Method and System for Reporting Project Problem Information

Through the project problem information reporting system, preset strategies are used to automatically analyze and deal with project problems, and the problem of untimely reporting of project problems is solved, and efficient and accurate solution generation and process management are achieved.

CN116823140BActive Publication Date: 2025-07-11HUATENG JIANXIN TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310441459.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-04-21
Publication Date
2025-07-11
Estimated Expiration
2043-04-21

AI Technical Summary

Technical Problem

The existing reporting methods for engineering project problems cannot be guaranteed to be solved in a timely manner, resulting in unsmooth project processes and cumbersome and inefficient processing.

Method used

The project problem information is passed to the upper-level equipment end through the lower-level equipment end, and the preset project problem solving strategy is used for automatic analysis and processing, a solution is generated, and awaiting confirmation within the preset time; if it is not confirmed, it will be automatically reported to the upper-level equipment end for processing, reducing manual intervention.

Benefits of technology

It improves the timeliness and accuracy of handling project problems, reduces the workload of manual processing, ensures that project problems are solved in a timely manner, and ensures that the process is carried out in an orderly manner.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116823140B_ABST
    Figure CN116823140B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and a system for reporting project problem information. The method includes: a lower-level device terminal sends the project problem information to be solved edited by a project leader to the upper-level device terminal of the upper-level person in charge; the upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a processing result of the project problem information, and notifies the upper-level person in charge of the processing result of the project problem information; the upper-level device terminal determines whether the upper-level person in charge edits and confirms the project problem solution based on the processing result of the project problem information within a preset time period; if not, the upper-level device terminal reports the project problem information to the upper-level device terminal of the upper-upper-level person in charge for the upper-upper-level person in charge to process; if so, the upper-level device terminal returns the project problem solution to the lower-level device terminal. The present invention can ensure that project problems are processed in a timely manner and ensure the orderly progress of the project process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing, and particularly to a method and system for reporting problem information of engineering projects. Background Art

[0002] With the construction of various projects such as civil engineering, construction engineering, and installation engineering, various engineering projects have emerged. An engineering project takes a building or a structure as the target output, and needs to be completed within a certain time, in accordance with a certain procedure, at a certain cost, and should meet the quality requirements. In order to ensure the safety of the target output of the engineering project, it is usually necessary to conduct an acceptance inspection on the target output to avoid potential safety hazards due to quality problems.

[0003] Currently, during the implementation of the entire engineering project, the project leader can supervise the progress of the engineering project and also control the quality of the target output. The project leader records the problems that do not meet the quality requirements of the engineering project and uploads them to the system to notify the superior unit for handling.

[0004] However, the current method of reporting engineering project problems only serves as an information push, and cannot ensure that engineering project problems are resolved in a timely manner. Moreover, engineering project problems need to be manually analyzed and processed by relevant personnel, which is a cumbersome process and has low efficiency. Therefore, the existing method of reporting engineering project problems cannot guarantee the orderly progress of the engineering project process. Summary of the Invention

[0005] Embodiments of the present invention provide a method and system for reporting problem information of engineering projects, which can ensure that engineering project problems are processed in a timely manner and guarantee the orderly progress of the engineering project process.

[0006] An embodiment of the present invention provides a method for reporting problem information of engineering projects, including:

[0007] The lower-level device terminal sends the project problem information edited by the project leader that needs to be solved to the upper-level device terminal of the upper-level person in charge;

[0008] The upper-level device terminal processes the project problem information based on a preset project problem solution strategy, obtains a project problem information processing result, and notifies the upper-level person in charge of the project problem information processing result;

[0009] The upper-level device terminal determines whether the upper-level person in charge edits and confirms a project problem solution based on the project problem information processing result within a preset time period;

[0010] If not, the upper-level device terminal reports the project problem information to the upper-level device terminal of the upper-upper-level person in charge for the upper-upper-level person in charge to process;

[0011] If so, the upper-level device terminal returns the project problem solution to the lower-level device terminal for the project person in charge to edit and confirm.

