A steel guide rail pole and pole external equipment installation method

By welding the steel guide rail on the pillar body to form a card slot installation device connection device, the problem of weak loading capacity of aluminum alloy guide rails and the risk of drop equipment drop equipment is solved, and higher bearing capacity and stability are achieved.

CN114046486BActive Publication Date: 2025-01-24DEYANG HENGDA LUMINAIRE MFG
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202111521632.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-13
Publication Date
2025-01-24
Estimated Expiration
2041-12-13

AI Technical Summary

Technical Problem

The load-bearing capacity of aluminum alloy guide rails on the existing pole column bodies is weak, and the installation of heavier external equipment has the problem of falling risk.

Method used

The steel guide rail pillar is used, and the steel guide rail is welded on the side wall of the pillar body to form a card slot to install the first device connection device to improve the carrying capacity of the external device.

Benefits of technology

It improves the loading capacity of external devices, enhances the stability of installation, and avoids the risk of dropping the drop of external equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114046486B_ABST
    Figure CN114046486B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of communication lighting facilities, and in particular to a steel guide rail pole and a method for installing pole external equipment, comprising a pole body, at least one group of steel guide rails being welded on the side wall of the pole body, each group of the steel guide rails forming a slot with the side wall of the pole body, the slot being used for arranging cables and installing a first equipment connection device, the steel guide rails having high strength and strong bearing capacity, the steel guide rails being welded on the side wall of the pole body, the steel guide rails forming a slot with the side wall of the pole body, the cables of the external equipment being arranged in the slot, the slot being also used for installing the first equipment connection device, having good stability, and being able to improve the ability of the external equipment to bear the weight compared to arranging the aluminum alloy guide rail on the pole body to install the external equipment, thereby solving the problem that the bearing capacity of the aluminum alloy guide rail on the existing pole body is weak and there is a risk of falling when installing heavier external equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of communication lighting facilities, and in particular to a steel guide rail pole and a method for installing pole external equipment. Background Art

[0002] With the rapid urbanization process in my country, street lamps are no longer limited to lighting functions. Various external devices such as cameras, LED lights, communication devices or billboards are often installed on the poles according to needs. With the increase in the number and quality of external devices, the requirements for the load-bearing capacity and installation stability of external devices installed on poles are gradually increasing. Conventionally, the following are installed on poles: Fig.30 The "C"-shaped steel rail shown is used to install external equipment. Under the action of lateral wind load, the external equipment is prone to shaking, resulting in a gap between the external equipment and the "C"-shaped steel rail, which in turn affects the stability of the connection between the external equipment and the steel rail. Aluminum alloy rails are installed on the poles to install external equipment. The bearing capacity of aluminum alloy rails is weak, and there is a risk of falling for external equipment with heavy installation weight.

[0003] In summary, there is an urgent need for a technical solution to solve the technical problem that the aluminum alloy guide rail on the pole body has a weak bearing capacity and there is a risk of falling when installing heavier external equipment. Summary of the invention

[0004] The purpose of the present invention is to provide a steel guide rail pole and a pole external equipment installation method to address the problem that the aluminum alloy guide rail on the existing pole body has weak bearing capacity and there is a risk of falling when installing heavier external equipment.

[0005] To achieve the above object, the technical solution adopted by the present invention is:

[0006] A steel guide rail pole comprises a pole body, on the side wall of which at least one group of steel guide rails is welded, each group of the steel guide rails forms a slot with the side wall of the pole body, and a first equipment connection device is installed in the slot.

[0007] The steel guide rail has high strength and strong load-bearing capacity. The steel guide rail is welded to the side wall of the pole body. The steel guide rail and the side wall of the pole body form a slot. The cable of the external device is arranged in the slot. The slot is also used to install the first device connection device. It has good stability. Compared with arranging aluminum alloy guide rails on the pole body to install external devices, it can improve the ability to bear the weight of external devices and solve the problem that the aluminum alloy guide rails on the existing pole body have weak load-bearing capacity and there is a risk of falling when installing heavier external devices.

[0008] Preferably, the first device connection device comprises a special-shaped bolt fastener and an external device connection member; the external device connection member is detachably connected to the slot via the special-shaped bolt fastener, so as to facilitate installation and disassembly of the external device connection member at the construction site.

[0009] Preferably, the special-shaped bolt fastener comprises a special-shaped screw and a first nut, one end of the special-shaped screw is provided with a hook wedge portion, and the hook wedge portion matches the inner side wall of the steel guide rail. The special-shaped bolt fastener is installed in the slot through the hook wedge portion, and the hook wedge portion matches the inner side wall of the steel guide rail, which is conducive to improving the stability of the installation of the special-shaped screw and the slot.

[0010] Preferably, the special-shaped screw is further provided with a limiting part, the limiting part and the hook wedge part are located at one end of the special-shaped screw, and the limiting part can abut against the bottom of the slot, thereby generating a pre-tightening force for positioning the special-shaped screw relative to the steel guide rail. The limiting part abuts against the bottom of the slot, generating a pre-tightening force that can abut and position the hook wedge part against the inner wall of the steel guide rail, preventing the special-shaped screw from moving along the slot under the action of gravity and falling, making it convenient for operators to install external device connectors on the special-shaped screw.

