A pipeline bridge structure, a bridge device and an installation method thereof

By setting up a connection structure on the hooking member to hook the fixed bridge, and using the hooking member and the hooking part of the hooking member to hook each other, the existing bridge is solved by solving the high cost and complex installation of the multi-layer deployment. Problem, fast and flexible multi-layer bridge installation is achieved, improving wiring harness capacity and reducing costs.

CN115428284BActive Publication Date: 2025-02-14SHENZHEN HANGYI IP SERVICE CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202280002557.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-05
Publication Date
2025-02-14
Estimated Expiration
2042-08-05

AI Technical Summary

Technical Problem

When existing bridge trays realize multi-layer deployment, the production cost is high and the installation is complex, making it difficult to quickly and flexibly install multi-layer hooked bridges.

Method used

By setting up a connecting structure on the hooking member and hooking on both sides of the fixed bridge, the fast installation and fixing of the hooking member is achieved; at the same time, the first hook part on the hooking member and the second hook part on the hooking member are mutually connected with each other. Mounting, realizes rapid installation and fixing of the hooked bridge.

Benefits of technology

Quickly and flexibly install multi-layer hooking bridges on the basis of existing fixed bridges, which improves wiring harness capacity, reduces production costs, and eliminates the need for specific tools, avoids the generation of metal particles or dust, and ensures circuit safety performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115428284B_ABST
    Figure CN115428284B_ABST
Patent Text Reader

Abstract

A pipeline bridge structure, a bridge device and an installation method thereof. The pipeline bridge structure (100) comprises: a hanging piece (110) and a hanging bridge (120); the hanging piece (110) is provided with a connection structure (111), and the connection structure (111) is used to hang with two sides of a fixed bridge (200) to fix the hanging piece (110) to the fixed bridge (200); the hanging piece (110) is also provided with a first hanging part (112), and the hanging bridge (120) is provided with a second hanging part (121), and the first hanging part (112) and the second hanging part (121) are hung with each other, so that the hanging bridge (120) is fixed to the hanging piece (110). Through the above-mentioned method, the present invention can realize the rapid and flexible installation of a multi-layer hanging bridge (120) on the basis of an existing fixed bridge (200), thereby increasing the wire harness capacity and meeting work requirements under the premise of controlling costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of cable bridges, and in particular to a pipeline bridge structure, a bridge device and an installation method thereof. Background Art

[0002] The bridge is a commonly used tool in the power supply field. It is used for centralized laying of cables to facilitate routing, improve space utilization, and facilitate subsequent centralized maintenance and inspection of cables.

[0003] Existing bridges are generally fixed by brackets or hangers. To deploy multi-layer bridges, it is necessary to make molds to produce multi-layer bridges or fix multi-layer bridges on brackets or hangers. The production cost is high, and the installation is complicated, time-consuming and labor-intensive. Summary of the invention

[0004] In view of the above problems, the present invention provides a pipeline bridge structure, a bridge device and an installation method thereof, which can realize the rapid and flexible installation of multi-layer hanging bridges on the basis of existing fixed bridges, increase the wiring harness capacity, and meet work requirements under the premise of controlling costs.

[0005] According to one aspect of the present invention, there is provided a pipeline bridge structure, comprising: a hanging member and a hanging bridge; the hanging member is provided with a connecting structure, and the connecting structure is used to hang with two sides of a fixed bridge to fix the hanging member to the fixed bridge; the hanging member is also provided with a first hanging part, and the hanging bridge is provided with a second hanging part, the first hanging part and the second hanging part are hung with each other, so that the hanging bridge is fixed to the hanging member.

[0006] In the pipeline bridge structure provided in the present application, the hanging parts are hung and fixed to the two sides of the existing fixed bridge through the connecting structure thereon, so as to realize the rapid installation and fixation of the hanging parts on the fixed bridge, and the first hanging part on the hanging part and the second hanging part on the hanging bridge are hung with each other, so as to realize the rapid installation and fixation of the hanging bridge on the hanging parts, and then the hanging bridge can be quickly and flexibly installed on the basis of the existing fixed bridge, so as to increase the wiring harness capacity and meet the work requirements under the premise of controlling the cost, and the hanging and fixing method does not require specific tools, and will not generate metal particles or dust during the installation process, so as to effectively ensure the safety performance of the cable circuit.

[0007] In an optional manner, when the hanging member is fixed to the fixed bridge, the hanging member protrudes from at least one side of the fixed bridge in the height direction, and the first hanging portion is arranged at a position where the hanging member protrudes from the fixed bridge in the height direction. When the hanging member is fixed to the fixed bridge, by protruding the hanging member from at least one side of the fixed bridge in the height direction and arranging the first hanging portion at a position where the hanging member protrudes from the fixed bridge in the height direction, the hanging bridge can be conveniently installed on either side of the top and bottom of the fixed bridge or can be conveniently installed on both sides of the top and bottom of the fixed bridge at the same time, so that the hanging bridge can be adaptively installed according to the space at the top and bottom of the existing fixed bridge, thereby increasing the capacity of the wiring harness.

[0008] In an optional manner, the connecting structure includes a first screwing mechanism rotatably arranged on the hanging member, and a first flat clamping portion is arranged at one end of the first screwing mechanism; the first flat clamping portion is used to extend into the first sliding grooves on both sides of the fixed bridge frame, and the first screwing mechanism is used to drive the first flat clamping portion to rotate, so that the first flat clamping portion abuts against the first limiting wall at the notch of the first sliding groove to limit the displacement of the hanging member relative to the fixed bridge frame along the width direction. By setting the connecting structure to a first screwing mechanism rotatably connected to the hanging member, and setting a first flat clamping portion at one end of the first screwing mechanism, the first flat clamping portion can be extended into the first slide grooves on both sides of the fixed bridge frame, and the first flat clamping portion is driven to rotate by rotating the first screwing mechanism, so that the first flat clamping portion is clamped with the first limiting wall at the notch of the first slide groove, so that the hanging member is fixed relative to the fixed bridge frame in the width direction, thereby cleverly realizing the convenient installation of the hanging member on both sides of the fixed bridge frame, and the installation process does not require specific tools, and no dust or metal particles will be generated during the construction process, effectively ensuring the stability of the circuit structure.

