Bitter and salty water evaporation utilization system in arid areas

Through the evaporation and utilization system of bitter and salt water in arid areas and the use of multi-stage filter layer and electric heating system, the low water efficiency and sediment problems of bitter and salt water in arid areas are solved, and efficient and low-cost freshwater preparation and water use needs are achieved, adapting to Water demand in different seasons.

CN116239248BActive Publication Date: 2024-11-01NINGXIA UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310029000.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-09
Publication Date
2024-11-01
Estimated Expiration
2043-01-09

AI Technical Summary

Technical Problem

The water-making efficiency of bitter and salty water in arid areas is low, the process is complex, and the cost is high. The high silt content of natural rivers leads to a large amount of silt and sand accumulation in the evaporation pond, which reduces the floor area ratio.

Method used

A bitter and salty water evaporation utilization system in arid areas was designed, including river channels, water inlet channels, evaporation utilization systems and water outlet channels. By setting up water inlet channels in the upstream of the river, water filtration and evaporation are achieved using a multi-stage filter layer and an electric heating system. Including water guide weirs, beam lamination gates, seepage dams, water collection tanks and electric heaters, reducing silt and salt content, and assisting evaporation through photovoltaic power generation plates.

Benefits of technology

It realizes efficient and low-cost freshwater preparation, reduces the risk of evaporation pool blockage, improves freshwater storage floor area ratio, adapts to water needs in different seasons, and has rapid construction and low construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116239248B_ABST
    Figure CN116239248B_ABST
Patent Text Reader

Abstract

The present application discloses a brackish water evaporation and utilization system in arid areas, which belongs to the technical field of brackish water resource utilization. The system includes a river channel, an inlet channel, an evaporation and utilization system, and an outlet channel. The inlet channel is arranged on the upstream convex bank of the river channel, and the outlet channel is arranged on the downstream of the river channel. An evaporation and utilization system is arranged between the inlet channel and the outlet channel, which is used to evaporate brackish water and collect fresh water. By taking water from the convex bank, using stacked beam gates to isolate sand, and using seepage dams to filter, the sand content of the diverted water is effectively reduced, the blockage of the evaporation pool is avoided, the effective volume ratio is improved, and the evaporation efficiency of brackish water is increased. The problem of insufficient water resources in arid areas is effectively solved. Fresh water can be prepared all year round without time restrictions, and the water production efficiency is high and the cost is low. Especially in the high water use period in summer, the auxiliary electric heating system can prepare a large amount of fresh water in a short time to meet the peak water demand.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of brackish water resource utilization, and in particular to a brackish water evaporation utilization system in arid areas. Background Art

[0002] Water resources are scarce in arid areas, and the development of unconventional water resources (such as brackish water, rainwater, dew, etc.) will become an important way for industrial and agricultural production in the region. In the arid areas of northwest my country, rivers flow through special geographical environments, leaching rocks and soils, and strong evaporation increases the salt content of water resources in natural rivers, resulting in the phenomenon that water cannot be used. Therefore, it is urgent to purify brackish water to alleviate the problem of water shortage in the arid areas of northwest China.

[0003] In order to purify brackish water, scholars have proposed many measures, such as electrolysis, ion membrane, freezing method, etc., which can realize the resource utilization of brackish water to a certain extent. However, it will cause high water production costs, inability to produce a large amount of fresh water in a short period of time, and complex processes. At the same time, water resources in arid areas are unevenly distributed, and the heavy rains in summer are strong, which can easily cause mudslides. The water body has a large amount of sediment, which can easily cause a large amount of sediment to accumulate in the evaporation pond and reduce the volume ratio. Summary of the invention

[0004] The purpose of this application is to propose a brackish water evaporation and utilization system in arid areas in order to solve the above-mentioned problems of low water production efficiency, complex procedures, high cost of preparing fresh water, high sediment content in natural rivers, and easy accumulation of large amounts of sediment in evaporation ponds.

