A geological disaster monitoring device and power supply method thereof
By using solar panels, lithium batteries and supercapacitors in geological disaster monitoring equipment, combined with the alternate power supply scheme of multiple energy storage units, the problem of insufficient power supply of high-power modules in the field environment is solved, and the reliability and reliability of the equipment are improved. Power supply stability.
Patent Information
- Application Number
- CN202010659717.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-10
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-07-10
AI Technical Summary
Existing universal geological disaster monitoring equipment is difficult to meet the power supply needs of high-power modules in the wild environment, especially Beidou communication, radar transceiver and other modules that have insufficient instantaneous high-power power supply capabilities.
A geological disaster monitoring equipment is designed, which uses solar panels, lithium batteries, supercapacitors and multiple energy storage units. The alternating power supply is controlled by the processor to ensure stable power supply for high-power modules, including solar panels, charge controllers, batteries, The power module and energy storage unit use multiple energy storage units to supply power in turn to avoid insufficient power in a single energy storage unit.
It improves the reliability and power supply stability of geological disaster monitoring equipment, meets the power supply needs of high-power electronic devices, and extends the service life of the equipment.
Smart Images

Figure CN113922480B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electrical equipment, and in particular to a geological disaster monitoring device and a power supply method thereof. Background Art
[0002] Universal geological disaster monitoring equipment is mainly used for disaster risk monitoring that threatens less than 10 people or less than 1 million assets. It has the characteristics of functional applicability, low cost, low power consumption, easy installation and cloud-based collaborative management.
[0003] In the prior art, most universal geological disaster monitoring equipment is an integrated device that integrates sensors, data acquisition, data transmission, and power supply for easy installation in the field. Due to the many limitations of the field environment and the equipment itself, the solar energy and battery combination power supply unit generally has a small amount of power, especially the ability to provide instantaneous high-power power supply is poor. However, in actual applications, due to reasons such as the communication environment and measurement methods, universal geological disaster monitoring equipment needs to include multiple high-power modules such as Beidou communication, radar transceiver, GNSS, etc., and using only solar energy and battery combination power supply often cannot meet the power supply requirements.
[0004] Therefore, how to propose a geological disaster monitoring device that can guarantee the power supply needs of high-power modules to improve the reliability of the device has become an important issue that needs to be solved in this field. Summary of the invention
[0005] In view of the problems in the prior art, an embodiment of the present invention provides a geological disaster monitoring device and a power supply method thereof, which can at least partially solve the problems in the prior art.
[0006] On the one hand, the present invention provides a geological disaster monitoring device, including a solar panel, a first charge controller, a battery, a first power module, a second charge controller, at least two energy storage units and a second power module, wherein:
[0007] The solar panel is connected to the first charge controller, the first charge controller is respectively connected to the battery, the second charge controller and the first power module, the battery is respectively connected to the first power module and the second charge controller, the second charge controller is connected to each energy storage unit through a first switch unit, and each energy storage unit is connected to the second power module through a second switch unit; wherein the first power module includes a processor, and the processor is respectively connected to the first switch unit and the second switch unit.
[0008] The first power module further includes a temperature sensor and a memory, and the processor is connected to the temperature sensor and the memory respectively.
[0009] Wherein, the second power module includes at least one of a communication unit, a radar, an image collector and an infrared sensor.
[0010] Wherein, the communication unit is a Beidou communication unit.
[0011] Wherein, the geological disaster monitoring equipment includes two energy storage units.
[0012] Wherein, the energy storage unit adopts a super capacitor.
[0013] Wherein, the storage battery is a lithium battery.
[0014] Wherein, the processor adopts a micro control unit.
[0015] On the other hand, the present invention provides a power supply method, which is applied to the geological disaster monitoring equipment described in any of the above embodiments, comprising:
[0016] If the processor learns that the periodic task is started, it triggers the storage battery through the first charging controller to supply power to the first power module so that the first power module performs the first periodic subtask;
[0017] The processor detects the power status of each energy storage unit, and controls an energy storage unit with the most sufficient power to supply power to the second power module so that the second power module performs the second periodic subtask.
