Construction method of a non-particle artificial turf

By employing a granule-free construction method, which involves compacting the ground, laying layers of gravel and medium-fine sand, and combining this with permeable pipes and sprinkler systems, the problems of granule pollution and high costs are solved. This achieves environmentally friendly and low-cost lawn construction, while improving the flatness and comfort of the site.

CN115573220BActive Publication Date: 2025-12-12GUANGZHOU XINGWEI GRASS IND CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202211203786.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-29
Publication Date
2025-12-12
Estimated Expiration
2042-09-29

AI Technical Summary

Technical Problem

The granules used to fill existing artificial turf pollute the environment, are costly, and are easily lost, resulting in uneven surfaces and affecting safety.

Method used

The design adopts a granule-free approach. By compacting the site, laying layers of gravel and medium-fine sand, and combining permeable pipes and sprinkler systems, a sand granule barrier filter layer that is permeable to water but not to sand and a medium-fine sand buffer layer are formed. The surface layer of medium-fine sand is filled, eliminating the need for granules.

Benefits of technology

It achieves environmentally friendly and low-cost lawn construction, improves the flatness and comfort of the site, and avoids problems such as granule pollution and loss.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115573220B_ABST
    Figure CN115573220B_ABST
Patent Text Reader

Abstract

The application discloses a construction method of glue-particle-free artificial turf, which comprises the following steps: tamping and leveling a site to form a soil tamping layer; spreading gravel with a particle size of 10-30 mm on the surface of the soil tamping layer to form a gravel layer; laying a sand particle blocking filter layer; laying a medium-fine sand buffer layer; laying medium-fine sand with a particle size of 0.1-1 mm on the surface of the sand particle blocking filter layer; laying a turf layer; and filling the medium-fine sand to form a medium-fine sand surface layer. The construction method of the patent saves glue particles, increases the amount of sand, and uses medium-fine sand, so that the turf has the same buffering effect, solves the problem of glue particle pollution of the environment, saves the construction cost, solves the problem of high cost of the artificial turf, and additionally arranges a spraying device to adjust the temperature of the artificial turf on the site, so as to improve the comfort of people in the environment.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of artificial turf, in particular to a construction method of artificial turf. BACKGROUND

[0002] Football has been more and more popular among Chinese people, and the number of people engaged in football has doubled every year. Football field is indispensable to football, and football field is mainly divided into natural grass football field and artificial turf football field. Natural grass football field cannot meet the high frequency of use due to high maintenance cost, so people focus on the construction of artificial turf football field. In order to improve the resilience of the lawn, the existing artificial turf football field directly fills the particles into the artificial turf. This structure has the following defects: first, the filled particles pollute the surrounding environment; second, the cost of artificial turf is high; third, when it rains, rainwater can only be discharged on the surface of the lawn, and the filled particles are easy to be washed away by water, resulting in particle loss and uneven ground, which is easy to cause injury to players.

[0003] For example, the patent document with publication number CN108914746A discloses a construction method of a new artificial turf playground, which is characterized in that the construction method comprises the following steps: (1) leveling the site, removing plants and sundries on the original land; (2) taking the midpoint of the site centerline as a reference point, setting a slope towards all directions based on the reference point, forming a tortoise-back type drainage structure with high middle and low periphery; (3) compacting the soil layer, repeatedly compacting and densifying the soil layer with a 10-15 ton vibrating roller to prevent uneven settlement of the soil layer; (4) laying waterproof coiled material, laying a layer of waterproof coiled material on the surface of the compacted soil; (5) laying a multifunctional base pad, the multifunctional base pad is laid on the surface of the waterproof coiled material; (6) laying artificial turf, the artificial turf is laid on the surface of the multifunctional base pad; (7) filling quartz sand, filling quartz sand on the surface of the artificial turf by professional machinery or manually; (8) filling buffer particles, filling natural cork particles or synthetic rubber particles on the surface of the quartz sand. The construction method of "filling synthetic rubber particles" in the technical solution has the above-mentioned defects. SUMMARY

[0004] The purpose of the present application is to provide a more environmentally friendly and lower cost construction method of a particle-free artificial turf.

[0005] To solve the above technical problems, the technical solution adopted by the present application is:

[0006] A construction method of a particle-free artificial turf, comprising the following steps:

[0007] Step S1, compacting and leveling the site: a 30-40 ton roller is used to repeatedly compact and densify the foundation, and the site is leveled to form a soil compaction layer.

