A full-cycle control method and system for rail vehicle component maintenance
Through the full cycle management and control methods and systems of rail vehicle component maintenance, the problem of differences between the maintenance cycle and the inconvenience of data management is solved, the whole life cycle management and data visualization of component maintenance are realized, and the maintenance efficiency and data security are improved.
Patent Information
- Application Number
- CN202111480606.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-06
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2041-12-06
AI Technical Summary
The time difference between the maintenance cycle of urban rail vehicle parts and the maintenance cycle of complete vehicles is increasing, resulting in increased maintenance complexity and inconvenient data management, which affects the accuracy and timeliness of data.
A full cycle management and control method and system of rail vehicle component maintenance is proposed. By obtaining the basic data of the component, the next maintenance time interval is predicted, the maintenance process is tracked, the maintenance data is shared, and the full life cycle management of component maintenance is realized.
The full life cycle management of rail vehicle components is implemented, the accuracy and visualization of the prediction of maintenance and the visualization of data are improved, the mixing and cost of maintenance are reduced, and the security and timeliness of the data are ensured.
Smart Images

Figure CN114239877B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of rail vehicle equipment maintenance management, and in particular relates to a full-cycle management and control method and system for rail vehicle component maintenance. Background Art
[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] With the rapid development of urban rail vehicles, the number of rail vehicles and the mileage are getting longer and longer, and the vehicle parts are constantly being repaired and replaced. As a result, the time difference between the maintenance cycle of the whole vehicle and the maintenance cycle of the parts (especially large parts) will become larger and larger. The complexity of maintenance is constantly increasing. There is an increasing demand for business departments to separately track and predict the maintenance status of parts. Component maintenance operation has become a key issue in urban rail operations.
[0004] At the same time, due to maintenance qualifications, parts at some maintenance locations need to be repaired in other subsidiaries, which causes a lot of inconvenience in the data management of parts maintenance and is not conducive to ensuring the accuracy and timeliness of part maintenance data. Summary of the invention
[0005] In order to solve the above problems, the present invention proposes a full-cycle control method and system for rail vehicle component maintenance. The present invention can predict rail vehicle components before maintenance, timely track data during maintenance, and share data after maintenance, thereby realizing the full life cycle management of urban rail component maintenance.
[0006] According to some embodiments, the present invention adopts the following technical solutions:
[0007] A full-cycle control method for rail vehicle component maintenance includes the following steps:
[0008] Obtain basic data of rail vehicle components;
[0009] Extract the corresponding component maintenance information and vehicle operation information from the basic data, comprehensively consider the two types of information, and predict the time interval for the next maintenance of the component;
[0010] Receive maintenance requests for components, find the corresponding predicted maintenance time interval, and determine whether the maintenance request is reasonable. If so, proceed to the next step; otherwise, trace the usage of components;
[0011] According to the maintenance component information in the maintenance request, determine the maintenance process flow and required time, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order;
[0012] Continuously record and update the execution information of the maintenance work order until the maintenance process is completed;
[0013] Inspect and record the maintenance quality to form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order;
[0014] Monitor and track the maintenance materials and quality inspection material information involved in the maintenance work order, and update the corresponding material status based on the monitoring and tracking.
[0015] As an optional implementation, the basic data includes assignment information, structure information, feature information, repair process information, maintenance process information and vehicle operation information.
[0016] As an optional implementation manner, the maintenance information includes some of the maintenance cycle, theoretical time, upper tolerance of time, lower tolerance of time, theoretical mileage, upper tolerance of mileage and lower tolerance of mileage.
[0017] As an optional implementation, the vehicle operation information includes some of the current running cumulative mileage, cumulative days, last maintenance trip, last maintenance round, last maintenance cumulative mileage, last cumulative maintenance days and daily average running mileage.
[0018] As an optional implementation method, the specific process of determining whether a maintenance request is reasonable includes: obtaining the parts to be maintained, quantity and planned cycle of the components, determining whether the parts to be maintained and quantity meet the corresponding historical thresholds, and determining whether the planned cycle falls within the predicted maintenance time interval. If so, the maintenance request is determined to be reasonable.
