Water replacement storage field and its application

Through the water displacement construction method, using structures such as water-stop embankments and riprap prisms, the problems of space occupation and high investment in existing yard construction have been solved, achieving efficient yard expansion and improved project cost-effectiveness.

CN115852902BActive Publication Date: 2025-09-16CCCC FIRST HARBOR ENGINEERING CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310056278.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-21
Publication Date
2025-09-16
Estimated Expiration
2042-10-21

AI Technical Summary

Technical Problem

In the existing yard construction method, the embankment filling occupies a large amount of enclosed space and consumes engineering investment, and the main function of the filler is to change the water environment into a land environment, resulting in a low engineering cost-effectiveness.

Method used

A water displacement construction method is adopted to create dry construction conditions through the construction of water-stop dikes, enclosure drainage and yard construction. The water space within the water-stop dike is used as storage space to avoid land reclamation. Riprap prisms and wave-breaking walls are combined to enhance stability, and low and high floors are constructed to facilitate the movement of stacking and reclaiming equipment and material storage.

Benefits of technology

It has expanded the yard capacity, saved land reclamation costs, improved the project cost-effectiveness, shortened the construction period, and provided fast vehicle driving access and yard construction conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115852902B_ABST
    Figure CN115852902B_ABST
Patent Text Reader

Abstract

The present application provides a water body replacement storage yard, including a water-stop dike and a storage yard; wherein, the storage yard is constructed in the internal space enclosed by the water-stop dike, and is located on a pit formed after the water inside the water-stop dike is drained; the storage yard includes a lower low-level floor and a higher high-level floor; wherein, the low-level floor is lower than the average water level outside the water-stop dike, and a warehouse is constructed on it; the high-level floor can be used for the movement of stacking and reclaiming equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of water transport engineering, and in particular relates to a water body replacement type storage field construction method and a storage field obtained by using the construction method. Background Art

[0002] A storage yard is one of the key infrastructures used for bulk cargo storage in water transport projects. Due to the need to be close to the dock, existing construction methods often involve first constructing a dike to enclose a portion of water, then converting the enclosed water area into land through hydraulic filling or land reclamation, and then building the storage yard on top of it.

[0003] The problem with existing storage yard construction methods is that the fill material placed in the water within the enclosure takes up a significant amount of space and consumes a significant amount of engineering investment; the investment in fill material reduces the enclosed space. During the filling process, the fill material primarily transforms the water environment into a dry land environment, facilitating material storage. Summary of the Invention

[0004] A first aspect of the present application provides a water displacement storage field construction method, comprising the following steps:

[0005] Construction of water-stopping embankment: Construction forms embankment with water-stopping function;

[0006] Enclosure and drainage construction: After the water-stop enclosure is closed, the water within the enclosure is drained to expose the pit body and create dry construction conditions;

[0007] Yard construction: Under dry construction conditions, yard construction is carried out on the pit, including constructing a lower ground and a higher ground; wherein the lower ground is lower than the average water level outside the water-stop embankment; the higher ground can be used for the movement of stacking and reclaiming equipment, and the stacking and reclaiming equipment can transport materials to or from the silo;

[0008] Construction of the warehouse body: the warehouse body is constructed on the low floor.

[0009] In some embodiments of the present application, the steps of constructing the water-stop embankment also include: first, using a vibratory hammer group to insert the cylindrical steel plate into the soft soil foundation; then, using a vibratory hammer group to insert two auxiliary grid steel plates along the mortise and tenon of the outer wall of the cylindrical steel plate into the soft soil foundation between each two adjacent cylindrical steel plates to close the gap between the adjacent cylindrical steel plates; again, backfilling the interior of the cylindrical steel plate and the inner cavity formed between the two auxiliary grid steel plates to form the water-stop embankment.

[0010] In some embodiments of the present application, the enclosure and drainage construction step also includes: leveling the pit body, generally without filling and raising it, and then constructing a storage yard thereon.

[0011] In some embodiments of the present application, the water displacement storage site construction method further includes constructing riprap prisms: The riprap prisms are constructed on both the inner and outer sides of the waterstop embankment, forming a substantially right-angled trapezoidal shape that fits the waterstop embankment on both the inner and outer sides; the upper surfaces of the riprap prisms are substantially flush with the upper surface of the waterstop embankment. The upper portion of the waterstop embankment or the upper portion of the outer riprap prisms may also be constructed to form an upwardly extending wave barrier.

[0012] In some embodiments of the present application, during the construction steps of the storage yard, the low-level floor is 3-20 m lower than the average water level outside the water-stop embankment.

