A time-segmented continuous rolling clearing system for power grid trading

By using a time-segmented continuous rolling clearing system and employing a high-low matching method to automatically match the two parties in a power grid transaction, the problem of low efficiency in quantity and price consultation in existing technologies has been solved, achieving efficient automation and rapid price matching in power grid transactions.

CN116862715BActive Publication Date: 2026-11-17NORTHWEST BRANCH OF STATE GRID POWER GRID CO
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202310859956.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-13
Publication Date
2026-11-17
Estimated Expiration
2043-07-13

AI Technical Summary

Technical Problem

In the existing power grid trading system, the efficiency of quantity and price consultation is low and the degree of automation is insufficient, resulting in low trading efficiency.

Method used

The system adopts a time-segmented continuous rolling clearing system, including a central processing module, an application review module, a one-way bid matching and clearing module, and a monthly rolling clearing module. It automatically matches the two parties in a transaction using a high-low matching method, generates a transaction notification, and realizes automated bid matching and rolling clearing for the power grid company.

Benefits of technology

It has improved the efficiency and automation of power grid transactions, reduced human intervention, enabled rapid bid acquisition and automated matching between power grid companies, and optimized transaction organization and power resource allocation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116862715B_ABST
    Figure CN116862715B_ABST
Patent Text Reader

Abstract

This invention discloses a time-segmented continuous rolling clearing system for power grid transactions, including a central processing module. The central processing module is signal-connected to a declaration and review module, a one-way bid matching and clearing module, and a monthly rolling clearing module. In the declaration and review module, regional power grid companies declare their short-term intended power transmission prices and upper limits for power transmission volume, as well as their intended power purchase prices and upper limits for power purchase volume, for the following month. Administrators review these declarations, and data that meets specifications is marked as approved. The one-way bid matching and clearing module converts the prices declared by each province to the power purchase node according to the power transmission side price and then matches transactions using a high-low matching method. The monthly rolling clearing module performs centralized bid matching based on the one-way power transmission prices and one-way power purchase prices adjusted by each province within the month. It calculates the eligible trading parties using the high-low matching method, prioritizes them according to price, and generates the latest transaction notification. This invention improves the efficiency and automation of power grid transactions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the technical field of power trading systems, and particularly relates to a time-segmented continuous rolling clearing system for power grid trading. Background Technology

[0002] Grid trading refers to the process of balancing supply and demand and transferring electricity in the electricity market. Time-of-use (TOU) continuous rolling clearing is a market mechanism for grid trading that combines market participants' bids with grid load conditions to determine the optimal match between electricity volume and price, thereby achieving efficient and fair electricity trading. Specifically, TOU divides the electricity market into different time periods. Within each time period, electricity market participants (such as power plants and users) submit corresponding bids based on their capacity and demand. The grid management authority then uses a clearing algorithm to calculate the electricity volume and corresponding clearing price for each time period based on the current grid load and participants' bids. This ensures supply and demand balance in each time period and determines market prices in a transparent manner. Through TOU continuous rolling clearing, the electricity market can achieve dynamic supply and demand balance, improve market efficiency, and promote the effective allocation of electricity resources. Simultaneously, this system can support the large-scale integration of renewable energy sources, as it can flexibly adjust according to the fluctuation characteristics of renewable energy and market demand, ensuring the stable operation of the grid.

[0003] In existing technologies, it is usually necessary to consult each other about quantity and price via telephone or email, and then match them after obtaining the quantity and price information from each province. This is inefficient and has a low degree of automation. Summary of the Invention

[0004] To address the problems existing in the prior art, this invention provides a time-segmented continuous rolling clearing system for power grid transactions, which has the advantages of high efficiency and high degree of automation. It solves the problems of low efficiency and low degree of automation in the prior art, which usually requires mutual consultation on quantity and price by telephone or email, and then matching after obtaining the quantity and price provided by each province.

[0005] The present invention is implemented as follows: a time-segmented continuous rolling clearing system for power grid transactions, including a central processing module, wherein the central processing module is signal-connected to an application review module, a one-way bid matching clearing module, and a monthly rolling clearing module;

[0006] In the application and review module, each regional power grid company submits its short-term intended power transmission price and upper limit for power transmission, as well as its intended power purchase price and upper limit for power purchase for the following month. The administrator reviews the application and marks it as approved once the data meets the specifications.

[0007] The one-way bid matching and clearing module converts the bid prices submitted by each province to the power purchaser node according to the power supply side price and then uses the high-low matching method to match and trade.

[0008] The monthly rolling clearing module conducts centralized bidding and matching based on the one-way power transmission price and one-way power purchase price adjusted by each province within the month. It calculates the eligible trading parties according to the high-low matching method, prioritizes them according to price, and generates the latest transaction notification.

[0009] To improve the efficiency of short-term trading, a monthly basis is used. Before short-term trading begins, power grid companies (e.g., the Northwest Five Provinces (Regions) Power Grid Company) submit their intended short-term power transmission prices and upper limits for power transmission, as well as intended power purchase prices and upper limits for power purchase, for the following month, according to peak, valley, and flat periods. The State Grid (Northwest Branch) centrally matches the one-way power transmission and one-way power purchase prices submitted by each province (region). When multiple power purchase and transmission prices can be matched, the clearing is carried out according to the price matching method (high-low matching method). The Northwest Five Provinces (Regions) Power Grid Company can adjust the intended power prices and volumes on a rolling basis within the month, continuously clearing the market.

