receiving clock path (ie, 201-202-206), and the minimum voltage value 0.80 is used as the target voltage data of the standard cell 202 on the transmitting clock path (ie, 201-202-203).

[0130] In some embodiments of the present disclosure, the larger the voltage of the logic unit, the smaller the clock delay. Therefore, a smaller voltage value can be used as the target voltage data of the logic unit on the sending clock path, and a larger voltage value can be used as the target voltage data of the logic unit on the receiving clock path. This can make static timing analysis (such as setup time detection) more rigorous.

[0131] Some other embodiments of the present disclosure provide a static timing analysis method for an integrated circuit. The integrated circuit includes a plurality of logic units, and the method includes: obtaining power supply voltage simulation data obtained by simulating the integrated circuit in a plurality of simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the plurality of logic units in the plurality of simulation cycles; determining at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units; processing the power supply voltage simulation sub-data corresponding to each of the at least one logic unit in each timing path to obtain target voltage data of each of the at least one logic unit; and configuring the target voltage data of each of the at least one logic unit into a static timing analysis tool as the power supply voltage data of each of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of each of the at least one logic unit to perform static timing analysis on each timing path. The method uses the static timing analysis tool to directly analyze each timing path according to the power supply voltage data of each logic unit, thereby making the analysis result of the static timing analysis more accurate and reducing the pessimism of the analysis result.

[0132] Fig. 7A A flowchart of a static timing analysis method for an integrated circuit provided by at least one embodiment of the present disclosure is shown.

[0133] like Fig. 7A As shown, the static timing method may include steps S710 to S740.

[0134] Step S710: Acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles.

[0135] The power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in a plurality of logic units in a plurality of simulation cycles.

[0136] This step S710 is similar to the above Figure 1A The process is similar to step S10 in , and will not be described in detail here.

[0137] Step S720: determining at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units.

[0138] This step S720 is similar to the above Figure 1A The process is similar to step S20 in , and will not be repeated here.

[0139] Step S730: Process the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of at least one logic unit.

[0140] In some embodiments of the present disclosure, the timing path includes a clock path and a data path, and at least one logic unit in each timing path includes at least one clock path logic unit located in the clock path and at least one data path logic unit located in the data path.

[0141] Figure 7B It shows that at least one embodiment of the present disclosure provides Fig. 7A Schematic diagram of the method of step S730 in FIG.

[0142] like Figure 7B As shown, step S730 may include step S731 and step S732.

[0143] Step S731: Process the power supply voltage simulation sub-data corresponding to each of the at least one clock path logic units in each timing path to obtain target voltage data of each of the at least one clock path logic units.

[0144] In some embodiments of the present disclosure, for example, the above reference Figure 1A The method described in step S20 in the above process processes the power supply voltage simulation sub-data corresponding to each clock path logic unit in each timing path.

[0145] For example, for each clock path logic unit in at least one clock path logic unit, the power supply voltage simulation sub-data of each clock path logic unit in every two adjacent simulation cycles in the multiple simulation cycles are processed to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each clock path logic unit in adjacent cycles; and based on the voltage fluctuation characterization parameters, the target voltage data of each clock path logic unit is determined.

[0146] For example, according to the above reference Figure 3 to Figure 6The described method processes power supply voltage simulation sub-data of a clock path logic unit to obtain voltage fluctuation characterization parameters of the clock path logic unit, and determines target voltage data of each clock path logic unit based on the voltage fluctuation characterization parameters.

[0147] For step S731 , please refer to the implementation methods in the above multiple embodiments of the method for determining power supply voltage data in static timing analysis of an integrated circuit, which will not be described in detail here.

[0148] Step S732: Process the power supply voltage simulation sub-data corresponding to at least one data path logic unit in each timing path to obtain target voltage data of at least one data path logic unit.

[0149] In some embodiments of the present disclosure, for example, for each data path logic unit in each timing path, the minimum value of the power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles is determined, and the minimum value is used as the target voltage data of each data path logic unit.

[0150] In some other embodiments of the present disclosure, for example, for each data path logic unit in each timing path, the average value of the power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles is calculated, and the average value is used as the target voltage data of each data path logic unit.

[0151] Step S740: configuring the target voltage data of at least one logic unit into the static timing analysis tool as the power supply voltage data of at least one logic unit, so that the static timing analysis tool performs static timing analysis on each timing path using the power supply voltage data of at least one logic unit.