[0009] In an optional manner, the connection structure includes a first hanging hole, and the first hanging hole is used to engage with the first hanging blocks on both sides of the fixed bridge. By setting the connection structure as the first hanging hole, the hanging member can be quickly installed on the first hanging block of the fixed bridge through the first hanging hole, and can also be easily and quickly removed, saving time and effort.

[0010] In an optional manner, the first hanging part includes a second screwing mechanism rotatably arranged on the hanging member, a second flat clamping part is arranged at one end of the second screwing mechanism, the second hanging part includes a second slide groove arranged on both sides of the hanging bridge, and a second limiting wall is arranged at the notch of the second slide groove; the second flat clamping part extends into the second slide groove, and the second screwing mechanism is used to drive the second flat clamping part to rotate so that the second flat clamping part abuts against the second limiting wall to limit the displacement of the hanging bridge relative to the hanging member along the width direction. After the second flat clamping part extends into the second slide groove, the second screwing mechanism is rotated to make the second flat clamping part abut against the second limiting wall, so as to cleverly realize the convenient installation of the hanging bridge on the hanging member, and then on the basis of the existing fixed bridge, the hanging bridge can be quickly and conveniently installed to increase the cable holding capacity, and after the second flat clamping part abuts against the second limiting wall, the hanging bridge can move relative to the hanging member in the length direction, so as to facilitate the position adjustment of the hanging bridge.

[0011] In an optional manner, the first hanging portion includes a second hanging hole, the second hanging portion includes a second hanging block, and the second hanging block is engaged with the second hanging hole. By engaging the second hanging block with the second hanging hole, it is convenient to quickly connect the hanging bridge and the hanging member, which is convenient to operate and helps to improve the efficiency of assembling the pipeline bridge structure on the fixed bridge.

[0012] In an optional manner, a snap-in structure with radially enlarged dimensions is provided at the end of the second hanging block, the second hanging hole includes a first hole position and a second hole position provided on the side of the first hole position in the height direction, the first hole position is connected to the second hole position, and the cross-sectional area of ​​the first hole position is larger than the cross-sectional area of ​​the second hole position, the first hole position is used for the snap-in structure to pass through, and the second hole position is used for snapping with the snap-in structure. By providing a snap-in structure with radially enlarged dimensions at the end of the second hanging block, the second hanging hole is provided as a first hole position and a second hole position that are connected to each other, and the cross-sectional area of ​​the first hole position is larger than the cross-sectional area of ​​the second hole position, so that the snap-in structure can smoothly pass through the first hole position, and after the second hanging block enters the second hole position, the snap-in structure and the second hole position abut against each other, so as to realize the rapid installation and fixation between the hanging bridge and the hanging member, and ensure the structural stability of the hanging bridge after connection, and provide reliable guarantee for the subsequent cable laying.

[0013] In an optional manner, the end of the second hanging block is provided with a snap-on structure with an increased radial size, the second hanging hole includes a strip hole extending in the height direction, the strip hole is provided with a third hole position with an increased size in the length direction, the side of the strip hole is further provided with a fourth hole position, the fourth hole position is connected with the strip hole, the third hole position is used for the snap-on structure to pass through, the strip hole position is used for the second hanging block to move inside to the fourth hole position, the fourth hole position is used for snap-on with the snap-on structure. The second hanging hole is set as a strip hole, and a third hole position with an increased size in the length direction is set on the strip hole for the snap-on structure to pass through, a fourth hole position is set on the side of the strip hole, and the fourth hole position is snap-on with the snap-on structure to achieve a convenient connection between the hanging bridge and the hanging member.

[0014] In an optional manner, the second hanging block is movably connected to the hanging bridge. By movably connecting the second hanging block to the hanging bridge, when the hanging bridge is fixed to the hanging member, the position of the second hanging block can be adjusted to adapt to the manufacturing error, so that a flexible connection is formed between the hanging bridge and the hanging member, thereby ensuring structural stability.

[0015] In an optional manner, the hanging member is provided with a plurality of the first hanging parts along the height direction. By providing a plurality of the first hanging parts along the height direction on the hanging member, a multi-layer hanging bridge can be installed and fixed on one hanging member, thereby saving costs and increasing the wire harness capacity.

[0016] According to another aspect of the present invention, a bridge device is provided, comprising a fixed bridge and any one of the above-mentioned pipeline bridge structures, wherein a matching structure is provided on both sides of the fixed bridge, and the connecting structure is detachably connected to the matching structure. In the bridge device provided in the present application, by conveniently installing the hanging bridge on the fixed bridge through the hanging member, the wire harness capacity is increased, and the production cost can be saved.

[0017] According to another aspect of the present invention, a bridge device installation method is provided, comprising: connecting a connection structure on a hanging member to two sides of a fixed bridge; connecting a second hanging portion on the hanging bridge to the first hanging portion on the hanging member to form the bridge device. Through the above method, one or more layers of hanging bridges can be quickly and conveniently installed on an existing fixed bridge, thereby increasing the capacity of the wiring harness and meeting work requirements under the premise of controlling costs.

