Monitoring method, equipment and storage medium for underground operation safety information

By acquiring and processing underground environmental data and introducing risk prediction models for early warning, the problem of insufficient prior warning in the existing technology is solved, and the safety monitoring effect of underground operations is significantly improved.

CN114331022BActive Publication Date: 2024-10-11SHENHUA HOLLYSYS INFORMATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111459820.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-02
Publication Date
2024-10-11
Estimated Expiration
2041-12-02

AI Technical Summary

Technical Problem

Existing technology cannot effectively provide advance warning for underground operations, resulting in poor accident monitoring effects.

Method used

By obtaining underground external environment data, internal environment data and safety production factor data, standard data points are generated and imported into the risk prediction calculation model to generate safety prediction values ​​in real time. When the prediction value is greater than the preset threshold, an early warning operation is performed.

Benefits of technology

It achieves advance warning, significantly improves the monitoring effect of underground work accidents, and ensures the safety of underground operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114331022B_ABST
    Figure CN114331022B_ABST
Patent Text Reader

Abstract

The present disclosure relates to the technical field of mine accident information processing, and provides a monitoring method, equipment and storage medium for underground operation safety information. The method includes: obtaining underground external environment data, underground internal environment data and underground production safety factor data; performing standard processing on the underground external environment data, underground internal environment data and underground production safety factor data to generate standard data points; importing the standard data points into a risk prediction calculation model to generate a real-time safety prediction value; when the real-time safety prediction value is greater than a preset safety threshold, performing an early warning operation. The embodiment of the present disclosure collects and processes the underground external environment data, underground internal environment data and underground production safety factor data, imports the risk prediction calculation model to generate a prediction value, and performs an early warning operation when the early warning conditions are met, so that an early warning can be effectively performed in advance, greatly improving the accident monitoring effect of underground work.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of mine accident information processing, and in particular to a monitoring method, equipment and storage medium for underground operation safety information. Background Art

[0002] As the first production site of coal, the fully mechanized mining face has the characteristics of small working space, many mechanical equipment and high temperature. It is a frequent site of mine accidents. Among them, roof accidents in coal mining faces account for more than 40% of all deaths. Among roof accidents, 80% are caused by improper management and untimely warning.

[0003] In the existing technology, the monitoring method for roof safety usually relies on passive monitoring means such as support equipment, underground vibration monitoring, surrounding rock separation monitoring and stress monitoring, and issues accident alarms through changes in the physical state before the accident occurs. Since such methods are in-process alarms, they cannot provide effective pre-warning and have poor monitoring effects on possible accidents. Summary of the invention

[0004] In view of this, the embodiments of the present disclosure provide a method, device and storage medium for monitoring underground operation safety information to solve the problem that the prior art cannot provide effective advance warning and has poor monitoring effect on possible accidents.

[0005] A first aspect of an embodiment of the present disclosure provides a method for monitoring underground operation safety information, including: acquiring underground external environment data, underground internal environment data and underground production safety factor data; generating standard data points based on the underground external environment data, the underground internal environment data and the underground production safety factor data; importing the standard data points into a risk prediction calculation model to generate a real-time safety prediction value; when the real-time safety prediction value is greater than a preset safety threshold, performing an early warning operation.

[0006] According to a second aspect of an embodiment of the present disclosure, a computer device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above method when executing the computer program.

[0007] According to a third aspect of the embodiments of the present disclosure, a computer-readable storage medium is provided, which stores a computer program. When the computer program is executed by a processor, the steps of the above method are implemented.

[0008] Compared with the prior art, the beneficial effects of the embodiments of the present disclosure include at least the following: By collecting and processing underground external environment data, underground internal environment data and underground production safety factor data, importing the risk prediction calculation model to generate prediction values, and executing the warning operation when the warning conditions are met, effective advance warning can be carried out, greatly improving the accident monitoring effect of underground work. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0010] Figure 1 It is a schematic diagram of an application scenario of the method for monitoring underground operation safety information provided by an embodiment of the present disclosure;

[0011] Figure 2 It is a flowchart of some embodiments of a method for monitoring safety information of underground operations provided according to an embodiment of the present disclosure;

[0012] Figure 3 is a flow chart of some other embodiments of another method for monitoring safety information of underground operations provided according to an embodiment of the present disclosure;

[0013] Figure 4 It is a structural schematic diagram of a monitoring device for underground operation safety information provided according to an embodiment of the present disclosure;

[0014] Figure 5 is a schematic diagram of a computer device provided according to an embodiment of the present disclosure. DETAILED DESCRIPTION

[0015] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments set forth herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.

[0016] It should also be noted that, for ease of description, only the parts related to the present disclosure are shown in the drawings. In the absence of conflict, the embodiments and features in the embodiments of the present disclosure can be combined with each other.

[0017] It should be noted that the concepts such as "first" and "second" mentioned in the present disclosure are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.

[0018] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".

[0019] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.

[0020] The present disclosure will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0021] Figure 1 It is a schematic diagram of an application scenario of a method for monitoring underground operation safety information according to some embodiments of the present disclosure.