[0012] As an improvement to the above solution, the upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a project problem information processing result, including:

[0013] The upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information;

[0014] The upper-level device terminal searches for a project problem information processing strategy corresponding to the relevant project problem type in a preset project problem information processing strategy library based on the relevant project problem type; the project problem information processing strategy contains a content template of the project problem solution for each corresponding project problem type, and the content template of the project problem solution is pre-made and stored.

[0015] The upper-level device terminal processes the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result.

[0016] As an improvement to the above solution, the upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information, including:

[0017] The upper-level device terminal uses a keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with the sample keywords in a preset project problem type library, and obtains the relevant project problem types in the project problem information according to the fuzzy matching result.

[0018] As an improvement to the above solution, the upper-level device terminal processes the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result, including:

[0019] The upper-level device terminal extracts the content template of the project problem solution from the project problem information processing strategy;

[0020] The upper-level device terminal generates the content template of the project problem solution in the template form in response to the template form selected by the upper-level person in charge, so as to obtain a corresponding project problem information processing result.

[0021] As an improvement to the above solution, the template form includes at least one of the following: form, PPT, report document;

[0022] The preset time period is 12 hours, 24 hours or 72 hours.

[0023] Another embodiment of the present invention correspondingly provides an engineering project problem information reporting system, which includes: a lower-level device end, an upper-level device end and an upper-upper-level device end;

[0024] The lower-level device end is used to send the project problem information to be solved edited by the project leader to the upper-level device end of the upper-level person in charge;

[0025] The upper-level device end is used to process the project problem information based on a preset project problem solving strategy, obtain a project problem information processing result, and notify the upper-level person in charge of the project problem information processing result;

[0026] The upper-level device end is further used to judge whether the upper-level person in charge edits and confirms a project problem solution based on the project problem information processing result within a preset time period;

[0027] If not, the upper-level device end is further used to report the project problem information to the upper-upper-level device end of the upper-upper-level person in charge for the upper-upper-level person in charge to process;

[0028] If so, the upper-level device end is further used to return the project problem solution to the lower-level device end for the project leader to edit and confirm.

[0029] As an improvement of the above solution, the upper-level device end is specifically used for:

[0030] Using a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information;

[0031] Based on the relevant project problem types, search for project problem information processing strategies corresponding to the relevant project problem types in a preset project problem information processing strategy library; the project problem information processing strategy includes content templates of project problem solutions for each corresponding project problem type, and the content templates of the project problem solutions are pre-made and stored;

[0032] Based on the project problem information processing strategy, process the project problem information to obtain a corresponding project problem information processing result.

[0033] As an improvement of the above solution, the upper-level device end is more specifically used for:

[0034] Using a keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with sample keywords in a preset project problem type library, and obtaining the relevant project problem types in the project problem information according to the fuzzy matching result.

[0035] As an improvement to the above solution, the upper-level device terminal is more specifically used for:

[0036] Extract the content template of the project problem solution from the project problem information processing strategy;

[0037] Respond to the template form of the content template selected by the upper-level person in charge, generate the content template of the project problem solution in the template form, so as to obtain the corresponding project problem information processing result.

[0038] As an improvement to the above solution, the template form includes at least one of the following: form, PPT, report document;

[0039] The preset time period is 12 hours, 24 hours or 72 hours.

[0040] Compared with the prior art, one of the technical solutions in the above technical solutions has the following advantages:

[0041] When the project person in charge discovers a project problem, the project person in charge uses the lower-level device terminal to send the project problem information edited by the project person in charge to the upper-level device terminal of the upper-level person in charge; the upper-level device terminal processes the project problem information based on the preset project problem solution strategy to obtain the project problem information processing result, and notifies the upper-level person in charge of the project problem information processing result; the upper-level device terminal judges whether the upper-level person in charge edits and confirms the project problem solution based on the project problem information processing result within the preset time period; if not, the upper-level device terminal reports the project problem information to the upper-level device terminal of the upper-level person in charge of the upper-level person in charge for the upper-level person in charge to process; if so, the upper-level device terminal returns the project problem solution to the lower-level device terminal. Thus, it can be seen that the present invention can improve the timeliness and accuracy of project problem processing and reduce the workload of pure manual processing by using the preset project problem solution strategy to process the project problem information; at the same time, when the upper-level person in charge does not edit and confirm the project problem solution within the preset time period, the project problem information is automatically reported and notified to the upper-level person in charge of the upper-level person in charge for processing, so as to ensure that the engineering project problems are processed in time, and further ensure the orderly progress of the engineering project process. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 is a flowchart of a method for reporting engineering project problem information provided by an embodiment of the present invention;

[0043] Figure 2 is a structural diagram of a system for reporting engineering project problem information provided by an embodiment of the present invention. DETAILED DESCRIPTION OF THE INVENTION

[0044] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts shall fall within the protection scope of the present invention.