[0008] Step S2, paving gravel: paving the gravel with particle size of 10-30mm on the surface of the compacted soil layer to form the gravel layer;

[0009] Step S3, laying sand barrier filter layer: laying non-woven fabric on the surface of the gravel layer to form the sand barrier filter layer which is permeable to water but impermeable to sand;

[0010] Step S4, laying medium-fine sand buffer layer: laying the medium-fine sand with particle size of 0.1-1mm on the surface of the sand barrier filter layer;

[0011] Step S5, laying lawn layer;

[0012] Step S6, filling medium-fine sand: filling the medium-fine sand with particle size of 0.1-1mm on the surface of the lawn layer to form the medium-fine sand surface layer.

[0013] Further, in step S1, before the site is compacted by the road roller, the sundries on the surface of the site are removed, the site is ploughed, and the site soil is broken and leveled by the rotary cultivator.

[0014] Further, in step S2, the specific paving method is as follows: the gravel with particle size of 10-30mm is roughened and pushed flat on the surface of the compacted soil layer by the bulldozer, and then it is finely leveled by hand, and the gravel layer with thickness of 8-20cm is formed by compaction with the vibration roller with weight of more than 12 tons.

[0015] Further, in step S6, the thickness of the medium-fine sand filled by the hand-pushed sand covering machine in each single pass is adjusted, and the sand covering width is also adjusted, and the medium-fine sand is filled in multiple passes, and the grass filaments of the lawn layer are brushed after the end of each pass from the second pass.

[0016] Further, in step S6, the specific method for filling the medium-fine sand is as follows:

[0017] S6.1, the medium-fine sand is filled into the hand-pushed sand covering machine and shaken, and a straight line is drawn east-west on the lawn layer, and the sand covering machine walks along the straight line as the center line, and the medium-fine sand is filled in a single pass with thickness of 3-5mm;

[0018] S6.2, the straight line is adjusted to be north-south in the second pass, and the medium-fine sand is filled in a single pass with thickness of 3-5mm, and then the triangular plastic combing board is used to comb the grass filaments repeatedly until the grass filaments of the lawn layer are completely upright;

[0019] S6.3, however, the straight line is adjusted to be east-west in the third pass, and the medium-fine sand is filled in a single pass with thickness of 3-5mm, and the total thickness of the sand is ensured to be 9-15mm, and the grass filaments of the lawn layer are brushed again;

[0020] S6.4, steps S6.2 and S6.3 are repeated, and the filling of the medium-fine sand is completed when the seventh pass is reached.

[0021] Further, in step S1, before the road roller compacts the site, the water supply pipeline connected with the multiple branch pipes is embedded into the site soil, and the multiple spray pipes are connected with the corresponding branch pipes.

[0022] Further, in step S2, the drainage pipe is embedded during the paving of the gravel.

[0023] Further, the drainage pipe is a Yanshan net type permeable pipe.

[0024] Further, the upper end of the spray pipe sequentially penetrates the sand particle blocking filter layer, the medium fine sand buffer layer, the lawn layer, and the medium fine sand surface layer upwards and is connected with the self-rotating spray head; the spray pipe adopts a telescopic structure.

[0025] Further, the thickness of the medium fine sand buffer layer is 8-20 cm.

[0026] The present application has the following beneficial effects:

[0027] First, the present patent technical solution saves the glue particles, increases the amount of sand, and uses the medium fine sand, so that the lawn has the same buffering effect, solves the problem of environmental pollution caused by the glue particles, saves the construction cost, and solves the problem of high cost of the artificial lawn.

[0028] Second, the spraying device is additionally arranged, the temperature of the site artificial lawn is adjusted through the spraying device, and the comfort of people in this environment is improved. BRIEF DESCRIPTION OF DRAWINGS

[0029] The present application is further described by using the drawings, but the embodiments in the drawings do not constitute any limitation on the present application, and other drawings can be obtained by the ordinary skilled in the art without creative labor on the basis of the following drawings:

[0030] Figure 1 The present application is further described by using the drawings, but the embodiments in the drawings do not constitute any limitation on the present application, and other drawings can be obtained by the ordinary skilled in the art without creative labor on the basis of the following drawings:

[0031] Figure 2 The present application is further described by using the drawings, but the embodiments in the drawings do not constitute any limitation on the present application, and other drawings can be obtained by the ordinary skilled in the art without creative labor on the basis of the following drawings:

[0032] In the drawings: 1, soil compaction layer; 2, gravel layer; 3, sand particle blocking filter layer; 4, medium fine sand buffer layer; 5, lawn layer; 6, medium fine sand surface layer; 7, drainage pipe; 8, water supply pipeline; 9, spray pipe; 10, branch pipe; 11, self-rotating spray head. DETAILED DESCRIPTION

[0033] In order for the person skilled in the art to better understand the technical solutions of the present application, the present application will be further described in detail below in conjunction with the drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0034] In the description of the present application, it should be understood that the orientations or positional relationships indicated by the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper surface", "lower surface", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "forward rotation", "reverse rotation", "axial", "radial", "circumferential" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and therefore cannot be understood as indicating or implying that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as limiting the present application.

[0035] As shown in Figure 1 , 2 , a construction method of a glue-free artificial turf, comprising the following steps:

[0036] Step S1, compacting and leveling the site: removing the sundries on the surface of the site, turning over the site with a plow, then breaking and raking the site soil with a rotary cultivator, and then repeatedly rolling and compacting the foundation with a 30-40 ton roller, and leveling the site to form a soil compacting layer 1.

[0037] Step S2, paving gravel: paving gravel with a particle size of 10-30 mm on the surface of the soil compacting layer to form a gravel layer; the specific paving method is: roughening and pushing the gravel with a particle size of 10-30 mm on the surface of the soil compacting layer with a bulldozer, then manually fine leveling, and then compacting with a 12-ton vibrating roller to form a gravel layer 2 with a thickness of 8-20 cm; during the paving of the gravel, a drainage pipe is pre-buried, and the drainage pipe is a Yashan net type permeable pipe. The drainage pipe 7 is laid in the gravel layer 2 to drain the water seeping into the gravel layer 2 from the surface of the turf, and in order to improve the drainage performance, the drainage pipe 7 is a Yashan net type permeable pipe, and a plurality of water permeable holes are distributed on the pipe wall of the permeable pipe.

[0038] Step S3, laying a sand particle blocking and filtering layer 3: laying a non-woven fabric on the surface of the gravel layer to form a sand particle blocking and filtering layer 3 that is permeable to water but not to sand. The non-woven fabric effectively blocks the medium and fine sand in the fine sand buffer layer, preventing the medium and fine sand from seeping downward into the gravel layer 2, thereby improving the drainage effect of the gravel layer 2.

[0039] Step S4, laying the medium-fine sand buffer layer 4: on the surface of the sand particle barrier filter layer, medium-fine sand with a particle size of 0.1-1mm is laid, and the thickness of the medium-fine sand buffer layer is 8-20cm. The above-mentioned medium-fine sand particle size parameters help to improve the buffering degree of the fine sand buffer layer.

[0040] Step S5, laying the lawn layer 5: the lawn layer is laid in a conventional manner, and the specific steps are not described.

[0041] Step S6, filling the medium-fine sand: on the surface of the lawn layer, medium-fine sand with a particle size of 0.1-1mm is filled, and the thickness of the medium-fine sand filled by the hand-pushed sand covering machine in one pass is 3-5mm. At the same time, the sand covering width is adjusted, and the medium-fine sand is filled for multiple times. After the second pass, the grass filaments of the lawn layer are brushed to form the medium-fine sand surface layer 6.

[0042] The specific method for filling the medium-fine sand is as follows:

[0043] S6.1, the medium-fine sand is filled into the hand-pushed sand covering machine and shaken, and straight lines are drawn in the east-west direction on the lawn layer. When the sand covering machine is running, the straight lines are used as the center lines, and the medium-fine sand is filled in one pass with a thickness of 3-5mm;

[0044] S6.2, in the second pass, the straight lines are drawn in the north-south direction, and the medium-fine sand is filled in one pass with a thickness of 3-5mm. Then, a triangular plastic grass combing plate is used to repeatedly comb the grass filaments until the grass filaments of the lawn layer are completely upright.

[0045] S6.3, in the third pass, the straight lines are drawn in the east-west direction, and the medium-fine sand is filled in one pass with a thickness of 3-5mm. The total thickness of the sand covering is ensured to be 9-15mm, and the grass filaments of the lawn layer are brushed again.

[0046] S6.4, steps S6.2 and S6.3 are repeated, and the filling of the medium-fine sand is completed in the seventh pass.