[0011] Preferably, the limiting portion includes a limiting block, the limiting block is arranged at one side of the hook wedge portion, the limiting block is provided with a first screw hole penetrating therethrough, a stud is arranged in the first screw hole, and the stud is threadedly connected to the first screw hole. The stud is threadedly connected to the first screw hole, the stud moves along the axial direction of the first screw hole, one end of the stud abuts against the bottom of the slot, and the reaction force of the bottom of the slot on the stud can generate a pre-tightening force through the limiting block to make the hook wedge portion abut against the inner wall of the slot, thereby achieving the purpose of positioning the special-shaped screw in the slot.

[0012] Preferably, a protrusion is provided on the inner side wall of the steel guide rail, and the protrusion matches the hook wedge portion.

[0013] Preferably, the hook wedge portion is provided with a first contact portion and a second contact portion, respectively, and the first contact portion and the second contact portion can contact both sides of the protrusion at the same time. The first contact portion contacts the inner wall of the card slot to form a first clamping force, and the second contact portion contacts the inner wall of the card slot to form a second clamping force. The normal line of the first clamping force along the contact surface and the normal line of the second clamping force along the contact surface can intersect to form an angle. Through the joint action of the first clamping force and the second clamping force, and the normal line of the first clamping force along the contact surface and the normal line of the second clamping force along the contact surface can intersect to form an angle, the hook wedge portion generates a clamping force on the card slot, which can effectively reduce the force shaking of the external device connected by the special-shaped screw.

[0014] Preferably, the hook wedge portion is also provided with a profile, and the profile is located between the first contact portion and the second contact portion. When the first contact portion and the second contact portion contact both sides of the protrusion at the same time, a gap is formed between the profile and the protrusion. Under the action of a lateral external force, the hook wedge portion of the special-shaped screw rod is the main force-bearing portion, and the contact portion between the first contact portion and the slot and the contact portion between the second contact portion and the slot are both prone to deformation. The gap between the profile and the inner wall of the slot forms an elastic deformation space for the hook wedge portion, thereby forming a pre-tensioning force on the hook wedge portion relative to the slot. Under the action of the pre-tensioning force, the hook wedge portion has the effect of reducing the rigidity of the connection between the hook wedge portion and the slot, preventing the special-shaped screw rod from loosening, and enhancing the stability of the installation of the first equipment connection device.

[0015] Preferably, the first contact portion is in arc surface contact with the slot, and the second contact portion is in line contact or point contact with the slot.

[0016] Preferably, the cross-section of the column body is a triangular cross-section or a polygonal cross-section, and the steel guide rail is located on at least one side of the column body (1); or, the cross-section of the column body (1) is a circular cross-section or a special-shaped cross-section, and at least one set of the steel guide rails is provided on the side wall of the column body.

[0017] Preferably, part of the side wall of the rod column body is recessed inward to form a first groove, and the steel guide rail is arranged in the first groove.

[0018] Preferably, the rod column body is a tapered structural member or a tapered diameter-changing structural member, which has the effect of enhancing the stability of the rod column body and saving materials.

[0019] Preferably, the cross-section of the column body is a triangular cross-section or a polygonal cross-section, and the steel guide rail is located on at least one side of the column body; or the cross-section of the column body is a circular cross-section or a special-shaped cross-section, and at least one set of the steel guide rails is provided on the side wall of the column body.

[0020] Preferably, part of the side wall of the rod column body is recessed inward to form a first groove, and the steel guide rail is arranged in the first groove.

[0021] Preferably, the rod column body comprises an inner rod body and an outer rod body, wherein the outer rod body is arranged outside the inner rod body, and the inner rod body and the outer rod body are fixedly connected. The outer rod body is connected to an external device, and the lateral load on the external device is transmitted to the inner rod body through the outer rod body, and the inner rod body can enhance the ability of the rod column body to resist the lateral load.

[0022] Preferably, the cross section of the outer rod body is a triangular cross section or a polygonal cross section, and the steel guide rail is located on at least one side of the rod column body; or it is a circular cross section or a special-shaped cross section, and at least one set of the steel guide rails is provided on the side wall of the rod column body.

[0023] Preferably, part of the side wall of the outer rod body is recessed inward to form a first groove, and the steel guide rail is arranged in the first groove.

[0024] Preferably, the outer rod body is a tapered structural member or a tapered diameter-changing structural member.

[0025] Preferably, the cross-section of the inner rod body is a triangular cross-section, a triangular conical cross-section, a polygonal cross-section, a polygonal conical cross-section, a special-shaped cross-section, a special-shaped conical cross-section or a conical cross-section.

[0026] A street lamp comprises a pole body, a lamp holder and a cross bar, wherein the lamp holder is arranged on the upper part of the pole body, the cross bar is arranged on the side wall of the pole body, and at least one group of steel guide rails is welded to the side wall of the pole body, each group of the steel guide rails forms a slot with the side wall of the pole body, and a first equipment connecting device is installed in the slot.