[0005] In order to achieve the above purpose, this application adopts the following technical solutions:

[0006] An evaporation and utilization system for brackish water in arid areas, comprising a river channel, an inlet channel, an evaporation and utilization system and an outlet channel, wherein the inlet channel is arranged on the upstream convex bank of the river channel, the outlet channel is arranged on the downstream of the river channel, and an evaporation and utilization system is arranged between the inlet channel and the outlet channel for evaporating brackish water and collecting fresh water;

[0007] The evaporation utilization system comprises a drainage channel, a plurality of evaporation pools are arranged side by side on one side of the drainage channel, a confluence channel is arranged on one side of the evaporation pool, and a fresh water storage tank is arranged on one side of the confluence channel;

[0008] An arch shed is set up on the upper part of the evaporation pool, on which a transparent plastic film is laid, water collecting troughs are opened on the top of the walls on both sides of the evaporation pool inside the arch shed for collecting evaporated water, and rain collecting troughs are opened on the top of the walls on both sides of the evaporation pool outside the arch shed for collecting rainwater; the fresh water storage tank is used to store the fresh water collected by the water collecting trough and the rain collecting trough.

[0009] As a further description of the above technical solution:

[0010] The water inlet of the evaporation pool is provided with a second water inlet gate, the water outlet is provided with a second water outlet gate, the bottom and four walls of the evaporation pool are coated with a black coating, and the bottom of the evaporation pool is provided with a slope inclined towards the second water outlet gate.

[0011] As a further description of the above technical solution:

[0012] A water collection trough is also arranged at the tail of the water collection trough and the rainwater collection trough, and a water collection pipe is installed on the water collection trough, and the water collection pipe penetrates into the interior of the fresh water storage tank.

[0013] As a further description of the above technical solution:

[0014] The outlet channel is provided with a first regulating gate and an outlet gate, the diversion channel is provided with a second regulating gate matching the number of evaporation pools, the second regulating gate is arranged at a position far away from the second inlet gate, and a flushing channel connected to the outlet channel is also arranged at the end of the diversion channel.

[0015] As a further description of the above technical solution:

[0016] A salt water tank is also arranged on one side of the confluence channel where the fresh water tank is arranged. A salt water inlet gate is installed at the connection between the salt water tank and the confluence channel. A sand discharge gate is arranged at the end of the confluence channel. A cover plate is arranged on the top of the fresh water tank.

[0017] As a further description of the above technical solution:

[0018] The water inlet channel is provided with a water diversion weir, a stopcock, a seepage dam and a first water inlet gate in sequence from the entrance; the seepage dam comprises a symmetrically arranged crushed stone layer, a gravel layer, a sand and gravel layer and a fine sand layer, a metal mesh box is installed in the middle of the fine sand layers on both sides, and a biochar barrier is arranged inside the metal mesh box.

[0019] As a further description of the above technical solution:

[0020] A groove is provided on the water inlet channel, the bottom of the seepage dam is placed in the groove, and the depth of the groove is not less than 30 cm; a plurality of geogrids are staggeredly laid inside the crushed stone layer, gravel layer, sand and gravel layer and fine sand layer, and the length of the geogrids between different filter layers is not less than 15 cm.

[0021] As a further description of the above technical solution:

[0022] A plurality of high-pressure flushing pipes are arranged inside the gravel layer at the upstream side of the water inlet channel, and a plurality of high-pressure nozzles are evenly arranged on the high-pressure flushing pipes.

[0023] As a further description of the above technical solution:

[0024] The evaporation utilization system also includes an electric heating system, which includes a photovoltaic power generation panel arranged on one side of the evaporation pool and an electric heater arranged inside the evaporation pool.

[0025] In summary, due to the adoption of the above technical solution, the beneficial effects of this application are:

[0026] 1. In this application, by taking advantage of the abundant light and heat resources in arid areas, the evaporation and utilization of brackish water is realized, which effectively solves the problem of insufficient water resources in arid areas. Fresh water can be prepared all year round without time restrictions, and the water production efficiency is high and the cost is low. Especially in the high water consumption period in summer, with the auxiliary electric heating system, a large amount of fresh water can be prepared in a short time to meet the peak water demand.

[0027] 2. In this application, by taking water from the convex bank, using stacked beam gates to isolate sand, and filtering with seepage dams, the sand content of the diverted water is effectively reduced, the blockage of the evaporation pool is avoided, the effective volume ratio is improved, and the evaporation efficiency of brackish water is increased. The seepage dam includes symmetrically arranged crushed stone layers, gravel layers, sand and gravel layers, and fine sand layers. Metal mesh boxes are installed in the middle of the fine sand layers on both sides. Biochar interlayers are arranged inside the metal mesh boxes. The biochar interlayers can be replaced. While filtering sand, they absorb salt in the water body to a certain extent, reducing the salt content of the water entering the pool.