[0018] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:

[0020] Figure 1 A schematic structural diagram of a bridge device with a pipeline bridge structure provided in an embodiment of the present invention;

[0021] Figure 2 A schematic diagram of the structure of a hanging member in a pipeline bridge structure provided by an embodiment of the present invention;

[0022] Figure 3 A schematic structural diagram of a hanging member in a pipeline bridge structure provided by another embodiment of the present invention;

[0023] Figure 4 A schematic structural diagram of a bridge device provided in another embodiment of the present invention;

[0024] Figure 5 A schematic diagram of the structure of the pipeline bridge structure provided by an embodiment of the present invention when the first flat clamping portion extends into the first sliding groove;

[0025] Figure 6 A schematic diagram of the structure of the first flat clamping portion and the first sliding groove being clamped together in the pipeline bridge structure provided by an embodiment of the present invention;

[0026] Figure 7 A schematic diagram of an exploded structure of a first hanging hole in a pipeline bridge structure and a first hanging block on a fixed bridge provided in an embodiment of the present invention;

[0027] Figure 8 A schematic diagram of the structure of the pipeline bridge structure provided by an embodiment of the present invention when the second flat clamping portion extends into the second sliding groove;

[0028] Fig. 9 A schematic diagram of the structure of the second flat clamping portion and the second slide groove being clamped in the pipeline bridge structure provided by an embodiment of the present invention;

[0029] Fig.10 A schematic structural diagram of a bridge device provided in another embodiment of the present invention;

[0030] Fig.11 A schematic structural diagram of a hanging member in a pipeline bridge structure provided by another embodiment of the present invention;

[0031] Fig.12 A schematic diagram of an exploded structure of a first hanging part and a second hanging part in a pipeline bridge structure provided by an embodiment of the present invention;

[0032] Fig.13 A schematic structural diagram of a bridge device provided in another embodiment of the present invention;

[0033] Fig.14 A schematic structural diagram of a bridge device provided in another embodiment of the present invention;

[0034] Fig.15 The present invention provides a flow chart of a bridge device installation method according to an embodiment of the present invention.

[0035] The reference numerals in the specific implementation manner are as follows:

[0036] 10. Bridge device; 100. Pipeline bridge structure; 110. Hanging member; 111. Connection structure; 1111. First screwing mechanism; 1112. First flat clamping portion; 1113. First hanging hole; 112. First hanging portion; 1121. Second screwing mechanism; 1122. Second flat clamping portion; 1123. Second hanging hole; 11231. First hole position; 11232. Second hole position; 11233, strip hole; 11234, third hole position; 11235, fourth hole position; 120, hanging bridge; 121, second hanging part; 1211, second slide groove; 1212, second limiting wall; 1213, second hanging block; 12131, clamping structure; 200, fixed bridge; 210, first slide groove; 211, first limiting wall; 220, first hanging block; 230, matching structure. DETAILED DESCRIPTION

[0037] The following embodiments of the technical solution of the present invention are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention.

[0038] For multi-layer bridges produced by mold opening, since the brackets or hangers are integrated or welded, it is impossible to adjust the distance between the bridges and the position of the hangers. For the method of fixing each layer of the bridge with the brackets or hangers in the multi-layer bridge, the installation process is time-consuming and requires a lot of manpower and material resources.

[0039] In addition, for the existing multi-layer bridge, each layer of the bridge is fixedly connected to the bracket or hanger. Since specific tools are required to adjust the height and spacing of the bridge, and dust or metal particles are generated during the construction process, it is easy to cause a short circuit threat to the electrical facilities in the equipment room. This is a huge loss for application scenarios such as data centers that require highly reliable environmental conditions.

[0040] Based on this, the present application provides a pipeline bridge structure, in which the hanging parts are hung and fixed to the two sides of the existing fixed bridge through the connecting structure thereon, so as to realize the rapid installation and fixation of the hanging parts on the fixed bridge, and the first hanging part on the hanging part and the second hanging part on the hanging bridge are hung with each other, so as to realize the rapid installation and fixation of the hanging bridge on the hanging parts, and then the hanging bridge can be quickly and flexibly installed on the basis of the existing fixed bridge, so as to increase the wiring harness capacity and meet the work requirements under the premise of controlling costs, and the hanging and fixing method does not require specific tools, and no metal particles or dust will be generated during the installation process, which effectively reduces the safety threat of the construction environment to the surrounding equipment.

[0041] Please refer to Figure 1 , the figure shows a bridge device with a pipeline bridge structure provided by an embodiment of the present invention. As shown in the figure, the pipeline bridge structure 100 includes a hanging member 110 and a hanging bridge 120. The hanging member 110 is provided with a connecting structure 111, and the connecting structure 111 is used to be detachably connected to both sides of the fixed bridge 200 to fix the hanging member 110 to the fixed bridge 200. The hanging member 110 is also provided with a first hanging portion 112, and the hanging bridge 120 is provided with a second hanging portion 121, and the first hanging portion 112 is detachably connected to the second hanging portion 121, so that the hanging bridge 120 is fixed to the hanging member 110.

[0042] It should be noted that for the sake of convenience, Figure 1 Only the hanging member 110 connected to one side of the fixed bridge 200 is shown. In a specific implementation process, the hanging members 110 need to be connected to both sides of the fixed bridge 200 to achieve reliable fixing of the hanging bridge 120 on the hanging members 110.

[0043] Among them, the fixed bridge frame 200 can be an existing installed bridge frame, and the two sides of the fixed bridge frame 200 generally have hanging holes or slide rails. The connecting structure 111 can be a fastening structure fixedly connected to the hanging hole (for example, it can be riveted, clamped or threaded) or a slider clamped with the slide rail. By detachably connecting the connecting structure 111 to the fixed bridge frame 200, the fixing of the hanging component 110 on the existing fixed bridge frame 200 is achieved.

[0044] The detachable connection between the first hanging part 112 and the second hanging part 121 can be specifically a hook hanging and fitting with each other on the hanging hole, a card slot and a card block are clamped and fitted after being squeezed against each other, or a rivet and a hole are riveted together, etc. Through the detachable connection between the first hanging part 112 and the second hanging part 121, the hanging bridge frame 120 is fixed on the hanging member 110, thereby realizing the convenient installation of the hanging bridge frame 120 on the existing fixed bridge frame 200.

[0045] It is understandable that, generally, only one hanging component 110 needs to be provided on each side of the fixed bridge 200 to achieve the fixation of the hanging bridge 120 on the fixed bridge 200. However, considering the supporting stability of the hanging bridge 120 after the cables are subsequently placed, it is preferred to provide at least two hanging components 110 on each side of the fixed bridge 200, and one side of a hanging bridge 120 is detachably connected to at least two hanging components 110, thereby fully ensuring the structural stability of the hanging bridge 120 after the cables are placed.