[0022] exist Figure 1 In the application scenario of, first, the computing device 101 can obtain the underground external environment data 102, the underground internal environment data 103 and the underground safety production factor data 104. Then, the computing device 101 can generate the standard data point 105 based on the underground external environment data 102, the underground internal environment data 103 and the underground safety production factor data 104. Then, the computing device 101 can import the standard data point 105 into the risk prediction calculation model 106 to generate a real-time safety prediction value 107. Finally, when the real-time safety prediction value 107 is greater than the preset safety threshold, the computing device 101 can perform the early warning operation 108.

[0023] It should be noted that the computing device 101 can be hardware or software. When the computing device is hardware, it can be implemented as a distributed cluster consisting of multiple servers or terminal devices, or as a single server or a single terminal device. When the computing device is embodied as software, it can be installed in the hardware devices listed above. It can be implemented as multiple software or software modules for providing distributed services, or as a single software or software module. No specific limitation is made here.

[0024] It should be understood that Figure 1 The number of computing devices in the embodiment is only illustrative. Any number of computing devices may be provided according to implementation requirements.

[0025] Continue to refer Figure 2 , shows a process 200 of some embodiments of the method for monitoring underground operation safety information according to the present disclosure. The method can be Figure 1 The method for monitoring underground operation safety information comprises the following steps:

[0026] Step 201, obtaining underground external environment data, underground internal environment data and underground production safety factor data.

[0027] In some embodiments, the execution subject of the method for monitoring underground operation safety information (such as Figure 1 The computing device 101 shown can be connected to the target device by wireless connection, and then obtain the underground external environment data, underground internal environment data and underground safety production factor data. The above information can be obtained by crawling through a network crawler, manual search, etc., which can be set as needed and is not specifically limited here.

[0028] It should be noted that the above-mentioned wireless connection methods may include but are not limited to 3G / 4G connection, WiFi connection, Bluetooth connection, WiMAX connection, Zigbee connection, UWB (ultra wideband) connection, and other wireless connection methods currently known or to be developed in the future.

[0029] In some optional implementations of some embodiments, the underground external environment data may refer to the acquired relevant data outside the mine. As an example, the underground external environment data may include but is not limited to one of the following: geographical location related information, earthquake related information, rainstorm warning related information, accident related information, etc.

[0030] The information related to the geographical location may refer to the information related to the geographical location near the mine obtained, wherein the information related to the geographical location may include longitude and latitude information, territorial information, etc. As an example, the geographical location information may be "longitude: 37.94231424835259, latitude: 109.34861808242798, province: Shanxi Province, city: Yulin City, district: Yuyang District, township: Zhangleigou Village". The information related to the geographical location may also include other information related to the geographical location, which is not specifically limited here.

[0031] Earthquake-related information may refer to the information obtained about an earthquake that has occurred near a mine, wherein the earthquake-related information may include information such as magnitude, time of occurrence, longitude, latitude, depth, etc. As an example, the earthquake-related information may be “time of occurrence: 2020.08.01, magnitude: 5.1, longitude: 87.04, latitude: 42.30, depth: 21”. The earthquake-related information may also include time, location or other information related to the earthquake, which is not specifically limited here.

[0032] The information related to the rainstorm warning may refer to the information related to the rainstorm warning that has occurred near the mine, wherein the information related to the rainstorm warning may include information such as the rainstorm warning time and the rainstorm warning level. As an example, the information related to the rainstorm warning may be "rainstorm warning time: 2021.08.10, rainstorm warning level: blue". The information related to the rainstorm warning may also include time, location or other information related to the rainstorm warning, which is not specifically limited here.

[0033] The accident-related information may refer to the obtained information about the underground accident of the mine, wherein the accident-related information may include information such as the underground accident time, number of casualties, and type of cause of the accident. As an example, the accident-related information may be "underground accident time: 2021.05.19, number of casualties: 8, type of cause of the accident: gas outburst". The accident-related information may also include time, location or other information related to the accident, which is not specifically limited here.

[0034] In some optional implementations of some embodiments, the underground internal environment data may refer to relevant data inside the mine. As an example, the underground internal environment data may include but is not limited to one of the following: underground space three-dimensional data, underground space vertex coordinate data, mining speed data, mining area data, etc.

[0035] The three-dimensional data of underground space may refer to the relevant information of the spatial structure inside the mine, wherein the three-dimensional data of underground space may include width data, length data, and height data. The three-dimensional data of underground space is updated at fixed intervals and stored in a data storage device; the frequency of its update can be set according to demand and is not limited here. When obtaining the three-dimensional data of underground space, the underground infrared scanning plane map can be obtained through the horizontal infrared sensing modules of multiple underground equipment; the underground infrared scanning section map can be obtained through the longitudinal infrared sensing modules of multiple underground equipment; the underground infrared scanning plane map and the underground infrared scanning section map are transmitted to the above-mentioned execution subject, and the execution subject can form a three-dimensional underground space map based on the graphic analysis and calculation module to calculate the underground space information, including the above-mentioned width data, length data and height data.