[0152] The static timing analysis tool may be any tool for static timing analysis available to those skilled in the art, such as Tempus, Primetime, and the like.

[0153] For example, the power supply voltage data of each logic unit is input or back-annotated into a static timing analysis tool, and the static timing analysis tool calculates the uncertainty of the setup time of each timing path according to the power supply voltage data, thereby obtaining the analysis result of the static timing analysis.

[0154] Figure 8 A flowchart of another static timing analysis method provided by at least one embodiment of the present disclosure is shown.

[0155] like Figure 8 As shown, the method may include steps S401 to S411.

[0156] Step S401: Obtain a simulation netlist.

[0157] In some embodiments of the present disclosure, the simulation netlist records the connection relationship between various logic units of the integrated circuit at a certain logic level (for example, gate-level circuit).

[0158] Step S402: Obtain VCD file.

[0159] For example, a VCD file records the signal information generated by an EDA simulation tool when simulating an integrated circuit.

[0160] Step S403: Utilize an EDA simulation tool to perform a power supply dynamic voltage drop simulation to obtain a simulation result.

[0161] For example, an EDA simulation tool uses a simulation netlist and a VCD file to simulate the dynamic voltage drop of an integrated circuit to obtain a simulation result.

[0162] For example, the simulation result may include power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, and the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles.

[0163] Step S404: Determine the power supply voltage simulation sub-data of each logic unit in the data path from the simulation result.

[0164] Step S405: Determine the power supply voltage simulation sub-data of each logic unit in the clock path from the simulation results.

[0165] Steps S401 to S405 are similar to the above-mentioned steps. Figure 1A Step S10 described.

[0166] Step S406: Calculate the average voltage value of each logic unit in the clock path.

[0167] For example, in step S406, the above reference may be performed Figure 4 The described step S321 is to determine the average voltage value of each logic unit in a plurality of simulation cycles based on the power supply voltage simulation sub-data of each logic unit.

[0168] Step S407: Calculate the absolute value of the voltage difference between adjacent cycles of each logic unit in the clock path.

[0169] For example, in step S407, the above reference may be performed Figure 3 The steps S301 and S302 described above are not described in detail here.

[0170] Step S408: Determine target voltage data of each logic unit located on the transmission clock path.

[0171] Step S409: Determine target voltage data of each logic unit located on the receiving clock path.

[0172] For example, step S408 and step S409 may be performed similarly to the above reference. Figure 4 The described step S322 will not be repeated here.

[0173] Step S410: determining target voltage data of each logic unit located on the data path.

[0174] For example, in step S410, the above reference may be performed Figure 4 The described step S732 will not be repeated here.

[0175] Step S411: The static timing analysis tool performs static timing analysis using the target voltage data.

[0176] For example, in step S410, the above reference may be performed Fig. 7A The described step S740 will not be repeated here.

[0177] Fig.9A A schematic block diagram of an apparatus 900 for determining power supply voltage data in static timing analysis of an integrated circuit provided by at least one embodiment of the present disclosure is shown.

[0178] For example, Fig.9A As shown, the device 900 includes a first acquisition module 910 , a first determination module 920 , a first processing module 930 and a second determination module 940 .

[0179] The first acquisition module 910 is configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in multiple simulation cycles. The first acquisition module 910 may, for example, execute Figure 1A Step S10 described.

[0180] In some embodiments of the present disclosure, power supply voltage simulation data obtained by simulating an integrated circuit in multiple simulation cycles is obtained, including: obtaining a simulation netlist and a simulation stimulus file corresponding to the integrated circuit, the simulation stimulus file including signal information of the circuit; and simulating power supply voltage fluctuations of the integrated circuit based on the simulation netlist and the simulation stimulus file to obtain power supply voltage simulation data.

[0181] The first determination module 920 is configured to determine at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units. The first determination module 920 may, for example, execute Figure 1A Step S20 described.

[0182] The first processing module 930 is configured to process the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain the target voltage data of at least one logic unit. The first processing module 930 may, for example, execute Figure 1A Step S30 described.

[0183] In some embodiments of the present disclosure, the first processing module includes: a first processing sub-module, configured to process, for each timing path, the power supply voltage simulation sub-data of each logic unit in at least one logic unit in each two adjacent simulation cycles in multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and a first determination sub-module, configured to determine the target voltage data of each logic unit based on the voltage fluctuation characterization parameters.