[0045] See Figure 1 , which is a schematic flowchart of a method for reporting project problem information provided by an embodiment of the present invention. The method includes steps S10 to S14:

[0046] S10, the lower-level device terminal sends the project problem information to be solved edited by the project leader to the upper-level device terminal of the upper-level leader.

[0047] Among them, when the project leader discovers a project problem, the project leader uses the lower-level device terminal to send the project problem information to be solved edited by the project leader to the upper-level device terminal of the upper-level leader. Specifically, the lower-level device terminal can be a smart phone, a tablet computer, a notebook computer, a desktop computer, etc. used by the project leader, which is not specifically limited herein. And the upper-level device terminal can be a smart phone, a tablet computer, a notebook computer, a desktop computer, etc. used by the upper-level leader of the project leader, which is not specifically limited herein. Among them, the upper-level leader can be a project manager.

[0048] S11, the upper-level device terminal processes the project problem information based on a preset project problem solving strategy, obtains a project problem information processing result, and notifies the upper-level leader of the project problem information processing result;

[0049] Among them, the upper-level device terminal stores or obtains various preset project problem solving strategies from the cloud. These project problem solving strategies are pre-developed based on a large amount of engineering project problem processing experience and are used to process different project problem information. For example, in engineering projects, there are problems such as structural component quality problems, construction period problems, budget overrun problems, etc. By pre-combing and using the existing manual experience to solve these problems, the basic content of the engineering problem solution can be pre-developed for each engineering problem, so as to form different project problem solving strategies.

[0050] S12, the upper-level device terminal determines whether the upper-level leader edits and confirms the project problem solution based on the project problem information processing result within a preset time period;

[0051] Among them, after obtaining the processing result of the project problem information, it is pushed and displayed for the review of the superior responsible person, so that the superior responsible person can further edit and confirm the project problem solution according to the specific project progress needs, so that the project problem solution can better meet the actual needs, rather than being completely formulated according to the preset template. For example, regarding the quality problem of structural components in an engineering project, the processing result of the project problem information obtained through the preset project problem solving strategy is: arrange xx department's yy personnel to repurchase the same structural components that meet the relevant standards within the zz time limit, where the name of the relevant standards, the dimensions and names of the structural components, etc. are pre-determined. However, xx department, yy personnel, and zz time limit can be edited and confirmed by the superior responsible person according to actual needs.

[0052] In addition, as an example, the preset time period can be set to 12 hours, 24 hours, 72 hours, etc. according to the time limit requirements for processing at different levels.

[0053] S13, if not, the upper-level device terminal reports the project problem information to the upper-level device terminal of the upper-upper-level responsible person for the upper-upper-level responsible person to handle;

[0054] Among them, the upper-upper-level responsible person can be the management manager of the project management department of the project, the general manager of the engineering management center of the entire project, or the general manager of the group, etc.

[0055] S14, if so, the upper-level device terminal returns the project problem solution to the lower-level device terminal for the project responsible person to edit and confirm.

[0056] In an embodiment of the present invention, when the project leader discovers a project problem, the project leader uses the subordinate device terminal to send the project problem information edited by the project leader that needs to be solved to the upper-level device terminal of the upper-level leader; the upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a project problem information processing result, and notifies the upper-level leader of the project problem information processing result; the upper-level device terminal determines whether the upper-level leader edits and confirms the project problem solution based on the project problem information processing result within a preset time period; if not, the upper-level device terminal reports the project problem information to the upper-upper-level device terminal of the upper-upper-level leader for the upper-upper-level leader to process; if so, the upper-level device terminal returns the project problem solution to the subordinate device terminal. Thus, it can be seen that the present invention can improve the timeliness and accuracy of project problem processing and reduce the workload of pure manual processing by using a preset project problem solving strategy to process the project problem information; at the same time, when the upper-level leader does not edit and confirm the project problem solution within the preset time period, the project problem information is automatically reported and notified to the upper-upper-level leader for processing, so as to ensure that engineering project problems are processed in a timely manner and further ensure the orderly progress of the engineering project process.