[0019] As an optional implementation method, the specific process of determining the maintenance process flow and required time, arranging the maintenance time according to the process and time of the maintenance department, and generating the maintenance work order includes:
[0020] Search for all existing maintenance process information under the corresponding component according to the component model, and schedule production according to the sequence of the main maintenance processes in the maintenance process information, combined with the maximum capacity of the key processes and the available time of the maintenance department's processes. Then calculate the required time based on the relationship between the main process and the entire maintenance process. Then calculate the start time of the work order through the work order of the maintenance object where the process is located. According to the process task list, determine the maintenance person in charge, labor time quota and material quota, and generate a work order.
[0021] As an optional implementation method, before continuously recording and updating the execution information of the maintenance work order, it is necessary to confirm whether the maintenance work order and the information of the component to be repaired and the maintenance personnel information match. If they match, maintenance is carried out, otherwise a warning is issued.
[0022] As an optional implementation, the execution information includes fault information, tool and fixture information, maintenance qualification information, execution process information, maintenance status information and working time information.
[0023] As an optional implementation method, the specific process of detecting and recording the maintenance quality includes: based on the maintenance work order information, determining whether the personnel qualification information, dynamic assembly history information and quality measurement values during the maintenance process meet the corresponding requirements; if so, the maintenance quality is deemed to be qualified, and the fault phenomenon, cause of the fault and solution are recorded; otherwise, the maintenance quality is deemed to be unqualified.
[0024] As an optional implementation method, the specific process of monitoring and tracking the maintenance material and quality inspection material information involved in the maintenance work order includes: monitoring all material business operation process information related to material status transfer, updating material resume information in real time and accurately, and forward tracking and reverse tracing all relevant information of specific materials at each business stage in their life cycle at any time.
[0025] A full-cycle management and control system for rail vehicle component maintenance, comprising:
[0026] A basic information management module, configured to obtain and store basic data of rail vehicle components;
[0027] A maintenance prediction module is configured to extract the maintenance process information of the corresponding component and the vehicle operation information from the basic data, comprehensively consider the two kinds of information, and predict the time interval of the next maintenance of the component;
[0028] The maintenance judgment module is configured to receive the maintenance request of the component, find the corresponding predicted maintenance time interval, and judge whether the maintenance request is reasonable. If so, it will proceed to the next step, otherwise it will trace the usage of the component;
[0029] The maintenance scheduling management module is configured to determine the maintenance process flow and required time according to the maintenance component information in the maintenance request, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order;
[0030] The maintenance process management module is configured to continuously record and update the fault information, execution process information, maintenance status information and working time information of the maintenance work order until the maintenance process flow is completed;
[0031] The maintenance quality inspection management module is configured to detect and record the maintenance quality, form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order;
[0032] The maintenance material management module is configured to monitor and track the maintenance material and quality inspection material information involved in the maintenance work order, and update the corresponding material status based on the monitoring and tracking.
[0033] It also includes a maintenance process management module, which is configured to digitize the information of the actual component structure and convert it into basic data, establish component configuration and instantiated unit configuration, associate maintenance requirements and maintenance data with the maintenance configuration, and associate operation data and maintenance history with the instantiated unit configuration to form a closed-loop data flow.
[0034] An electronic device comprises a memory and a processor, and computer instructions stored in the memory and executed on the processor. When the computer instructions are executed by the processor, the steps in the above method are completed.
[0035] A computer-readable storage medium is used to store computer instructions, and when the computer instructions are executed by a processor, the steps in the above method are completed.
[0036] Compared with the prior art, the present invention has the following beneficial effects:
[0037] The present invention comprehensively considers the similarities and differences between component maintenance business and urban rail vehicle business, and ultimately realizes the system application and process control of core businesses such as pre-maintenance prediction in the urban rail component maintenance process; process tracking, fault handling and technical modification during maintenance; and post-maintenance data sharing, thereby realizing the full life cycle management of urban rail component maintenance.
[0038] The present invention realizes effective isolation of each business data authority through data layer data separation, authority division, business subject division, etc., ensures data visibility and security, and avoids data leapfrogging.
[0039] The present invention solves the problems of rapid delivery management and refined maintenance based on urban rail component maintenance business, realizes process management of urban rail component maintenance, and makes the maintenance process digital, visual and refined, which is of great significance for ensuring operational safety, improving maintenance efficiency and avoiding unnecessary losses.