[0184] In some embodiments of the present disclosure, the timing path includes a clock path, and the first processing sub-module includes: a clock logic determination sub-module, configured to determine at least one clock path logic unit located on the clock path in each timing path; and a data processing sub-module, configured to process power supply voltage simulation sub-data of each clock path logic unit in at least one clock path logic unit in each two adjacent simulation cycles in multiple simulation cycles.

[0185] In some embodiments of the present disclosure, the multiple simulation cycles are N simulation cycles, where N is an integer greater than 0, and the first processing sub-module includes: a first voltage determination sub-module, configured to determine, for each timing path, a first voltage value of each logic unit in at least one logic unit in each of the N simulation cycles; a difference calculation sub-module, configured to calculate the difference between the first voltage values ​​of each logic unit in each two adjacent simulation cycles of the N simulation cycles to obtain N-1 differences, and to take absolute values ​​of the N-1 differences to obtain N-1 voltage difference absolute values; and an absolute value calculation sub-module, configured to calculate the N-1 voltage difference absolute values ​​to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0186] In some embodiments of the present disclosure, every two adjacent simulation cycles include a first simulation cycle and a second simulation cycle, and the first voltage determination submodule includes: a first cycle voltage determination submodule, configured to use the maximum value in the power supply voltage simulation sub-data in the first simulation cycle as the first voltage value of the first simulation cycle; and a second cycle voltage determination submodule, configured to use the minimum value in the power supply voltage simulation sub-data in the second simulation cycle as the first voltage value of the second simulation cycle.

[0187] In some embodiments of the present disclosure, the absolute value calculation submodule includes: a parameter calculation submodule, configured to calculate the average value and / or standard deviation of N-1 voltage difference absolute values ​​to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles.

[0188] In some embodiments of the present disclosure, the first determination submodule includes: an average voltage determination submodule, configured to determine the average voltage value of each logic unit in multiple simulation cycles based on the power supply voltage simulation sub-data of each logic unit; and a first target voltage determination submodule, configured to determine the target voltage data of each logic unit based on the average voltage value and the voltage fluctuation characterization parameter.

[0189] In some embodiments of the present disclosure, the voltage fluctuation characterization parameters include the average value and standard deviation of N-1 voltage difference absolute values, and the first determination submodule includes: an interval determination submodule, configured to determine the confidence interval based on the average value and standard deviation of the N-1 voltage difference absolute values; and a second target voltage determination submodule, configured to determine the target voltage data of each logic unit based on the average voltage value and the confidence interval.

[0190] In some embodiments of the present disclosure, the timing path includes a clock path, the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives a data signal, and the second target voltage determination submodule includes: a first fluctuation value determination submodule, configured to determine the larger endpoint value of two endpoint values ​​in a confidence interval as the fluctuation value; a first sending path voltage determination submodule, configured to use the difference between the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the sending clock path; and a first receiving path voltage determination submodule, configured to use the sum of the average voltage value and 1 / 2 times the fluctuation value as the target voltage data of each logic unit on the receiving clock path.

[0191] In some embodiments of the present disclosure, the confidence interval is [μ-3×σ, μ+3×σ], where μ is the average value of the absolute value of the voltage difference and σ is the standard deviation.

[0192] In some embodiments of the present disclosure, the first processing submodule includes: a voltage difference determination submodule, configured to determine, for each timing path, the maximum value of the voltage difference between each adjacent two simulation cycles of each logic unit in at least one logic unit in multiple simulation cycles; a voltage value determination submodule, configured to determine the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value; and a parameter determination submodule, configured to use the minimum voltage value and the maximum voltage value as voltage fluctuation characterization parameters.

[0193] In some embodiments of the present disclosure, the timing path includes a clock path, the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives a data signal, and the first determination submodule includes: a second sending path voltage determination submodule, configured to use a minimum voltage value as the target voltage data of each logic unit on the sending clock path; and a second receiving path voltage determination submodule, configured to use a maximum voltage value as the target voltage data of each logic unit on the receiving clock path.

[0194] The second determination module 940 is configured to use the target voltage data of at least one logic unit as the power supply voltage data of at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of at least one logic unit to perform static timing analysis on each timing path. The second determination module 940 can, for example, execute Figure 1A Step S40 described.

[0195] Fig. 9B A schematic block diagram of a static timing analysis device 1000 for an integrated circuit provided by at least one embodiment of the present disclosure is shown.

[0196] For example, Fig. 9B As shown, the static timing analysis device 1000 includes a second acquisition module 1010 , a third determination module 1020 , a second processing module 1030 and a fourth determination module 1040 .