[0036] The underground space vertex coordinate data may refer to the coordinate data formed based on the space origin based on the vertices of the above-mentioned underground three-dimensional space diagram. Among them, the space origin may refer to the position of a fixed-position device in the underground three-dimensional space diagram. As an example, one of the underground space vertex coordinate data may be "vertex 1, 11.25 (X coordinate), 25.39 (Y coordinate), 8.0 (Z coordinate)". The X-coordinate axis may refer to a straight line on the underground space section that passes through the space origin and is parallel to the horizontal plane (since mines are generally excavated parallel to the ground or diagonally up and down, the space section must have an intersection line with the horizontal plane). The Y-coordinate axis may refer to a straight line on the underground space section that passes through the space origin and is perpendicular to the X-coordinate axis. The Z-coordinate axis may refer to a straight line perpendicular to the underground space section and passing through the space origin. The X-coordinate may refer to data in the X-coordinate axis direction in the underground three-dimensional space, the Y-coordinate may refer to data in the Y-coordinate axis direction in the underground three-dimensional space, and the Z-coordinate may refer to data in the Z-coordinate axis direction in the underground three-dimensional space. The measurement units of the X-coordinate, Y-coordinate or Z-coordinate data can be meters, centimeters and other common data units, which can be set as needed. In addition, the underground space vertex coordinate data is updated at fixed intervals and stored in the data storage device; the update frequency can be set according to needs and is not limited here. It should be pointed out that the underground space vertex coordinate data can also include time, location or other information related to the spatial structure inside the mine, which can be set as needed.

[0037] The mining speed data may refer to the information related to the movement speed of the mining equipment obtained. As an example, the mining speed data may be “20210501142130 (time), JX00002 (sensor code), 12 (mining speed)”.

[0038] The mining area data may refer to the cross-sectional area data of the space in the mine. When generating the mining area data, the image data may be collected based on the image acquisition module built into the equipment in the mine, and the image data may be transmitted to the computing device 101, and then the computing device 101 may generate the cross-sectional area data based on the collected image data. As an example, the mining area data may be "20210611084528 (time), JX00003 (sensor code), 2.6 (mining area)".

[0039] In some optional implementations of some embodiments, the underground production safety factor data may refer to data related to safety protection production inside the mine. As an example, the underground internal environment data may include but is not limited to one of the following: support equipment coordinate data and support equipment change data.

[0040] The support equipment coordinate data may refer to a data set consisting of the two-dimensional coordinate data of the support equipment based on the above-mentioned spatial origin. As an example, one of the support equipment coordinate data may be "20210515113600 (time), ZH00013 (support equipment code), 8.11 (XX coordinate), 5.56 (YY coordinate)". Among them, the XX coordinate may refer to the data along the X-axis direction of the above-mentioned underground three-dimensional space, and the YY coordinate may refer to the data along the Y-axis direction of the above-mentioned underground three-dimensional space. The support equipment coordinate data is updated at regular intervals and stored in the data storage device; the update frequency can be set according to needs, and there is no restriction here.

[0041] Support equipment change data may refer to a data set consisting of data such as the total amount data and position change data of the support equipment acquired most recently. Since the two-dimensional (or three-dimensional) coordinate data of each support equipment will be updated at a certain frequency, all support equipment change data must be calculated once each time it is updated. As an example, a support equipment change data may be "20210515113600 (scanning time), 1 (number of new / reduced support equipment), 0 (offset of the moved support equipment)".

[0042] The support resistance data may refer to a data set consisting of relevant data of the support equipment in terms of resistance. Among them, the support resistance data may include equipment code, rated resistance support resistance data, and real-time support resistance data. As an example, a support resistance data may be "20210515113600 (scanning time), ZH00012 (support equipment code), 5.91 (X coordinate), 4.75 (Y coordinate), 18000 (rated support resistance), 15121 (real-time support resistance)".

[0043] Step 202, standard processing is performed on underground external environment data, underground internal environment data and underground production safety factor data to generate standard data points.

[0044] In some embodiments, the above-mentioned execution subject may perform standard processing on the underground external environment data, the underground internal environment data and the underground production safety factor data to generate standard data points. Standard processing may refer to the steps or methods for processing the underground external environment data, the underground internal environment data and the underground production safety factor data. After the standard processing, standard data points for subsequent processing may be generated. Standard data points may refer to data structures used for machine calculation models.

[0045] Step 203, importing the standard data points into the risk prediction calculation model to generate a real-time safety prediction value.

[0046] In some embodiments, the above-mentioned execution entity may import standard data points into a risk prediction calculation model to generate a real-time safety prediction value. The risk prediction calculation model may refer to a calculation model used to predict accident risks. The calculation model may be a machine learning model such as a back propagation neural network, a convolutional neural network, etc., which may be selected as needed. The real-time safety prediction value may refer to the data generated after the current standard data points are imported into the risk prediction calculation model. The safety prediction value may be data in a target interval, such as data between 0 and 1, between 0 and 100, or between -1 and 1, which may be set as needed and is not limited here. As an example, when the safety prediction value is between 0 and 1, the safety prediction value may be 0, 0.15, 0.9, etc.

[0047] In some optional implementations of some embodiments, the risk prediction calculation model is a single hidden layer feedforward neural network model. In order to balance the training efficiency and the stability of the model system, the learning rate is selected to be a value between 0.05-0.5. More preferably, the learning rate can be selected to be 0.2.