[0057] In one embodiment, the upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a project problem information processing result, including steps S110 - S112:

[0058] S110, the upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information;

[0059] Among them, the keyword fuzzy matching algorithm can be the Simhash algorithm or other existing relevant keyword fuzzy matching algorithms.

[0060] S111, the upper-level device terminal searches for a project problem information processing strategy corresponding to the relevant project problem type in a preset project problem information processing strategy library based on the relevant project problem type; the project problem information processing strategy contains content templates of project problem solutions for each corresponding project problem type, and the content templates of the project problem solutions are pre-made and stored.

[0061] S112, the upper-level device terminal processes the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result.

[0062] In one embodiment, more specifically, the upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information, including:

[0063] The upper-level device uses a keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with the sample keywords in the preset project problem type library, and obtains the relevant project problem types in the project problem information according to the fuzzy matching results.

[0064] Among them, different project problem keyword samples are preset in the project problem type library. By performing fuzzy matching on the keywords in the project problem information with the sample keywords in the preset project problem type library, the sample keyword of the project problem with the highest similarity can be obtained, and thus the relevant project problem types in the project problem information can be determined accordingly.

[0065] In one embodiment, the upper-level device processes the project problem information based on the project problem information processing strategy to obtain the corresponding project problem information processing result, including:

[0066] The upper-level device extracts the content template of the project problem solution from the project problem information processing strategy;

[0067] The upper-level device responds to the template form of the content template selected by the upper-level person in charge, generates the content template of the project problem solution in the template form, and thus obtains the corresponding project problem information processing result.

[0068] In this embodiment, by way of example, the template form includes at least one of the following: form, PPT, report document. The content template of the project problem solution in the corresponding template form can be generated according to the template form of the content template selected by the upper-level person in charge, which can meet the user's usage needs and greatly reduce the user's workload of document processing.

[0069] See Figure 2 , which is a schematic structural diagram of an engineering project problem information reporting device / terminal device provided by an embodiment of the present invention. An engineering project problem information reporting system provided by an embodiment of the present invention includes: a lower-level device 10, an upper-level device 11, and an upper-upper-level device 12;

[0070] The lower-level device 10 is used to send the project problem information to be solved edited by the project person in charge to the upper-level device 11 of the upper-level person in charge;

[0071] The upper-level device 11 is used to process the project problem information based on the preset project problem solution strategy to obtain the project problem information processing result, and notify the upper-level person in charge of the project problem information processing result;

[0072] The upper-level device terminal 11 is further configured to determine whether the upper-level person in charge edits and confirms the project problem solution based on the project problem information processing result within a preset time period;

[0073] If not, the upper-level device terminal 11 is further configured to report the project problem information to the upper-level device terminal 12 of the person in charge at the level above the upper-level person in charge for the person in charge at the level above the upper-level person in charge to process;

[0074] If so, the upper-level device terminal 11 is further configured to return the project problem solution to the lower-level device terminal for the project person in charge to edit and confirm.

[0075] In the embodiment of the present invention, when the project person in charge discovers a project problem, the project person in charge uses the lower-level device terminal to send the project problem information edited by the project person in charge that needs to be solved to the upper-level device terminal of the upper-level person in charge; the upper-level device terminal processes the project problem information based on a preset project problem solution strategy to obtain a project problem information processing result, and notifies the upper-level person in charge of the project problem information processing result; the upper-level device terminal determines whether the upper-level person in charge edits and confirms the project problem solution based on the project problem information processing result within a preset time period; if not, the upper-level device terminal reports the project problem information to the upper-level device terminal of the person in charge at the level above the upper-level person in charge for the person in charge at the level above the upper-level person in charge to process; if so, the upper-level device terminal returns the project problem solution to the lower-level device terminal. It can be seen that the present invention can improve the timeliness and accuracy of project problem processing and reduce the workload of pure manual processing by using a preset project problem solution strategy to process the project problem information; at the same time, when the upper-level person in charge does not edit and confirm the project problem solution within a preset time period, the project problem information is automatically reported and notified to the person in charge at the level above the upper-level person in charge for processing, so as to ensure that project problems are processed in a timely manner and further ensure the orderly progress of the project process.