[0046] In the pipeline bridge structure 100 provided in the present application, the hanging member 110 is hung and fixed to the two sides of the existing fixed bridge 200 through the connecting structure 111 thereon, so as to realize the quick installation and fixation of the hanging member 110 on the fixed bridge 200, and the first hanging part 112 on the hanging member 110 and the second hanging part 121 on the hanging bridge 120 are hung with each other, so as to realize the quick installation and fixation of the hanging bridge 120 on the hanging member, and then the hanging bridge can be quickly and flexibly installed on the basis of the existing fixed bridge, so as to increase the wiring harness capacity and meet the work requirements under the premise of controlling the cost, and the hanging and fixing method does not require specific tools, and no metal particles or dust will be generated during the installation process, which effectively reduces the safety threat of the construction environment to the surrounding equipment.

[0047] Please continue reading Figure 1 , and further combined with Figure 2 and Figure 3 , Figure 2 and Figure 3 The structures of two kinds of hanging parts in the pipeline bridge structure provided by the embodiment of the present invention are respectively shown. As shown in the figure, in some embodiments, when the hanging part 110 is fixed to the fixed bridge 200, the hanging part 110 is connected along the height direction ( Figure 1 and 2 The first hanging portion 112 is disposed at a position where the hanging member 110 protrudes from the fixed bridge frame 200 (in the z-axis direction).

[0048] The hanging bridge 120 can be a trapezoidal bridge, with two sides used to connect with the hanging parts 110, and the middle trapezoidal structure is used to receive cables to realize the routing and arrangement of cables.

[0049] Specifically, Figure 1 As shown in the figure, the connecting structure 111 can be arranged on the top of the hanging member 110. After the hanging member 110 is connected to the fixed bridge frame 200 through the connecting structure 111, the hanging member 110 protrudes from one side of the bottom of the fixed bridge frame 200, and the first hanging portion 112 is arranged at the position where the hanging member 110 protrudes from one side of the bottom of the fixed bridge frame 200. The hanging bridge frame 120 is connected to the first hanging portion 112 through the second hanging portion 121 to realize the convenient installation of the hanging bridge frame 120 at the bottom of the fixed bridge frame 200.

[0050] like Figure 2 As shown in the figure, the connecting structure 111 can also be arranged at the bottom of the hanging member 110. After the hanging member 110 is connected to the fixed bridge frame 200 through the connecting structure 111, the hanging member 110 protrudes from one side of the top of the fixed bridge frame 200, and the first hanging portion 112 is arranged at the position where the hanging member 110 protrudes from one side of the top of the fixed bridge frame 200. The hanging bridge frame 120 is connected to the first hanging portion 112 through the second hanging portion 121 to realize the convenient installation of the hanging bridge frame 120 on the top of the fixed bridge frame 200.

[0051] Please combine Figure 1 and Figure 2 It is also possible to simultaneously provide a hanging member 110 protruding from the top side and a hanging member 110 protruding from the bottom side on both sides of the fixed bridge 200, so as to realize the installation of the hanging bridge 120 above and below the existing fixed bridge 200 at the same time.

[0052] like Figure 3 As shown in the figure, the connecting structure 111 can also be arranged in the middle position of the hanging member 110. After the hanging member 110 is connected to the fixed bridge frame 200 through the connecting structure 111, the hanging member 110 protrudes from both the top and bottom sides of the fixed bridge frame 200 at the same time, and the first hanging part 112 is provided at the position where the hanging member 110 protrudes from both sides of the fixed bridge frame 200. The hanging bridge frame 120 is connected to the first hanging part 112 through the second hanging part 121 to realize the convenient installation of the hanging bridge frame 120 on both the top and bottom sides of the fixed bridge frame 200 at the same time.

[0053] When the hanging member 110 is fixed to the fixed bridge 200, by protruding the hanging member 110 from at least one side of the fixed bridge 200 in the height direction and arranging the first hanging portion 112 at a position where the hanging member 110 protrudes from the fixed bridge 200 in the height direction, the hanging bridge 120 can be conveniently installed on any side of the top and bottom of the fixed bridge 200 or can be conveniently installed on both sides of the top and bottom of the fixed bridge 200 at the same time, so that the hanging bridge 120 can be adaptively installed according to the space at the top and bottom of the existing fixed bridge 200, thereby realizing an increase in the wiring harness capacity.

[0054] Regarding the connection between the hanging member 110 and the fixed bridge 200, the present application further proposes an implementation method. Figures 4 to 6 , Figure 4 FIG. 2 shows a bridge device with a pipeline bridge structure provided by another embodiment of the present invention. Figure 5 The figure shows a structure in which the connecting structure provided by an embodiment of the present invention extends into the first slide groove of the fixed bridge frame. Figure 6The figure shows the structure of the connection structure and the first slide slot clamping provided by the embodiment of the present invention. As shown in the figure, the connection structure 111 includes a first screwing mechanism 1111 rotatably arranged on the hanging member 110, and a first flat clamping portion 1112 is arranged at one end of the first screwing mechanism 1111. The first flat clamping portion 1112 is used to extend into the first slide slot 210 on both sides of the fixed bridge 200. The first screwing mechanism 1111 is used to drive the first flat clamping portion 1112 to rotate, so that the first flat clamping portion 1112 abuts against the first limiting wall 211 at the notch of the first slide slot 210, so as to limit the hanging member 110 from being connected along the width direction ( Figure 1 and Figure 5 The displacement of the bridge 200 (in the y-axis direction) relative to the fixed bridge 200.