[0048] In some optional implementations of some embodiments, the risk prediction calculation model is a single-layer feedforward neural network model, and the number of neurons in its hidden layer can be determined by grey relational analysis, including:

[0049] The first step is to set the number of neurons in the hidden layer of the above feedforward neural network model to 20. Generally, when setting the number of neurons in the hidden layer, if it exceeds 20, the training efficiency will be greatly affected, so the number of neurons in the hidden layer is initially set to 20.

[0050] The second step is to train the risk prediction calculation model based on a pre-set training set and comparison machine until the training objectives are met.

[0051] The third step is to import the training set into the trained risk prediction calculation model, obtain the output data of each hidden layer node (i.e., neuron), calculate the 20 output data based on the grey correlation analysis method, and generate the grey correlation threshold.

[0052] The fourth step is to delete the nodes whose node output is less than the grey correlation threshold to form a new risk prediction calculation model.

[0053] Repeat steps 2 to 4 until the output of all hidden layer nodes is not less than the generated grey correlation threshold, determine the number of nodes in the hidden layer, and generate a trained risk prediction calculation model.

[0054] Step 204: When the real-time safety prediction value is greater than a preset safety threshold, a warning operation is performed.

[0055] In some embodiments, when the real-time safety prediction value is greater than a preset safety threshold, the above-mentioned execution subject may perform an early warning operation. The safety threshold may refer to a preset limit value used to determine whether the real-time safety prediction value requires an early warning. As an example, when the real-time safety prediction value is data between 0 and 1, 0 may represent no risk, 1 may represent the maximum probability of an accident, and the preset safety threshold may be 0.8; that is, when the real-time safety prediction value is greater than 0.8, an early warning operation is performed. An early warning operation may refer to an operation of issuing an alarm message. As an example, when the real-time safety prediction value is greater than a preset safety threshold, the computing device 101 may perform operations such as sound warnings and image warnings. As another example, when the real-time safety prediction value is greater than a preset safety threshold, the computing device 101 may send an alarm instruction to the target device, and the target device may perform operations such as sound warnings and image warnings. Set as needed, without limitation here.

[0056] The beneficial effects of one of the above-mentioned embodiments of the present disclosure include at least: by collecting and processing underground external environment data, underground internal environment data and underground production safety factor data, importing a risk prediction calculation model to generate a prediction value, and executing a warning operation when the warning conditions are met, effective advance warning can be performed, greatly improving the accident monitoring effect of underground work.

[0057] Continue to refer Figure 3 , shows a process 300 of another embodiment of the method for monitoring underground operation safety information according to the present disclosure. The method can be Figure 1 The method for monitoring underground operation safety information comprises the following steps:

[0058] Step 301, obtaining underground external environment data, underground internal environment data and underground production safety factor data.

[0059] In some embodiments, the specific implementation of step 301 and the technical effects brought about can be referred to Figure 2 The corresponding step 201 in the embodiments will not be described in detail here.

[0060] Step 302, obtaining the current rainstorm warning related data of the underground external environment data, as well as the underground accident data, roof accident data and earthquake related data within the target time period.

[0061] In some embodiments, the above-mentioned execution subject can obtain the current rainstorm warning related data of the underground external environment data, as well as the underground accident data, roof accident data and earthquake related data within the target time period. The current rainstorm warning related data may refer to the relevant information of the rainstorm warning at the current time. The underground accident data may refer to the number of underground accidents that occurred within the target time period. The roof accident data may refer to the number of roof accidents that occurred within the target time period. The earthquake related data may refer to the information related to the earthquake within the target time period, such as the number of earthquakes, the magnitude data of each earthquake, the depth data, etc.

[0062] In some optional implementations of the embodiments, the target time period may refer to an event within a period of time from the current time. As an example, the target time period may be within 1 month, 6 months or a year, etc., and may be set as required.

[0063] Step 303, generating a roof accident standard value based on the underground accident data and the roof accident data.

[0064] In some embodiments, the above-mentioned execution subject may generate a roof accident standard value based on the underground accident data and the roof accident data. The roof accident standard value may refer to data representing the proportion of roof accidents. The computing device 101 may generate the roof accident standard value based on the following method: roof accident standard value = roof accident data / underground accident data.

[0065] Step 304, generating earthquake standard values ​​based on earthquake-related data.

[0066] In some embodiments, the above-mentioned execution subject can generate an earthquake standard value based on earthquake-related data. The earthquake standard value may refer to the ratio of the average data representing earthquakes in the target time period to the maximum earthquake. The computing device 101 can generate an earthquake standard value based on the following steps: the first step is to obtain at least one earthquake-related data in the target time period. The second step is to calculate the average value based on the product of the magnitude and the earthquake depth of each earthquake-related data in the at least one earthquake-related data to generate an average earthquake index. The third step is to divide the average earthquake index by the earthquake index of the maximum magnitude to generate the earthquake standard value. Among them, the magnitude of the maximum magnitude can be 12, the maximum depth of the earthquake can be 60 kilometers, and the earthquake index of the maximum magnitude can be 12*60=720.

[0067] Step 305: Generate a rainstorm warning standard value based on the rainstorm warning related data and the preset rainstorm warning index.