[0040] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0042] Figure 1 is a system schematic diagram of this embodiment;
[0043] Figure 2 Schematic diagram of the maintenance management process of this embodiment. DETAILED DESCRIPTION
[0044] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0045] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0046] Embodiment 1:
[0047] A full-cycle control system for rail vehicle component maintenance, such as Figure 1 , Figure 2 As shown, including:
[0048] A basic information management module, configured to obtain and store basic data of rail vehicle components;
[0049] A maintenance prediction module is configured to extract the maintenance process information of the corresponding component and the vehicle operation information from the basic data, comprehensively consider the two kinds of information, and predict the time interval of the next maintenance of the component;
[0050] The maintenance judgment module is configured to receive the maintenance request of the component, find the corresponding predicted maintenance time interval, and judge whether the maintenance request is reasonable. If so, the maintenance scheduling management module is triggered, otherwise, the component usage is traced;
[0051] The maintenance scheduling management module is configured to determine the maintenance process flow and required time according to the maintenance component information in the maintenance request, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order;
[0052] The maintenance process management module is configured to continuously record and update the fault information, execution process information, maintenance status information and working time information of the maintenance work order until the maintenance process flow is completed;
[0053] The maintenance quality inspection management module is configured to detect and record the maintenance quality, form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order;
[0054] The maintenance material management module is configured to monitor and track the maintenance material and quality inspection material information involved in the maintenance work order, and update the corresponding material status based on the monitoring and tracking.
[0055] This embodiment realizes the full life cycle management of components by coordinating maintenance prediction, maintenance scheduling (planning), maintenance execution, maintenance quality inspection and Internet of Things management, avoids missed maintenance and excessive maintenance of components, improves the quality of component maintenance, and reduces the cost of component maintenance.
[0056] It can not only record the parts maintenance tasks of our company, but also perform parts maintenance for other companies. When performing parts maintenance tasks for other subsidiaries, the authority is isolated through the material serial number. The parts serial number is shipped out of other companies and entered into our company. After entering the factory, the current part’s history information can be viewed to realize data sharing of parts maintenance.
[0057] For repair tasks of parts that are not owned by the vehicle, unified management methods are adopted to achieve full coverage and control of maintenance business, laying a good foundation for subsequent enhancement of market competitiveness.
[0058] First, the maintenance process management module is introduced. The maintenance process management module is configured to digitize the information of the actual component structure and convert it into basic data, establish component configuration and instantiated unit configuration, associate maintenance requirements and maintenance data with the maintenance configuration, and associate operating data and maintenance history with the instantiated unit configuration, so as to drive the maintenance process with data and form a closed-loop system maintenance management data flow.
[0059] When a new product is delivered to a customer, it is necessary to establish basic data for it in the maintenance process management module, build a maintenance configuration, create maintenance requirements and instantiate the configuration.
[0060] The maintenance prediction module can calculate the time interval for the next maintenance of the component by combining the component maintenance cycle (maintenance cycle rhythm, theoretical time, upper time tolerance, lower time tolerance, theoretical mileage, upper mileage tolerance, lower mileage tolerance) and the operation information of the train where the component is installed (current cumulative running mileage, cumulative number of days, last maintenance cycle, last maintenance round, last cumulative mileage, last cumulative maintenance days, average daily running mileage), thereby providing data support for long-term procurement and material preparation and resource planning.
[0061] The maintenance judgment module is used to manage component maintenance requirements and component access types; it uses the rule-based maintenance strategy representation and judgment method in the system to calculate the maintenance activities and plans required for the product to be repaired. Taking the information of the component to be repaired as input, first obtain the maintenance component, quantity and planned cycle of the component, and then calculate the personalized maintenance activities of the component through the maintenance procedure judgment tool to determine whether the maintenance request is reasonable. If it is reasonable, the maintenance scheduling management module is triggered, and the process corresponding to the maintenance requirement is used as the operation guide. If it is unreasonable, a component access containing a work order is generated to trace the use of the component.