[0018] The power supply method provided by the embodiment of the present invention further includes:
[0019] If the processor determines that the energy storage unit supplying power to the second power module is insufficient in power, the processor switches the storage unit supplying power to the second power module and charges the insufficient energy storage unit.
[0020] The geological disaster monitoring equipment and power supply method thereof provided by the embodiment of the present invention include a solar panel, a first charging controller, a battery, a first power module, a second charging controller, at least two energy storage units and a second power module. The solar panel is connected to the first charging controller, the first charging controller is respectively connected to the battery, the second charging controller and the first power module, the battery is respectively connected to the first power module and the second charging controller, the second charging controller is connected to each energy storage unit through a first switch unit, each energy storage unit is connected to the second power module through a second switch unit, the first power module includes a processor, the processor is respectively connected to the first switch unit and the second switch unit, and the second power module is alternately powered by multiple energy storage units, which can meet the power supply requirements of high-power electronic devices and improve the reliability of the geological disaster monitoring equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0022] Figure 1 It is a structural schematic diagram of a geological disaster monitoring device provided by an embodiment of the present invention.
[0023] Figure 2 It is a structural schematic diagram of a geological disaster monitoring device provided by another embodiment of the present invention.
[0024] Figure 3 It is a flowchart of a power supply method provided by an embodiment of the present invention.
[0025] Figure 4 It is a flowchart of a power supply method provided by another embodiment of the present invention.
[0026] Description of reference numerals:
[0027] 1-solar panel; 2-first charge controller; 3-battery; 4-first power module;
[0028] 5-second charging controller; 6-energy storage unit; 7-second power module; 41-processor;
[0029] 42- temperature sensor; 43- memory. DETAILED DESCRIPTION
[0030] In order to make the purpose, technical scheme and advantages of the embodiments of the present invention more clear, the embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. Here, the illustrative embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention. It should be noted that, in the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other arbitrarily.
[0031] Figure 1 FIG. 1 is a schematic diagram of the structure of a geological disaster monitoring device provided by an embodiment of the present invention. Figure 1 As shown, the geological disaster monitoring device provided by the embodiment of the present invention includes a solar panel 1, a first charging controller 2, a battery 3, a first power module 4, a second charging controller 5, at least two energy storage units 6 and a second power module 7, wherein:
[0032] The solar panel 1 is connected to the first charge controller 2, the first charge controller 2 is respectively connected to the storage battery 3, the second charge controller 5 and the first power module 4, the storage battery 3 is respectively connected to the first power module 4 and the second charge controller 5, the second charge controller 5 is connected to each energy storage unit 6 through the first switch unit 8, and each energy storage unit is connected to the second power module 7 through the second switch unit 9; wherein, the first power module 4 includes a processor 41, and the processor 41 is respectively connected to the first switch unit 8 and the second switch unit 9. The processor 41 controls the first switch unit 8 and the second switch unit 9 to connect each energy storage unit 6 to the charging line or the power supply line. When the energy storage unit 6 is connected to the charging line, the energy storage unit 6 can be charged by the solar panel 1 or the storage battery 3, and when the energy storage unit 6 is connected to the power supply line, the energy storage unit 6 can supply power to the second power module 7.
[0033] Specifically, the solar panel 1 is used to charge the battery 3 and each energy storage unit 6, and the battery 3 is used to power the first power module 4 and charge each energy storage unit 6. The first charging controller 2 is used to control the charging of the battery 3, monitor the charging state of the battery 3 during the charging process of the battery 3, and can also play a role in charging protection for the battery 3. The first power module 4 may include low-power electronic devices such as a processor, a temperature sensor, an acceleration sensor, and a memory, which are set according to actual needs and are not limited in the embodiment of the present invention. The electronic devices included in the first power module 4 do not have a circuit with a large instantaneous current consumption. The energy storage unit 6 is used to power the second power module 7, and the processor 41 controls the first switch unit 8 and the second switch unit 9 to realize that multiple energy storage units 6 take turns to power the second power module 7. The second charging controller 5 is used to control the charging of each energy storage unit 6, monitor the charging state of each energy storage unit 6 during the charging process of each energy storage unit 6, and can also play a role in charging protection for each energy storage unit 6. The second power module 7 may include high-power electronic devices such as a communication unit, a radar, an image collector, and an infrared sensor, which are set according to actual needs and are not limited in the embodiment of the present invention. The second power module 7 includes electronic devices including circuits that consume a large instantaneous current.
