A comprehensive construction method of partial dewatering and support for saturated soft loess tunnels

Through the comprehensive construction method of partial precipitation and support, combined with the use of spray anchor nets and immersed pipe sand and gravel piles, the problems of high difficulty and poor stability of saturated soft loess layer are solved, and more efficient and safe tunnel construction is achieved, reducing the number of times Surface settlement and construction costs.

CN115324591BActive Publication Date: 2024-11-22XI'AN UNIVERSITY OF ARCHITECTURE AND TECHNOLOGY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211137708.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-19
Publication Date
2024-11-22
Estimated Expiration
2042-09-19

AI Technical Summary

Technical Problem

When crossing the saturated soft loess layer, tunnel construction is difficult, existing methods are time-consuming and labor-intensive and prone to problems such as uneven surface settlement and damage to nearby buildings.

Method used

The comprehensive construction method of partial precipitation-support is adopted, and the global precipitation is carried out through the cooperation of the precipitation well and the water stop curtain, and the excavation and support are performed in steps. The initial support is used with a spray anchor net, and the immersed pipe sand and stone are used at the bottom of the tunnel arch. Pile reinforcement to form a scientific and reasonable comprehensive precipitation-support construction method.

Benefits of technology

It improves soil layer stability, reduces total and differential settlement of the surface, slows down the settlement consolidation rate of tunnel base formations, shortens the construction cycle, improves construction efficiency and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115324591B_ABST
    Figure CN115324591B_ABST
Patent Text Reader

Abstract

A comprehensive construction method for partial dewatering and support of saturated soft loess tunnels, firstly, an external dewatering well is used in conjunction with a water-stop curtain to carry out global dewatering, and then a step-by-step, partial dewatering, excavation, and support construction cycle is carried out for the tunnel, the cycle is short and orderly, and the initial support of the "spray anchor net" combination is strong and powerful; the external dewatering well takes into account both dewatering and observation functions, which is convenient for real-time control of the groundwater level; considering that the arch foot of the tunnel in the soft loess layer is prone to collapse and instability, the tunnel arch bottom soil is reinforced with pipe-sunk gravel piles, and a set of scientific and reasonable comprehensive dewatering and support construction methods are formed in accordance with "advanced dewatering, partial excavation, short advance, strong support, and fast cycle", which improves the engineering properties of saturated soft loess by dewatering in advance, and can improve the stability of the surrounding soil layer, reduce the total surface settlement and differential settlement, and slow down the settlement consolidation rate of the tunnel base stratum with the timely excavation and appropriate support measures, and has the advantages of compact and reasonable steps, so that the engineering properties of the saturated soft loess layer are improved, and the safe and orderly progress of the tunnel construction is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of saturated soft loess layer construction, and also belongs to the technical field of tunnel construction, and in particular to a saturated soft loess tunnel partial dewatering-support comprehensive construction method. Background Art

[0002] Saturated soft loess is a special soft stratum widely distributed in Xi'an. It often exists below the groundwater level and is in a soft plastic or fluid plastic state. The characteristics of large porosity and high water content make the stratum highly sensitive and unstable, and prone to large deformation when encountering additional loads. These characteristics make it difficult to carry out excavation and support work when tunnels pass through saturated soft loess, and it is difficult to form a tunnel.

[0003] At present, when tunnel projects pass through saturated soft loess layers, the projects mostly use construction methods such as shield method, freezing method, grouting reinforcement, etc., which are not only time-consuming and labor-intensive, but also extremely expensive. If not handled properly, they can easily cause problems such as uneven surface settlement, cracking and damage to nearby buildings and pipelines. Summary of the invention

[0004] In order to solve the above problems, the present invention discloses a comprehensive construction method of partial dewatering and support for saturated soft loess tunnels, and puts forward measures to control the construction risks of saturated soft loess strata. Firstly, an external dewatering well is used in cooperation with a water-stop curtain to carry out global dewatering, and then a step-by-step, partial dewatering, excavation and support construction cycle is carried out for the tunnel. The cycle is short and orderly, and the initial support of the "sprayed anchor net" combination is strong and powerful. The external dewatering well takes into account both dewatering and observation functions, which is convenient for real-time control of the groundwater level. Considering that the arch foot of the tunnel in the soft loess stratum is prone to collapse and instability, the tunnel arch bottom soil is reinforced with sunken pipe sand and gravel piles, thereby forming a complete set of scientific and reasonable comprehensive dewatering and support construction methods, which have the advantages of being able to improve the stability of the surrounding soil layers, reduce the total surface settlement and differential settlement, and slow down the settlement and consolidation rate of the tunnel base strata.