[0062] The maintenance scheduling management module is used to find all process networks under the component according to the component model, and schedule the production according to the sequence of the main maintenance processes of the process network, combined with the maximum capacity of the key processes, and the time of the main process of the system. Then, according to the relationship between the main process and the process, the system calculates the time of the process, and then calculates the start date of the work order through the work order of the maintenance object where the process is located. After calculating the date, according to the process task list, arrange the person in charge, labor time quota and material quota corresponding to the activity, generate and output the work order, and pass the material demand information to the SAP system, which generates procurement requirements and executes procurement. When the planner issues the plan, he can summarize and issue the overall maintenance schedule, or adjust the maintenance schedule of a single component according to the details. After completing the preliminary plan, a specific work order can be optimized to generate a maintenance schedule that meets the actual situation and form an executable work order.
[0063] The maintenance process management module is used to manage maintenance processes and maintenance production, that is, to implement standardized management of specific maintenance activity processes to ensure maintenance quality.
[0064] The maintenance production related modules are driven by the issued work process instructions, and the main contents include: maintenance team information, alternative teams, material information, material drawing number, evaluation type, factory, inventory, maintenance source, factory-level route, material inventory WBS, material substitution relationship, quality inspection information, quality inspection execution status, project classification, maintenance content, maintenance standards, item category, maintenance method, maintenance tool requirements, environmental requirements, measurement values, process disassembly and installation location, history material code, history manufacturer, history production date, component repair process, and technical documents.
[0065] In other embodiments, the above contents may be modified.
[0066] The team execution personnel collect materials according to the material requirements in the operation process guide, and perform maintenance according to the standard procedures in the operation process guide. Before production execution, the serial number and history must be confirmed first. If they are wrong, the maintenance object can be changed. After confirmation, the maintenance production personnel obtain work-related content (product manufacturing process information and product maintenance history information) to assist in maintenance work.
[0067] The main information during execution includes: obtaining technical documents (document number, document name, document directory, document version, file name), collecting tools and tools according to tool and tooling requirements (tool code, tool description, tool type, tool specifications, tool model, tool quantity), checking the qualifications of maintenance personnel according to personnel qualification requirements (qualification code, qualification description, qualification level), disassembly and installation according to operating procedures, and conducting self-inspection, mutual inspection, and special inspection according to the quality inspection planning content (inspection content, inspection standard, quality level, operator, upper and lower limits of measurement, unit of measurement, maintenance equipment, valve serial number).
[0068] After the maintenance, the system records the corresponding maintenance status information (operating tools, self-inspection / mutual inspection / special inspection values, abnormal descriptions), working time information (type of working hours, personnel, working hours) according to the maintenance results, and feedbacks the execution progress in the system. After the maintenance activity is completed, the system records the changed maintenance configuration, and closes the work order after closing all operation steps, thus marking the completion of all maintenance work.
[0069] The maintenance quality inspection management module is responsible for the inspection planning of the maintenance process before maintenance (inspection content, inspection standards, quality level, operator, upper and lower limits of measurement, measurement unit, maintenance equipment, valve serial number), and dynamic assembly history management during the maintenance process (position, process name, material code, history serial number, history manufacturer, history production date, disassembly and installation serial number, whether it is scrapped, whether the old parts are put into storage, disassembly date, disassembly person, installation date, installer), quality inspection value records (operator, upper and lower limits of measurement, measurement unit, maintenance equipment), quality inspection approval process (whether self-inspection, whether mutual inspection, special inspection personnel). At the same time, a maintenance fault management system is established, including a fault dictionary and fault management.
[0070] Fault management is another important part of maintenance quality inspection management, including fault dictionary and fault solution management (i.e. fault resolution process management).
[0071] The fault dictionary includes fault object (current node, number, description), fault phenomenon (mode code, mode category, mode description, source), fault cause (whether valid, cause code, cause name, cause code, cause classification, cause description, fault cause classification) and fault solution (solution code, solution description, solution classification, solution process plan); fault resolution process management (fault work order management), including reporting, analysis and resolution after the fault is discovered, as well as post-fault analysis (main responsible unit, other responsible units, final cause analysis, final handling measures, fault object, fault mode, fault plan), thereby forming a closed-loop fault management.
[0072] The maintenance material management module is mainly used to solve material management problems for component maintenance business, and has functions such as material demand planning, material warehousing, outsourcing management, warranty period management, and material serial number management. It monitors all system business operations related to material status transfer (material warehousing, material request, material acquisition and return, material maintenance result feedback, etc.), updates material resume information in real time and accurately, and forward and reversely tracks all relevant information of specific materials at each business stage in their life cycle at any time, ultimately providing guarantee for material status and structure tracking.