[0028] 3. The brackish water evaporation and utilization system of the present application can be quickly constructed in arid areas. Sand and gravel and other materials can be obtained locally, and the construction cost is low. At the same time, a salt water storage tank is set up to collect and utilize the residual high-salt water to prevent salt damage to downstream organisms, and it has a high application prospect. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 This is a schematic diagram of the floor plan of this application.

[0030] Figure 2 This is a schematic diagram of the cross-sectional structure of the applied seepage dam.

[0031] Figure 3 This is the schematic diagram of the metal mesh cage installation application.

[0032] Figure 4 This is the schematic diagram of the arch shed installation applied for.

[0033] Figure 5 This is a schematic diagram of the structure of the evaporation utilization system applied for.

[0034] In the figure:

[0035] 1. River channel; 2. Inlet channel; 21. Water diversion weir; 22. Stoplog gate; 23. Seepage dam; 231. Gravel layer; 232. Gravel layer; 233. Sand and gravel layer; 234. Fine sand layer; 235. Geogrid; 236. Biochar barrier; 237. High-pressure flushing pipe; 238. Metal mesh box; 24. First inlet gate; 3. Evaporation pond; 31. Second inlet gate; 32. Second outlet gate; 33. Arch shed; 3 4. Water collecting trough; 35. Rainwater collecting trough; 36. Water collecting trough; 37. Water collecting pipe; 4. Outlet channel; 41. First regulating gate; 42. Outlet gate; 5. Fresh water storage tank; 51. Cover plate; 6. Salt water storage tank; 61. Salt water inlet gate; 7. Diversion channel; 71. Second regulating gate; 8. Converging channel; 81. Sand discharge gate; 9. Flushing channel; 10. Electric heating system; 101. Photovoltaic power generation panel; 102. Electric heater. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0037] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. Unless otherwise specified, "multiple" and "several" mean two or more, and the terms "first", "second", "third", etc. are used for descriptive purposes only and cannot be understood as indicating or implying relative importance. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0038] See also Figure 1-5 , this application provides a technical solution:

[0039] The brackish water evaporation utilization system in arid areas includes a river channel 1, an inlet channel 2, an evaporation utilization system and an outlet channel 4. The inlet channel 2 is arranged on the upstream convex bank of the river channel 1. The water flow rate on the convex bank is slow and sediment is deposited. The inlet channel 2 is arranged on the convex bank to take the upper clean water, reduce the amount of sediment drawn, and play a role in primary sediment reduction. The outlet channel 4 is arranged downstream of the river channel 1. An evaporation utilization system is arranged between the inlet channel 2 and the outlet channel 4 to evaporate the brackish water and collect fresh water;

[0040] The evaporation utilization system includes a drainage channel 7, a plurality of evaporation pools 3 are arranged side by side on one side of the drainage channel 7, a confluence channel 8 is arranged on one side of the evaporation pools 3, and a fresh water storage tank 5 is arranged on one side of the confluence channel 8; the water introduced through the inlet channel 2 is replenished into the evaporation pool 3 through the drainage channel 7, and the high-salt residual water after evaporation is discharged through the confluence channel 8.

[0041] An arch shed 33 is set up on the upper part of the evaporation pool 3, and a transparent plastic film is laid on the arch shed 33. A water collecting trough 34 is opened on the top of the walls on both sides of the evaporation pool 3 inside the arch shed 33 to collect evaporated water, and a rain collecting trough 35 is opened on the top of the walls on both sides of the evaporation pool 3 outside the arch shed 33 to collect rainwater; the fresh water storage tank 5 is used to store the fresh water collected by the water collecting trough 34 and the rain collecting trough 35. The arid area has abundant light and heat resources. By setting up the arch shed 33, the evaporation of brackish water is achieved. The inner wall of the plastic film is preferably coated with a hydrophobic coating, and the evaporated water vapor can be quickly collected into the inside of the water collecting trough 34 after condensing into water droplets. Rainwater resources are also rare in arid areas and extremely precious. Compared with evaporation water production, it is of great significance to collect and utilize rainwater resources brought by short-term heavy rainfall. It is best to set up a circle of isolation nets around the evaporation utilization system to prevent wild animals, tumbleweeds, etc. from damaging the plastic film.