[0027] The street lamp comprises a pole body, a lamp holder and a cross bar, the lamp holder is arranged at the top end of the pole body, the cross bar is arranged on the side wall of the pole body, and at least one set of steel guide rails are welded to the side wall of the pole body, the steel guide rails have high strength and strong bearing capacity, the steel guide rails and the side wall of the pole body form a slot, the slot is used to arrange the cable of the external device, the slot is also used to install the first device connection device, and has good stability. Compared with arranging aluminum alloy rails on the street lamp to install external devices, the ability to bear the weight of the external device can be improved, and the problem that the bearing capacity of the aluminum alloy rails on the existing street lamps is weak and there is a risk of falling when installing heavier external devices is solved.

[0028] Preferably, the cross section of the cross bar is a circular cross section, a quadrilateral cross section, a hexagonal cross section, an octagonal cross section or a special-shaped cross section.

[0029] Preferably, at least one set of steel rails is welded to the upper surface of the crossbar, and each set of the steel rails forms a slot with the side wall of the crossbar, and the slot is used to arrange cables and install the first device connection device or the second device connection device. The slot facilitates the arrangement of cables and the installation of the first device connection device or the second device connection device on the crossbar.

[0030] Preferably, the second device connection device comprises a bolt fastening assembly and an external device connection piece, and the external device connection piece is detachably connected to the card slot via a bolt fastener. This facilitates the installation and removal of the external device connection piece at the construction site.

[0031] Preferably, the bolt fastening assembly comprises a screw rod, a second nut and a clamping plate, wherein the clamping plate is provided with a second screw hole penetrating therethrough, one end of the screw rod is threadedly connected to the second screw hole, and the other end of the screw rod is threadedly connected to the second nut.

[0032] Preferably, the clamping plate can contact the raised portion on the inner side wall of the steel guide rail, and the screw rod can abut against the bottom of the slot to generate a pre-tightening force for positioning the screw rod relative to the slot. The screw rod abuts against the bottom of the slot to generate a pre-tightening force that can position the clamping plate against the raised portion on the inner side wall of the slot, thereby preventing the screw rod from moving along the slot and falling under the action of gravity, and facilitating the operator to install the external device connector or the external device connector on the screw rod.

[0033] Preferably, part of the side wall of the clamping plate is recessed toward one side to form a second groove. The second groove and the clamping slot are combined to form a cavity, which is convenient for arranging the cables.

[0034] A method for installing a crossbar external device comprises the following steps:

[0035] S1: Weld the steel guide rail to the upper surface of the crossbar; S2: Set the clamp in the slot, and adjust the lateral position of the clamp in the slot according to the installation position of the external device, rotate the screw along the second screw hole of the clamp to pre-tighten the screw and the inner wall of the slot; S3: Arrange the cables in the slot; S4: The screw passes through the connecting hole on the external device connector, and then is connected to the second nut through the screw to install and position the external device connector on the steel guide rail.

[0036] A method for installing a pole external device comprises the following steps:

[0037] S1: Install the steel guide rail on the side wall of the pole body; S2: Set the hook wedge part of the special-shaped screw in the slot, and adjust the vertical installation position of the special-shaped screw in the slot according to the installation height of the external device, rotate the stud along the first screw hole of the limiting part, so that the hook wedge part of the special-shaped screw and the inner wall of the slot are pre-tightened and positioned; S3: Arrange the cables in the slot; S4: The special-shaped screw passes through the connecting hole on the external device connector, and then is connected to the first nut through the special-shaped screw, so that the external device connector is installed and positioned on the steel guide rail.

[0038] Compared with the prior art, the advantages of the present invention are: the present invention provides a steel guide rail pole column, the steel guide rail has high strength and strong bearing capacity, the steel guide rail is welded to the side wall of the pole column body, the steel guide rail and the side wall of the pole column body form a slot, the slot is used to arrange the cable of the external device, the slot is also used to install the first device connection device, the stability is good, and the ability to bear the weight of the external device can be improved compared to arranging the aluminum alloy guide rail on the pole column body to install the external device, and solves the problem that the bearing capacity of the aluminum alloy guide rail on the existing pole column body is weak and there is a risk of falling when installing heavier external devices.

[0039] The beneficial effects of other embodiments of the present application are:

[0040] 1. The shape of the steel guide rail is adapted to the outer wall of the pole body, which helps to improve the stability of the steel guide rail when installed on the pole body.

[0041] 2. The special-shaped bolt fastener is installed in the slot through the hook wedge portion, and the hook wedge portion matches the inner side wall of the slot, which is beneficial to improving the stability of the installation of the special-shaped screw and the slot.

[0042] 3. By abutting the limiting part against the bottom of the slot, a pre-tightening force is generated to enable the hook wedge part to abut against the inner wall of the slot to position it, thereby preventing the special-shaped screw from moving along the slot and falling under the action of gravity, making it convenient for operators to install external device connectors on the special-shaped screw.

[0043] 4. The stud is threadedly connected to the first screw hole. The stud moves axially along the first screw hole. One end of the stud abuts against the bottom of the slot. The reaction force of the bottom of the slot on the stud can generate a pre-tightening force through the limit block to make the hook wedge abut against the inner wall of the slot, thereby achieving the purpose of positioning the special-shaped screw in the slot.