[0073] In terms of database, the system continues to use the existing overhaul system database and data table structure, customizes and develops new system data structure and applications, and directly connects to the existing Oracle database to perform operations such as adding, deleting, modifying and checking data when each module performs business processing operations. The system will distinguish data between different users and business categories by separating data permissions. Each user can only query and operate his own data to ensure data security.
[0074] In terms of system application services and database interaction, a comprehensive and detailed evaluation of the existing urban rail overhaul system logic is conducted, and optimization is performed on demand according to application conditions to improve the overall system operation efficiency. At the same time, in the optimization of logic, configurability is emphasized, and all modified logics have good scalability for reverse application to EMU component maintenance business in the future.
[0075] Embodiment 2:
[0076] A full-cycle control method for rail vehicle component maintenance includes the following steps:
[0077] Obtain basic data of rail vehicle components;
[0078] Extract the corresponding component maintenance information and vehicle operation information from the basic data, comprehensively consider the two types of information, and predict the time interval for the next maintenance of the component;
[0079] Receive maintenance requests for components, find the corresponding predicted maintenance time interval, and determine whether the maintenance request is reasonable. If so, proceed to the next step; otherwise, trace the usage of components;
[0080] According to the maintenance component information in the maintenance request, determine the maintenance process flow and required time, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order;
[0081] Continuously record and update the execution information of the maintenance work order until the maintenance process is completed;
[0082] Inspect and record the maintenance quality to form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order;
[0083] Monitor and track the maintenance materials and quality inspection material information involved in the maintenance work order, and update the corresponding material status based on the monitoring and tracking.
[0084] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0085] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0086] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0087] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0088] Although the above describes the specific implementation mode of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art on the basis of the technical solution of the present invention without creative work are still within the scope of protection of the present invention.
Claims
1. A full-cycle control method for rail vehicle component maintenance, characterized by: The following steps are involved: Obtain basic data of rail vehicle components; Extract the corresponding component maintenance information and vehicle operation information from the basic data, comprehensively consider the two types of information, and predict the time interval for the next maintenance of the component; The basic data includes allocation information, structure information, feature information, repair process information, maintenance process information and vehicle operation information; The maintenance information includes some of the maintenance cycle, theoretical time, upper tolerance of time, lower tolerance of time, theoretical mileage, upper tolerance of mileage and lower tolerance of mileage; The vehicle operation information includes some of the current running cumulative mileage, cumulative days, last maintenance trip, last maintenance round, last maintenance cumulative mileage, last cumulative maintenance days and daily average running mileage; Receive maintenance requests for components, find the corresponding predicted maintenance time interval, and determine whether the maintenance request is reasonable. If so, proceed to the next step; otherwise, trace the usage of components; According to the maintenance component information in the maintenance request, determine the maintenance process flow and required time, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order; Continuously record and update the execution information of the maintenance work order until the maintenance process is completed; Inspect and record the maintenance quality to form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order; Monitor and track the maintenance materials and quality inspection material information involved in the maintenance work order, and update the corresponding material status based on the monitoring and tracking; It also includes maintenance process management, digitizing the actual component structure and converting it into basic data, establishing component configuration and instantiated unit configuration, associating maintenance requirements and maintenance data with the maintenance configuration, and associating operation data and maintenance history with the instantiated unit configuration to form a closed-loop data flow.
2. A full-cycle control method for rail vehicle component maintenance as claimed in claim 1, characterized in that: The specific process of judging whether a maintenance request is reasonable includes: obtaining the parts to be repaired, the quantity and the planned cycle of the components, judging whether the parts to be repaired and the quantity meet the corresponding historical thresholds, judging whether the planned cycle falls within the predicted maintenance time interval. If so, the maintenance request is judged to be reasonable.
3. A full-cycle control method for rail vehicle component maintenance as claimed in claim 1, characterized in that: Determine the maintenance process flow and required time, arrange the maintenance time according to the maintenance department's process and time, and generate the maintenance work order. The specific process includes: Search for all existing maintenance process information under the corresponding component according to the component model, and schedule production according to the sequence of the main maintenance processes in the maintenance process information, combined with the maximum capacity of the key processes and the available time of the maintenance department's processes. Then calculate the required time based on the relationship between the main process and the entire maintenance process. Then calculate the start time of the work order through the work order of the maintenance object where the process is located. According to the process task list, determine the maintenance person in charge, labor time quota and material quota, and generate a work order.