[0005] A saturated soft loess tunnel partial dewatering-support comprehensive construction method, comprising the following steps:

[0006] a. Measurement, positioning and setting out: Level the site, measure and position the lines; mark the ground surface along the excavation direction of the tunnel to be built, 3 to 5 meters away from both sides of the tunnel outer contour, and prepare to construct the water-stop curtain 1;

[0007] b. Construct water-stop curtains 1 on both sides along the tunnel excavation direction;

[0008] c. Construct the outer and inner drainage wells of the water-stop curtain 1;

[0009] d. Dewater the outer side of the water-stop curtain 1 and then dewater the inner dewatering well;

[0010] e. Advance support, excavation, initial support for the upper left part of the tunnel, and setting of the first temporary invert 8 and the first middle partition 9; advance support, excavation, initial support for the upper right part of the tunnel, and setting of the second temporary invert 18: use anchor rod advance reinforcement, drill and blast excavation, advance 1 to 2 m, lay waterproof layer 6, erect arch frame 7, construct support for the first temporary invert 8, lay mesh, and spray fiber concrete;

[0011] f. Grouting to reinforce the tunnel arch; after the excavation and support of the upper steps of the tunnel are completed, construct a small duct 10 within the range of 150° to 180° of the arch, and inject grout into the small duct 10 to form an arched slurry-soil reinforcement body above the tunnel that meets the load-bearing requirements; the small and medium ducts 10 have a diameter of 38mm to 50mm, a circumferential spacing of 30 to 60cm, and are evenly arranged within the range of 150° to 180° of the tunnel arch.

[0012] g. Construction of a dewatering well at the bottom of the tunnel to advance dewatering of the lower steps;

[0013] h. Advance support, excavation and initial support of the lower left part of the tunnel, and setting of the third temporary invert 15 and the second intermediate partition wall 19;

[0014] i. Advance support, excavation, initial support of the lower right part of the tunnel, and setting of the fourth temporary invert 16:

[0015] j. Install several foot-locking anchor rods 11 on both sides of the tunnel to reinforce the arch feet. The foot-locking anchor rods 11 are 6 to 8 meters long and are driven into the soil around the tunnel at an angle of 55° to 60° with the vertical direction;

[0016] k. Excavate a concrete invert 14 above the third temporary invert 15 and the fourth temporary invert 16: construct a pipe-sinking gravel pile 12 at the tunnel arch bottom for foundation reinforcement, and lay a medium sand cushion 13, backfill concrete above the third temporary invert 15 and the fourth temporary invert 16 to form a concrete invert 14, so that the initial support forms a full-section closure; the diameter of the pipe-sinking gravel pile 12 is 500-800mm, the pile length is 6-8m, the pile spacing is 600-1000mm, and the medium sand cushion 13 is 300-500mm thick;

[0017] l. Carry out quality inspection and deformation monitoring on the initial support of the tunnel. If the strength of the initial support concrete does not reach 80% of the design value or the deformation of the surrounding rock is still unstable, it is unqualified, and reinforcement measures are taken; if the strength of the initial support concrete reaches more than 80% of the design value and the deformation of the surrounding rock tends to converge, it is qualified, and temporary support structures such as temporary inverts and intermediate partitions are removed;

[0018] m. Carry out the next construction cycle.

[0019] The step b adopts the form of double-row high-pressure rotary jet piles, and the double-row high-pressure rotary jet piles are constructed along the marking line set in step a, and the depth should exceed the tunnel arch bottom H26~8m; the diameter of the high-pressure rotary jet piles is 600~1000mm, and the adjacent piles are interlocked with each other by 100~200mm, and the adjacent rows of high-pressure rotary jet piles are arranged closely without any interval.

[0020] The step c specifically comprises:

[0021] c1. Drainage wells are drilled every 2 to 3 meters downwards at 1.5 to 2.5 meters outside the water-stop curtain 1. The depth should reach the bottom of the tunnel. Each drainage well is connected to a water pump with a pipeline. The external drainage well 2 also serves as a groundwater level observation well to monitor the water level in real time.

