Test control methods, systems, apparatus, computer devices, and storage media

By properly scheduling the shutdown and power-off times during the testing of servers and smart network cards, the stability issues caused by inconsistent timing during server and smart network card testing were resolved, ensuring the normal operation of the test program.

CN115454744BActive Publication Date: 2026-06-09INSPUR SUZHOU INTELLIGENT TECH CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
INSPUR SUZHOU INTELLIGENT TECH CO LTD
Filing Date
2022-08-29
Publication Date
2026-06-09

AI Technical Summary

Technical Problem

In existing testing technologies for servers and smart network interface cards (NICs), the power-on and power-off timings of the server and the NIC are determined by their respective independently running test programs. This raises the issue that a power outage on one NIC may affect the normal operation of the test program on the other NIC.

Method used

When both the first and second test procedures are completed, the control server host performs a shutdown operation, then sends a shutdown signal to the smart network card, and finally instructs the control device to power down the server host and the smart network card. The timing of the shutdown of the server host, the shutdown of the smart network card, and the power-down of the server host are arranged reasonably to ensure the stability of the test process.

Benefits of technology

By arranging the timing of the testing procedures appropriately, the impact of premature shutdown or power failure of the server host or smart network card on the other party's testing procedures was avoided, thus ensuring the stability and reliability of the testing process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115454744B_ABST
    Figure CN115454744B_ABST
Patent Text Reader

Abstract

Embodiments of the present disclosure relate to a test control method, system, device, computer device and storage medium. When the test control method is implemented, when the first test program and the second test program are both executed and completed, the server host is controlled to perform a shutdown operation, then the intelligent network card is instructed to perform a shutdown, and then the control device is instructed to perform a power-off operation on the server host. By reasonably arranging the shutdown time of the server host, the shutdown time of the intelligent network card and the power-off time of the server host, the stability of the test process of the test program of the server host and the test program of the intelligent network card is ensured.