[0197] The second acquisition module 1010 is configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in multiple simulation cycles. The second acquisition module 1010, for example, executes the above reference Fig. 7A Step S710 described above or reference Figure 1A Step S10 described.

[0198] The third determination module 1020 is configured to determine at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units. The third determination module 1020, for example, performs the above reference Fig. 7A Step S720 described above refers to Figure 1A Step S20 described.

[0199] The second processing module 1030 is configured to process the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain the target voltage data of at least one logic unit. Fig. 7A Step S730 described above refers to Figure 1A Step S30 described.

[0200] The fourth determination module 1040 is configured to configure the target voltage data of at least one logic unit into the static timing analysis tool as the power supply voltage data of at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of at least one logic unit to perform static timing analysis on each timing path. The fourth determination module 1040, for example, performs the above reference Fig. 7A Step S740 described above refers to Figure 1A Step S40 described.

[0201] In some embodiments of the present disclosure, the timing path includes a clock path and a data path, and at least one logic unit in each timing path includes at least one clock path logic unit located in the clock path and at least one data path logic unit located in the data path. The second processing module includes: a clock path processing sub-module, configured to process the power supply voltage simulation sub-data corresponding to each of the at least one clock path logic units in each timing path to obtain the target voltage data of each of the at least one clock path logic units; and a data path processing sub-module, configured to process the power supply voltage simulation sub-data corresponding to each of the at least one data path logic units in each timing path to obtain the target voltage data of each of the at least one data path logic units.

[0202] In some embodiments of the present disclosure, the clock path processing submodule includes: a second processing submodule, configured to process, for each clock path logic unit in at least one clock path logic unit, the power supply voltage simulation sub-data of each clock path logic unit in every two adjacent simulation cycles in multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each clock path logic unit in adjacent cycles; and a second determination submodule, configured to determine the target voltage data of each clock path logic unit based on the voltage fluctuation characterization parameters.

[0203] In some embodiments of the present disclosure, the data path processing submodule includes: a third determination submodule, configured to determine, for each data path logic unit in each timing path, a minimum value of power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles, and use the minimum value as the target voltage data of each data path logic unit; or a fourth determination submodule, configured to calculate, for each data path logic unit in each timing path, an average value of power supply voltage simulation sub-data of each data path logic unit in multiple simulation cycles, and use the average value as the target voltage data of each data path logic unit.

[0204] For example, the first acquisition module 910, the first determination module 920, the first processing module 930, the second determination module 940, the second acquisition module 1010, the third determination module 1020, the second processing module 1030 and the fourth determination module 1040 may be hardware, software, firmware and any feasible combination thereof. For example, the first acquisition module 910, the first determination module 920, the first processing module 930, the second determination module 940, the second acquisition module 1010, the third determination module 1020, the second processing module 1030 and the fourth determination module 1040 may be dedicated or general circuits, chips or devices, etc., or may be a combination of a processor and a memory. The embodiments of the present disclosure do not limit the specific implementation forms of the above-mentioned units.

[0205] It should be noted that, in the embodiment of the present disclosure, the various units of the device 900 for determining the power supply voltage data in the static timing analysis of the integrated circuit correspond to the various steps of the aforementioned method for determining the power supply voltage data in the static timing analysis of the integrated circuit. For the specific functions of the device 900, please refer to the relevant description of the method for determining the power supply voltage data, which will not be repeated here. Fig.9A The components and structures of the device 900 shown are only exemplary and non-restrictive. The device 900 may also include other components and structures as needed. In the embodiment of the present disclosure, the various units of the static analysis device 1000 correspond to the various steps of the aforementioned static timing analysis method. For the specific functions of the static analysis device 1000, reference may be made to the relevant description of the method for determining power supply voltage data, which will not be repeated here. Fig. 9B The components and structures of the static analysis device 1000 shown are merely exemplary and non-limiting. The static analysis device 1000 may further include other components and structures as required.

[0206] At least one embodiment of the present disclosure also provides an electronic device, the electronic device includes a processor and a memory, the memory includes one or more computer program modules. The one or more computer program modules are stored in the memory and are configured to be executed by the processor, and the one or more computer program modules include instructions for implementing the above-mentioned method for determining power supply voltage data in static timing analysis of an integrated circuit or a static timing analysis method. The electronic device can reduce the pessimistic amount of power supply voltage data used for static timing analysis, thereby making the result of static timing analysis more accurate.