[0022] c2. Divide the tunnel section 4 into an upper step and a lower step. The upper step is further divided into the upper left part of the tunnel ① and the upper right part of the tunnel ②. The lower step is further divided into the lower left part of the tunnel ③ and the lower right part of the tunnel ④. Drill the first dewatering well I and the second dewatering well II downward on the inner side of the water-stop curtain 1 and directly above the left and right parts of the tunnel section 4, respectively. Connect them to the water pump with pipelines. The depths of the first dewatering well I and the second dewatering well II reach the bottom of the upper step.

[0023] The step d specifically comprises:

[0024] d1. Dewatering outside the water-stop curtain 1: Start the water pump connected to the external dewatering well 2 to dewater the saturated soft loess layer as a whole;

[0025] d2. Dewatering the inner side of the water-stop curtain 1 and the steps on the tunnel: start the water pumps connected to the first dewatering well I and the second dewatering well II to dewater the steps on the upper left part ① and the upper right part ② of the tunnel.

[0026] The step e specifically comprises:

[0027] After the water level drops below the bottom of the upper step of the tunnel, construction will be carried out on the soil in the upper left part of the tunnel:

[0028] e1. Drive glass fiber anchor rods 5 into the soil at the upper left part ① of the ring tunnel, including the upper right part ② and the lower left part ③ of the tunnel, at a certain external insertion angle to advance the reinforcement of the surrounding saturated soft loess layer;

[0029] e2. Use drilling and blasting method to excavate the soil in the upper left part of the upper step, with a penetration of 1 to 2 m;

[0030] e3. Immediately thereafter, a waterproof layer 6 is laid around the soil of the upper left part of the tunnel ①, a steel arch frame 7 is erected, and the first temporary invert 8 and the first intermediate partition 9 are constructed with steel support. Then, a steel mesh is laid on the steel arch frame 7 and steel fiber concrete is sprayed to form the initial support of "sprayed anchor mesh";

[0031] e4. Repeat steps e1 to e3 several times to make the excavation progress of the upper left part of the tunnel ① lead that of the upper right part of the tunnel ② by 3 to 5 meters.

[0032] The step g specifically comprises:

[0033] After the tunnel upper step excavation and support are fully advanced to 6-8m, the lower step of the tunnel is dewatered:

[0034] g1. Construct the third and fourth dewatering wells III and IV downwards at the center of the bottom of the steps at the upper left part of the tunnel ① and the upper right part of the tunnel ②, and connect the third and fourth dewatering wells III and IV to the pump. The depth of the third and fourth dewatering wells III and IV should reach 6 to 8 meters below the tunnel arch bottom;

[0035] g2. Start the water pump to carry out advance precipitation of the saturated soft loess under the tunnel steps and below.

[0036] The step h specifically comprises:

[0037] After the water level drops below the lower step of the tunnel, construction will be carried out on the soil in the lower left part ③ and the lower right part ④ of the lower step, including:

[0038] The soil in the lower left part ③ of the tunnel is successively supported by glass fiber anchor rods 5, excavated by drilling and blasting method (advance 1-2m), laid out waterproof layer 6, erected steel arch frame 7, constructed steel-supported temporary invert and middle partition, laid steel mesh, and sprayed with steel fiber concrete; the excavation advance of the soil in the lower left part ③ of the system is 3-5m ahead of the soil in the lower right part ④.

[0039] The step i specifically comprises:

[0040] The soil in the lower right part ④ of the tunnel is successively supported by glass fiber anchor rods 5, excavated by drilling and blasting method (advance 1-2m), laid out waterproof layer 6, erected steel arch frame 7, constructed steel support temporary invert, laid steel mesh, and sprayed steel fiber concrete.

[0041] The advance support measures in steps e, f, h, and i adopt glass fiber anchor rods 5, whose length is 4 to 6 m; the initial support includes a waterproof layer 6, a steel arch frame 7, a steel mesh and sprayed steel fiber concrete to form a "sprayed anchor mesh" mixed support; the steel arch frame 7 adopts a steel frame, the steel mesh is made of steel bars with a diameter of 6 mm to 10 mm, and the mesh size of the steel mesh is 20 cm × 20 cm to 25 cm × 25 cm.

[0042] The certain external insertion angle described in step e means that the external insertion angle of the anchor rod driven into the soil outside the tunnel excavation contour line is 25-35 degrees, and the anchor rod is driven into the tunnel excavation contour line and along the vertical face.