[0034] In actual operation, the geological disaster monitoring device may have three power supply states: idle state, first power supply state and second power supply state. In idle state, the geological disaster monitoring device is in sleep mode, each electronic device enters low power consumption or power-off state, and the processor 41 enters sleep state. At this time, the solar panel 1 can charge the battery 3 and each energy storage unit 6 to fully charge the battery 3 and each energy storage unit 6, so that the battery 3 and each energy storage unit 6 are in a fully charged state. In the first power supply state, the battery 3 supplies power to the first power module 4, at which time each energy storage unit 6 may not work and is in a fully charged state. In the second power supply state, the battery 3 supplies power to the first power module 4, and the processor 41 controls the first switch unit 8 and the second switch unit 9 to realize that each energy storage unit 6 alternately supplies power to the second power module 7. Among them, in the process of each energy storage unit 6 alternately supplying power to the second power module 7, if the power of a certain energy storage unit 6 is insufficient, the processor 41 can control the battery 3 to charge the insufficient energy storage unit 6. The processor 41 controls the first switch unit 8 and the second switch unit 9 to realize that one energy storage unit 6 supplies power to the second power module 7, and the other energy storage units 6 are in a charging state or an idle state. Since the geological disaster monitoring device is in a sleep mode for a long time in actual work, there is enough time to fully charge the battery 3 and each energy storage unit 6 during the periodic task.
[0035] The geological disaster monitoring equipment provided by the embodiment of the present invention includes a solar panel, a first charging controller, a storage battery, a first power module, a second charging controller, at least two energy storage units and a second power module, the solar panel is connected to the first charging controller, the first charging controller is respectively connected to the storage battery, the second charging controller and the first power module, the storage battery is respectively connected to the first power module and the second charging controller, the second charging controller is connected to each energy storage unit through the first switch unit, each energy storage unit is connected to the second power module through the second switch unit, the first power module includes a processor, the processor is respectively connected to the first switch unit and the second switch unit, and the second power module is alternately powered by multiple energy storage units, which can meet the power supply requirements of high-power electronic devices and improve the reliability of the geological disaster monitoring equipment. In addition, the first power module is powered by the storage battery, and the second power module is powered by the energy storage unit, so as to avoid the influence of the instantaneous large current of the high-power electronic device on the small-power electronic device, and improve the power supply stability of the geological disaster monitoring equipment.
[0036] Figure 2 FIG. 1 is a schematic diagram of the structure of a geological disaster monitoring device provided by another embodiment of the present invention. Figure 2As shown, based on the above embodiments, the first power module 4 further includes a temperature sensor 42 and a memory 43, and the processor 41 is respectively connected to the temperature sensor 42 and the memory 43. The temperature sensor 42 is used to collect temperature data, and the processor 41 can store the collected temperature data in the memory 43.
[0037] On the basis of the above embodiments, further, the second power module 7 includes at least one of a communication unit, a radar, an image collector and an infrared sensor. The communication unit may be a mobile communication unit or a satellite communication unit. The image collector may be a camera.
[0038] On the basis of the above embodiments, further, the communication unit is a Beidou communication unit, which can upload the collected data.
[0039] On the basis of the above embodiments, further, the geological disaster monitoring equipment includes two energy storage units 6, and the two energy storage units 6 can realize alternating power supply to the second power module 7. When one energy storage unit 6 is supplying power to the second power module 7, the other energy storage unit 6 can be charged, thereby realizing continuous power supply to the second power module 7.
[0040] On the basis of the above embodiments, further, the energy storage unit 6 adopts a super capacitor.
[0041] On the basis of the above embodiments, further, the storage battery 3 is a lithium battery.
[0042] On the basis of the above embodiments, further, the processor 41 adopts a microcontroller unit (MCU), which is also called a single chip microcomputer.