[0013] In some embodiments of the present application, in the construction steps of the yard, the average depth from the pit to the top of the water-stop embankment is L1, and the depth from the surface of the low floor to the top of the water-stop embankment is L2, wherein L2 / L1≥50%.

[0014] In some embodiments of the present application, during the construction steps of the storage yard, a permeable cushion layer, a water-blocking cushion layer, a waterproof layer, and a bottom plate layer are formed from bottom to top within the drained pit to form the low-level floor. More specifically, the permeable cushion layer is formed by laying a permeable material within the pit; the water-blocking cushion layer is formed by pouring cement or concrete on the permeable cushion layer; the waterproof layer is formed by coating a waterproof material on the water-blocking cushion layer or laying a physical waterproof layer; and the bottom plate layer is poured with cement or concrete.

[0015] In some embodiments of the present application, the bottom plate layer further has spaced-apart ground beams; the ground beams are plate structures extending downward into the pit body.

[0016] In some embodiments of the present application, during the construction steps of the silo body, a storage silo and a ballast silo are set on the low floor, wherein the ballast silos are distributed around the storage silo; the storage silo can be used to store materials, and the ballast silo can be used to fill ballast.

[0017] In some embodiments of the present application, the storage bins and ballast bins are both long and narrow and are spaced apart from each other; adjacent storage bins and ballast bins share the same long side wall, and the short side walls of multiple side-by-side storage bins and the short side walls of the ballast bins form a common side wall; wherein the width of the storage bins is greater than the width of the ballast bins.

[0018] In some embodiments of the present application, during the yard construction process, the elevated floor is constructed on the silo. More specifically, a main road of the elevated floor is constructed approximately perpendicular to the elongated silo; a branch road of the elevated floor is formed above the ballast tank and connected to the main road; both the main road and the branch road are capable of accommodating stacking and reclaiming equipment.

[0019] In some embodiments of the present application, a support plate for supporting the main road is provided in the bin body corresponding to the main road, and the support plate is a vertically arranged steel plate or reinforced concrete plate; the long side wall of the ballast bin is made of reinforced concrete or steel structure, and its height is roughly the same as the main road of the high floor to form a branch road on the ballast bin, and the long side wall of the ballast bin is used as the basis of the walking track of the stacking and reclaiming equipment.

[0020] In some embodiments of the present application, a connecting beam connecting the two long side walls is provided on the upper parts of the two long side walls of the same ballast tank.

[0021] The second aspect of the present application provides an application of a water displacement storage field construction method in the construction of a port yard, and the construction method described in any of the above embodiments can be adopted.

[0022] A third aspect of the present application provides a water displacement storage site, which can be constructed using the construction method described in any of the above embodiments.

[0023] The water-displacement storage yard includes a water-stop embankment and a storage yard. The storage yard is constructed within the internal space enclosed by the water-stop embankment, located on a pit formed by drainage from the water-stop embankment. The storage yard includes a lower ground level and a higher ground level. The lower ground level is lower than the average water level outside the water-stop embankment and houses a storage structure. The higher ground level can be used for the movement of stacking and reclaiming equipment.

[0024] In some embodiments of the present application, the pit body is leveled and generally not filled and raised; the storage yard is located on the leveled pit body.

[0025] In some embodiments of the present application, the waterstop embankment comprises a plurality of cylindrical steel plates and auxiliary grid steel plates positioned between adjacent cylindrical steel plates; the cylindrical steel plates are spaced apart along the length of the waterstop embankment; the auxiliary grid steel plates are arc-shaped and are tightly joined to the cylindrical steel plates via tongue-and-groove arrangements on the cylindrical steel plates. Two opposing auxiliary grid steel plates are positioned between adjacent cylindrical steel plates, each with its arc-shaped convex surface facing outward, forming an inner cavity therebetween; the interiors of the cylindrical steel plates and the inner cavities of the auxiliary grid steel plates are both filled with backfill soil.

[0026] In some embodiments of the present application, riprap prisms are respectively provided on the inner and outer sides of the water-stop embankment; and a wave-retaining wall extending upward is provided on the top of the water-stop embankment.

[0027] In some embodiments of the present application, the low floor is 3-20m lower than the average water level outside the water-stop embankment.

[0028] In some embodiments of the present application, the average depth from the pit body to the top of the water-stop embankment is L1, and the depth from the surface of the low floor to the top of the water-stop embankment is L2, wherein 100% ≥ L2 / L1 ≥ 50%.