[0042] In the embodiment of the present invention:

[0043] The water inlet of the evaporation pool 3 is provided with a second water inlet gate 31, and the water outlet is provided with a second water outlet gate 32. The bottom and four walls of the evaporation pool 3 are coated with a black coating, and the bottom of the evaporation pool 3 is provided with a slope inclined to the second water outlet gate 32. The second water inlet gate 31 and the second water outlet gate 32 are provided. The gates are closed at ordinary times, and the evaporation pool 3 forms a closed space, which is convenient for heat collection and evaporation. When the salinity of the water in the pool is high, water is replenished and replaced, and the corresponding gates are opened. The slope is provided to facilitate the flow of water, and the slope is generally 1%-2%.

[0044] In the embodiment of the present invention:

[0045] The tail of the water collecting trough 34 and the rain collecting trough 35 is also provided with a water collecting trough 36, and a water collecting pipe 37 is installed on the water collecting trough 36, and the water collecting pipe 37 penetrates the interior of the fresh water storage tank 5. The water collecting trough 36 is provided to collect the collected fresh water, and then store it in the fresh water storage tank 5 through the water collecting pipe 37. It should be noted that, in order to facilitate the convergence of water bodies, the cross section of the water collecting trough 36 is preferably larger than the cross section of the two groups of water collecting troughs 34 and rain collecting troughs 35, and the downward inclination angle of the water collecting pipe 37 is not less than 15°. It should also be noted that at the connection between the rain collecting trough 35 and the water collecting trough 36, it is best to set 1-2 layers of filter screens. The mesh number of the filter screen is selected according to actual needs, so that the silt in the air and the fallen leaves blown onto the plastic film by the wind can be filtered, so as to avoid clogging the water collecting trough 36 and prevent the silt from entering the fresh water storage tank 5. A layer of grates is provided on the upper part of the rain collecting trough 35, which plays a filtering role on the one hand and is convenient for the staff to walk and inspect on the other hand.

[0046] In the embodiment of the present invention:

[0047] The outlet channel 4 is provided with a first control gate 41 and an outlet gate 42. The first control gate 41 prevents the backflow of the river water, and the outlet gate 42 is for controlling the discharge of tailwater. The diversion channel 7 is provided with a second control gate 71 matching the number of evaporation pools 3. The second control gate 71 is arranged at a position far away from the second inlet gate 31. Each second control gate 71 and each second inlet gate 31 control the water replenishment of an evaporation pool 3. The diversion channel 7 is preferably set as a reverse slope with a slope of 1%-2%, which slows down the flow rate of the water body, allows a small amount of sediment in the water body to settle again, and reduces the sediment content entering the evaporation pool 3. A flushing channel 9 connected to the outlet channel 4 is also provided at the end of the diversion channel 7. When there is a lot of sediment inside the diversion channel 7, all second control gates 71 are opened for flushing, and the flushing water is discharged into the flushing channel 9.

[0048] In the embodiment of the present invention:

[0049] A salt water reservoir 6 is also provided on one side of the confluence channel 8 where the fresh water reservoir 5 is provided. A salt water inlet gate 61 is installed at the connection between the salt water reservoir 6 and the confluence channel 8. The residual water after evaporation enters the salt water reservoir 6 for storage, and can be used for salt extraction according to actual needs, while preventing high salt water from flowing downstream and threatening aquatic organisms. A sand discharge gate 81 is provided at the end of the confluence channel 8. After working for a period of time, although the pre-system has a good effect on the silt filtration, it is inevitable that a small amount of silt will still exist in the evaporation pool 3. At this time, the evaporation pool 3 needs to be flushed, and the flushed silt is discharged downstream with the water flow through the sand discharge gate 81. A cover plate 51 is provided on the top of the fresh water reservoir 5, which can effectively prevent the evaporation of fresh water. The fresh water reservoir 5 is set with corresponding sizes according to needs, and the stored fresh water is transported to the water terminal through a water pipeline and a water pump for industrial and agricultural production.

[0050] In the embodiment of the present invention:

[0051] The water inlet channel 2 is provided with a water diversion weir 21, a stopcock 22, a seepage dam 23 and a first water inlet sluice 24 in sequence from the entrance; the water diversion weir 21 plays a role in diversion, and the stopcock 22 is the second barrier to reduce the sediment content of the diverted water. By setting the opening and closing degree of the stopcock 22, the sediment is intercepted, so that a large amount of sediment is intercepted outside the stopcock 22. The seepage dam 23 includes a symmetrically arranged crushed stone layer 231, a gravel layer 232, a sand and gravel layer 233 and a fine sand layer 234, and a metal mesh box 238 is installed in the middle of the fine sand layer 234 on both sides, and a biochar barrier 236 is arranged inside the metal mesh box 238. The seepage dam 23 is the third barrier to reduce the sand content of the diverted water. Through the layered arrangement of crushed stone layer 231, gravel layer 232, sand and gravel layer 233, fine sand layer 234 and biochar interlayer 236, not only the sediment is effectively intercepted, but also the salinity of the water body is reduced, so that the salt content of the diverted water itself is reduced and the subsequent evaporation efficiency is improved. To ensure the adsorption effect, the thickness of the crushed stone layer 231, gravel layer 232, sand and gravel layer 233, fine sand layer 234 and biochar interlayer 236 is not less than 30cm, and the particle size decreases layer by layer. By setting up a metal mesh box 238, it is convenient to replace the biochar interlayer 236. When the biochar adsorption tends to be saturated, the system continues to function by replacing the biochar interlayer 236.

[0052] In the embodiment of the present invention:

[0053] A groove is provided on the water inlet channel 2, and the bottom of the seepage dam 23 is placed in the groove. The depth of the groove is not less than 30 cm. The groove is provided to improve the stability of the seepage dam 23, so that the dam foundation is buried below the concrete structure of the floor of the water inlet channel 2. A plurality of geogrids 235 are staggeredly laid inside the crushed stone layer 231, the gravel layer 232, the sand and stone layer 233 and the fine sand layer 234. The length of the geogrid 235 between different filter layers is not less than 15 cm. By providing the geogrid 235, each filter layer is connected as a whole, thereby improving the overall stability. In addition, a layer of plastic-coated metal mesh can also be laid on the outside of the crushed stone layer 231 according to actual needs to improve the overall anti-scouring and stability capabilities.

[0054] In the embodiment of the present invention:

[0055] A plurality of high-pressure flushing pipes 237 are arranged inside the gravel layer 232 on the upstream side of the water inlet channel 2, and a plurality of high-pressure nozzles are evenly arranged on the high-pressure flushing pipes 237. The upstream is easily blocked by sediment, which reduces the water flow capacity. The high-pressure flushing pipes 237 are arranged, and the high-pressure nozzles are combined to flush the sediment accumulated in the gravel layer 232 and the crushed stone layer 231, thereby improving the water flow capacity of the seepage dam 23.

[0056] In the embodiment of the present invention:

[0057] The evaporation utilization system also includes an electric heating system 10, which includes a photovoltaic panel 101 arranged on one side of the evaporation pool 3 and an electric heater 102 arranged inside the evaporation pool 3. The arid area has abundant light and heat resources, and evaporation in summer can meet the water demand, but in the cold winter or spring and autumn seasons, the amount of water obtained by evaporation alone is small. Therefore, with the help of the electric heating system 10, evaporation can be assisted by electric heating, so that a large amount of fresh water can be quickly obtained in cold periods.

[0058] Working principle:

[0059] During operation, the natural river water is diverted through the water diversion weir 21 to allow the natural river water to enter the water inlet channel 2, the water flow rate entering the water inlet channel 2 is slowed down, a large amount of silt is deposited in front of the stoplog gate 22, and the upper clean water is filtered through the seepage dam 23 at multiple stages, at which time most of the silt and a part of the salt can be filtered out. After the seepage dam 23 has been in operation for a period of time, a crane is used to replace the biochar barrier 236, and the high-pressure nozzle on the high-pressure flushing pipe 237 is used to flush the silt deposited in the gravel layer 232 and the crushed stone layer 231. The filtered water enters the diversion channel 7 through the first water inlet gate 24. By controlling the opening and closing of the second regulating gate 71 and the second water inlet gate 31, the water replenishment and water replacement of the evaporation pool 3 and the flushing of the diversion channel 7 are realized. The flushing water of the diversion channel 7 is discharged to the outlet channel 4 through the flushing channel 9. The water in the evaporation pool 3 evaporates and condenses into the water collection tank 34. The rainfall is collected into the rainwater collection tank 35. The water in the water collection tank 34 and the rainwater collection tank 35 enters the water collection tank 36 through the tail, and then enters the interior of the fresh water storage tank 5 through the water collection pipe 37. The residual water of the evaporation pool 3 is discharged into the confluence channel 8, and the high-salt water enters the salt water storage tank 6 through the confluence channel 8 for utilization. The sediment flushing water of the evaporation pool 3 is discharged to the outlet channel 4 through the confluence channel 8.

[0060] The above is only a preferred specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can make equivalent substitutions or changes within the technical scope disclosed in the present application according to the technical solution and application concept of the present application, which should be covered by the protection scope of the present application.