[0055] Specifically, both sides of the conventional fixed bridge 200 have T-slot structures ( Figure 5 The first slide groove 210 with the first limiting wall 211 shown in the figure is, for example, an aluminum profile structure, so based on the T-slot structure on both sides of the fixed bridge 200, a first screwing mechanism 1111 can be correspondingly provided on the hanging member 110, and a first flat clamping portion 1112 can be provided at one end of the first screwing mechanism 1111. If there is no T-slot structure on both sides of the existing fixed bridge 200, the T-slot structure can also be installed on both sides of the fixed bridge 200 before installing the pipeline bridge structure 100. Figure 5 As shown in FIG. 1 , when the hanging member 110 is installed on the fixed bridge 200, the first flat clamping portion 1112 is first rotated to be parallel to the first slide slot 210, and then the first flat clamping portion 1112 is extended into the first slide slot 210, and then the first flat clamping portion 1112 is driven to rotate by rotating the first screwing mechanism 1111, preferably rotating 90°, so that the first flat clamping portion 1112 is in a Figure 6 In the state shown in FIG. 1 , the first flat clamping portion 1112 is clamped with the first limiting wall 211 at the notch of the first slide slot 210, so that the hanging member 110 is fixed relative to the fixed bridge 200 in the width direction, and the hanging member 110 is fixed relative to the fixed bridge 200 in the length direction ( Figure 1 and Figure 5 The connecting member 110 can move along the first slide slot 210 relative to the fixed bridge 200 in the x-axis direction, thereby facilitating the position adjustment of the connecting member 110 in the length direction.

[0056] By setting the connecting structure 111 as a first screwing mechanism 1111 rotatably connected to the hanging member 110, and setting a first flat clamping portion 1112 at one end of the first screwing mechanism 1111, the first flat clamping portion 1112 can extend into the first slide grooves 210 on both sides of the fixed bridge frame 200, and the first flat clamping portion 1112 is driven to rotate by rotating the first screwing mechanism 1111, so that the first flat clamping portion 1112 is clamped with the first limiting wall 211 at the notch of the first slide groove 210, so that the hanging member 110 is fixed relative to the fixed bridge frame 200 in the width direction, thereby cleverly realizing the convenient installation of the hanging member 110 on both sides of the fixed bridge frame 200, and the installation process does not require specific tools, and no dust or metal particles will be generated during the construction process, effectively ensuring the stability of the circuit structure.

[0057] Regarding the installation method of the hanging member 110 on the fixed bridge 200, this application also proposes an implementation method. Figure 7 , the figure shows a connection structure 111 in a pipeline bridge structure 100 provided by another embodiment of the present invention. As shown in the figure, the connection structure 111 includes a first hanging hole 1113, and the first hanging hole 1113 is used to be clamped with the first hanging blocks 220 on both sides of the fixed bridge 200.

[0058] like Figure 7 As shown in the figure, the first hanging hole 1113 has an insertion hole position with a larger cross-sectional area and a clamping hole position with a smaller cross-sectional area. The first hanging block 220 has an end portion with a larger cross-sectional area. The end portion of the first hanging block 220 passes through the insertion hole position of the first hanging hole 1113 so that the first hanging block 220 is clamped with the clamping hole position of the first hanging hole 1113, thereby fixing the hanging component 110 on the fixed bridge frame 200.

[0059] Specifically, before installing the hanging member 110 on the existing fixed bridge 200 , the first hanging block 220 can be fixed to the fixed bridge 200 by welding, clamping or threading, and then the first hanging hole 1113 on the hanging member 110 is connected to the first hanging block 220 .

[0060] By setting the connection structure 111 as the first hanging hole 1113, the hanging member 110 can be quickly installed on the first hanging block 220 of the fixed bridge frame 200 through the first hanging hole 1113, and can also be easily and quickly disassembled, saving time and effort.

[0061] It should be noted that, in some other embodiments, the first hanging block 220 and the first hanging hole 1113 can also be interchanged. Specifically, the first hanging hole 1113 is set on the fixed bridge frame 200, and the first hanging block 220 is set on the hanging component 110. Similarly, the first hanging block 220 is snap-fitted with the first hanging hole 1113 to achieve quick installation and fixation of the hanging component 110 on the fixed bridge frame 200.

[0062] Regarding the connection relationship between the first hanging portion 112 and the second hanging portion 121, the present application further proposes an implementation method. Figure 1 , and further combined with Figure 8 and Fig. 9 , Figure 8 FIG. 2 shows a structure in which the second flat clamping portion of the hanging bridge structure provided by an embodiment of the present invention extends into the second sliding groove. Fig. 9 The structure of the second flat clamping portion and the second slide groove being clamped together is shown in the figure. As shown in the figure, the first hanging portion 112 includes a second screwing mechanism 1121 rotatably arranged on the hanging member 110, and a second flat clamping portion 1122 is arranged at one end of the second screwing mechanism 1121. The second hanging portion 121 includes a second slide groove 1211 arranged on both sides of the hanging bridge 120, and a second limiting wall 1212 is arranged at the notch of the second slide groove 1211. The second flat clamping portion 1122 extends into the second slide groove 1211, and the second screwing mechanism 1121 is used to drive the second flat clamping portion 1122 to rotate, so that the second flat clamping portion 1122 abuts against the second limiting wall 1212 to limit the hanging bridge 120 along the width direction ( Figure 1 and Figure 8 The displacement of the mounting member 110 (in the y-axis direction shown in FIG. 1 ) relative to the mounting member 110.

[0063] The connection method between the second flat clamping portion 1122 and the second slide groove 1211 is the same as the connection method between the first flat clamping portion 1112 and the first slide groove 210. Figure 8 As shown in FIG. 1 , the second flat clamping portion 1122 is first rotated to a position parallel to the second slide slot 1211 by the second screwing mechanism 1121, and then the second flat clamping portion 1122 is extended into the second slide slot 1211, as shown in FIG. Fig. 9 As shown in , the second flat clamping portion 1122 is then rotated by rotating the second screwing mechanism 1121, preferably by 90°, so that the second flat clamping portion 1122 abuts against the second limiting wall 1212, thereby realizing convenient installation of the hanging bridge 120 on the hanging member 110.

