Superimposed arrangement method of clear water pool and building with consideration of landscape
By building an annular building on the roof of the water purification plant's clear water pool and setting ventilation holes and landscape water sources, the problem of large land occupation and high landscape requirements of the water pool is solved, and the effect of land conservation and landscape improvement is achieved.
Patent Information
- Application Number
- CN202310683403.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-09
- Publication Date
- 2025-08-12
- Estimated Expiration
- 2043-06-09
AI Technical Summary
The water purification plant's clear water pool covers a large area and, when the land is tight and the landscape requirements are high, how to effectively utilize the upper space of the clear water pool to reduce project land and investment, while achieving ecological and social benefits.
The circular building is built on the roof of the clear water pool, the side walls and roof panels of the rectangular clear water pool are used as reinforced concrete structures, and the inner ring of the building is tangent to the side wall of the clear water pool, ventilation holes and ventilation ducts are installed to ensure air circulation, and the tail water of the clear water pool is used as the landscape water source, and a landscape pool and green belt are installed on the roof.
It has achieved the superposition of buildings on limited land, saving project land, reducing investment, and improving landscape effects and achieving ecological and social benefits.
Smart Images

Figure CN116657739B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the construction of a water purification plant, and in particular to a method for superimposing a clear water pool and buildings while taking landscape into consideration. Background Art
[0002] Water purification plant projects are typically located within urban construction land, which is relatively limited in area. As people's demands for water quality increase, more water treatment processes are required, and the number of water treatment structures has increased. Clear water tanks occupy the largest area of water plant structures.
[0003] The clear water tank is a regulating structure in the urban water supply system that regulates the uniform water supply of the water plant and meets the uneven water use of users. It is used to store the purified water in the water plant to regulate the difference between the water production and water supply of the water plant, and to meet the chlorination contact time. The general practice of the clear water tank is to cover the top with soil and greening to play a role in heat preservation and sun protection, and set air vents at appropriate positions on the top of the clear water tank. With the development of social economy, modern water purification plants have increasingly emphasized ecology and greenness, and have even become urban science popularization bases. Therefore, under the premise of being restricted by the water plant land use indicators and ensuring the landscape effect of the water plant and the structure of the clear water tank, how to use the superimposed buildings on the top of the clear water tank is an important issue to be studied by technical personnel in this field. Summary of the Invention
[0004] The purpose of the present invention is to provide a method for superimposing a clear water pool and a building while taking into account the landscape, so as to save land resources and achieve ecological and social benefits.
[0005] To achieve the above object, the present invention adopts the following technical solutions:
[0006] The method for superimposing a clear water pool and a building while taking into account the landscape of the present invention comprises the following steps:
[0007] Step 1: excavate a foundation pit according to design requirements and construct a rectangular clear water tank in the foundation pit; the side walls, bottom plate and top plate of the rectangular clear water tank adopt a reinforced concrete tank structure, and the guide wall in the clear water tank adopts a concrete wall as a support for the top plate;
[0008] Step 2: constructing an annular building on the top plate; the inner ring structural columns of the annular building are supported on the bottom plate; the outer ring centerline of the annular building is tangent to the side wall of the rectangular clear water tank, the outer ring structural columns located at the tangent position and the side wall of the clear water tank are an integrated reinforced concrete structure, and the remaining outer ring structural columns are supported on the bottom plate;
[0009] Step 3, in order to ensure the circulation of air inside the clear water tank, a ventilation hole is opened on the top plate outside the annular building, a ventilation pipe is vertically arranged upward at the ventilation hole, and a shower-shaped dust cover is arranged at the upper pipe mouth of the ventilation pipe.
[0010] Optionally, an observation port is provided on the top plate located in the inner circle of the annular building, and the observation port is sealed by tempered glass.
[0011] Optionally, a landscape pool and a green belt are provided on the top plate located in the inner circle of the annular building.
[0012] Optionally, the inner and outer ring structural columns located on the bottom plate of the clear water tank are cylinders to reduce water flow resistance in the clear water tank.
[0013] The advantage of the present invention is that when the land use indicators of the water purification plant are limited and the landscape requirements are high, and it is impossible to build a traditional clear water pool, the upper space of the clear water pool with the largest area is used to superimpose buildings, and the tail water is used as the landscape water source, so as to reduce the project area, save project investment, and achieve ecological and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the plan layout of the annular building described in the present invention.
[0015] Figure 2 yes Figure 1 AA section structure diagram.
[0016] Figure 3 It is a structural schematic diagram of the ventilation pipe and the shower-shaped dust cover of the present invention.