[0043] Figure 3 is a flow chart of a power supply method provided by an embodiment of the present invention, such as Figure 3 As shown, the power supply method provided in the embodiment of the present invention is applied to the geological disaster monitoring equipment described in any of the above embodiments, including:
[0044] S301: If the processor learns that a periodic task is started, the processor triggers the battery to supply power to the first power module through the first charging controller so that the first power module performs the first periodic subtask;
[0045] Specifically, the geological disaster monitoring device will set a periodic task that is started regularly. If the processor learns that the periodic task is started, it will trigger the battery to power the first power module through the first charging controller. After the first power module obtains power, the geological disaster monitoring device is in a first power supply state, and the first power module will perform a first periodic subtask. Among them, the first periodic subtask is set according to actual needs, such as data collection, which is not limited in the embodiment of the present invention. It is understandable that the geological disaster monitoring device can be in a sleep mode during the period when the periodic task is not executed, and the power supply state of the geological disaster monitoring device is an idle state.
[0046] S302: The processor detects the power status of each energy storage unit, and controls an energy storage unit with the most power to supply power to the second power module so that the second power module performs the second periodic subtask.
[0047] Specifically, after the first power module completes the first cycle subtask, the processor will detect the power status of each energy storage unit, and control the energy storage unit with the most power to power the second power module through the first switch unit and the second switch unit. After the second power module obtains power, the geological disaster monitoring equipment is in a second power supply state, and the second power module will perform the second cycle subtask. Among them, the second cycle subtask is set according to actual needs, such as data transmission, and the embodiment of the present invention is not limited. It is understandable that if the power status of at least two energy storage units in each energy storage unit is the same, for example, both are 100%, then an energy storage unit can be randomly selected to power the second power module.
[0048] According to the power supply method provided by the embodiment of the present invention, after the processor learns that a periodic task has started, the processor triggers the battery through the first charging controller to supply power to the first power module so that the first power module performs the first periodic subtask. The processor detects the power status of each energy storage unit, controls the energy storage unit with the most sufficient power to supply power to the second power module so that the second power module performs the second periodic subtask. The first power module is supplied by the battery, and the second power module is supplied by the energy storage unit, thereby avoiding the influence of instantaneous high current of high-power electronic devices on small-power electronic devices, and improving the power supply stability of the geological disaster monitoring equipment.
[0049] Figure 4 is a flow chart of a power supply method provided by another embodiment of the present invention, such as Figure 4 As shown, based on the above embodiments, the power supply method provided in the embodiment of the present invention further includes:
[0050] S303: If the processor determines that the energy storage unit supplying power to the second power module is insufficient in power, the processor switches the storage unit supplying power to the second power module and charges the insufficient energy storage unit.
[0051] Specifically, when the energy storage unit supplies power to the second power module, the second charging controller will report the remaining power of the energy storage unit to the processor, and the processor will compare the remaining power of the energy storage unit with the power supply threshold. If the remaining power is less than the power supply threshold, it indicates that the power of the energy storage unit is insufficient. The processor will select an energy storage unit with sufficient power from the remaining energy storage units, and then control the first switch unit and the second switch unit to switch the storage unit that supplies power to the second power module from the insufficient energy storage unit to the sufficient energy storage unit, and charge the insufficient energy storage unit. The power supply threshold is set according to actual experience, for example, it is set to 10%, and the embodiment of the present invention does not limit it.
[0052] The power supply method provided in the embodiment of the present invention can meet the power supply requirements of high-power electronic devices and improve the reliability of geological disaster monitoring equipment by alternately supplying power to the second power module through multiple energy storage units.
[0053] The following is a specific example to illustrate the structural composition of the geological disaster monitoring equipment provided by the embodiment of the present invention. The solar panel 1 adopts a solar panel with a specification of 5.5V and 3W. The first charging controller 2 uses a CN3082 chip. The battery 3 adopts a 3.7V and 20Ah lithium battery, and the operating voltage of the lithium battery is 2.5-4.2V. The first power module 4 includes an MCU, a temperature sensor and a memory. The second charging controller 5 uses a CN3125 chip. Two energy storage units 6 are used, and the energy storage unit 6 uses a supercapacitor. The first switch unit 8 and the second switch unit 9 respectively use two single-pole double-throw (SPDT) switches, and the input end of each energy storage unit 6 is connected to a SPDT switch, and the output end of each energy storage unit 6 is connected to a SPDT switch. The second power module 7 includes a Beidou communication unit.