[0207] Fig.10 A schematic block diagram of an electronic device provided in some embodiments of the present disclosure. Fig.10 As shown, the electronic device 1100 includes a processor 1110 and a memory 1120. The memory 1120 is used to store non-transitory computer-readable instructions (e.g., one or more computer program modules). The processor 1110 is used to execute non-transitory computer-readable instructions. When the non-transitory computer-readable instructions are executed by the processor 1110, the method for determining power supply voltage data in the static timing analysis of an integrated circuit or one or more steps in the static timing analysis method described above can be executed. The memory 1120 and the processor 1110 can be interconnected through a bus system and / or other forms of connection mechanisms (not shown).

[0208] For example, the processor 1110 may be a central processing unit (CPU), a graphics processing unit (GPU), or other forms of processing units having data processing capabilities and / or program execution capabilities. For example, the central processing unit (CPU) may be an X86 or ARM architecture, etc. The processor 1110 may be a general-purpose processor or a dedicated processor, and may control other components in the electronic device 1100 to perform desired functions.

[0209] For example, the memory 1120 may include any combination of one or more computer program products, and the computer program product may include various forms of computer-readable storage media, such as volatile memory and / or non-volatile memory. Volatile memory may include, for example, random access memory (RAM) and / or cache memory (cache), etc. Non-volatile memory may include, for example, read-only memory (ROM), hard disk, erasable programmable read-only memory (EPROM), portable compact disk read-only memory (CD-ROM), USB memory, flash memory, etc. One or more computer program modules may be stored on the computer-readable storage medium, and the processor 1110 may run one or more computer program modules to implement various functions of the electronic device 1100. Various applications and various data, as well as various data used and / or generated by the application, etc. may also be stored in the computer-readable storage medium.

[0210] It should be noted that in the embodiment of the present disclosure, the specific functions and technical effects of the electronic device 1100 can refer to the above description of the method for determining power supply voltage data in static timing analysis of an integrated circuit or the static timing analysis method, and will not be repeated here.

[0211] Fig.11 A schematic block diagram of another electronic device provided in some embodiments of the present disclosure. The electronic device 1200 is suitable for implementing the method for determining power supply voltage data in static timing analysis of an integrated circuit or the static timing analysis method provided in the embodiments of the present disclosure. The electronic device 1200 may be a terminal device, etc. It should be noted that, Fig.11 The electronic device 1200 shown is merely an example and does not impose any limitation on the functions and scope of use of the embodiments of the present disclosure.

[0212] like Fig.11 As shown, the electronic device 1200 may include a processing device (e.g., a central processing unit, a graphics processor, etc.) 1210, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 1220 or a program loaded from a storage device 1280 to a random access memory (RAM) 1230. In the RAM 1230, various programs and data required for the operation of the electronic device 1200 are also stored. The processing device 1210, the ROM 1220, and the RAM 1230 are connected to each other via a bus 1240. An input / output (I / O) interface 1250 is also connected to the bus 1240.

[0213] Typically, the following devices may be connected to the I / O interface 1250: an input device 1260 including, for example, a touch screen, a touch pad, a keyboard, a mouse, a camera, a microphone, an accelerometer, a gyroscope, etc.; an output device 1270 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; a storage device 1280 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 1290. The communication device 1290 may allow the electronic device 1200 to communicate with other electronic devices wirelessly or by wire to exchange data. Although Fig.11 The electronic device 1200 is shown to have various devices, but it should be understood that it is not required to implement or possess all the devices shown, and the electronic device 1200 may alternatively implement or possess more or fewer devices.

[0214] For example, according to an embodiment of the present disclosure, the above-mentioned method for determining power supply voltage data in static timing analysis of an integrated circuit or a static timing analysis method can be implemented as a computer software program. For example, an embodiment of the present disclosure includes a computer program product, which includes a computer program carried on a non-transitory computer-readable medium, and the computer program includes a program code for executing the above-mentioned method for determining power supply voltage data in static timing analysis of an integrated circuit or a static timing analysis method. In such an embodiment, the computer program can be downloaded and installed from a network through a communication device 1290, or installed from a storage device 1280, or installed from a ROM 1220. When the computer program is executed by the processing device 1210, the functions defined in the method for determining power supply voltage data in static timing analysis of an integrated circuit or a static timing analysis method provided in an embodiment of the present disclosure can be implemented.