[0064] After the second flat clamping portion 1122 is extended into the second sliding groove 1211, the second screwing mechanism 1121 is rotated to make the second flat clamping portion 1122 abut against the second limiting wall 1212, so that the hanging bridge 120 can be conveniently installed on the hanging member 110, and then on the basis of the existing fixed bridge 200, the hanging bridge 120 can be quickly and conveniently installed to increase the cable accommodating capacity, and after the second flat clamping portion 1122 abuts against the second limiting wall 1212, the hanging bridge 120 can be relative to the hanging member 110 in the length direction ( Figure 1 The bridge 120 can be moved in the x-axis direction (as shown in FIG. 1 ) to facilitate the position adjustment of the bridge 120 .

[0065] When the connection structure 111 adopts the first screwing mechanism 1111 and the first flat clamping portion 1112, and the first hanging structure adopts the second screwing mechanism 1121 and the second flat clamping portion 1122, the hanging member 110 can be respectively relative to the fixed bridge 200 and the hanging bridge 120 along the length direction ( Figure 1 By moving the hanging member 110 in the x-axis direction, not only can the position of the hanging member 110 be adjusted, but the flexible connection method that can be moved along the length direction can also avoid stress at the connection between the hanging member 110 and the fixed bridge 200 and the hanging bridge 120. When the hanging bridge 120 is moved alone, the position of the hanging bridge 120 can also be adjusted, making the bridge device more flexible as a whole, convenient for disassembly and assembly, and adaptive adjustment of the position, thereby improving the compatibility of the pipeline bridge structure 100.

[0066] Regarding the connection relationship between the hanging bridge 120 and the hanging member 110, the present application further proposes an implementation method. Figure 4 , and further combined with Fig.10 , Fig.10 The structure of the second hanging hole and the second hanging block is shown in FIG. As shown in the figure, the first hanging part 112 includes a second hanging hole 1123 , and the second hanging part 121 includes a second hanging block 1213 , and the second hanging block 1213 is engaged with the second hanging hole 1123 .

[0067] Specifically, Fig.10 As shown in , the second hanging block 1213 on the hanging bridge 120 extends into the second hanging hole 1123 on the hanging member 110 , so that the hanging bridge 120 can be conveniently and quickly installed and fixed on the second hanging block 1213 .

[0068] It should be noted that in order to facilitate the display of the structure, Fig.10 Only the structure of setting the hanging member 110 on one side of the fixed bridge frame 200 and the hanging bridge frame 120 is shown. In the actual implementation process, the hanging member 110 needs to be set on both sides to ensure the structural stability of the hanging bridge frame 120 after being installed and fixed on the fixed bridge frame 200.

[0069] By engaging the second hanging block 1213 with the second hanging hole 1123 , the hanging bridge 120 and the hanging member 110 can be quickly connected, which is convenient to operate and helps to improve the efficiency of assembling the pipeline bridge structure 100 on the fixed bridge 200 .

[0070] In order to improve the structural stability after the second hanging block 1213 is connected to the second hanging hole 1123, the present application further proposes an implementation method. Fig.10 As shown in the figure, a snap-on structure 12131 with an enlarged radial dimension is provided at the end of the second hanging block 1213, and the second hanging hole 1123 includes a first hole position 11231 and a second hole position 11232 arranged on the side of the first hole position 11231 along the height direction, the first hole position 11231 is connected to the second hole position 11232, and the cross-sectional area of ​​the first hole position 11231 is larger than the cross-sectional area of ​​the second hole position 11232, the first hole position 11231 is used for the snap-on structure 12131 to pass through, and the second hole position 11232 is used for snapping with the snap-on structure 12131.

[0071] The end of the second hanging block 1213 is provided with a clamping structure 12131 with an increased radial dimension, which means that the clamping structure 12131 is located in the plane in the length direction and the height direction ( Figure 1 The radial dimension of the plane where the x-axis and z-axis are shown in the figure is larger than the radial dimension of the second hanging block 1213 in the plane, that is, the cross-sectional area of ​​the plane where the clamping structure 12131 is located in the length direction and the height direction is larger than the cross-sectional area of ​​the plane where the second hanging block 1213 is located. The cross-sectional area of ​​the first hole 11231 and the second hole 11232 is similar, which is also the cross-sectional area on the plane where the length direction and the height direction are located.

[0072] Specifically, when connecting the hanging bridge 120 to the hanging member 110, first align the snap-on structure 12131 and pass it through the first hole 11231, then slide the second hanging block 1213 downward along the second hole 11232 and abut against the bottom of the second hole 11232, so that the hanging bridge 120 can be fixed on the hanging member 110. The installation process is quick and convenient, saving time and effort.

[0073] By setting a snap-fit ​​structure 12131 with an enlarged radial dimension at the end of the second hanging block 1213, the second hanging hole 1123 is set to be a first hole position 11231 and a second hole position 11232 which are interconnected, and the cross-sectional area of ​​the first hole position 11231 is larger than the cross-sectional area of ​​the second hole position 11232, so that the snap-fit ​​structure 12131 can smoothly pass through the first hole position 11231, and after the second hanging block 1213 enters the second hole position 11232, the snap-fit ​​structure 12131 and the second hole position 11232 abut against each other, thereby realizing rapid installation and fixation between the hanging bridge 120 and the hanging component 110, and ensuring the structural stability of the hanging bridge 120 after connection, thereby providing reliable guarantee for subsequent cable laying.

[0074] For the structure of the second hanging hole 1123, the present application further proposes an implementation method. Fig.11 , the figure shows the structure of the hanging member provided by another embodiment of the present invention. As shown in the figure, the second hanging hole 1123 includes a Figure 1 The strip hole 11233 extends in the z-axis direction shown in FIG. 1 , and the strip hole 11233 is provided with a plurality of holes along the length direction ( Figure 1 The third hole position 11234 with an increased size (in the x-axis direction as shown in FIG. 1 ), the side of the strip hole 11233 is further provided with a fourth hole position 11235, the fourth hole position 11235 is connected to the strip hole 11233, and the end of the second hanging block 1213 is also provided with a Fig.10 In the clamping structure 12131 shown in the figure, the third hole 11234 is used for the clamping structure 12131 to pass through, the strip hole 11233 is used for the second hanging block 1213 to move to the fourth hole 11235, and the fourth hole 11235 is used to clamp with the clamping structure 12131.