[0044] 5. The first contact portion contacts the inner wall of the slot to form a first clamping force, the second contact portion contacts the inner wall of the slot to form a second clamping force, the normal line of the first clamping force along the contact surface and the normal line of the second clamping force along the contact surface can intersect to form an angle, through the joint action of the first clamping force and the second clamping force, and the normal line of the first clamping force along the contact surface and the normal line of the second clamping force along the contact surface can intersect to form an angle, so that the hook wedge portion generates a clamping force on the slot, which can effectively reduce the force shaking of the external device connected by the special-shaped screw.

[0045] 6. The rod column body includes an inner rod body and an outer rod body. The outer rod body is connected to the external equipment. The lateral load on the external equipment is transmitted to the inner rod body through the outer rod body. The inner rod body can enhance the ability of the rod column body to resist the lateral load.

[0046] 7. The external device is connected through the outer rod body, and the lateral load on the external device is transmitted to the inner rod body through the outer rod body. The inner rod body can enhance the ability of the rod column body to resist the lateral load.

[0047] 8. The screw rod abuts against the bottom of the slot, generating a pre-tightening force that enables the clamp plate to abut against the raised portion on the inner wall of the slot to position the clamp, thereby preventing the screw rod from moving along the slot and falling under the action of gravity, making it convenient for operators to install external device connectors or external device connectors on the screw rod.

[0048] 9. The second groove and the card slot form a cavity, which is convenient for the arrangement of cables. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 The present invention is a structural schematic diagram of a steel guide rail pole.

[0050] Figure 2 for Figure 1 Schematic diagram of the cross-section structure.

[0051] Figure 3 for Figure 2 A partial enlarged view of area A in the middle.

[0052] Figure 4 It is a schematic diagram of the structure of a special-shaped bolt fastener.

[0053] Figure 5 Schematic diagram of the structure for installing cross bars on steel guide rail poles.

[0054] Figure 6 for Figure 5 A schematic structural diagram of the cross section of the middle cross bar mounting the second equipment connection device.

[0055] Figure 7 Schematic diagram of the structure of the splint.

[0056] Figure 8 for Figure 5 A schematic structural diagram of the cross section of the first equipment connection device installed on the middle cross bar.

[0057] Fig. 9 for Figure 5 A three-dimensional structural schematic diagram of the first equipment connecting device installed on the middle cross bar.

[0058] Fig.10 for Figure 5 A three-dimensional structural schematic diagram of the first device connecting device installed on the middle cross bar from another perspective.

[0059] Fig.11 Schematic diagram of the structure of the cross section of a hexagonal crossbar.

[0060] Fig.12 It is a structural schematic diagram of the cross section of a "D"-shaped crossbar.

[0061] Fig.13 It is a structural schematic diagram of the cross section of the octagonal cross bar.

[0062] Fig.14 It is a structural schematic diagram of the cross section of a circular crossbar.

[0063] Fig.15 This is a schematic diagram of the structure of a steel rail street light.

[0064] Fig.16 It is a structural schematic diagram of an octagonal column cross section.

[0065] Fig.17 It is a structural schematic diagram of a hexagonal rod column section.

[0066] Fig.18Schematic diagram of the structure of a hexagonal rod column section with grooves.

[0067] Fig.19 It is a schematic diagram of the structure of a chamfered quadrilateral column section with grooves.

[0068] Fig. 20 It is a schematic diagram of the structure of a quadrilateral column section with grooves.

[0069] Fig.21 It is a schematic diagram of the structure of a special-shaped rod column section with grooves.

[0070] Fig. 22 It is a schematic diagram of the structure of the tapered rod column of the steel guide rail.

[0071] Fig.23 for Fig. 22 Schematic diagram of the cross-section structure.

[0072] Fig.24 It is a schematic diagram of the structure of a composite steel guide rail column with grooves.

[0073] Fig.25 It is a cross-sectional view of a composite pole column with grooves.

[0074] Fig.26 It is a cross-sectional view of a composite special-shaped rod column with grooves.

[0075] Fig. 27 It is a schematic diagram of the structure of a conical composite steel guide rail column with grooves.

[0076] Fig.28 It is a structural schematic diagram of the cross section of a conical composite rod column with grooves (the inner rod body is a regular hexagon).

[0077] Fig.29 It is a schematic diagram of the structure of another conical composite rod column section with grooves.

[0078] Fig.30 It is a structural schematic diagram of the "C"-shaped steel guide rail installed on the pole body.

[0079] Reference numerals

[0080] 1-pole column body, 1a-lead hole, 1b-first groove, 1c-inner rod body, 1d-outer rod body, 2-steel guide rail, 2a-slot, 2a1-protrusion, 3-lamp holder, 4-first equipment connecting device, 4a-special-shaped bolt fastener, 4a1-special-shaped screw, 4a2-first nut, 4a3-hook wedge, 4a31-first contact portion, 4a32-second contact portion, 4a33-profile, 4a4-limiting portion, 4a41-first screw hole, 4a42-stud, 4b-external equipment connecting piece, 6-cross bar, 7-second equipment connecting device, 7a-bolt fastening assembly, 7a1-screw, 7a2-second nut, 7a3-clamp plate, 7a31-second screw hole, 7a32-second groove, 8-"C" type steel guide rail. DETAILED DESCRIPTION