[0215] At least one embodiment of the present disclosure also provides a computer-readable storage medium, which is used to store non-temporary computer-readable instructions. When the non-temporary computer-readable instructions are executed by a computer, the above-mentioned method for determining power supply voltage data in static timing analysis of an integrated circuit or static timing analysis method can be implemented. By using the computer-readable storage medium, the pessimistic amount of power supply voltage data used for static timing analysis can be reduced, thereby making the result of static timing analysis more accurate.

[0216] Fig.12 A schematic diagram of a storage medium provided in some embodiments of the present disclosure. Fig.12 As shown, the storage medium 1300 is used to store non-transitory computer-readable instructions 1310. For example, when the non-transitory computer-readable instructions 1310 are executed by a computer, one or more steps of the method for determining power supply voltage data in static timing analysis of an integrated circuit or the static timing analysis method described above can be performed.

[0217] For example, the storage medium 1300 may be applied to the electronic device 1100. Fig.10 The memory 1120 in the electronic device 1100 is shown. For example, the relevant description of the storage medium 1100 can refer to Fig.10 The corresponding description of the memory 1120 in the electronic device 1100 is shown and will not be repeated here.

[0218] There are a few points to note:

[0219] (1) The drawings of the embodiments of the present disclosure only relate to the structures involved in the embodiments of the present disclosure, and other structures may refer to the general design.

[0220] (2) In the absence of conflict, the embodiments of the present disclosure and the features therein may be combined with each other to obtain new embodiments.

[0221] The above description is only a specific implementation of the present disclosure, but the protection scope of the present disclosure is not limited thereto. The protection scope of the present disclosure shall be based on the protection scope of the claims.

Claims

1. A method for determining power supply voltage data in static timing analysis of an integrated circuit, the integrated circuit comprising a plurality of logic units, the method comprising: Acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; determining at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic cell in the plurality of logic cells; Processing the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and using the target voltage data of the at least one logic unit as the power supply voltage data of the at least one logic unit, so that the static timing analysis tool performs static timing analysis on each timing path by using the power supply voltage data of the at least one logic unit. Wherein, the at least one timing path includes a clock path, and the clock path includes a sending clock path and a receiving clock path, the sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives the data signal; The processing of the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit includes: For each timing path, processing the power supply voltage simulation sub-data of each logic unit in the at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and Determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter; The processing of the power supply voltage simulation sub-data of each logic unit in each two adjacent simulation cycles in the multiple simulation cycles for each timing path to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles includes: For each of the timing paths, determining a maximum value of a voltage difference between two adjacent simulation cycles in each of the at least one logic unit in the plurality of simulation cycles, Determine the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value, and Using the minimum voltage value and the maximum voltage value as the voltage fluctuation characterization parameters; Wherein, determining the target voltage data of each logic unit based on the voltage fluctuation characterization parameter includes: using the minimum voltage value as target voltage data of each logic unit on the transmission clock path, and The maximum voltage value is used as target voltage data of each logic unit on the receiving clock path.

2. The method according to claim 1, wherein: For each timing path, processing power supply voltage simulation sub-data of each logic unit in the at least one logic unit in every two adjacent simulation cycles in the multiple simulation cycles includes: determining at least one clock path logic unit located on the clock path in each of the timing paths; and The power supply voltage simulation sub-data of each clock path logic unit in the at least one clock path logic unit in every two adjacent simulation cycles in the plurality of simulation cycles are processed.

3. The method according to claim 1, wherein: The multiple simulation cycles are N simulation cycles, where N is an integer greater than 0. For each timing path, processing the power supply voltage simulation sub-data of each logic unit in the at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles, including: For each of the timing paths, determining a first voltage value of each of the at least one logic unit in each of the N simulation cycles; Calculating the difference between the first voltage values ​​of each logic unit in each two adjacent simulation cycles of the N simulation cycles to obtain N-1 difference values, and taking absolute values ​​of the N-1 difference values ​​to obtain N-1 voltage difference absolute values; and The voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles are obtained by calculating the N-1 voltage difference absolute values.

4. The method according to claim 3, wherein: Each two adjacent simulation cycles include a first simulation cycle and a second simulation cycle. Determining a first voltage value of each logic unit in each simulation cycle of the N simulation cycles includes: taking the maximum value in the power supply voltage simulation sub-data in the first simulation cycle as the first voltage value of the first simulation cycle; and The minimum value in the power supply voltage simulation sub-data in the second simulation cycle is used as the first voltage value of the second simulation cycle.