[0075] like Fig.11As shown, the arrow direction in the figure indicates the moving path and direction of the second hanging block 1213 in the second hanging hole 1123. Specifically, the number of the third hole position 11234 and the fourth hole position 11235 can be multiple, so that the clamping structure 12131 can pass through the hanging member 110 from the nearest third hole position 11234 according to the position of the fourth hole position 11235 to be clamped therewith, thereby reducing the distance that the second hanging block 1213 needs to move in the second hanging hole 1123, thereby improving the assembly efficiency. In addition, by setting multiple fourth holes 11235, the hanging bridge 120 can be installed and fixed at different heights on the hanging member 110, and when adjusting the height, it is not necessary to separate the hanging bridge 120 from the hanging member 110. It is only necessary to move the second hanging block 1213 on the hanging bridge 120 along the strip hole 11233 to the corresponding fourth hole position 11235 to achieve height adjustment, which is convenient and quick to operate. Furthermore, after a plurality of fourth hole positions 11235 are provided, it is also possible to simultaneously install and fix multiple layers of hanging bridges 120 on one hanging component 110, thereby saving costs and further increasing the wiring harness capacity.

[0076] The second hanging hole 1123 is set as a strip hole 11233, and a third hole position 11234 with an increased size along the length direction is set on the strip hole 11233 for the clamping structure 12131 to pass through, and a fourth hole position 11235 is set on the side of the strip hole 11233. The fourth hole position 11235 is clamped with the clamping structure 12131 to achieve a convenient connection between the hanging bridge 120 and the hanging component 110.

[0077] In order to improve the compatibility of the connection between the hanging bridge 120 and the hanging member 110, and avoid the stress caused by the connection between the hanging bridge 120 and the hanging member 110 due to manufacturing errors, which affects the stability of the structure, the present application further proposes an implementation method. Fig.12 , the figure shows the structure of the second hanging block and the second hanging hole provided by the embodiment of the present invention. As shown in the figure, the second hanging block 1213 is movably connected to the hanging bridge 120.

[0078] Specifically, Fig.12 As shown in FIG. 1 , a slide rail or a slide groove is provided on the hanging bridge 120, and the end of the second hanging block 1213 away from the hanging member 110 is slidably connected to the slide rail or the slide groove. It can be understood that the second hanging block 1213 can be as follows Fig.12 As shown in the length direction ( Figure 1 The x-axis direction shown in FIG. 1 is slidably connected to the hanging bridge 120, and the plane in the length direction and the height direction ( Figure 1The second hanging block 1213 can be slidably connected to the hanging bridge 120 in any one or more directions within the plane where the x-axis and the z-axis are located, so that the position of the second hanging block 1213 can be adjusted. The specific sliding direction is not limited here.

[0079] When assembling the hanging component 110 and the hanging bridge 120, it is necessary to set the second hanging blocks 1213 on both sides or at the four end points of the hanging bridge 120, and connect them with the second hanging holes 1123 on the hanging component 110 through the second hanging blocks 1213. Considering that when the hanging bridge 120 or the hanging component 110 is manufactured with poor straightness and there is a position deviation in the second hanging block 1213 or the second hanging hole 1123 during manufacturing, if the two sides or four end points of the hanging bridge 120 are rigidly connected to the hanging component 110, there may be stress between the hanging bridge 120 and the hanging component 110 themselves or between them, thereby affecting the stability of the overall structure.

[0080] Based on this, by movably connecting the second hanging block 1213 to the hanging bridge 120, when the hanging bridge 120 is fixed to the hanging member 110, the position of the second hanging block 1213 can be adjusted to adapt to the manufacturing error, so that a flexible connection is formed between the hanging bridge 120 and the hanging member 110 to ensure structural stability.

[0081] In order to fully increase the capacity of the wiring harness, this application further proposes an implementation method. Please refer to Figures 2 to 4 As shown in the figure, the hanging member 110 is along the height direction ( Figure 2 A plurality of first hanging portions 112 are provided (in the z-axis direction shown in FIG).

[0082] By arranging a plurality of first hanging portions 112 along the height direction on the hanging member 110 , a plurality of hanging bridges 120 can be installed and fixed on one hanging member 110 , thereby saving costs and increasing the wire harness accommodation capacity.

[0083] See also Fig.13 , the figure shows the structure of a bridge device with a pipeline bridge structure provided by another embodiment of the present invention. As shown in the figure, in a preferred embodiment, if the space at the top and bottom of the existing fixed bridge 200 allows, the hanging bridge 120 can be installed at the top and bottom of the fixed bridge 200 through the hanging parts 110 at the same time, so as to fully increase the wire harness capacity and improve the space utilization.

[0084] For further information, see Fig.14The figure shows the structure of a bridge device with a bridge hanging frame provided by another embodiment of the present invention. As shown in the figure, in a preferred embodiment, a plurality of first hanging portions 112 can be provided on the hanging member 110, or first hanging portions 112 of different heights can be provided between two hanging members 110, so as to achieve the purpose of obliquely installing the hanging bridge 120.

[0085] According to another aspect of the embodiment of the present invention, a structure of a bridge device 10 is provided. Fig.13 As shown in the figure, the bridge device 10 includes a fixed bridge 200 and a pipeline bridge structure 100 in any of the above embodiments, and matching structures 230 are provided on both sides of the fixed bridge 200, and the connecting structure 111 is detachably connected to the matching structure 230.

[0086] Specifically, the matching structure 230 can be Fig.13 In other embodiments, the matching structure 230 may also be Fig.10 The first hanging block shown in FIG. 1 , correspondingly, the connecting structure 111 is a first hanging hole.

[0087] In the bridge device 10 provided in the present application, the hanging bridge 120 is conveniently installed on the fixed bridge 200 through the hanging member 110, so that the wire harness accommodation capacity is improved and the production cost can be saved.

