The invention provides a ground source
heat pump buried
pipe system design method based on building load change, comprising the following steps: S1, acquiring
geological survey data, meteorological data and building load data, and presetting buried
pipe heat exchange
system parameters; s2, establishing a multi-
physics field
coupling numerical model; s3, transient
simulation is carried out through a multi-
physics field
coupling numerical model, and
system short-term thermal response characteristic data corresponding to each candidate length are acquired and stored; s4, constructing and training a long-term dynamic
performance prediction model through the long and short-
term memory network model; and S5, based on a multi-objective optimization
algorithm, solving a multi-objective
optimization problem, obtaining a group of
Pareto optimal buried
pipe total length solution sets, and selecting a final buried pipe optimal total length from the optimal solution sets. According to the method, the design precision of the ground source
heat pump buried pipe can be remarkably improved, the long-term
dynamic prediction capacity is achieved, the reliability, economical efficiency and environment friendliness of long-term operation of a ground source
heat pump system can be guaranteed, and the design efficiency and reliability are improved.