5. The method according to claim 3, wherein: The voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles are obtained by calculating the N-1 voltage difference absolute values, including: The voltage fluctuation characterization parameter of the power supply voltage simulation sub-data of each logic unit in adjacent cycles is obtained by calculating the average value and / or standard deviation of the N-1 voltage difference absolute values.

6. The method according to claim 3, wherein: Determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter includes: determining an average voltage value of each logic unit in the plurality of simulation cycles based on the power supply voltage simulation sub-data of each logic unit; and The target voltage data of each logic unit is determined based on the average voltage value and the voltage fluctuation characterization parameter.

7. The method according to claim 6, wherein: The voltage fluctuation characterization parameters include the average value and standard deviation of the N-1 voltage difference absolute values, Determining the target voltage data of each logic unit based on the average voltage value and the voltage fluctuation characterization parameter includes: Determining a confidence interval based on an average of the N-1 absolute values ​​of the voltage differences and the standard deviation; and Target voltage data of each logic unit is determined based on the average voltage value and the confidence interval.

8. The method according to claim 7, wherein: Determining target voltage data of each logic unit based on the average voltage value and the confidence interval includes: Determine the larger endpoint value of the two endpoint values ​​in the confidence interval as the fluctuation value; Using the difference between the average voltage value and the 1 / 2 times fluctuation value as the target voltage data of each logic unit on the transmission clock path; and The sum of the average voltage value and the 1 / 2 times fluctuation value is used as target voltage data of each logic unit on the receiving clock path.

9. The method according to claim 8, wherein: The confidence interval is [μ-3×σ, μ+3×σ], where μ is the average value of the absolute value of the voltage difference, and σ is the standard deviation.

10. The method according to claim 1, acquiring power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, comprising: Acquire a simulation netlist and a simulation stimulus file corresponding to the integrated circuit, wherein the simulation stimulus file includes signal information of the circuit; as well as A power supply voltage fluctuation simulation is performed on the integrated circuit based on the simulation netlist and the simulation stimulus file to obtain the power supply voltage simulation data.

11. A static timing analysis method for an integrated circuit, wherein: The integrated circuit includes a plurality of logic units, and the method includes: Acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; determining at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic cell in the plurality of logic cells; Processing the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and configuring the target voltage data of each of the at least one logic unit into a static timing analysis tool as the power supply voltage data of each of the at least one logic unit, so that the static timing analysis tool performs static timing analysis on each of the timing paths using the power supply voltage data of each of the at least one logic unit, The at least one timing path includes a clock path, and the clock path includes a sending clock path and a receiving clock path. The sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives the data signal. The processing of the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit includes: For each timing path, processing the power supply voltage simulation sub-data of each logic unit in the at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and Determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter; The processing of the power supply voltage simulation sub-data of each logic unit in each two adjacent simulation cycles in the multiple simulation cycles for each timing path to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles includes: For each of the timing paths, determining a maximum value of a voltage difference between two adjacent simulation cycles in each of the at least one logic unit in the plurality of simulation cycles, Determine the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value, and Using the minimum voltage value and the maximum voltage value as the voltage fluctuation characterization parameters; Wherein, determining the target voltage data of each logic unit based on the voltage fluctuation characterization parameter includes: using the minimum voltage value as target voltage data of each logic unit on the transmission clock path, and The maximum voltage value is used as target voltage data of each logic unit on the receiving clock path.

12. The method according to claim 11, wherein: The timing path also includes a data path, and the at least one logic unit in each timing path includes at least one clock path logic unit located in the clock path and at least one data path logic unit located in the data path. Processing the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit includes: Processing the power supply voltage simulation sub-data corresponding to each of the at least one clock path logic units in each of the timing paths to obtain target voltage data of each of the at least one clock path logic units; and The power supply voltage simulation sub-data corresponding to each of the at least one data path logic units in each of the timing paths are processed to obtain target voltage data of each of the at least one data path logic units.

13. The method according to claim 12, wherein: Processing the power supply voltage simulation sub-data corresponding to each of the at least one clock path logic units in each of the timing paths to obtain target voltage data of each of the at least one clock path logic units includes: For each clock path logic unit in the at least one clock path logic unit, processing the power supply voltage simulation sub-data of each clock path logic unit in every two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each clock path logic unit in adjacent cycles; and Based on the voltage fluctuation characterization parameter, target voltage data of each clock path logic unit is determined.