[0081] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0082] Example 1

[0083] like Figure 1 to Figure 4 The steel guide rail pole of the present embodiment shown in the figure comprises a pole body 1, comprising a pole body 1, at least one group of steel guide rails 2 are welded on the side wall of the pole body 1, each group of the steel guide rails 2 and the side wall of the pole body 1 form a slot 2a, the cable is passed through the lead hole 1a, the slot 2a is used to arrange the cable and install the first equipment connection device 4, the steel guide rail 2 has high strength and strong bearing capacity, the steel guide rail 2 is welded to the side wall of the pole body 1, the steel guide rail 2 and the side wall of the pole body 1 form a slot 2a, the cable of the external device is arranged in the slot 2a, the slot 2a is also used to install the first equipment connection device 4, the stability is good, compared with arranging aluminum alloy rails on the pole body 1 to install external devices, the ability to bear the weight of the external equipment can be improved, and the problem that the bearing capacity of the aluminum alloy rails on the existing pole body 1 is weak and there is a risk of falling when installing heavier external equipment is solved.

[0084] The first device connection device 4 includes a special-shaped bolt fastener 4a and an external device connection member 4b; the external device connection member 4a is detachably connected to the slot 2a via the special-shaped bolt fastener 4a, so as to facilitate the installation and removal of the external device connection member 4b.

[0085] The special-shaped bolt fastener 4a includes a special-shaped screw 4a1 and a first nut 4a2, wherein the first nut 4a2 is adapted to the rod column of the special-shaped screw 4a1, and a hook wedge portion 4a3 is provided at one end of the special-shaped screw 4a1, wherein the hook wedge portion 4a3 matches the inner side wall of the slot 2a, which is beneficial to improving the stability of the installation of the special-shaped screw 4a1 and the slot 2a, and a limiting portion 4a4 is further provided on the special-shaped screw 4a1, wherein the limiting portion 4a4 and the hook wedge portion 4a3 are located at one end of the special-shaped screw 4a1 and are arranged at an angle of 90°, and the limiting portion 4a4 includes a limiting block, wherein the limiting block is provided with a first screw hole 4a penetrating therethrough 41, a stud 4a42 is provided in the first screw hole 4a41, and the stud 4a42 is threadedly connected with the first screw hole 4a41. By rotating the stud 4a42 along the first screw hole 4a41, one end of the stud 4a42 abuts against the bottom of the slot 2a. The reaction force of the bottom of the slot 2a on the stud 4a42 can generate a pre-tightening force through the limit block to make the hook wedge part 4a3 abut against the inner wall of the slot 2a, thereby achieving the purpose of positioning the special-shaped screw 4a1 in the slot 2a, preventing the special-shaped screw 4a1 from moving and falling along the slot 2a under the action of gravity, and facilitating the operator to install the external device connector 4b on the special-shaped screw 4a1.

[0086] The hook wedge portion 4a3 is respectively provided with a first contact portion 4a31 and a second contact portion 4a32, the first contact portion 4a31 is in arc surface contact with the card slot 2a, the second contact portion 4a32 is in line contact or point contact with the card slot 2a, the first contact portion 4a31 and the second contact portion 4a32 can contact the inner wall of the card slot 2a at the same time, the first contact portion 4a31 contacts the inner wall of the card slot 2a to form a first clamping force, and the second contact portion 4a32 contacts the inner wall of the card slot 2a to form a second clamping force; the first clamping force along the normal line of the contact surface and the second clamping force along the normal line of the contact surface can intersect to form a wedge-shaped angle, so that the hook wedge portion 4a3 generates a clamping force on the card slot 2a, has good stability, and can effectively reduce the force shaking of the external device connected to the special-shaped screw 4a1, and the hook wedge portion 4a3 is also provided with a profile 4a33, the profile 4a33 is located between the first contact portion 4a31 and the second contact portion 4a32. When the first contact portion 4a31 and the second contact portion 4a32 are in contact with the inner wall of the slot 2a at the same time, a gap is formed between the profile 4a33 and the inner wall of the slot 2a. Under the action of lateral external force, the hook wedge portion 4a3 of the special-shaped screw 4a1 serves as the main force-bearing portion. The contact portion between the first contact portion 4a31 and the slot 2a and the contact portion between the second contact portion 4a32 and the slot 2a are both prone to deformation. A buffer space for elastic deformation of the hook wedge portion 4a3 is formed through the gap between the profile 4a33 and the inner wall of the slot 2a, thereby forming a pre-tensioning force on the hook wedge portion 4a3 relative to the slot 2a. Under the action of the pre-tensioning force, the rigidity of the connection between the hook wedge portion 4a3 and the slot 2a is reduced, thereby preventing the special-shaped screw 4a1 from loosening.

[0087] Example 2

[0088] like Figure 5 to Figure 15 The difference between the present embodiment shown and the embodiment 1 is that a cross bar 6 is further provided on the side wall of the pole column body 1, and at least one group of steel guide rails 2 is welded to the upper surface of the cross bar 6. Each group of the steel guide rails 2 forms a slot 2a with the side wall of the cross bar 6. The slot 2a is used for arranging cables and installing the first device connecting device 4 or the second device connecting device 7. The slot 2a has the function of facilitating the arrangement of cables and the installation of the first device connecting device 4 or the second device connecting device 7 on the cross bar 6. The second device connecting device 7 includes a bolt fastening assembly 7a and an external device connecting member 4b. The external device connecting member 4b is detachably connected to the slot 2a by the bolt fastening assembly 7a, so as to facilitate the installation and disassembly of the external device connecting member 4b at the construction site.