[0054] The CN3125 chip limits the charging current of the two supercapacitors to a maximum of 1A, and the supercapacitor charging and discharging efficiency is 90%. The Beidou communication unit has two power supply states when working, namely, a power supply state of 3A for 10s and a power supply state of 600mA for 30s. The Beidou communication unit has a maximum of 3 working cycles in one working process, and each working cycle interval is 1 minute.
[0055] The Beidou communication unit first sends data during work. At this time, it is powered by a super capacitor with a current of 3A for 10s. After the data transmission is completed, it switches to the data receiving state. At this time, it is powered by a current of 600mA for 30s, still powered by a super capacitor. If no reply information is received in the data receiving state, it indicates that the data transmission failed. The Beidou communication unit feeds back the information of data transmission failure to the MCU, and the MCU will instruct the Beidou communication unit to resend the data after one minute until the Beidou communication unit receives the feedback information or the Beidou communication unit has sent data three times.
[0056] The power consumption of a single working cycle of the Beidou communication unit is 3A×10s+0.6A×30s=0.013Ah. When one supercapacitor powers the Beidou communication unit, the other supercapacitor is charged. In a single working cycle of the Beidou communication unit, the supercapacitor replenishes power of 1A×60s×90%=0.015Ah, that is to say, the power replenished by the supercapacitor can meet the consumption of a single working cycle of the Beidou communication unit. When two supercapacitors supply power alternately, the power consumption requirements of multiple working cycles of the Beidou communication unit can be guaranteed.
[0057] The following specific embodiment is used to illustrate the power supply process of the geological disaster monitoring equipment provided by the above embodiment.
[0058] The first step is to power on the geological disaster monitoring device for initialization. After the initialization is completed, the start time of the periodic task has not been reached. The power supply state of the geological disaster monitoring device is idle, the geological disaster monitoring device is in sleep mode, the MCU, temperature sensor and memory of the geological disaster monitoring device enter a low power consumption state, and the solar panel charges the battery and two supercapacitors. Among them, when there is no periodic task, the power supply state of the geological disaster monitoring device is idle. When the battery power is less than 10%, the power supply state of the geological disaster monitoring device will also become idle.
[0059] Step 2: The MCU detects whether the periodic task start time has arrived. If the periodic task start time has arrived, the power supply state of the geological disaster monitoring equipment is the first power supply state. The MCU will trigger the battery through the first charging controller to power the MCU, temperature sensor and memory, so that the MCU, temperature sensor and memory can work normally.
[0060] Step 3: The temperature sensor will collect temperature data and transmit the temperature data to the MCU, which will store the collected temperature data in the memory. The MCU will determine whether the temperature data needs to be sent through the Beidou communication unit. If so, it will proceed to step 4; if not, it will proceed to step 8.
[0061] Step 4, MCU detects the power status of the two supercapacitors, and then selects a supercapacitor with sufficient power, and disconnects the charging circuit of the supercapacitor with sufficient power and opens the power supply circuit of the supercapacitor with sufficient power by controlling the input SPDT switch and the output SPDT switch of the supercapacitor with sufficient power, so that the supercapacitor with sufficient power supplies power to the Beidou communication unit, and the geological disaster monitoring equipment is in the second power supply state. For the other supercapacitor, by controlling the input SPDT switch and the output SPDT switch of the other supercapacitor, disconnect the power supply circuit of the other supercapacitor and open the charging circuit of the other supercapacitor, and charge the other supercapacitor. The CN3125 chip will detect the charging status of the other supercapacitor. When the other supercapacitor is fully charged, the CN3125 chip will disconnect the charging circuit, so that the other supercapacitor stops charging.
[0062] Step 5. The Beidou communication unit receives the temperature data transmitted by the MCU and sends the temperature data. At this time, the supercapacitor provides 3A current to the Beidou communication unit and lasts for 10s. After the data transmission is completed, the Beidou communication unit switches to the data receiving state. At this time, the supercapacitor provides 600mA current to the Beidou communication unit and lasts for up to 30s. If the Beidou communication unit does not receive a reply message, it indicates that the temperature data transmission failed, and it will enter the sixth step. If the Beidou communication unit receives a reply message, it indicates that the temperature data was successfully sent, and it will enter the seventh step.