[0029] In some embodiments of the present application, the low-level floor comprises, from bottom to top, a permeable cushion layer, a water-blocking cushion layer, a waterproof layer, and a bottom plate layer. The permeable cushion layer is formed by laying crushed stone in the pit; the water-blocking cushion layer is formed by pouring cement or concrete on the permeable cushion layer; the waterproof layer is formed by coating a waterproof material on the water-blocking cushion layer or laying a physical waterproof layer; and the bottom plate layer is poured with cement or concrete.

[0030] In some embodiments of the present application, the bottom plate layer further has spaced-apart ground beams; the ground beams are plate structures extending downward into the pit.

[0031] In some embodiments of the present application, a storage bin and a ballast bin are provided on the low floor, wherein the ballast bins are distributed around the storage bin; the storage bin can be used to store materials, and the ballast bin can be used to fill ballast.

[0032] In some embodiments of the present application, the storage bins and ballast bins are both rectangular and spaced apart; adjacent storage bins and ballast bins share the same long side wall, and the short side walls of multiple side-by-side storage bins and the short side walls of the ballast bins form a common side wall; wherein the width of the storage bins is greater than the width of the ballast bins.

[0033] In some embodiments of the present application, the elevated floor is located on the warehouse body, including a main road and a branch road connected to the main road, both of which can be used for stacking and reclaiming equipment to travel; the main road is arranged in a direction roughly perpendicular to the rectangular warehouse body; the branch road is located above the ballast bin.

[0034] In some embodiments of the present application, a support plate for supporting the main road is provided in the bin body corresponding to the main road, and the support plate is a vertically arranged steel plate or reinforced concrete plate; the long side wall of the ballast bin is made of reinforced concrete or steel structure, and its height is roughly flush with the main road of the high floor to form a branch road on the ballast bin, and the long side wall of the ballast bin is used as the basis of the walking track of the stacking and reclaiming equipment.

[0035] In some embodiments of the present application, a plurality of connecting beams connecting the two long side walls are provided at intervals on the upper portions of the two long side walls of the same ballast tank.

[0036] A fourth aspect of the present application provides an application of a water body replacement storage field in a port yard, which can adopt the water body replacement storage field described in any of the above embodiments.

[0037] Compared with the prior art, the present invention has the following advantages:

[0038] The water replacement storage yard provided in at least one embodiment of the present application adopts a water-stopping embankment for waterproofing instead of land reclamation, thereby changing a water environment into a waterless environment and replacing the space occupied by the water body within the water-stopping embankment with storage space, thereby expanding the yard capacity and saving the cost of land reclamation, thereby greatly improving the cost-effectiveness of the project.

[0039] The water displacement storage yard provided in at least one embodiment of the present application uses an inserted cylindrical structure to reinforce the foundation of the embankment and serve as a water-stopping and retaining structure. It can not only quickly construct a vehicle driving channel in the water to form conditions for filling the water-stop embankment, but also quickly build an enclosure to form dry construction conditions for the yard within the water-stop embankment, creating conditions for parallel construction of the yard and the water-stop embankment, greatly shortening the construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 This is a construction diagram of the water-stop embankment;

[0041] Figure 2 yes Figure 1 A partial enlarged view of

[0042] Figure 3 This is a construction diagram of the warehouse;

[0043] Figure 4 yes Figure 3 A partial enlarged view of

[0044] Figure 5 This is a schematic diagram of the warehouse after material is piled up;

[0045] Figure 6 yes Figure 5 A partial enlarged view of

[0046] Figure 7 is a schematic front view of a storage yard according to one embodiment;

[0047] Figure 8 is a schematic side view of a storage field according to one embodiment;

[0048] Numbers in the figure: 1 water-stop embankment, 101 cylindrical structure, 1011 cylindrical steel plate, 1012 auxiliary grid steel plate, 1013 inner cavity, 2 pit body, 3 storage yard, 4 riprap prism, 5 wave-breaking wall, 6 low-level floor, 601 permeable cushion layer, 602 water-blocking cushion layer, 603 waterproof layer, 604 bottom plate layer, 6041 ground beam, 7 high-level floor, 701 main road, 702 branch road, 8 warehouse body, 801 storage warehouse, 802 ballast warehouse, 803 long side wall, 804 common side wall, 805 support plate, 806 connecting beam. DETAILED DESCRIPTION

[0049] The technical solution of the present application is described in detail below in conjunction with specific embodiments. However, it should be understood that without further description, the elements, structures and features in one embodiment may also be beneficially combined with other embodiments.