[0088] According to another aspect of the embodiment of the present invention, a bridge device installation method is also provided. Fig.15 , the figure shows the process of the method. As shown in the figure, the bridge device installation method includes the following steps:

[0089] Step 310: Connect the connection structure on the hanging member to both sides of the fixed bridge.

[0090] In this step, the first flat clamping portion on the hanging member can be extended into the first slide grooves on both sides of the fixed bridge frame, and the first flat clamping portion can be clamped and fixed with the first limiting wall at the notch of the first slide groove by rotating the first screwing mechanism. Alternatively, the first hanging hole on the hanging member can be passed through the first hanging blocks on both sides of the fixed bridge frame to hang the hanging member on the fixed bridge frame and fix it.

[0091] Step 320: Connect the second hanging part on the hanging bridge with the first hanging part on the hanging member to form a bridge device.

[0092] In this step, similarly, the second slide groove on the hanging bridge can be inserted into the second flat clamping part on the hanging member, and the second flat clamping part can be clamped and fixed with the second limiting wall at the groove of the second slide groove by rotating the second screwing mechanism. Alternatively, the second hanging block on the hanging bridge can be inserted into the second hanging hole on the hanging member to hang and fix the hanging bridge on the hanging member.

[0093] Through the above method, one or more layers of hanging bridges can be quickly and conveniently installed on the existing fixed bridge, thereby increasing the wiring harness capacity and meeting work needs while controlling costs.

[0094] It should be noted that, unless otherwise specified, the technical terms or scientific terms used in the embodiments of the present invention should have the common meanings understood by technicians in the field to which the embodiments of the present invention belong.

[0095] In the description of the embodiments of the present invention, the technical terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the embodiments of the present invention.

[0096] In addition, the technical terms "first", "second", etc. are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. In the description of the embodiments of the present invention, the meaning of "multiple" is more than two, unless otherwise clearly and specifically defined.

[0097] In the description of the embodiments of the present invention, unless otherwise clearly specified and limited, technical terms such as "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present invention can be understood according to specific circumstances.

[0098] In the description of the embodiments of the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0099] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in each embodiment can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.

Claims

1. A pipeline bridge structure (100), characterized in that: include: A hanging member (110) and a hanging bridge (120); The hanging member (110) is provided with a connection structure (111), and the connection structure (111) is used to hang with two sides of the fixed bridge (200) to fix the hanging member (110) to the fixed bridge (200); The hanging member (110) is also provided with a first hanging portion (112), and the hanging bridge (120) is provided with a second hanging portion (121), and the first hanging portion (112) and the second hanging portion (121) are hung on each other, so that the hanging bridge (120) is fixed to the hanging member (110); The first hanging portion (112) comprises a second hanging hole (1123), the second hanging portion (121) comprises a second hanging block (1213), and the second hanging block (1213) is clamped with the second hanging hole (1123); The end of the second hanging block (1213) is provided with a clamping structure (12131) with an increased radial size, the second hanging hole (1123) comprises a strip hole (11233) extending along the height direction of the hanging bridge (120), the strip hole (11233) is provided with a third hole position (11234) with an increased size along the length direction of the hanging bridge (120), and the side of the strip hole (11233) is also provided with There is a fourth hole position (11235), the fourth hole position (11235) is connected to the strip hole (11233), the third hole position (11234) is used for the clamping structure (12131) to pass through, the strip hole (11233) is used for the second hanging block (1213) to move inside to the fourth hole position (11235), and the fourth hole position (11235) is used to clamp with the clamping structure (12131).

2. The pipeline bridge structure (100) according to claim 1, characterized in that: When the hanging member (110) is fixed to the fixed bridge frame (200), the hanging member (110) protrudes from at least one side surface of the fixed bridge frame (200) along the height direction, and the first hanging portion (112) is arranged at a position where the hanging member (110) protrudes from the fixed bridge frame (200) along the height direction.

3. The pipeline bridge structure (100) according to claim 1, characterized in that: The connection structure (111) comprises a first screwing mechanism (1111) rotatably arranged on the hanging member (110), and a first flat clamping portion (1112) is arranged at one end of the first screwing mechanism (1111); The first flat clamping portion (1112) is used to extend into the first sliding grooves (210) on both sides of the fixed bridge frame (200), and the first screwing mechanism (1111) is used to drive the first flat clamping portion (1112) to rotate, so that the first flat clamping portion (1112) abuts against the first limiting wall (211) at the notch of the first sliding groove (210), so as to limit the displacement of the hanging member (110) relative to the fixed bridge frame (200) along the width direction of the hanging bridge frame (120).

4. The pipeline bridge structure (100) according to claim 1, characterized in that: The connection structure (111) comprises a first hanging hole (1113), and the first hanging hole (1113) is used for clamping with the first hanging blocks (220) on both sides of the fixed bridge (200).

5. The pipeline bridge structure (100) according to claim 1, characterized in that: The second hanging block (1213) is movably connected to the hanging bridge (120).

6. The pipeline bridge structure (100) according to any one of claims 1 to 5, characterized in that: A plurality of first hanging portions (112) are arranged on the hanging member (110) along the height direction.

7. A bridge device (10), characterized in that: It comprises a fixed bridge (200) and the pipeline bridge structure (100) according to any one of claims 1 to 6, wherein matching structures (230) are provided on both sides of the fixed bridge (200), and the connecting structure (111) is detachably connected to the matching structure (230).

8. A method for installing a bridge device, characterized in that: Applicable to the pipeline bridge structure according to any one of claims 1 to 6, the bridge device installation method comprises: Connect the connection structure on the hanging piece to both sides of the fixed bridge; Pass the clamping structure on the second hanging block through the third hole; The second hanging block is moved in the strip hole to the fourth hole position and is engaged with the fourth hole position, so as to hang the hanging bridge frame and the hanging member to form a bridge frame device.

Citation Information

Patent Citations

  • Board dry-hanging system and construction method thereof

    CN105863132A

  • Wiring frame

    CN209562050U

  • Machine room cabling rack with shockproof function

    CN210669359U