[0047] In addition, in step S1, before the site is compacted by the road roller, a water supply pipe 8 is embedded in the soil compaction layer 1. The gravel layer 2 is provided with a plurality of spray pipes 9, the lower end of the spray pipe 9 is connected to the water supply pipe 8 through a branch pipe 10, the upper end of the spray pipe 9 is sequentially penetrated through the sand particle barrier filter layer 3, the medium-fine sand buffer layer 4, the lawn layer 5, and the medium-fine sand surface layer 6, and is connected to a self-rotating spray head 11. The spray pipe 9 adopts a telescopic structure, and is retracted below the lawn when not in use.

[0048] In addition, the different embodiments or examples described in the specification and the features of the different embodiments or examples can be combined and combined by those skilled in the art without contradiction. Although the embodiments of the present application have been shown and described above, it is understood that the above embodiments are exemplary and cannot be construed as limiting the present application, and those skilled in the art can make changes, modifications, replacements and variations to the above embodiments within the scope of the present application.

Claims

1. A method of installing a tufted artificial turf without adhesive, characterized in that, It comprises the following steps: Step S1, tamping and leveling the site: using 30-40 tons of roller repeatedly compacts the foundation and makes the site level, forming a soil tamping layer; before the site is compacted by the roller, remove the sundries on the surface of the site, use a plow to turn over the soil of the site, and then use a rotary cultivator to break up the soil clods and rake the site flat; before the site is compacted by the roller, pre-bury the water supply pipeline connected with multiple branch pipes into the soil of the site, and connect multiple spray pipes with corresponding branch pipes; the upper end of the spray pipe successively penetrates the sand blocking filter layer, the medium-fine sand buffer layer, the lawn layer, and the medium-fine sand surface layer upwards, and is connected with a self-rotating spray head; the spray pipe adopts a telescopic structure; Step S2, paving gravel: paving 10-30mm particle size gravel on the surface of the soil tamping layer to form a gravel layer; the specific paving method is: using a bulldozer to roughen and flatten the 10-30mm particle size gravel on the surface of the soil tamping layer, then manually fine-tuning and leveling, and using a vibration roller of more than 12 tons to compact, forming a gravel layer with a thickness of 8-20cm; during the paving of the gravel, pre-bury the drain pipe, which is a Yashan net type permeable pipe; Step S3, laying the sand blocking filter layer: laying non-woven fabric on the surface of the gravel layer to form a sand blocking filter layer that is permeable to water but not to sand; Step S4, laying the medium-fine sand buffer layer: laying 0.1-1mm particle size medium-fine sand on the surface of the sand blocking filter layer, the thickness of the medium-fine sand buffer layer is 8-20cm; Step S5, laying the lawn layer; Step S6, filling medium-fine sand: filling 0.1-1mm particle size medium-fine sand on the surface of the lawn layer to form a medium-fine sand surface layer; adjust the hand-push sand covering machine to fill the medium-fine sand with a thickness of 3-5mm per pass, and adjust the sand covering width, fill the medium-fine sand for multiple passes, and brush the grass filaments of the lawn layer after each pass starting from the second pass; the specific method for filling medium-fine sand is as follows: S6.1, fill the hand-push sand covering machine with medium-fine sand and shake it, first pull straight lines in the east-west direction on the lawn layer, and use the pulled lines as the center line when the sand covering machine is walking, fill the medium-fine sand with a thickness of 3-5mm per pass; S6.2, adjust the second pass to pull straight lines in the north-south direction, fill the medium-fine sand with a thickness of 3-5mm per pass, then use a triangular plastic combing board to repeatedly comb the grass filaments until the grass filaments of the lawn layer are completely upright; S6.3, however, the third pass is changed to fill the medium-fine sand with a thickness of 3-5mm per pass in the east-west direction, the total sand covering thickness is guaranteed to be 9-15mm, and the grass filaments of the lawn layer are brushed again; S6.4, repeat step S6.2 and step S6.3, and fill the medium-fine sand to the seventh pass.

Citation Information

Patent Citations

  • Construction method of novel artificial turf sports field

    CN108914746A

  • Soft foundation structure of sports ground lawn and construction method of soft foundation structure

    CN110042726A

  • Environment-friendly cavernous body artificial turf and construction method thereof

    CN111335112A

  • Artificial turf without colloidal particles

    CN218711935U

  • Ground with sand mixed artificial grasslaid tmero on

    JP1994207402A