[0050] In the description of this application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood to indicate or imply relative importance or implicitly specify the number of technical features indicated. Therefore, features specified as "first" or "second" may explicitly or implicitly include one or more of such features.

[0051] In the description of this application, it should be understood that the terms "upper", "lower", "bottom", "inner" and the like indicate positions or location relationships based on the attached Figure 7 The orientation or positional relationship shown is only for the convenience of describing this application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be understood as a limitation on this application.

[0052] In the description of this application, it should be noted that, unless otherwise expressly specified or limited, the terms "connected" and "connection" should be understood in a broad sense. For example, they can refer to fixed connection, detachable connection, or integral connection; they can refer to direct connection, indirect connection through an intermediate medium, or internal communication between two components. Those skilled in the art will understand the specific meanings of the above terms in this application based on the specific circumstances.

[0053] The first embodiment of the present application provides a construction method of a water displacement storage field, such as Figure 1-5 As shown, the following steps are included:

[0054] (1) Construction of water-stop embankment 1:

[0055] In one embodiment, a cylindrical structure 101 can be inserted into the water to reinforce the foundation of the enclosure and serve as a water-stopping and enclosure structure to form a water-stop enclosure 1. Specifically: the cylindrical structure 101 includes a cylindrical steel plate 1011 and a sub-grid steel plate 1012, such as Figure 1 and Figure 2 .

[0056] First, the cylindrical steel plate 1011 is inserted into the soft soil foundation to enhance the soil shear strength. The cylindrical steel plate 1011 can be inserted into the soft soil by using a vibrating hammer set suspended from a crane.

[0057] Then, two auxiliary grid steel plates 1012 are inserted into the soft soil between each two adjacent cylindrical steel plates 1011 along the tongue and groove (not shown in the figure, the tongue and groove in the prior art can be used) on the outer wall of the cylindrical steel plates 1011 to close the gap between the adjacent cylindrical steel plates 1011. Sealing material is applied to the connection between the auxiliary grid steel plates 1012 and the tongue and groove to achieve watertightness.

[0058] The auxiliary grid steel plate 1012 can also be inserted into the soft foundation using a vibratory hammer system suspended from a crane vessel. The sealing material can be a mixture of sawdust, asphalt, or other materials pre-placed in the mortise to maintain a watertight seal during the insertion of the auxiliary grid steel plate 1012. Alternatively, the sealing material can be cement slurry, which is injected into the mortise using a preset pipeline pressure after the auxiliary grid steel plate 1012 is inserted into the mortise, thereby achieving a watertight seal.

[0059] Secondly, the interior of the cylindrical steel plate 1011 and the inner cavity 1013 formed between every two opposing auxiliary grid steel plates 1012 are backfilled to form the water-stop embankment 1.

[0060] The backfill can be carried out using sand and gravel, either from the water or from land. The pressure from the sand and gravel prevents the cylindrical steel plate from shrinking. The strength of the sand and gravel and the cylindrical structure 101 prevents the cylindrical steel plate from bending or breaking. The gravity of the sand and gravel, the gravity of the cylindrical structure 101, and the frictional resistance of its buried portion prevent the water-stop embankment 1 from tipping or sliding, thus maintaining overall stability. The top of the water-stop embankment 1 can also be leveled and compacted to create a construction road for the passage of construction machinery and vehicles.

[0061] (2) Enclosure and drainage construction

[0062] After the water-stop embankment 1 is sealed, the water within its enclosed area is removed, exposing the pit 2 and creating dry construction conditions. Depending on actual conditions, the pit 2 can be leveled to facilitate the construction of the storage yard 3 within the water-stop embankment 1. Leveling refers to making the pit level in whole or in part, and does not involve conventional filling; the primary purpose of filling is to increase the height, and the material used is significantly higher than for leveling.

[0063] (3) Construction of riprap prism 4

[0064] like Figure 4 As shown, the riprap prisms 4 can be constructed on the inner and outer sides of the water-stop embankment 1 respectively; so that the riprap prisms 4 roughly form a right-angled trapezoidal shape on the inner and outer sides that fits the water-stop embankment 1 respectively, and the upper surface of the riprap prisms 4 is roughly flush with the upper surface of the water-stop embankment 1.

[0065] The portion of the riprap prism 4 below the water surface can be filled from the water using a riprap boat, or partially filled using land-based equipment, with the remaining portion filled from the water using a riprap boat. The portion of the riprap prism 4 above the water surface can be filled using land-based equipment. The riprap prism 102 inside the waterstop embankment can also be filled entirely using land-based equipment.