[0063] Step 6: The Beidou communication unit transmits the sending failure information to the MCU. After receiving the sending failure information, the MCU will determine how many times the sending has failed. If the number of sending failures is not equal to 3, it is determined to resend the data and repeat step 4 after 1 minute. If the number of sending failures is equal to 3, it means that the current communication conditions are not very good, and the temperature data will be sent after the next periodic task is started, and the process goes to step 8.
[0064] Step 7: The Beidou communication unit transmits the sending success information to the MCU, and the MCU controls the power supply line of the supercapacitor currently powering the Beidou communication unit to be disconnected and the charging line to be opened, and the Beidou communication unit is in a power-off state.
[0065] Step 8: After the cycle task is completed, the MCU will trigger the battery to reduce the power supply to the MCU, temperature sensor and memory through the first charging controller, so that the MCU, temperature sensor and memory enter a low power consumption state. The geological disaster monitoring device enters a sleep mode, and the power supply state is an idle state.
[0066] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0067] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0068] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0069] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0070] In the description of this specification, the description with reference to the terms "one embodiment", "a specific embodiment", "some embodiments", "for example", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0071] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A geological disaster monitoring device, characterized in that: It includes a solar panel, a first charging controller, a rechargeable battery, a first power module, a second charging controller, at least two energy storage units and a second power module, wherein: The solar panel is connected to the first charge controller, the first charge controller is respectively connected to the rechargeable battery, the second charge controller and the first power module, the rechargeable battery is respectively connected to the first power module and the second charge controller, the second charge controller is connected to each energy storage unit through a first switch unit, and each energy storage unit is connected to the second power module through a second switch unit; wherein the first power module includes a processor, and the processor is respectively connected to the first switch unit and the second switch unit; in, The power of the electronic components of the first power module is less than the power of the electronic components of the second power module; When the start time of the periodic task has not been reached, the solar panel is controlled by the first charging controller and the second charging controller to charge the rechargeable battery and the energy storage unit; When the start time of the periodic task is reached, the first charging controller triggers the rechargeable battery to power the first power module, so that the first power module performs the first periodic subtask; the first switch unit and the second switch unit control the energy storage unit with the most power to power the second power module, so that the second power module performs the second periodic subtask.
2. The geological disaster monitoring device according to claim 1, characterized in that: The first power module further includes a temperature sensor and a memory, and the processor is connected to the temperature sensor and the memory respectively.
3. The geological disaster monitoring device according to claim 1, characterized in that: The second power module includes at least one of a communication unit, a radar, an image collector, and an infrared sensor.
4. The geological disaster monitoring device according to claim 3, characterized in that: The communication unit is a Beidou communication unit.
5. The geological disaster monitoring device according to claim 1, characterized in that: Includes two energy storage units.
6. The geological disaster monitoring device according to claim 1, characterized in that: The energy storage unit adopts a super capacitor.
7. The geological disaster monitoring device according to claim 1, characterized in that: The rechargeable battery is a lithium battery.
8. The geological disaster monitoring device according to any one of claims 1 to 7, characterized in that: The processor is a micro control unit.
9. A power supply method, applied to the geological disaster monitoring equipment according to any one of claims 1 to 8, characterized in that: include: If the processor learns that the periodic task is started, it triggers the rechargeable battery through the first charging controller to supply power to the first power module so that the first power module performs the first periodic subtask; The processor detects the power status of each energy storage unit, and controls an energy storage unit with the most sufficient power to supply power to the second power module so that the second power module performs the second periodic subtask.
10. The method according to claim 9, characterized in that Also includes: If the processor determines that the energy storage unit supplying power to the second power module is insufficient in power, the processor switches the energy storage unit supplying power to the second power module and charges the insufficient energy storage unit.
Citation Information
Patent Citations
Control system and control method
CN111146857A
Super capacitor compensation type solar energy street lamp power supply system and control device thereof
CN204350377U
Robot hybrid power supply system
CN209562207U