[0089] The bolt fastening assembly 7a includes a screw rod 7a1, a second nut 7a2 and a clamping plate 7a3, wherein the clamping plate 7a3 is provided with a second screw hole 7a31 penetrating therethrough, one end of the screw rod 7a1 is threadedly connected to the second screw hole 7a31, and the other end of the screw rod 7a1 is threadedly connected to the second nut 7a2, the clamping plate 7a3 can contact the protrusion 2a1 on the inner side wall of the slot 2a, and the screw rod 7a1 can abut against the bottom of the slot 2a to generate a pre-tightening force for positioning the screw rod 7a1 relative to the slot 2a, to prevent the screw rod 7a1 from moving and falling along the slot 2a under the action of gravity, so as to facilitate the operator to install the external device connector 4b on the screw rod 7a1, and part of the side wall of the clamping plate 7a3 is recessed to one side to form a second groove 7a32, and the second groove 7a32 and the slot 2a enclose a cavity to facilitate the arrangement of cables.

[0090] like Fig. 9 As shown, the street lamp assembled on the basis of the above-mentioned steel guide rail pole comprises a pole body 1, a lamp holder 3 and a cross bar 6, wherein the lamp holder 3 is arranged at the top of the pole body 1, and the cross bar 6 is arranged on the side wall of the pole body 1. At least one group of steel guide rails 2 is welded to the side wall of the pole body 1, and each group of the steel guide rails 2 forms a slot 2a with the side wall of the pole body 1, and the slot 2a is used for arranging cables and installing a first equipment connection device 4. The steel guide rail 2 has high strength and strong bearing capacity, and can improve the ability to bear the weight of external equipment, thereby solving the problem that the bearing capacity of the aluminum alloy rails on the existing street lamps is weak and there is a risk of falling when installing heavier external equipment.

[0091] A method for installing a crossbar external device comprises the following steps:

[0092] S1: Weld the steel guide rail 2 to the upper surface of the cross bar 6; S2: Set the clamp 7a3 in the slot 2a, and adjust the lateral installation position of the clamp 7a3 in the slot 2a according to the installation position of the external device, rotate the screw 7a1 along the second screw hole 7a31 of the clamp 7a3, so that the screw 7a1 is pre-tightened and positioned with the inner wall of the slot 2a; S3: Arrange the cables in the slot 2a; S4: The screw 7a1 passes through the connecting hole on the external device connector 4b, and then is connected to the second nut 7a2 through the screw 7a1, so that the external device connector 4b is installed and positioned on the steel guide rail 2.

[0093] A method for installing a pole external device, characterized in that it comprises the following steps:

[0094] S1: Install the steel guide rail 2 on the side wall of the rod column body 1; S2: Set the hook wedge portion of the special-shaped screw 4a1 in the slot 2a, and adjust the vertical installation position of the special-shaped screw 4a1 in the slot 2a according to the installation height of the external device, and rotate the stud 4a42 along the first screw hole 4a41 of the limit part 4a4 to pre-tighten the hook wedge portion of the special-shaped screw 4a1 and the inner wall of the slot 2a; S3: Arrange the cables in the slot 2a; S4: The shaped screw 4a1 passes through the connection hole on the external device connector 4b, and then is connected to the first nut through the special-shaped screw, so that the external device connector is installed and positioned on the steel guide rail; S5: Install the cover plate 3 on the outside of the steel guide rail 2, install the wire port cover 5 at the wire hole position of the rod column body 1, install the wire port cover 5 on the rod column body 1, and install bolts or rivets in the holes opened at the bottom of the slot 2a of the steel guide rail 2 and the corresponding position on the rod column body 1. , so that the steel guide rail 2 is installed on the pole body 1, and the vertical position of the special-shaped screw 4a1 in the slot 2a is adjusted according to the installation height of the external device. The stud 4a42 in the first screw hole 4a41 is rotated to make the stud 4a42 abut against the bottom of the slot 2a, so that the special-shaped screw 4a1 is positioned in the slot 2a, which can effectively prevent the special-shaped screw 4a1 from shifting along the slot 2a under the vertical gravity during the installation process, which has the function of facilitating the operator to install the external device, lead out the cable in the pole body 1 through the lead-in hole 1a, arrange the cable in the slot 2a, lead out along the external device connector 4b1, and then connect the external device connector 4b1 through the special-shaped bolt fastener 4a, install the cover plate 3 on the outside of the steel guide rail 2 to hide the cable, install the wire port cover 5 on the pole body 1, cover the lead-in hole 1a, beautify the appearance of the pole body 1, and prevent rainwater from entering the pole body 1.

[0095] Example 3

[0096] like Figure 16 to Figure 21 As shown, the difference between this embodiment and embodiment 2 is that the cross section of the rod column body 1 is a polygonal cross section or a special-shaped cross section.

[0097] Example 4

[0098] like Fig. 22 and Fig.23 As shown, the difference between this embodiment and embodiment 2 is that the pole body 1 is a conical structural member, the conical structure has strong stability, strong wind load resistance, and can save the material of the pole body 1.