[0066] The upper part of the water-stop embankment 1 or the upper part of the riprap prism 4 located outside can also be constructed to form an upwardly extending wave-blocking wall 5 to reduce the number of waves entering the water-stop embankment 1. The wave-blocking wall 5 can be made of reinforced concrete.

[0067] (4) Construction of Yard 3

[0068] After the dry construction conditions are formed, the yard 3 is constructed, including the construction of the low-level floor 6 and the high-level floor 7. The low-level floor 6 is lower than the average water level outside the water-stopping embankment 1; depending on the actual water depth and construction environment, it may be 3-20m lower than the average water level to form material storage conditions. Or, as Figure 7 As shown, the average depth from the pit body 2 to the top of the water-stopping embankment 1 is L1, and the depth from the surface of the low-level floor 6 to the top of the water-stopping embankment 1 is L2. Then: 100% ≥ L2 / L1 ≥ 50%. For example, L2 / L1 ≥ 60%, L2 / L1 ≥ 65%, L2 / L1 ≥ 70%, L2 / L1 ≥ 75%, L2 / L1 ≥ 80%, etc. Because the surface of the low-level floor 6 is below the water surface, more usable space is created above it. The high-level floor 7 can be built on the basis of the low-level floor 6, its height is higher, creating conditions for the installation and operation of stacking and reclaiming equipment.

[0069] More specifically: Figure 7 and Figure 8As shown, a permeable cushion layer 601, a water-blocking cushion layer 602, a waterproof layer 603 and a bottom plate layer 604 are formed in sequence from bottom to top in the pit body 2 after drainage to form the low-level floor 6. The permeable cushion layer 601 can be formed by laying permeable gravel in the pit body 2. Since water may seep into the pit body 2, it will generate a buoyancy force on the low-level floor 6, which may break the low-level floor 6. By providing the permeable cushion layer 601, the pressure of the water can be reduced or dissipated, protecting other layers above from being crushed. Therefore, the permeable cushion layer 601 has both reverse filtration and pressure-reducing drainage functions. The water-blocking cushion layer 602 can be formed by pouring cement or concrete on the permeable cushion layer 601. The water-blocking cushion layer 602 can block water to a certain extent and facilitates the subsequent construction of the waterproof layer 603, becoming a connecting layer between the permeable cushion layer 601 and the waterproof layer 603. The waterproof layer 603 can be formed by coating a waterproof material on the water-blocking cushion layer 602 or laying a physical waterproof layer (such as a multi-layered or partially stacked waterproof geotextile), which plays the main waterproofing function and prevents water from seeping upward into the surface of the low-level floor 6. The bottom plate layer 604 located on the waterproof layer 603 is conventionally cast with cement or concrete. Figure 8 As shown, the bottom plate layer 604 also has spaced-apart ground beams 6041 extending downward. The ground beams 6041 are plate structures that extend into the pit body 2, thereby increasing the bearing capacity of the low-level floor 6.

[0070] (5) Construction of warehouse body 8

[0071] A bin body 8 is provided on the low floor 6, comprising a storage bin 801 and a ballast bin 802; wherein the ballast bin 802 is evenly distributed near the storage bin 801. The storage bin 801 is mainly used to store materials (such as ore, coal, food, etc.); the ballast bin 802 is mainly used to fill ballast (such as sand or stone, etc.) when the weight of the storage bin 801 is relatively light. Considering that there may be water seepage at the bottom of the low floor 6 (or the water-blocking cushion 602), when there is material of appropriate weight in the storage bin 801, a counter-pressure will be formed on the water seepage to overcome the buoyancy of the water seepage. However, when there is less material or no material in the storage bin 801, in order to avoid the damage to the low floor 6 caused by the buoyancy generated by the water seepage, ballast can be filled in the ballast bin 802 to increase the counter-pressure of the low floor 6 against the water seepage. It can be understood that the storage bin 801 and the ballast bin 802 can be used in combination; for example, when there is a lot of material, the material can be stored in the storage bin 801 and the ballast bin 802 at the same time, so that the ballast bin 802 also has the function of the storage bin 801; when there is less material, ballast can also be filled in the storage bin 801, so that the storage bin 801 has the function of the ballast bin 802.

[0072] The storage bin 801 and the ballast bin 802 can be arranged in zones, sections, and layers to rationally utilize the space above the low floor 6. Since the low floor 6 is located below the average water level, the space provided above it is much larger than the space formed by the stockpile obtained by conventional filling methods, thereby greatly increasing the height and volume of the storage bin 801 and allowing for the storage of more materials. In one embodiment, the storage bin 801 and the ballast bin 802 are both long strips and are spaced apart. Figure 3-6 As shown, the storage bins 801 and ballast bins 802 are both rectangular; adjacent storage bins 801 and ballast bins 802 share the same long side wall 803; and the short side walls of multiple side-by-side storage bins 801 and ballast bins 802 form a common side wall 804. In order to store more materials, the width of the storage bins 801 is greater than that of the ballast bins 802.