[0068] In some embodiments, the above-mentioned execution entity may generate a standard value for a rainstorm warning based on rainstorm warning related data and a preset rainstorm warning index. The standard value for a rainstorm warning may refer to the data corresponding to the rainstorm warning level data at the current time and the preset rainstorm warning index. As an example, the rainstorm warning index may be "1 (red warning), 0.7 (orange warning), 0.4 (yellow warning), 0.1 (blue warning), 0 (no warning)", that is, when the rainstorm warning is no warning, the standard value for a rainstorm warning is 0. When the rainstorm warning is a blue warning, the standard value for a rainstorm warning is 0.1. When the rainstorm warning is a yellow warning, the standard value for a rainstorm warning is 0.4. When the rainstorm warning is a red warning, the standard value for a rainstorm warning is 1.

[0069] Step 306, based on the real-time mining speed data of the underground internal environment data and the implemented mining area data, generate real-time mining progress data.

[0070] In some embodiments, the execution subject may generate real-time mining progress data based on the real-time mining speed data of the underground internal environment data and the implemented mining area data. The real-time mining speed data may refer to the product of the real-time mining speed data and the real-time mining area data.

[0071] Step 307, generating a mining intensity standard value based on the underground spatial three-dimensional data of the underground internal environment data and the implementation mining progress data.

[0072] In some embodiments, the above-mentioned execution subject can generate a mining intensity standard value based on the underground space three-dimensional data of the underground internal environment data and the implementation mining progress data. The mining intensity standard value can refer to the relevant data of the underground operation progress. The method for calculating the mining intensity standard value can be: mining intensity standard value = mining progress data / (length of the underground space three-dimensional data*width of the underground space three-dimensional data*height of the underground space three-dimensional data).

[0073] Step 308, based on the underground space three-dimensional data and underground space vertex coordinate data of the underground internal environment data, and the support equipment coordinate data and support resistance data in the underground production safety factor data, generate a support resistance stability standard value.

[0074] In some embodiments, the execution subject may generate the support resistance stability standard value through the following steps based on the underground space three-dimensional data and underground space vertex coordinate data of the underground internal environment data, and the support equipment coordinate data and support resistance data in the underground production safety factor data:

[0075] Step 1: The above-mentioned execution subject can generate the underground space center of gravity data based on the underground space vertex coordinate data.

[0076] Assume that there are N underground space vertex coordinate data, and the nth underground space vertex coordinate data can be "Xn, Yn, Zn", Xn can refer to the data of the nth underground space vertex coordinate data based on the X-axis direction of the underground three-dimensional space, Yn can refer to the data of the nth underground space vertex coordinate data based on the Y-axis direction of the underground three-dimensional space, and Zn can refer to the data of the nth underground space vertex coordinate data based on the Z-axis direction of the underground three-dimensional space, where n is a positive integer. Then the calculation formula for generating the underground space center of gravity data can be:

[0077] Downhole space center of gravity data = [(∑Xn) / N, (∑Yn) / N, (∑Zn) / N]

[0078] Among them, (∑Xn) / N is the data of the downhole space center of gravity data in the X-axis direction, (∑Yn) / N is the data of the downhole space center of gravity data in the Y-axis direction, and (∑Zn) / N is the data of the downhole space center of gravity data in the Z-axis direction.

[0079] Step 2: The above-mentioned execution entity can generate support plane center data based on the support equipment coordinate data.

[0080] Assume that there are M coordinate data of underground support equipment, and the coordinate data of the mth underground support equipment can be "XXm, YYm", XXm can refer to the data of the coordinate data of the mth underground support equipment based on the X-axis direction of the underground three-dimensional space, and YYm can refer to the data of the coordinate data of the mth underground support equipment based on the Y-axis direction of the underground three-dimensional space, where m is a positive integer. The calculation formula for generating the support plane center data can be:

[0081] Support plane center data = [(∑XXm) / M, (∑YYm) / M]

[0082] Wherein, (∑XXm) / M is the data of the center of the support plane in the X-axis direction, and (∑YYm) / M is the data of the center of the support plane in the Y-axis direction.

[0083] Step 3: The above-mentioned execution entity can generate target longitudinal coordinate data based on the longitudinal coordinate data of the specific downhole space vertex coordinate data, the rated support resistance data and the real-time support resistance data of the support resistance data.

[0084] The specific longitudinal coordinate data may refer to the longitudinal coordinate data of the vertex closest to the support device to be processed. The longitudinal coordinate data may refer to the data in the Z-axis direction of the underground three-dimensional space. Assuming that the longitudinal coordinate data of the specific underground space vertex coordinate data corresponding to one of the support devices is Zm, the rated support resistance is R, and the real-time support resistance data is A, the calculation formula of the target longitudinal coordinate data corresponding to the underground space vertex coordinate data can be:

[0085] Target longitudinal coordinate data ZZm=Zm*R / A.

[0086] Step 4: The above execution subject can generate relative center of gravity data based on the target longitudinal coordinate data and the support plane center data. The X-axis coordinate data and Y-axis coordinate data of the relative center of gravity data are the same as the corresponding data of the support plane center data, and the Z-axis coordinate data of the relative center of gravity data is the same as the above target longitudinal coordinate data, so the relative center data = [(∑XXm) / M, (∑YYm) / M, ∑ZZm / N]

[0087] Among them, (∑XXm) / M is the data in the X-axis direction relative to the center data, (∑YYm) / M is the data in the Y-axis direction relative to the center data, and ∑ZZm / N is the data in the Z-axis direction relative to the center data.