[0043] In step c2, the upper and lower steps of the tunnel section 4 are spaced 6 to 8 m apart, the upper left part ① of the tunnel and the upper right part ② of the tunnel are spaced 3 to 5 m apart, and the lower left part ③ of the tunnel and the lower right part ④ of the tunnel are spaced 3 to 5 m apart.

[0044] Compared with the prior art, the present invention has the following beneficial effects:

[0045] The present invention uses a dewatering well in conjunction with a water-stopping curtain 1 to carry out partial advance dewatering of the saturated soft loess layer, creating conditions for partial excavation and support of the tunnel face. The present invention follows the concept and principle of "advance dewatering, partial excavation, short advance, strong support, and fast circulation", and innovatively proposes the construction concept of "step-by-step dewatering and support", which improves the engineering properties of the saturated soft loess by dewatering in advance, and cooperates with timely excavation and appropriate support measures. The steps are compact and reasonable, so that the engineering properties of the saturated soft loess layer are improved, ensuring the safety and orderly progress of tunnel construction.

[0046] The present invention adheres to the concept and principle of "advanced descent, partial excavation, short advance, strong support and fast cycle", adopts a double-layer rotary jet pile water-stop curtain in conjunction with internal and external dewatering wells to carry out partial dewatering of the tunnel section, and then supports layer by layer after the loess layer is consolidated and stabilized. The initial support of the "sprayed anchor net" combination is both rigid and flexible and strong. Compared with the traditional construction method, the cycle of dewatering, excavation and support is shortened, the step sequence is compact and reasonable, and the cycle rhythm is accelerated, which is conducive to the closure of each small section as soon as possible and reaching a stable state in advance to facilitate the safe and rapid development of excavation work.

[0047] Among them, the inner and outer dewatering wells cooperate with each other, which not only improves the dewatering efficiency, but also can use the outer dewatering well as a water level observation well to monitor the water level in real time and issue water level warnings in advance; before the partial excavation, the soil of each part is fully surrounded and reinforced with fiberglass anchor rods, which can effectively ensure the safety of the excavation operation. Its removable feature means that the fiberglass anchor rods will not hinder the excavation of subsequent soil at the face.

[0048] Taking into account the fact that the soil in the arch is prone to collapse after tunnel excavation, after excavation and support of the upper steps of the tunnel, small grouting tubes are used over a large area of ​​the arch to form a solid arched slurry-soil reinforcement body, which basically eliminates the possibility of arch collapse.

[0049] The tunnel arch bottom soil is reinforced with sunken tube gravel piles. The soil is compacted while gravel is poured in through vibrating tubes. The compaction effect is good and the amount of sand and gravel is small. The soil density can be greatly improved, and the bearing capacity of the foundation at the arch bottom is also greatly increased. The gravel also has the effect of improving the drainage capacity of the soil. The use of sunken tube gravel piles has multiple positive benefits.

[0050] In summary, the present invention improves the construction efficiency when the tunnel passes through the saturated soft loess layer, increases the stability of the soil around the tunnel, improves the bearing capacity and drainage performance of the tunnel arch bottom, and the construction principle is simple and easy to understand, the process cycle is short and reasonable, which is conducive to maintaining the safety of tunnel excavation and operation, reducing uneven settlement, shortening the construction period, saving construction costs, and has promotion value in actual engineering. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] Figure 1 It is a construction process flow chart of the present invention.

[0052] Figure 2 It is a schematic diagram of the stratum and tunnel section 4 of the present invention.

[0053] Figure 3 It is a schematic diagram of the stratum and tunnel profile of the present invention.

[0054] Figure 4 It is a structural diagram of a tunnel section 4 taking the excavation and support of the upper left part of the tunnel ① as an example of the present invention.

[0055] Figure 5 The present invention Figure 4 1-1' cross-section.

[0056] Figure 6 It is a plan layout diagram of tunnel arch bottom sinking pipe gravel pile 12 of the present invention.

[0057] In the figure: 1. Water-stop curtain; 2. External dewatering well; 3. Internal dewatering well; I. First dewatering well; II. Second dewatering well; III. Third dewatering well; IV. Fourth dewatering well; 4. Tunnel section; 5. Fiber anchor rod; 6. Waterproof layer; 7. Steel arch frame; 8. First temporary invert; 9. First middle partition wall; 10. Small guide tube; 11. Locking foot anchor rod; 12. Sinking tube gravel pile; 13. Medium sand cushion layer; 14. Concrete invert; 15. Third temporary invert; 16. Fourth temporary invert; 18. Second temporary invert; 19. Second middle partition wall; H1. Depth of bottom of upper step of tunnel; H2. Depth of tunnel arch bottom. DETAILED DESCRIPTION

[0058] The technical solution provided by the present invention will be further described below in conjunction with the accompanying drawings.