[0073] In order to facilitate long-term storage of materials, a waterproof layer can be applied around and on the bottom of the storage bin 801 to enhance the waterproof effect.

[0074] (6) Construction of high floor

[0075] The stacking and reclaiming equipment mainly includes a stacker and a reclaimer, which are very heavy. In conventional use, in order to facilitate the movement of the stacking and reclaiming equipment, it is often necessary to pile on the foundation, then lay track beams on the ground, and lay tracks for the stacking and reclaiming equipment to move on the track beams. In the yard 3, the stacking and reclaiming equipment also requires special walking tracks. As described in step (4), a higher high-level floor 7 can be built on the basis of the low-level floor 6 to become a condition for the stacking and reclaiming equipment to move. However, if multiple high-level floor 7 passages are blindly built on the low-level floor 6, the high-level floor 7 will occupy too much space, thereby squeezing the space of the warehouse body 8.

[0076] In this embodiment, in order to solve the above problems, a high floor 7 can be built on the warehouse body 8. More specifically, Figure 3-6 As shown, a main road 701 of the elevated floor 7 is constructed along a direction roughly perpendicular to the long strip or rectangular warehouse body 8; a support plate 805 is provided in the warehouse body 8 below corresponding to the main road 701, which can be a steel plate or a reinforced concrete plate, forming conditions for supporting the stacking and reclaiming equipment to move on the main road 701. A branch road 702 of the elevated floor 7 is formed above the ballast warehouse 802, which is connected to the main road 701 and can also be used for the stacking and reclaiming equipment to move. Specifically, the long side wall 803 of the ballast warehouse 802 can be made of a relatively high-strength material such as reinforced concrete or steel structure, and its height is roughly the same as the elevated floor 7 (or main road 701); thereby, the walking tracks of the stacker and the reclaimer can be laid on the long side wall 803 of the ballast warehouse 802, as shown in FIG. Figure 5 and Figure 6 shown.

[0077] By setting the main road 701 and branch roads 702 of the elevated floor 7, the stacking and reclaiming equipment from the main road 701 can reach each branch road 702, thereby stacking or reclaiming materials along the length direction of the storage bin 801. Figure 6 As shown, the stacker can move along the branch road 702 on the first row of ballast bins 802 to stack materials in the first row of storage bins 801. The figure is a schematic diagram after the stacking is completed.

[0078] The long sidewalls 803 of the ballast tank 802 are provided with connecting beams 806 located above the long sidewalls 803 of the ballast tank 802. These connecting beams 806 are used to connect two adjacent long sidewalls 803 within the ballast tank 802. For example, multiple connecting beams 806 can be welded between the two long sidewalls. This arrangement can pull the upper portions of the long sidewalls 803 together, thereby overcoming the outward lateral pressure exerted on the long sidewalls 803 by the ballast load (e.g., a stacker / reclaimer) above, and thus increasing load stability.

[0079] It is worth noting that the order of the steps described in this embodiment is merely a description order, and in actual operation, it can be adjusted according to actual needs. Therefore, the description order does not constitute an absolute limitation to this application.

[0080] This embodiment creates more storage / warehouse space by constructing a low-level floor 6 directly within pit 2, lowering it below the average water level outside. Furthermore, by utilizing the vast majority of pit 2's surface area directly as storage / warehouse space, this embodiment avoids the need for conventional filling of pit 2, saving significant amounts of filler material, labor, and machinery, significantly improving the project's cost-effectiveness.

[0081] The second embodiment of the present application provides a water-displacement storage site, which can be constructed using the construction method described in any of the above embodiments. The water-displacement storage site comprises: a water-stopping embankment 1 and a storage yard 3; wherein the outer side of the water-stopping embankment 1 is adjacent to the water body; the storage yard 3 is formed within the internal space enclosed by the water-stopping embankment 1, and is located on a pit 2 formed after the water inside the water-stopping embankment 1 is drained.