[0076] As an improvement of the above solution, the upper-level device terminal is specifically configured to:

[0077] Use a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information;

[0078] Based on the relevant project problem types, search for project problem information processing strategies corresponding to the relevant project problem types in a preset project problem information processing strategy library; the project problem information processing strategy includes content templates of project problem solutions for each corresponding project problem type, and the content templates of the project problem solutions are pre-made and stored;

[0079] Process the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result.

[0080] As an improvement to the above solution, the upper-level device terminal is more specifically configured to:

[0081] Use the keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with the sample keywords in the preset project problem type library, and obtain the relevant project problem types in the project problem information according to the fuzzy matching results.

[0082] As an improvement to the above solution, the upper-level device terminal is more specifically configured to:

[0083] Extract the content template of the project problem solution from the project problem information processing strategy;

[0084] Respond to the template form of the content template selected by the upper-level person in charge, generate the content template of the project problem solution in the template form, so as to obtain the corresponding project problem information processing result.

[0085] As an improvement to the above solution, the template form includes at least one of the following: form, PPT, report document;

[0086] The preset time period is 12 hours, 24 hours or 72 hours.

[0087] It should be noted that the lower-level device terminal, the upper-level device terminal and the upper-upper-level device terminal described in the above invention embodiments may be computing devices such as a desktop computer, a notebook, a palm computer and a cloud server. These devices may include, but are not limited to, a processor and a memory. Those skilled in the art can understand that these devices also include more or fewer components, or combine certain components, or different components. For example, these devices may also include input and output devices, network access devices, buses, etc.

[0088] The so-called processor may be a central processing unit (CPU), or may also be other general-purpose processors, digital signal processors (DSPs), application specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc. The processor is the control center of these devices, and connects various parts of the entire device through various interfaces and lines.

[0089] The memory can be used to store the computer programs and / or modules. By running or executing the computer programs and / or modules stored in the memory, and invoking the data stored in the memory, the processor can implement various functions of these devices. The memory mainly includes a program storage area and a data storage area. Among them, the program storage area can store an operating system, application programs required for at least one function (such as a sound playback function, an image playback function, etc.); the data storage area can store data created according to the use of the mobile phone (such as audio data, phone book, etc.). In addition, the memory can include high-speed random access memory, and can also include non-volatile memory, such as a hard disk, memory, plug-in hard disk, smart media card (SMC), secure digital (SD) card, flash card, at least one magnetic disk storage device, flash device, or other volatile solid-state storage devices.

[0090] Among them, if the modules / units integrated in these devices are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, to implement all or part of the processes in the above method embodiments of the present invention, it can also be completed by a computer program instructing related hardware. The computer program can be stored in a computer-readable storage medium. When the computer program is executed by the processor, the steps of the above method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in the form of source code, object code, executable file, or some intermediate form, etc. The computer-readable medium can include: any entity or device capable of carrying the computer program code, recording medium, USB flash drive, mobile hard disk, magnetic disk, optical disc, computer memory, read-only memory (ROM), random access memory (RAM), electrical carrier signal, telecommunication signal, and software distribution medium, etc. It should be noted that the content included in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable medium does not include electrical carrier signals and telecommunication signals.

[0091] It should be noted that the device embodiments described above are merely illustrative. The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed to multiple network units. Some or all of the modules can be selected according to actual needs to achieve the purpose of the solution of this embodiment. In addition, in the attached drawings of the device embodiments provided by the present invention, the connection relationships between modules indicate that they have communication connections, which can be specifically implemented as one or more communication buses or signal lines. Those of ordinary skill in the art can understand and implement without creative efforts.

[0092] The above is the preferred embodiment of the present invention. It should be pointed out that for those of ordinary skill in the art, without departing from the principle of the present invention, several improvements and refinements can be made, and these improvements and refinements are also regarded as the protection scope of the present invention.