[0059] A saturated soft loess tunnel partial dewatering-support comprehensive construction method, comprising the following steps:

[0060] a. Level the site, measure and position the lines: mark the ground surface along the excavation direction of the tunnel to be built, 3 to 5 meters away from both sides of the tunnel outer contour, and prepare to construct the water-stop curtain 1;

[0061] b. Figure 1 , Figure 2As shown, construct water-stop curtain 1: adopt the form of double rows of high-pressure rotary jet piles, construct double rows of high-pressure rotary jet piles along the marking line set in step one, and the depth exceeds the tunnel arch bottom H26~8m; the diameter of the high-pressure rotary jet piles is 600~1000mm, and the adjacent piles in the same row are interlocked with each other by 100~200mm to achieve the effect of interlocking water stopping, and the adjacent rows of high-pressure rotary jet piles are arranged closely without intervals.

[0062] c. Drainage wells are constructed on the outside and inside of the water-stop curtain 1, including:

[0063] c1. Drainage wells are set every 2 to 3 meters downwards at 1.5 to 2.5 meters outside the water-stop curtain 1. The depth should reach the bottom of the tunnel. Each drainage well is connected to a water pump with a pipeline. The outer drainage well 2 also serves as an underground water level observation well to monitor the water level in real time. If there is any abnormality, timely measures should be taken.

[0064] c2. Divide the tunnel section 4 into an upper step and a lower step. The upper step is further divided into the upper left part of the tunnel ① and the upper right part of the tunnel ②. The lower step is further divided into the lower left part of the tunnel ③ and the lower right part of the tunnel ④. Drill the first dewatering well I and the second dewatering well II downwards on the inner side of the water-stop curtain 1 and directly above the left and right parts of the tunnel section 4, respectively. Connect them to the water pump with pipelines. The depths of the first dewatering well I and the second dewatering well II reach the bottom of the upper step.

[0065] d. Precipitation is carried out on the outer side and inner side of the water-stop curtain 1 successively, including:

[0066] d1. Dewatering outside the water-stop curtain 1: Start the water pump connected to the external dewatering well 2 to dewater the saturated soft loess layer as a whole;

[0067] d2. Dewatering the inner side of the water-stop curtain 1 and the steps on the tunnel: Start the pumps connected to the first dewatering well I and the second dewatering well II to dewater the steps on the upper left part ① and the upper right part ② of the tunnel;

[0068] e. When the water level drops below H1 at the bottom of the upper step of the tunnel, Figure 4 , Figure 5 As shown in the figure, taking the soil in the upper left part of the tunnel ① as an example, the excavation and support steps of the tunnel are described in detail. The subsequent excavation and support steps of the soil in the upper right part of the tunnel ②, the lower left part of the tunnel ③ and the lower right part of the tunnel ④ are the same, specifically including:

[0069] e1. Drive glass fiber anchor rods 5 into the soil at the upper left part ① of the ring tunnel, including the upper right part ② and the lower left part ③ of the tunnel, at a certain external insertion angle to advance the reinforcement of the surrounding saturated soft loess layer;

[0070] e2. Use drilling and blasting method to excavate the soil in the upper left part of the tunnel, with a penetration of 1 to 2 m;

[0071] The above two steps will play a role in all-round advance reinforcement of the soil in the upper left part of the tunnel to be excavated, which to a great extent ensures the safety of tunnel excavation;

[0072] e2. Use drilling and blasting method to excavate the soil in the upper left part of the tunnel;

[0073] e3. Carry out initial support for the soil in the upper left part of the tunnel, including:

[0074] Then, immediately around the upper left part of the tunnel①, a waterproof layer 6 is laid, a steel arch frame 7 is erected, and the first temporary invert 8 and the first intermediate partition wall 9 are supported by steel;

[0075] A steel mesh is laid on the steel arch frame 7, the temporary invert 8 and the middle partition wall 9. The steel mesh is composed of steel bars with a diameter of 6mm to 10mm and a mesh size of 20cm×20cm to 25cm×25cm;