[0082] The water-stop embankment 1 has a water-stopping function, preventing water from outside from entering the interior of the water-stop embankment 1; the water-stop embankment 1 can be constructed using the embankment 1 construction method in the prior art. As an embodiment, the water-stop embankment 1 includes a plurality of cylindrical steel plates 1011 and auxiliary grid steel plates 1012 located between adjacent cylindrical steel plates 1011. The cylindrical steel plates 1011 are cylindrical and are spaced apart along the length of the water-stop embankment 1. The auxiliary grid steel plates 1012 are arc-shaped and are in close contact with the cylindrical steel plates 1011 through the tongue and groove on the cylindrical steel plates 1011 to stop water. In one embodiment, there are two oppositely arranged auxiliary grid steel plates 1012 between adjacent cylindrical steel plates 1011, and the arc-shaped convex surface of each auxiliary grid steel plate 1012 faces outward, forming an inner cavity 1013 therebetween. The interior of the cylindrical steel plate 1011 and the inner cavity 1013 are backfilled with backfill soil to increase the stability of the water-stop embankment 1.

[0083] Optionally, riprap prisms 4 are provided on the inner and outer sides of the water-stop embankment 1, respectively, to reduce the lateral pressure exerted by the inner pile on the embankment 1 and to form a counterpressure on the foundation; and to reduce the force exerted by waves or currents on the embankment 1 and to form a counterpressure on the foundation, thereby enhancing the stability of the embankment 1. A wave barrier 5 may be provided on the top of the embankment 1 to reduce overtopping.

[0084] The yard 3 includes a lower low-level floor 6 and a higher high-level floor 7. The low-level floor 6 includes a permeable cushion layer 601, a water-blocking cushion layer 602, a waterproof layer 03 and a bottom plate layer 604 distributed from bottom to top. The permeable cushion layer 601 has a water-permeable function and can be paved in the pit body 2 with permeable materials (such as crushed stone, gravel); its thickness is 200-3000mm. The water-blocking cushion layer 602 is a cement layer or a concrete layer, which has a certain degree of water-blocking effect; its thickness is 100-300mm. The waterproof layer 603 is formed by coating a waterproof material on the water-blocking cushion layer 602 or laying a physical waterproof layer, and its thickness is 0.1-10mm. The bottom plate layer 604 is a cement layer or a concrete layer, which is a working surface layer; its thickness is 300-2500mm. The bottom plate layer 604 further has spaced-apart ground beams 6041 . The ground beams 6041 are a plurality of parallel plate structures and are formed by extending downward from the bottom plate layer 604 .

[0085] The surface of the low floor 6 is at least 1m lower than the average water level outside the water-stopping embankment 1, for example, 1-20m (such as 2m, 3m, 5m, 8m, 10m, 12m, 15m, 18m, etc.), which makes use of the space occupied by the original water body and greatly increases the material storage space.

[0086] The low floor 6 is provided with a storage body 8, comprising a storage bin 801 and a ballast tank 802. The ballast tank 802 is located adjacent to the storage bin 801. The storage bin 801 is used to store materials; the ballast tank 802 is used to fill the storage bin 801 with ballast to supplement the weight of the storage bin 801 when the weight is insufficient, thereby increasing the downward pressure of the low floor 6.

[0087] like Figure 4 As shown, in one embodiment, the storage bins 801 and the ballast tanks 802 are both rectangular, the width of the storage bins 801 is greater than the width of the ballast tanks 802, and the two are arranged at intervals; so that adjacent storage bins 801 and ballast tanks 802 share the same long side wall 803, and the short side walls of multiple storage bins 801 and the short side walls of the ballast tanks 802 arranged side by side form a common side wall 804.

[0088] The high floor 7 can be built on the low floor 6 for the movement of the stacking and reclaiming equipment. In one embodiment, the high floor 7 includes a main road 701 and a plurality of branch roads 702 connected to the main road 701. Figure 3-6 As shown, the main road 701 is arranged perpendicular to the length direction of the storage bin 801 and the ballast tank 802, and is located above the storage bin 801 and the ballast tank 802; the branch road 702 is formed above the ballast tank 802.

[0089] Furthermore, a support plate 805 is vertically provided in the silo 8 (storage silo 801 and ballast tank 802) below the main road 701. The support plate 805 is a reinforced concrete plate or a steel plate, which is used to support the main road 701. The long side wall 803 of the ballast tank is made of reinforced concrete or steel structure, and its height is flush with the height of the main road 701, so that the upper part of the ballast tank 802 serves as a branch road 702 for laying the track of the stacking and reclaiming equipment, such as Figure 7 As shown. Furthermore, the ballast tank 802 may be provided with a plurality of connecting beams 806, located between the upper portions of the two opposing long side walls 803 of the ballast tank, to connect the two long side walls and enhance pressure resistance. In this embodiment, the long side walls of the ballast tank can also serve as the foundation for the running track of the stacking and reclaiming equipment, eliminating the need for additional space for the track foundation, thereby increasing the storage space of the tank body 8.