4. A full-cycle control method for rail vehicle component maintenance as claimed in claim 1, characterized in that: Before continuously recording and updating the execution information of the maintenance work order, it is necessary to confirm whether the maintenance work order matches the information of the component to be repaired and the maintenance personnel information. If they match, the maintenance will be carried out, otherwise a warning will be issued; Or further, the execution information includes fault information, tool and fixture information, maintenance qualification information, execution process information, maintenance status information and working time information.
5. A full-cycle control method for rail vehicle component maintenance as claimed in claim 1, characterized in that: The specific process of testing and recording maintenance quality includes: based on the maintenance work order information, determining whether the personnel qualification information, dynamic assembly history information and quality measurement values during the maintenance process meet the corresponding requirements. If so, the maintenance quality is deemed qualified, and the fault phenomenon, cause of the fault and solution are recorded. Otherwise, the maintenance quality is deemed unqualified.
6. A full-cycle control method for rail vehicle component maintenance as claimed in claim 1, characterized in that: The specific process of monitoring and tracking the maintenance material and quality inspection material information involved in the maintenance work order includes: monitoring all material business operation process information related to the material status transfer, updating the material resume information in real time and accurately, and forward tracking and reverse tracing all relevant information of the specific material at each business stage in its life cycle at any time.
7. A full-cycle management and control system for rail vehicle component maintenance, based on a full-cycle management and control method for rail vehicle component maintenance as claimed in any one of claims 1 to 6, characterized in that: include: A basic information management module, configured to obtain and store basic data of rail vehicle components; A maintenance prediction module is configured to extract the maintenance process information of the corresponding component and the vehicle operation information from the basic data, comprehensively consider the two kinds of information, and predict the time interval of the next maintenance of the component; The basic data includes allocation information, structure information, feature information, repair process information, maintenance process information and vehicle operation information; The maintenance information includes some of the maintenance cycle, theoretical time, upper tolerance of time, lower tolerance of time, theoretical mileage, upper tolerance of mileage and lower tolerance of mileage; The vehicle operation information includes some of the current running cumulative mileage, cumulative days, last maintenance trip, last maintenance round, last maintenance cumulative mileage, last cumulative maintenance days and daily average running mileage; The maintenance judgment module is configured to receive the maintenance request of the component, find the corresponding predicted maintenance time interval, and judge whether the maintenance request is reasonable. If so, it will proceed to the next step, otherwise it will trace the usage of the component; The maintenance scheduling management module is configured to determine the maintenance process flow and required time according to the maintenance component information in the maintenance request, arrange the maintenance time according to the maintenance department's process and time, and generate a maintenance work order; The maintenance process management module is configured to continuously record and update the fault information, execution process information, maintenance status information and working time information of the maintenance work order until the maintenance process flow is completed; The maintenance quality inspection management module is configured to detect and record the maintenance quality, form a quality inspection record, associate the quality inspection record with the maintenance work order, and then close the maintenance work order; The maintenance material management module is configured to monitor and track the maintenance material and quality inspection material information involved in the maintenance work order, and update the corresponding material status according to the monitoring and tracking; It also includes a maintenance process management module, which is configured to digitize the information of the actual component structure and convert it into basic data, establish component configuration and instantiated unit configuration, associate maintenance requirements and maintenance data with the maintenance configuration, and associate operation data and maintenance history with the instantiated unit configuration to form a closed-loop data flow.
8. An electronic device comprising a memory and a processor and computer instructions stored in the memory and executed on the processor, wherein when the computer instructions are executed by the processor, the steps in any one of the methods of claims 1 to 6 are completed.
9. A computer-readable storage medium for storing computer instructions, wherein when the computer instructions are executed by a processor, the steps in any one of the methods of claims 1 to 6 are performed.
Citation Information
Patent Citations
Comprehensive management system and method for application and maintenance of machine vehicle
CN112598143A
Railway locomotive depot comprehensive data intelligent management and control platform
CN113052562A