[0099] Example 5

[0100] like Figure 24 to Figure 26 As shown, the difference between this embodiment and embodiment 3 is that the pole column body 1 includes an inner pole body 1c and an outer pole body 1d, the outer pole body 1d is arranged on the outside of the inner pole body 1c, the inner pole body 1c and the outer pole body 1d are fixedly connected by welding, part of the side wall of the outer pole body 1d is recessed inward to form a first groove 1b, the cross-section of the inner pole body 1c is a triangular cross-section, a polygonal cross-section or a conical cross-section, the steel guide rail 2 and the external equipment are arranged on the outer pole body 1d, and the lateral wind load on the external equipment is transmitted to the inner pole body 1c through the outer pole body 1d, and the ability of the pole column body 1 to resist the lateral wind load can be enhanced by setting the inner pole body 1c.

[0101] Example 6

[0102] like Figure 27 to Figure 29 As shown, the difference between this embodiment and embodiment 6 is that the inner rod body 1c and the outer rod body 1d are conical structural members, the conical structure has strong stability, strong wind load resistance, and can save materials of the inner rod body 1c and the outer rod body 1d.

[0103] The above embodiments are only used to illustrate the present invention and are not intended to limit the technical solutions described in the present invention. Although the present invention has been described in detail with reference to the above embodiments, the present invention is not limited to the above specific implementation methods. Therefore, any modification or equivalent replacement of the present invention; and all technical solutions and improvements thereof that do not depart from the spirit and scope of the invention should be included in the scope of the claims of the present invention.

Claims

1. A steel guide rail pole, comprising a pole body (1), characterized in that: At least one set of steel guide rails (2) is welded to the side wall of the rod column body (1); each set of the steel guide rails (2) forms a slot (2a) with the side wall of the rod column body (1); a first device connection device (4) is installed in the slot (2a); the first device connection device (4) comprises a special-shaped bolt fastener (4a) and an external device connection member (4b); the external device connection member (4b) is detachably connected to the slot (2a) via the special-shaped bolt fastener (4a); the special-shaped bolt fastener (4a) comprises a special-shaped screw rod (4a1) and a first nut (4a2), the first nut (4a2) is adapted to the rod column of the special-shaped screw (4a1), one end of the special-shaped screw (4a1) is provided with a hook wedge portion (4a3), and the hook wedge portion (4a3) matches the inner wall of the steel guide rail (2); the inner wall of the steel guide rail (2) is provided with a protrusion (2a1), and the protrusion (2a1) matches the hook wedge portion (4a3); the hook wedge portion (4a3) is respectively provided with a first contact portion (4a31) and a second contact portion (4a32), and the first contact portion (4a31) and the second contact portion (4a32) are respectively provided with a first contact portion (4a31) and a second contact portion (4a32). The hook wedge portion (4a3) is capable of contacting both sides of the raised portion (2a1) at the same time; the hook wedge portion (4a3) is also provided with a profile surface (4a33), the profile surface (4a33) is located between the first contact portion (4a31) and the second contact portion (4a32), when the first contact portion (4a31) and the second contact portion (4a32) are in contact with both sides of the raised portion (2a1) at the same time, a gap is formed between the profile surface (4a33) and the raised portion (2a1); the special-shaped screw (4a1) is also provided with a limiting portion (4a4), the limiting portion (4a 4) and the hook wedge portion (4a3) are located at one end of the special-shaped screw (4a1), and the limiting portion (4a4) can abut against the bottom of the slot (2a), thereby generating a pre-tightening force for positioning the special-shaped screw (4a1) relative to the steel guide rail (2); the limiting portion (4a4) includes a limiting block, which is arranged on one side of the hook wedge portion (4a3), and the limiting block is provided with a first screw hole (4a41) penetrating therethrough, and a stud (4a42) is provided in the first screw hole (4a41), and the stud (4a42) is threadedly connected to the first screw hole (4a41).

2. A steel guide rail pole according to claim 1, characterized in that: The cross section of the column body (1) is a triangular cross section or a polygonal cross section, and the steel guide rail (2) is located on at least one side of the column body (1); or, the cross section of the column body (1) is a circular cross section or a special-shaped cross section, and at least one set of the steel guide rails (2) is provided on the side wall of the column body (1).

3. A steel guide rail pole according to claim 2, characterized in that: Part of the side wall of the rod column body (1) is recessed inwards to form a first groove (1b), and the steel guide rail (2) is arranged in the first groove (1b).

4. A steel guide rail pole according to claim 1, characterized in that: The rod column body (1) is a tapered structural component or a tapered diameter-reducing structural component.

5. A steel guide rail pole according to claim 4, characterized in that: The cross section of the column body (1) is a triangular cross section or a polygonal cross section, and the steel guide rail (2) is located on at least one side of the column body (1); or the cross section of the column body (1) is a circular cross section or a special-shaped cross section, and at least one set of the steel guide rails (2) is provided on the side wall of the column body (1).

6. A steel guide rail pole according to claim 5, characterized in that: Part of the side wall of the rod column body (1) is recessed inwards to form a first groove (1b), and the steel guide rail (2) is arranged in the first groove (1b).