[0090] The described embodiments are merely descriptions of the preferred embodiments of the present application and do not limit the scope of the present application. Without departing from the design spirit of the present application, various modifications and improvements made to the technical solutions of the present application by ordinary technicians in this field should fall within the scope of protection determined by the claims of the present application.

Claims

1. A water displacement storage field, characterized in that: The invention comprises a water-stop enclosure and a storage yard; wherein the storage yard is constructed in the internal space enclosed by the water-stop enclosure, and is located on a pit formed after the water inside the water-stop enclosure is drained; the storage yard comprises a lower ground and a higher ground; wherein the lower ground is lower than the average water level outside the water-stop enclosure, and a storage body is constructed on it; the higher ground can be used for the movement of stacking and reclaiming equipment; The silo body includes a storage silo and a ballast silo, wherein the ballast silo is distributed around the storage silo; the storage silo can be used to store materials, and the ballast silo can be used to fill ballast; The storage bins and ballast bins are both rectangular and spaced apart; adjacent storage bins and ballast bins share the same long side wall, and the short side walls of multiple side-by-side storage bins and the short side walls of the ballast bins form a common side wall; wherein the width of the storage bins is greater than the width of the ballast bins; The elevated floor is located on the silo body and includes a main road and a branch road connected to the main road, both of which can be used for stacking and reclaiming equipment to travel; the main road is arranged in a direction substantially perpendicular to the rectangular silo body; the branch road is located above the ballast tank; A support plate for supporting the main road is provided in the bin body corresponding to the main road, and the support plate is a vertically arranged steel plate or reinforced concrete plate; the long side wall of the ballast bin is made of reinforced concrete or steel structure, and its height is flush with the main road of the high floor to form a branch road on the ballast bin, and the long side wall of the ballast bin is used as the basis of the walking track of the stacking and reclaiming equipment.

2. The water displacement storage field according to claim 1, characterized in that: The low-level floor is 3-20m lower than the average water level outside the water-stop embankment.

3. The water displacement storage field according to claim 1, characterized in that: The average depth from the pit body to the top of the water-stop embankment is L1, and the depth from the surface of the low floor to the top of the water-stop embankment is L2, among which 100%≥L2 / L1≥50%.

4. The water displacement storage field according to claim 1, characterized in that: The pit body is leveled and no filling or heightening is performed; the storage yard is located on the leveled pit body.

5. The water displacement storage field according to any one of claims 1 to 4, characterized in that: The water-stop embankment includes a plurality of cylindrical steel plates and auxiliary grid steel plates located between adjacent cylindrical steel plates; wherein the cylindrical steel plates are spaced apart along the length direction of the water-stop embankment; the auxiliary grid steel plates are arc-shaped and are tightly connected to the cylindrical steel plates through tongues and grooves on the cylindrical steel plates; there are two oppositely arranged auxiliary grid steel plates between adjacent cylindrical steel plates, and the arc-shaped convex surface of each auxiliary grid steel plate faces outward, forming an inner cavity therebetween; the interior of the cylindrical steel plates and the inner cavity of the auxiliary grid steel plates are filled with backfill soil; riprap prisms are respectively provided on the inner and outer sides of the water-stop embankment; and a wave-retaining wall extending upward is provided on the top of the water-stop embankment.

6. The water displacement storage field according to any one of claims 1 to 4, characterized in that: The low-level floor includes a permeable cushion layer, a water-blocking cushion layer, a waterproof layer and a bottom plate layer from bottom to top; wherein, the permeable cushion layer is formed by laying crushed stones in the pit body; the water-blocking cushion layer is formed by laying cement or concrete on the permeable cushion layer; the waterproof layer is formed by coating a waterproof material on the water-blocking cushion layer or laying a physical waterproof layer; and the bottom plate layer is cast by cement or concrete.

7. The water displacement storage field according to claim 6, characterized in that: The bottom plate layer also has ground beams arranged at intervals; the ground beams are plate structures and extend downward into the pit body; and a plurality of connecting beams connecting the two long side walls are arranged at intervals on the upper parts of the two long side walls of the same ballast tank.

8. Use of the water displacement storage field according to any one of claims 1 to 7 in a port yard.

Citation Information

Patent Citations

  • Geocell cofferdam and construction method thereof

    CN109056654A

  • Storehouse is stored up to grit aggregate

    CN206448584U