[0088] Step 5: The above-mentioned execution subject can generate offset center of gravity data based on the downhole space center of gravity data and relative center of gravity data.

[0089] Offset center of gravity data = [(∑XXm) / M-(∑Xn) / N, (∑YYm) / M-(∑Yn) / N, ∑ZZm / N-(∑Zn) / N]

[0090] Among them, [(∑XXm) / M-(∑Xn) / N is the data of the offset center of gravity data in the X-axis direction, (∑YYm) / M-(∑Yn) / N is the data of the offset center of gravity data in the Y-axis direction, ∑ZZm / N-(∑Zn) / N is the data of the offset center of gravity data in the Z-axis direction.

[0091] Step 6: The above-mentioned execution entity can generate a support resistance stability standard value based on the underground space three-dimensional data, rated support resistance data, real-time support resistance data and offset center of gravity data.

[0092] Assume that the X-axis data of the offset center of gravity data is X1, the data in the Y-axis direction is Y1, the data in the Z-axis direction is Z1, the underground space volume V = the length of the underground space three-dimensional data * the width of the underground space three-dimensional data * the height of the underground space three-dimensional data, the rated support resistance data of the m-th support device is Rm, and the real-time support resistance data of the m-th support device is Am.

[0093] Then the standard value of support resistance stability = [(X1*X2*X3) / V]*[∑|Am-Rm| / ∑|Rm].

[0094] Step 309, generating a support deployment stability standard value based on the support equipment change data of the underground production safety factor data within a specific time period.

[0095] In some embodiments, the above-mentioned execution entity can generate a support deployment stability standard value based on the support equipment change data of the underground production safety factor data within a specific time period through the following steps: The first step is to obtain the total support equipment data of the support equipment change data within 24 hours before the current time, as well as the movement frequency data of each support equipment. It should be pointed out that the specific time period can also be other time periods such as within 26 hours before the current time, which can be set as needed, and no specific restrictions are made here. The second step is to perform a summation calculation based on the movement frequency data of each support equipment to generate the total movement frequency data. The third step is to generate a support deployment stability standard value based on the above-mentioned support equipment total data and movement frequency data. Among them, the support deployment stability standard value = total movement frequency data / support equipment total data.

[0096] Step 310, based on the roof accident standard value, earthquake standard value, rainstorm warning standard value, mining intensity standard value, support resistance stability standard value and support deployment stability standard value, obtain standard data points.

[0097] In some embodiments, the above-mentioned execution entity can match the roof accident standard value, earthquake standard value, rainstorm warning standard value, mining intensity standard value, support resistance stability standard value and support deployment stability standard value with the input parameters of the risk prediction calculation model, and sort them to obtain standard data points, and use the standard data points as the input values ​​of the risk prediction calculation model.

[0098] Step 311, importing standard data points into the risk prediction calculation model to generate real-time safety prediction values.

[0099] Step 312: When the real-time safety prediction value is greater than the preset safety threshold, a warning operation is performed.

[0100] In some embodiments, the specific implementation of steps 311 to 312 and the technical effects brought about can be referred to Figure 2 The corresponding steps 203 to 204 in the embodiments are not described in detail here.

[0101] The beneficial effects of one of the above-mentioned embodiments of the present disclosure include at least: generating a support resistance stability standard value based on the underground space three-dimensional data of the underground internal environment data, and the support equipment coordinate data, underground space vertex coordinate data and support resistance data in the underground production safety factor data, which can form a more accurate support resistance stability standard value and greatly improve the prediction accuracy of the mine.

[0102] All the above optional technical solutions can be arbitrarily combined to form optional embodiments of the present application, which will not be described one by one here.

[0103] The following are embodiments of the device disclosed herein, which can be used to execute the method embodiments disclosed herein. For details not disclosed in the device embodiments disclosed herein, please refer to the method embodiments disclosed herein.

[0104] Further references Figure 4 As an implementation of the above methods in the above figures, the present disclosure provides some embodiments of a downhole operation safety information device. These device embodiments are similar to Figure 2 Corresponding to the above method embodiments, the device can be specifically applied to various electronic devices.

[0105] like Figure 4 As shown, in some embodiments, the monitoring device 400 for underground operation safety information includes:

[0106] The acquisition module 401 of the monitoring device for underground operation safety information is configured to acquire underground external environment data, underground internal environment data and underground production safety factor data.

[0107] The first generation module 402 of the monitoring device for underground operation safety information performs standard processing on underground external environment data, underground internal environment data and underground production safety factor data to generate standard data points.

[0108] The second generation module 403 of the monitoring device for underground operation safety information imports the standard data points into the risk prediction calculation model to generate a real-time safety prediction value.

[0109] The early warning module 404 of the monitoring device for underground operation safety information performs an early warning operation when the real-time safety prediction value is greater than a preset safety threshold.