Claims

1. A brackish water evaporation utilization system in arid areas, comprising a river channel (1), an inlet channel (2), an evaporation utilization system and an outlet channel (4), wherein the inlet channel (2) is arranged on an upstream convex bank of the river channel (1), the outlet channel (4) is arranged downstream of the river channel (1), and an evaporation utilization system is arranged between the inlet channel (2) and the outlet channel (4) for evaporating the brackish water to collect fresh water; The evaporation utilization system comprises a drainage channel (7), a plurality of evaporation ponds (3) are arranged side by side on one side of the drainage channel (7), a confluence channel (8) is arranged on one side of the evaporation ponds (3), and a fresh water storage tank (5) is arranged on one side of the confluence channel (8); An arch shed (33) is erected on the upper part of the evaporation pool (3), and a transparent plastic film is laid on the arch shed (33). Water collecting troughs (34) are provided on the tops of the walls on both sides of the evaporation pool (3) inside the arch shed (33) for collecting evaporated water, and rain collecting troughs (35) are provided on the tops of the walls on both sides of the evaporation pool (3) outside the arch shed (33) for collecting rainwater. The fresh water storage tank (5) is used to store the fresh water collected by the water collecting troughs (34) and the rain collecting troughs (35); The water inlet channel (2) is provided with a water diversion weir (21), a stopcock (22), a seepage dam (23) and a first water inlet sluice (24) in sequence from the inlet; the seepage dam (23) comprises a crushed stone layer (231), a gravel layer (232), a sandstone layer (233) and a fine sand layer (234) which are symmetrically arranged, a metal mesh box (238) is installed in the middle of the fine sand layers (234) on both sides, and a biochar barrier layer (236) is arranged inside the metal mesh box (238); The water inlet channel (2) is provided with a groove, the bottom of the seepage dam (23) is placed in the groove, and a plurality of geogrids (235) are alternately laid inside the crushed stone layer (231), the gravel layer (232), the sand and stone layer (233), and the fine sand layer (234); A plurality of high-pressure flushing pipes (237) are arranged inside the gravel layer (232) on the upstream side of the water inlet channel (2), and a plurality of high-pressure spray nozzles are evenly arranged on the high-pressure flushing pipes (237).

2. The system for evaporating and utilizing brackish water in arid areas according to claim 1, characterized in that: The water inlet of the evaporation pond (3) is provided with a second water inlet gate (31), and the water outlet is provided with a second water outlet gate (32). The bottom and four walls of the evaporation pond (3) are coated with a black coating, and the bottom of the evaporation pond (3) is provided with a slope inclined towards the second water outlet gate (32).

3. The system for evaporating and utilizing brackish water in arid areas according to claim 1, characterized in that: A water collection trough (36) is further provided at the tail of the water collection trough (34) and the rainwater collection trough (35), and a water collection pipe (37) is installed on the water collection trough (36), and the water collection pipe (37) penetrates into the interior of the fresh water storage tank (5).

4. The system for evaporating and utilizing brackish water in arid areas according to claim 2, characterized in that: The outlet channel (4) is provided with a first regulating gate (41) and an outlet gate (42), the diversion channel (7) is provided with a second regulating gate (71) matching the number of evaporation ponds (3), the second regulating gate (71) is arranged at a position away from the second inlet gate (31), and a flushing channel (9) connected to the outlet channel (4) is also provided at the end of the diversion channel (7).

5. The system for evaporating and utilizing brackish water in arid areas according to claim 1, characterized in that: A salt water storage tank (6) is also provided on one side of the confluence channel (8) where the fresh water storage tank (5) is provided. A salt water inlet gate (61) is installed at the connection between the salt water storage tank (6) and the confluence channel (8). A sand discharge gate (81) is provided at the end of the confluence channel (8). A cover plate (51) is provided on the top of the fresh water storage tank (5).

6. The system for evaporating and utilizing brackish water in arid areas according to claim 1, characterized in that: The depth of the groove is not less than 30 cm; the length of the geogrid (235) between different filter layers is not less than 15 cm.

7. The system for evaporating and utilizing brackish water in arid areas according to claim 1, characterized in that: The evaporation utilization system further comprises an electric heating system (10), wherein the electric heating system (10) comprises a photovoltaic power generation panel (101) arranged on one side of the evaporation pool (3) and an electric heater (102) arranged inside the evaporation pool (3).