[0017] Figure 4 It is a schematic diagram of the arrangement of the guide wall in the clear water tank of the present invention.
[0018] Figure 5 This is an effect diagram of the superposition of the clear water pool and the annular building described in the present invention. DETAILED DESCRIPTION
[0019] The following describes an embodiment of the present invention in detail with reference to the accompanying drawings. This embodiment is implemented based on the technical solution of the present invention, and provides a detailed implementation method and specific operation process. However, the protection scope of the present invention is not limited to the following embodiment.
[0020] It should be noted that, in the present invention, unless otherwise expressly specified or limited, the terms "installed," "connected," and "connected" should be understood in a broad sense. For example, they may refer to fixed, detachable, or integral connections; mechanical or electrical connections; direct or indirect connections through an intermediate medium; and internal communication between two components. Those skilled in the art will understand the specific meanings of the above terms in the present invention based on specific circumstances.
[0021] like Figure 1-5As shown, the method for superimposing a clear water pool and a building while taking into account the landscape of the present invention includes the following steps:
[0022] Step 1: excavate a foundation pit according to the design requirements and construct a rectangular clear water tank in the foundation pit; the side wall 1, bottom plate 2 and top plate 3 of the rectangular clear water tank adopt a reinforced concrete tank structure, and the guide wall 4 in the clear water tank adopts a concrete wall and serves as a support for the top plate 3;
[0023] Step 2: construct an annular building on the top plate 3, such as a water and natural science museum 12. Of course, other science museums can also be constructed. The inner ring structural columns 5 of the annular building are supported on the bottom plate 2. The center line of the outer ring of the annular building is tangent to the side wall 1 of the rectangular clear water tank. The outer ring structural columns 5 at the tangent point and the side wall 1 of the clear water tank are an integrated reinforced concrete structure. The remaining outer ring structural columns 5 are supported on the bottom plate 2.
[0024] In order to reduce the water flow resistance in the clear water tank, the inner and outer ring structural columns are cylindrical;
[0025] Step 3: Open a ventilation hole on the top plate 3 outside the annular building, set a ventilation pipe 6 vertically upward at the ventilation hole, and set a shower-shaped dust cover 7 at the top of the ventilation pipe 6. Figure 3 As shown, this not only ensures the air circulation inside the clear water pool, but also beautifies the environment and integrates with the surrounding environment;
[0026] In order to make full use of the tail water of the clear water pool, a landscape pool 8 and a green belt 9 are set on the top plate 3 located in the inner circle of the annular building, and the tail water of the clear water pool is introduced into the landscape pool 8 and the green belt 9 through pipes.
[0027] In order to enable visitors to overlook the surrounding landscape pools and green belts, a walkway 10 is built from the ground along the slope to the roof of the circular building; a manhole 11 of the clear water pool is arranged in the circular building.
Claims
1. A method for superimposing a clear water pool and a building while taking into account the landscape, characterized by: The steps include: Step 1: excavate a foundation pit according to design requirements and construct a rectangular clear water tank in the foundation pit; the side walls, bottom plate and top plate of the rectangular clear water tank adopt a reinforced concrete tank structure, and the guide wall in the clear water tank adopts a concrete wall and serves as a support for the top plate; Step 2: constructing an annular building on the top plate; the inner ring structural columns of the annular building are supported on the bottom plate; the outer ring centerline of the annular building is tangent to the side wall of the rectangular clear water tank, the outer ring structural columns located at the tangent position and the side wall of the clear water tank are an integrated reinforced concrete structure, and the remaining outer ring structural columns are supported on the bottom plate; Step 3: To ensure air circulation inside the clear water tank, a ventilation hole is opened on the top plate outside the annular building, a ventilation pipe is vertically arranged upward at the ventilation hole, and a shower-shaped dust cover is provided on the top of the ventilation pipe; An observation port is provided on the top plate located in the inner circle of the annular building and is sealed by tempered glass.
2. The method for superimposing a clear water pool and a building with consideration for landscape according to claim 1, characterized in that: A landscape pool and a green belt are arranged on the top plate located in the inner circle of the annular building, and the tail water of the clear water pool is introduced into the landscape pool and the green belt through pipelines.
3. The method for superimposing a clear water pool and a building with consideration for landscape according to claim 1, characterized in that: The inner and outer ring structural columns located on the bottom plate of the clear water tank are cylinders.
Citation Information
Patent Citations
Clean water tank guide wall construction structure
CN204356799U
Water pool structure is advanced to piped water supply engineering