[0110] In some optional implementations of some embodiments, the first generation module 402 of the monitoring device for underground operation safety information is further configured to: perform external standard processing on the underground external environment data to generate roof accident standard values, earthquake standard values ​​and heavy rain warning standard values; perform internal standard processing on the underground internal environment data to generate mining intensity standard values; perform safety production standard processing on the underground production safety factor data to generate support resistance stability standard values ​​and support deployment stability standard values; obtain standard data points based on roof accident standard values, earthquake standard values, heavy rain warning standard values, mining intensity standard values, support resistance stability standard values ​​and support deployment stability standard values.

[0111] In some optional implementations of some embodiments, external standard processing is performed on the underground external environmental data to generate roof accident standard values, earthquake standard values ​​and heavy rain warning standard values, including: obtaining heavy rain warning related data at the current time of the underground external environmental data, as well as underground accident data, roof accident data and earthquake related data within the target time period; generating roof accident standard values ​​based on the underground accident data and roof accident data; generating earthquake standard values ​​based on the earthquake related data; generating heavy rain warning standard values ​​based on the heavy rain warning related data and preset heavy rain warning indicators.

[0112] In some optional implementations of some embodiments, internal standard processing is performed on the underground internal environment data to generate standard values ​​of mining intensity, including: generating real-time mining progress data based on real-time mining speed data and implemented mining area data of the underground internal environment data; generating standard values ​​of mining intensity based on underground spatial three-dimensional data and implemented mining progress data of the underground internal environment data.

[0113] In some optional implementations of some embodiments, underground production safety factor data is processed according to production safety standards to generate standard values ​​for support resistance stability and support deployment stability, including: generating standard values ​​for support resistance stability based on underground space three-dimensional data of underground internal environment data, as well as support equipment coordinate data, underground space vertex coordinate data and support resistance data in the underground production safety factor data; generating standard values ​​for support deployment stability based on support equipment change data of the underground production safety factor data within a specific time period.

[0114] In some optional implementations of some embodiments, based on the three-dimensional data of the underground space of the underground internal environment data, and the support equipment coordinate data, the underground space vertex coordinate data and the support resistance data in the underground production safety factor data, a support resistance stability standard value is generated, including: generating the underground space center of gravity data based on the underground space vertex coordinate data; generating the support plane center data based on the support equipment coordinate data; generating the target longitudinal coordinate data based on the longitudinal coordinate data of the specific underground space vertex coordinate data, the rated support resistance data and the real-time support resistance data of the support resistance data; generating the relative center of gravity data based on the target longitudinal coordinate data and the support plane center data; generating the offset center of gravity data based on the underground space center of gravity data and the relative center of gravity data; generating the support resistance stability standard value based on the three-dimensional data of the underground space, the rated support resistance data, the real-time support resistance data and the offset center of gravity data.

[0115] In some optional implementations of some embodiments, the risk prediction calculation model is a single hidden layer back-propagation neural network model.

[0116] In some optional implementations of some embodiments, the number of nodes in the hidden layer is determined by grey relational analysis.

[0117] It is understood that the units described in the device 400 are similar to those described in the reference Figure 2 Therefore, the operations, features and beneficial effects described above for the method are also applicable to the device 400 and the units included therein, and will not be described in detail here.

[0118] like Figure 5 As shown, the electronic device 500 may include a processing device (e.g., a central processing unit, a graphics processing unit, etc.) 501, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 502 or a program loaded from a storage device 508 into a random access memory (RAM) 503. In the RAM 503, various programs and data required for the operation of the electronic device 500 are also stored. The processing device 501, the ROM 502, and the RAM 503 are connected to each other via a bus 504. An input / output (I / O) interface 505 is also connected to the bus 504.

[0119] Typically, the following devices may be connected to the I / O interface 505: an input device 506 including, for example, a touch screen, a touch pad, a keyboard, a mouse, a camera, a microphone, an accelerometer, a gyroscope, etc.; an output device 507 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; a storage device 508 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 509. The communication device 509 may allow the electronic device 500 to communicate with other devices wirelessly or by wire to exchange data. Although Figure 5 The electronic device 500 is shown with various devices, but it should be understood that it is not required to implement or possess all the devices shown. More or fewer devices may be implemented or possessed instead. Figure 5 Each block shown in the figure may represent one device, or may represent multiple devices as required.

[0120] In particular, according to some embodiments of the present disclosure, the process described above with reference to the flowchart can be implemented as a computer software program. For example, some embodiments of the present disclosure include a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In some such embodiments, the computer program can be downloaded and installed from the network through the communication device 509, or installed from the storage device 508, or installed from the ROM 502. When the computer program is executed by the processing device 501, the above-mentioned functions defined in the method of some embodiments of the present disclosure are executed.

[0121] It should be noted that the computer-readable medium in some embodiments of the present disclosure may be a computer-readable signal medium or a computer-readable storage medium or any combination of the two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In some embodiments of the present disclosure, the computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, device or device. In some embodiments of the present disclosure, the computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, in which a computer-readable program code is carried. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. The computer readable signal medium may also be any computer readable medium other than a computer readable storage medium, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer readable medium may be transmitted using any suitable medium, including but not limited to: wires, optical cables, RF (radio frequency), etc., or any suitable combination of the above.