[0076] Then, steel fiber concrete is sprayed on it to form a solid "sprayed anchor net" support;

[0077] e4. Repeat steps e1 to e3 several times to make the excavation progress of the upper left part of the tunnel ① lead the upper right part of the tunnel ② by 3 to 5 meters;

[0078] f. Grouting to reinforce the tunnel arch; after the excavation and support of the upper steps of the tunnel are completed, construct a small duct 10 within the range of 150° to 180° of the arch, and inject grout into the small duct 10 to form an arched slurry-soil reinforcement body above the tunnel that meets the load-bearing requirements; the small and medium ducts 10 have a diameter of 38mm to 50mm, a circumferential spacing of 30 to 60cm, and are evenly arranged within the range of 150° to 180° of the tunnel arch.

[0079] g. Construct the third and fourth dewatering wells III and IV downwards at the center of the bottom of the steps at the upper left part of the tunnel ① and the upper right part of the tunnel ②, and connect the third and fourth dewatering wells III and IV to the pump. The depth of the third and fourth dewatering wells III and IV should reach 6 to 8 meters below the tunnel arch bottom;

[0080] Start the water pump to carry out advance precipitation of the saturated soft loess under the tunnel step and below.

[0081] h. After the water level drops below the lower step of the tunnel, construction will be carried out on the soil in the lower left part of the tunnel ③ and the lower right part of the tunnel ④, including:

[0082] The soil of the lower left part ③ of the tunnel is successively supported by glass fiber anchor rods 5, excavated by drilling and blasting method (advanced footage 1-2m), laid out waterproof layer 6, erected steel arch frame 7, constructed the third temporary invert 15 and the second intermediate partition 19 with steel support, laid out steel mesh, and sprayed with steel fiber concrete; the excavation footage of the soil of the lower left part ③ of the system is 3-5m ahead of the soil of the lower right part ④;

[0083] i. The soil in the lower right part of the tunnel ④ is successively supported by glass fiber anchor rods 5, excavated by drilling and blasting method (advance 1-2m), laid waterproof layer 6, erected steel arch frame 7, constructed the fourth temporary invert arch 16 with steel support, laid steel mesh, and sprayed steel fiber concrete;

[0084] j. Reinforce the arch foot: Drive 2 to 4 foot-locking anchor rods 11 with a length of 6 to 8 m into the arch foot on both sides of the tunnel, with an angle of 45° to 60° with the vertical direction to prevent the arch foot from collapsing and settling;

[0085] k. Carry out the construction of the invert, including:

[0086] Invert excavation;

[0087] Construct the sunken gravel piles 12 in a triangular array at the bottom of the tunnel. Figure 6 As shown, the diameter of the pipe-sinking gravel pile 12 is 500-800 mm, the pile length is 6-8 m, and the pile spacing is 600-1000 mm;

[0088] After the pile construction is completed, the upper loose soil is compacted and a 300-500 mm thick medium sand cushion layer 13 is laid;

[0089] Lay the inverted arch steel frame 7 and connect it with the side wall arch frame 7 by welding, and cast and backfill the inverted arch with concrete inverted arch 14 to make the initial support and closure of the whole section of the tunnel;

[0090] l. Perform quality inspection and deformation monitoring on the initial support of the tunnel. If the initial support concrete strength does not reach 80% of the design value or the surrounding rock deformation is still unstable (unqualified), take corresponding strengthening measures; if the initial support concrete strength reaches more than 80% of the design value and the surrounding rock deformation tends to converge (qualified), remove the temporary support structures such as the temporary invert 8 and the middle partition wall 9;

[0091] m. Carry out the next construction cycle.

[0092] The technical means disclosed in the present invention are not limited to the technical means disclosed in the above-mentioned implementation manner, but also include a technical solution composed of any combination of the above technical features.