Claims

1. A method for reporting engineering project problem information, characterized in that, Including: The lower-level device terminal sends the project problem information edited by the project leader to the upper-level device terminal of the upper-level person in charge. The upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a project problem information processing result, and notifies the upper-level person in charge of the project problem information processing result; the upper-level device terminal is also used to generate a project problem solution in response to the editing confirmation of the upper-level person in charge. The upper-level device terminal determines whether the upper-level person in charge edits and confirms the project problem solution based on the project problem information processing result within a preset time period. If not, the upper-level device terminal reports the project problem information to the upper-upper-level device terminal of the upper-upper-level person in charge for the upper-upper-level person in charge to process. If so, the upper-level device terminal returns the project problem solution to the lower-level device terminal for the project leader to edit and confirm. The upper-level device terminal processes the project problem information based on a preset project problem solving strategy to obtain a project problem information processing result, including: The upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information. The upper-level device terminal searches in a preset project problem information processing strategy library for a project problem information processing strategy corresponding to the relevant project problem type based on the relevant project problem type; the project problem information processing strategy contains a content template of the project problem solution for each corresponding project problem type, and the content template of the project problem solution is pre-made and stored. The upper-level device terminal processes the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result. The upper-level device terminal uses a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information, including: The upper-level device terminal uses the Simhash keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with the sample keywords in a preset project problem type library, and obtains the relevant project problem types in the project problem information according to the fuzzy matching result. The upper-level device terminal processes the project problem information based on the project problem information processing strategy to obtain a corresponding project problem information processing result, including: The upper-level device terminal extracts the content template of the project problem solution from the project problem information processing strategy. The upper-level device terminal generates the content template of the project problem solution in the template form in response to the template form of the content template selected by the upper-level person in charge, so as to obtain a corresponding project problem information processing result.

2. The method for reporting project problem information according to claim 1, wherein The template form includes at least one of the following: form, PPT, report document; the preset time period is 12 hours, 24 hours or 72 hours.

3. An engineering project problem information reporting system, characterized in that Including: Lower-level device terminal, upper-level device terminal and upper-upper-level device terminal; The subordinate device terminal is used to send the information of the project problems to be solved edited by the project leader to the upper-level device terminal of the upper-level leader; The upper-level device terminal is used to process the project problem information based on a preset project problem solving strategy, obtain the processing result of the project problem information, and notify the upper-level leader of the processing result of the project problem information; the upper-level device terminal is also used to generate a project problem solution in response to the editing confirmation of the upper-level leader; The upper-level device terminal is also used to determine whether the upper-level leader edits and confirms the project problem solution based on the processing result of the project problem information within a preset time period; If not, the upper-level device terminal is also used to report the project problem information to the upper-level device terminal of the upper-upper-level leader for the upper-upper-level leader to process; If so, the upper-level device terminal is also used to return the project problem solution to the subordinate device terminal for the project leader to edit and confirm; The upper-level device terminal specifically is used for: Using a keyword fuzzy matching algorithm to analyze the relevant project problem types in the project problem information; Based on the relevant project problem types, searching for the project problem information processing strategies corresponding to the relevant project problem types in a preset project problem information processing strategy library; The project problem information processing strategy includes the content templates of the project problem solutions corresponding to each corresponding project problem type, and the content templates of the project problem solutions are pre-made and stored; Processing the project problem information based on the project problem information processing strategy to obtain the corresponding processing result of the project problem information; The upper-level device terminal is more specifically used for: Using the Simhash keyword fuzzy matching algorithm to perform fuzzy matching on each keyword in the project problem information with the sample keywords in a preset project problem type library, and obtaining the relevant project problem types in the project problem information according to the fuzzy matching result; The upper-level device terminal is more specifically used for: Extracting the content template of the project problem solution from the project problem information processing strategy; Responding to the template form of the content template selected by the upper-level leader, generating the content template of the project problem solution in the template form, so as to obtain the corresponding processing result of the project problem information.

4. The engineering project problem information reporting system according to claim 3, wherein, The template form includes at least one of the following: form, PPT, report document; the preset time period is 12 hours, 24 hours or 72 hours.