[0122] In some embodiments, the client and the server may communicate using any currently known or future developed network protocol such as HTTP (HyperText Transfer Protocol), and may be interconnected with any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include a local area network ("LAN"), a wide area network ("WAN"), an internet (e.g., the Internet), and a peer-to-peer network (e.g., an ad hoc peer-to-peer network), as well as any currently known or future developed network.

[0123] The computer-readable medium may be included in the device; or it may exist independently without being assembled into the electronic device. The computer-readable medium carries one or more programs. When the one or more programs are executed by the electronic device, the electronic device: obtains underground external environment data, underground internal environment data, and underground production safety factor data; performs standard processing on the underground external environment data, underground internal environment data, and underground production safety factor data to generate standard data points; imports the standard data points into the risk prediction calculation model to generate a real-time safety prediction value; and performs an early warning operation when the real-time safety prediction value is greater than a preset safety threshold.

[0124] Computer program code for performing the operations of some embodiments of the present disclosure may be written in one or more programming languages ​​or a combination thereof, including object-oriented programming languages ​​such as Java, Smalltalk, C++, and conventional procedural programming languages ​​such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In cases involving a remote computer, the remote computer may be connected to the user's computer via any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., via the Internet using an Internet service provider).

[0125] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present disclosure. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some implementations as replacements, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0126] The units described in some embodiments of the present disclosure may be implemented by software or hardware. The units described may also be arranged in a processor, for example, they may be described as: an acquisition module, a first generation module, a second generation module, and an early warning module. For example, the acquisition module may also be described as a "module for acquiring underground external environment data, underground internal environment data, and underground safety production factor data."

[0127] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.

[0128] The above descriptions are only some preferred embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the above-mentioned inventive concept. For example, the above-mentioned features are replaced with the technical features with similar functions disclosed in the embodiments of the present disclosure (but not limited to) and the technical solutions formed.

Claims

1. A method for monitoring underground operation safety information, characterized in that: The method comprises: Obtain underground external environment data, underground internal environment data and underground safety production factor data; The underground external environment data, the underground internal environment data and the underground production safety factor data are subjected to standard processing to generate standard data points, specifically: the underground external environment data is subjected to external standard processing to generate roof accident standard values, earthquake standard values ​​and rainstorm warning standard values; the underground internal environment data is subjected to internal standard processing to generate mining intensity standard values; the underground production safety factor data is subjected to production safety standard processing to generate support resistance stability standard values ​​and support deployment stability standard values; based on the roof accident standard value, the earthquake standard value, the rainstorm warning standard value, the mining intensity standard value, the support resistance stability standard value and the support deployment stability standard value, the standard data point is obtained. Importing the standard data points into a risk prediction calculation model to generate a real-time safety prediction value; When the real-time safety prediction value is greater than a preset safety threshold, an early warning operation is performed; The processing of the underground production safety factor data with production safety standards to generate a support resistance stability standard value and a support deployment stability standard value includes: Generate the support resistance stability standard value based on the underground space three-dimensional data and underground space vertex coordinate data of the underground internal environment data, and the support equipment coordinate data and support resistance data in the underground production safety factor data; Generate the support deployment stability standard value based on the support equipment change data of the underground production safety factor data within a specific time period; The method of generating the support resistance stability standard value based on the underground space three-dimensional data and underground space vertex coordinate data of the underground internal environment data, and the support equipment coordinate data and support resistance data in the underground production safety factor data, comprises: Based on the downhole space vertex coordinate data, generating downhole space center of gravity data; Based on the support equipment coordinate data, generating support plane center data; Generate target longitudinal coordinate data based on the longitudinal coordinate data of the specific downhole space vertex coordinate data, the rated support resistance data of the support resistance data, and the real-time support resistance data; Generate relative center of gravity data based on the target longitudinal coordinate data and the support plane center data; generating offset center of gravity data based on the downhole spatial center of gravity data and the relative center of gravity data; The support resistance stability standard value is generated based on the underground space three-dimensional data, the rated support resistance data, the real-time support resistance data and the offset center of gravity data.

2. The method according to claim 1, characterized in that The external standard processing of the underground external environment data to generate roof accident standard values, earthquake standard values ​​and rainstorm warning standard values ​​includes: Obtaining the rainstorm warning related data of the underground external environment data at the current time, as well as the underground accident data, roof accident data and earthquake related data within the target time period; generating the roof accident standard value based on the underground accident data and the roof accident data; Based on the earthquake-related data, generating the earthquake standard value; The heavy rain warning standard value is generated based on the heavy rain warning related data and the preset heavy rain warning index.

3. The method according to claim 1, characterized in that The performing internal standard processing on the underground internal environment data to generate a mining intensity standard value includes: Generate real-time mining progress data based on the real-time mining speed data and the implemented mining area data of the underground internal environment data; The mining intensity standard value is generated based on the underground space three-dimensional data of the underground internal environment data and the implementation mining progress data.

4. The method according to claim 1, characterized in that: The risk prediction calculation model is a back propagation neural network model with a single hidden layer.

5. The method according to claim 4, characterized in that The number of nodes in the hidden layer is determined by grey relational analysis.

6. A terminal device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 5 are implemented.

7. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.