Claims

1. A saturated soft loess tunnel partial dewatering-support integrated construction method, characterized in that: The following steps are involved: a. Surveying, positioning and setting out: Level the site, survey and position the lines; mark the ground surface along the excavation direction of the tunnel to be built, 3 to 5 meters away from both sides of the tunnel outer contour, and prepare to construct the water-stop curtain (1); b. Construct water-stop curtains (1) on both sides along the tunnel excavation direction; c. Construction of water-stop curtain (1) Outer and inner drainage wells; d. Dewater the outer side of the water-stop curtain (1), and then dewater the inner drainage well; e. Advance support, excavation, initial support for the upper left part of the tunnel, and setting of the first temporary invert (8) and the first intermediate partition (9); advance support, excavation, initial support for the upper right part of the tunnel, and setting of the second temporary invert (18): use anchor rod advance reinforcement, drill and blast excavation, advance of 1 to 2 m, lay waterproof layer (6), erect arch frame (7), construct support for the first temporary invert (8), lay mesh, and spray fiber concrete; f. Grouting to reinforce the tunnel arch; after the tunnel upper step is excavated and supported, a small conduit (10) is constructed within a range of 150° to 180° of the arch, and grouting is injected into the small conduit (10) to form an arched slurry-soil reinforcement body above the tunnel that meets the load-bearing requirements; the small conduits (10) have a diameter of 38 mm to 50 mm, a circumferential spacing of 30 to 60 cm, and are evenly arranged within a range of 150° to 180° of the tunnel arch; g. Construction of a dewatering well at the bottom of the tunnel to advance dewatering of the lower steps; h. Advance support, excavation, initial support of the lower left part of the tunnel, and setting of the third temporary invert (15) and the second intermediate partition wall (19); i. Advance support, excavation, initial support and installation of the fourth temporary invert (16) at the lower right part of the tunnel: j. A plurality of locking anchor rods (11) are driven into the arch feet on both sides of the tunnel for reinforcement. The locking anchor rods (11) are 6 to 8 m long and driven into the soil around the tunnel at an angle of 55° to 60° to the vertical direction; k. Excavating a concrete invert (14) above the third temporary invert (15) and the fourth temporary invert (16): constructing a pipe-sinking gravel pile (12) at the tunnel arch bottom to reinforce the foundation, and laying a medium sand cushion layer (13); backfilling concrete above the third temporary invert (15) and the fourth temporary invert (16) to form a concrete invert (14), so that the initial support forms a full-section closure; the diameter of the pipe-sinking gravel pile (12) is 500-800 mm, the pile length is 6-8 m, the pile spacing is 600-1000 mm, and the medium sand cushion layer (13) is 300-500 mm thick; l. Carry out quality inspection and deformation monitoring on the initial support of the tunnel. If the strength of the initial support concrete does not reach 80% of the design value or the deformation of the surrounding rock is still unstable, it is unqualified, and reinforcement measures are taken; if the strength of the initial support concrete reaches more than 80% of the design value and the deformation of the surrounding rock tends to converge, it is qualified, and the temporary invert and intermediate partition wall temporary support structure are removed; m. Carry out the next construction cycle; The step b adopts the form of double-row high-pressure rotary jet piles, and the double-row high-pressure rotary jet piles are constructed along the marking line set in step a, and the depth should exceed the tunnel arch bottom depth by 6-8m; the diameter of the high-pressure rotary jet piles is 600-1000mm, and the adjacent piles are interlocked with each other by 100-200mm, and the adjacent rows of high-pressure rotary jet piles are closely arranged without interval; The step c specifically comprises: c1. Drainage wells are drilled every 2 to 3 meters at a distance of 1.5 to 2.5 meters from the outside of the water-stop curtain (1). The depth should reach the bottom of the tunnel. Each drainage well is connected to a water pump with a pipeline. The external drainage well (2) also serves as a groundwater level observation well to monitor the water level in real time. c2. The tunnel section (4) is divided into an upper step and a lower step. The upper step is further divided into the upper left part of the tunnel ① and the upper right part of the tunnel ②. The lower step is further divided into the lower left part of the tunnel ③ and the lower right part of the tunnel ④. A first drainage well I and a second drainage well II are respectively drilled downward on the inner side of the water-stop curtain (1) and directly above the left and right parts of the tunnel section (4). They are connected to a water pump with a pipeline. The depths of the first drainage well I and the second drainage well II reach the bottom of the upper step.

2. A saturated soft loess tunnel partial dewatering-support comprehensive construction method according to claim 1, characterized in that: The step d specifically comprises: d1. Water-stop curtain (1) external dewatering: start the water pump connected to the external dewatering well (2) to dewater the saturated soft loess layer as a whole; d2. Dewatering the inner side of the water-stop curtain (1) and the steps on the tunnel: Start the water pumps connected to the first dewatering well I and the second dewatering well II to dewater the steps on the upper left part of the tunnel ① and the upper right part of the tunnel ②.