14. The method according to claim 12, processing the power supply voltage simulation sub-data corresponding to at least one data path logic unit in each timing path to obtain target voltage data of the at least one data path logic unit, comprising: For each data path logic unit in each timing path, determine a minimum value of power supply voltage simulation sub-data of each data path logic unit in the multiple simulation cycles, and use the minimum value as target voltage data of each data path logic unit; or For each data path logic unit in each timing path, an average value of power supply voltage simulation sub-data of each data path logic unit in the multiple simulation cycles is calculated, and the average value is used as target voltage data of each data path logic unit.

15. An apparatus for determining power supply voltage data in static timing analysis of an integrated circuit, comprising: A first acquisition module is configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; a first determination module configured to determine at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units; A first processing module is configured to process the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and The second determining module is configured to use the target voltage data of the at least one logic unit as the power supply voltage data of the at least one logic unit, so that the static timing analysis tool uses the power supply voltage data of the at least one logic unit to perform static timing analysis on each timing path. The at least one timing path includes a clock path, and the clock path includes a sending clock path and a receiving clock path. The sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives the data signal. The processing of the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit includes: For each timing path, processing the power supply voltage simulation sub-data of each logic unit in the at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and Determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter; The processing of the power supply voltage simulation sub-data of each logic unit in each two adjacent simulation cycles in the multiple simulation cycles for each timing path to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles includes: For each of the timing paths, determining a maximum value of a voltage difference between two adjacent simulation cycles in each of the at least one logic unit in the plurality of simulation cycles, Determine the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value, and Using the minimum voltage value and the maximum voltage value as the voltage fluctuation characterization parameters; Wherein, determining the target voltage data of each logic unit based on the voltage fluctuation characterization parameter includes: using the minimum voltage value as target voltage data of each logic unit on the transmission clock path, and The maximum voltage value is used as target voltage data of each logic unit on the receiving clock path.

16. A static timing analysis device for an integrated circuit, wherein: The integrated circuit includes a plurality of logic units, and the device includes: A second acquisition module is configured to acquire power supply voltage simulation data obtained by simulating the integrated circuit in multiple simulation cycles, wherein the power supply voltage simulation data includes power supply voltage simulation sub-data of each logic unit in the multiple logic units in the multiple simulation cycles; a third determination module configured to determine at least one timing path in the integrated circuit, wherein each timing path in the at least one timing path includes at least one logic unit in the plurality of logic units; A second processing module is configured to process the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit; and a fourth determination module configured to configure the target voltage data of each of the at least one logic unit into the static timing analysis tool as the power supply voltage data of each of the at least one logic unit, so that the static timing analysis tool performs static timing analysis on each of the timing paths using the power supply voltage data of each of the at least one logic unit; The at least one timing path includes a clock path, and the clock path includes a sending clock path and a receiving clock path. The sending clock path is a clock path of a device that sends a data signal, and the receiving clock path is a clock path of a device that receives the data signal. The processing of the power supply voltage simulation sub-data corresponding to at least one logic unit in each timing path to obtain target voltage data of the at least one logic unit includes: For each timing path, processing the power supply voltage simulation sub-data of each logic unit in the at least one logic unit in each two adjacent simulation cycles in the multiple simulation cycles to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles; and Determining target voltage data of each logic unit based on the voltage fluctuation characterization parameter; The processing of the power supply voltage simulation sub-data of each logic unit in each two adjacent simulation cycles in the multiple simulation cycles for each timing path to obtain voltage fluctuation characterization parameters of the power supply voltage simulation sub-data of each logic unit in adjacent cycles includes: For each of the timing paths, determining a maximum value of a voltage difference between two adjacent simulation cycles in each of the at least one logic unit in the plurality of simulation cycles, Determine the minimum voltage value and the maximum voltage value in the two simulation cycles corresponding to the maximum value, and Using the minimum voltage value and the maximum voltage value as the voltage fluctuation characterization parameters; Wherein, determining the target voltage data of each logic unit based on the voltage fluctuation characterization parameter includes: using the minimum voltage value as target voltage data of each logic unit on the transmission clock path, and The maximum voltage value is used as target voltage data of each logic unit on the receiving clock path.

17. An electronic device comprising: processor; a memory including one or more computer program instructions; The one or more computer program instructions are stored in the memory and, when executed by the processor, implement instructions of the method described in any one of claims 1 to 14.

18. A computer-readable storage medium for storing non-transitory computer-readable instructions, which, when executed by a computer, can implement the method of any one of claims 1 to 14.