7. The steel guide rail pole according to claim 1, characterized in that: The rod column body (1) comprises an inner rod body (1c) and an outer rod body (1d), wherein the outer rod body (1d) is arranged outside the inner rod body (1c), and the inner rod body (1c) and the outer rod body (1d) are fixedly connected.

8. A steel guide rail pole according to claim 7, characterized in that: Part of the side wall of the outer rod body (1d) is recessed inwards to form a first groove (1b), and the steel guide rail (2) is arranged in the first groove (1b).

9. A steel guide rail pole according to claim 8, characterized in that: The cross section of the outer rod body (1d) is a triangular cross section or a polygonal cross section, and the steel guide rail (2) is located on at least one side of the outer rod body (1d); or the cross section of the outer rod body (1d) is a circular cross section or a special-shaped cross section, and at least one of the steel guide rails (2) is arranged on the side wall of the outer rod body (1d).

10. A steel guide rail pole according to claim 9, characterized in that: The outer rod body (1d) is a conical structural component or a conical diameter-changing structural component.

11. The steel guide rail pole according to claim 7, characterized in that: The cross section of the inner rod body (1c) is a triangular cross section, a triangular conical cross section, a polygonal cross section, a polygonal conical cross section, a special-shaped cross section, a special-shaped conical cross section or a conical cross section.

12. A street lamp, characterized in that: It comprises a steel guide rail pole according to claim 1, a lamp holder (3) and a cross bar (6), wherein the lamp holder (3) is arranged on the upper part of the pole body (1), and the cross bar (6) is arranged on the side wall of the pole body (1).

13. A street lamp according to claim 12, characterized in that: The cross section of the cross bar (6) is a circular cross section, a quadrilateral cross section, a hexagonal cross section, an octagonal cross section or a special-shaped cross section.

14. A street lamp according to claim 13, characterized in that: At least one group of steel guide rails (2) is welded to the upper surface of the crossbar (6), and each group of the steel guide rails (2) forms a slot (2a) with the side wall of the crossbar (6), and the slot (2a) is used to arrange cables and install a first device connection device (4) or a second device connection device (7).

15. A street lamp according to claim 14, characterized in that: The second device connection device (7) comprises a bolt fastening assembly (7a) and an external device connection piece (4b), and the external device connection piece (4b) is detachably connected to the card slot (2a) via the bolt fastening assembly (7a).

16. A street lamp according to claim 15, characterized in that: The bolt fastening assembly (7a) comprises a screw rod (7a1), a second nut (7a2) and a clamping plate (7a3); the clamping plate (7a3) is provided with a second screw hole (7a31) extending therethrough; one end of the screw rod (7a1) is threadedly connected to the second screw hole (7a31); and the other end of the screw rod (7a1) is threadedly connected to the second nut (7a2).

17. A street lamp according to claim 16, characterized in that: The clamping plate (7a3) can contact the protrusion (2a1) on the inner wall of the steel guide rail (2), and the screw rod (7a1) can abut against the bottom of the slot (2a) to generate a preload force for positioning the screw rod (7a1) relative to the slot (2a).

18. A street lamp according to claim 17, characterized in that: Part of the side wall of the clamping plate (7a3) is recessed toward one side to form a second groove (7a32).

19. A method for installing a crossbar external device, characterized in that: The crossbar (6) is a crossbar in a street lamp according to claim 18, comprising the following steps: S1: Welding the steel guide rail (2) to the upper surface of the crossbar (6); S2: Setting the clamping plate (7a3) in the slot (2a), and adjusting the lateral installation position of the clamping plate (7a3) in the slot (2a) according to the installation position of the external device, rotating the screw rod (7a1) along the second screw hole (7a31) of the clamping plate (7a3) so that the screw rod (7a1) and the inner wall of the slot (2a) are pre-tightened and positioned; S3: Arranging cables in the slot (2a); S4: The screw rod (7a1) passes through the connection hole on the external device connector (4b), and then is connected to the second nut (7a2) through the screw rod (7a1), so that the external device connector (4b) is installed and positioned on the steel guide rail (2).

20. A method for installing a pole external device, characterized in that: The pole is a steel guide rail pole as claimed in claim 1, comprising the following steps: S1: welding the steel guide rail (2) to the side wall of the rod column body (1); S2: setting the hook wedge portion of the special-shaped screw rod (4a1) in the slot (2a), adjusting the vertical installation position of the special-shaped screw rod (4a1) in the slot (2a) according to the installation height of the external device, rotating the screw rod (4a42) along the first screw hole (4a41) of the limiting portion (4a4), so that the hook wedge portion of the special-shaped screw rod (4a1) and the inner wall of the slot (2a) are pre-tightened and positioned; S3: arranging cables in the slot (2a); S4: the special-shaped screw rod (4a1) passes through the connection hole on the external device connecting piece (4b), and then is connected to the first nut (4a2) through the special-shaped screw rod (4a1), so that the external device connecting piece (4b) is installed and positioned on the steel guide rail (2).

Citation Information

Patent Citations

  • Weak current interference resistant steel track rod column and external equipment installation method

    CN114017725A

  • Large bearing rod column capable of hiding cable and adjusting equipment installation height

    CN213269189U

  • Steel guide rail rod column and street lamp

    CN216281253U

  • Weak current interference resistant steel track rod column and street lamp

    CN216952826U