3. The method for comprehensive construction of partial dewatering and support for saturated soft loess tunnel according to claim 1 is characterized in that: The step e specifically comprises: After the water level drops below the bottom of the upper step of the tunnel, construction will be carried out on the soil in the upper left part of the tunnel: e1. Drive glass fiber anchor rods (5) into the soil at the upper left part ① of the ring tunnel, including the soil at the upper right part ② and the lower left part ③ of the tunnel, at a certain external insertion angle to advance reinforce the surrounding saturated soft loess layer; e2. Use drilling and blasting method to excavate the soil in the upper left part of the tunnel, with a penetration of 1~2m; e3. Immediately thereafter, a waterproof layer (6) is laid around the soil mass at the upper left part of the tunnel, a steel arch frame (7) is erected, a first temporary invert (8) and a first intermediate partition (9) are constructed with steel supports, and then a steel mesh is laid on the steel arch frame (7) and steel fiber concrete is sprayed to form an initial support of "sprayed anchor mesh"; e4. Repeat steps e1 to e3 several times to make the excavation progress of the upper left part of the tunnel ① lead that of the upper right part of the tunnel ② by 3 to 5 meters.

4. The method for comprehensive construction of partial dewatering and support for saturated soft loess tunnel according to claim 1 is characterized in that: The step g specifically comprises: After the tunnel upper step excavation and support are fully advanced to 6~8m, the lower step of the tunnel is dewatered: g1. Construct the third and fourth dewatering wells III and IV downwards at the center of the bottom of the steps at the upper left part of the tunnel ① and the upper right part of the tunnel ②, and connect the third and fourth dewatering wells III and IV to the pump. The depth of the third and fourth dewatering wells III and IV should reach 6~8m below the tunnel arch bottom; g2. Start the water pump to carry out advance precipitation of the saturated soft loess under the tunnel steps and below.

5. The method for comprehensive construction of partial dewatering and support for saturated soft loess tunnel according to claim 1 is characterized in that: The step h specifically comprises: After the water level drops below the lower step of the tunnel, construction will be carried out on the soil in the lower left part of the tunnel ③ and the lower right part of the tunnel ④, including: The soil of the lower left part ③ of the tunnel is successively supported by glass fiber anchor rods (5), excavated by drilling and blasting with a depth of 1 to 2 m, laid out a waterproof layer (6), erected a steel arch frame (7), constructed a third temporary steel-supported invert (15) and a second intermediate partition wall (19), laid a steel mesh, and sprayed steel fiber concrete; the excavation depth of the soil of the lower left part ③ is 3 to 5 m ahead of the soil of the lower right part ④.

6. The method for comprehensive construction of partial dewatering and support for saturated soft loess tunnel according to claim 1 is characterized in that: The step i specifically comprises: The soil in the lower right part of the tunnel (④) is supported in advance with glass fiber anchor rods (5), excavated with a drilling and blasting method of 1 to 2 m, a waterproof layer is laid (6), a steel arch frame is erected (7), a fourth temporary steel-supported invert is constructed (16), a steel mesh is laid, and steel fiber concrete is sprayed.

7. A saturated soft loess tunnel partial dewatering-support comprehensive construction method according to claim 3, characterized in that: The advance support measures in steps e, f, h and i adopt glass fiber anchor rods (5) with a length of 4 to 6 m; the initial support comprises a waterproof layer (6), a steel arch frame (7), a steel mesh and sprayed steel fiber concrete to form a "sprayed anchor mesh" mixed support; wherein the steel arch frame (7) adopts a steel frame, the steel mesh is made of steel bars with a diameter of 6 mm to 10 mm, and the mesh size of the steel mesh is 20 cm×20 cm to 25 cm×25 cm, wherein the certain external insertion angle in step e refers to: the external insertion angle of the anchor rod driven into the soil outside the tunnel excavation contour line is 25-35°, and the anchor rod is driven into the tunnel excavation contour line and along the vertical face.

8. The method for comprehensive construction of partial dewatering and support for saturated soft loess tunnel according to claim 1 is characterized in that: In step c2, the upper and lower steps of the tunnel section (4) are spaced 6 to 8 m apart, the upper left part ① and the upper right part ② of the tunnel are spaced 3 to 5 m apart, and the lower left part ③ and the lower right part ④ of the tunnel are spaced 3 to 5 m apart.