[0010] The system performs centralized matching based on the one-way power transmission volume and price and one-way power purchase price declared by each province (region). When multiple power purchase prices and power transmission prices can be matched, the system clears the market according to the price matching method (high-low matching method) and sorts them according to price priority.

[0011] As a preferred embodiment of the present invention, the application review module includes an electricity price transmission unit, an initial month application unit, and an application data review unit;

[0012] Electricity price transmission unit, used for electricity price transmission between the power supply side and the load side;

[0013] At the beginning of the month, before the commencement of short-term transactions, the reporting units shall submit their intended short-term power transmission price and upper limit for power transmission, as well as their intended power purchase price and upper limit for power purchase, for the following month, according to peak, valley, and flat periods respectively.

[0014] In the data review unit, the administrator reviews and verifies the short-term intended power transmission price and upper limit of power transmission volume, as well as the intended power purchase price and upper limit of power purchase volume submitted by the power grid company for the following month. Once the data meets the specifications, it is marked as approved.

[0015] As a preferred embodiment of the present invention, the peak period is set to 7:00-9:00 and 18:00-22:00, the valley period is set to 10:00-16:00, and the flat period is set to the remaining time periods outside the peak and valley periods.

[0016] As a preferred embodiment of the present invention, the application review module further includes a monthly rolling application unit, which flexibly adjusts the one-way power transmission price, one-way power purchase price, and power consumption limit according to changes in supply and demand.

[0017] As a preferred embodiment of the present invention, the application data review unit includes a data input and verification subunit, a rule verification subunit, a review processing subunit, a review operation subunit, a review record and notification subunit, and a data query and statistics subunit.

[0018] Data Input and Verification Subunit: Administrators input the short-term intended power transmission price and upper limit of power transmission volume, intended power purchase price and upper limit of power purchase volume for the following month submitted by the power grid company through the interface or API. The system verifies the format of the input data to ensure that it meets the specifications, such as data type and numerical range.

[0019] The rule verification subunit designs the rule verification logic, including regulations such as price range and power limit. It verifies whether the input data meets the requirements according to the rules. If it does not meet the rules, it returns an error message.

[0020] In the review and processing sub-unit, if the data meets the specifications, it is marked as pending review. Administrators can view the list of data pending review and perform review operations on each piece of data.

[0021] The review operation sub-unit allows administrators to review data according to customized review processes and rules. Review operations can include options such as approve, reject, or require modification. Administrators can select the appropriate operation and fill in their review comments.

[0022] Audit Record and Notification Sub-unit: The system records the audit results, auditors, and audit time information for each piece of data. Based on the audit results, the system can send a notification to the power grid company to inform them of the audit results and related comments.

[0023] Data Query and Statistics Sub-unit: Provides a query interface or API so that administrators can view the approved data, pending data, and approval records as needed. It supports the statistical analysis of the approved data, such as the approval rate and the distribution of approval time.

[0024] As a preferred embodiment of the present invention, the one-way quote matching and clearing module includes a first transaction judgment unit and a second transaction judgment unit;

[0025] In the first transaction judgment unit, the electricity sales price and the electricity purchase price are ranked according to price in the peak, valley and flat periods. When the electricity sales price is always higher than the electricity purchase price, no transaction is made.

[0026] In the second transaction judgment unit, during peak, valley, and flat periods, the electricity sales price and the electricity purchase price are ranked according to price from highest to lowest. When the purchaser's price is higher than the seller's price, the highest-priced purchaser and the lowest-priced seller form a transaction pair. The average price is the transaction price. Transactions are completed pair by pair in descending order of price difference. Transactions stop when the price difference is less than zero. The transaction price is the purchaser's node price minus the transmission price to obtain the seller's price.

[0027] As a preferred embodiment of the present invention, it also includes a monitoring module for real-time monitoring of changes in electricity market, participant bids and declarations, establishing a management mechanism to review and verify participant bids and declarations, and ensuring the reliability and standardization of data.

[0028] As a preferred embodiment of the present invention, it further includes a data collection unit, which includes a data source access subunit, a data acquisition subunit, a data processing subunit, a data storage and management subunit, a data analysis and mining subunit, a data access and sharing subunit, and a system monitoring and management subunit.

[0029] The data source access subunit supports access to various data sources (such as sensors, devices, databases, etc.) and provides adapters or interfaces to communicate and collect data from different types of data sources.

[0030] The data acquisition subunit collects data in real time and stores it in a specified storage medium (such as a database or file system). It supports batch acquisition and scheduled acquisition to meet the needs of different data sources.

[0031] Data processing subunit: Performs preprocessing operations such as cleaning, transformation, and standardization on the collected raw data. Supports data filtering, aggregation, calculation, and statistics to generate useful derived data.

[0032] Data storage and management subunit: Provides scalable data storage solutions, such as relational databases and distributed file systems. Designs data models and architectures to support the storage and retrieval of structured and unstructured data. Implements real-time data backup, disaster recovery, and security strategies to ensure data integrity and availability.

[0033] As a preferred embodiment of the present invention, the data collection unit further includes a data analysis and mining subunit and a data access and sharing subunit;

[0034] Data Analysis and Mining Subunit: Uses machine learning, statistical analysis, and data mining to perform data analysis and mining, and supports data visualization and report generation so that users can better understand and utilize data;

[0035] Data Access and Sharing Subunit: Design appropriate data access interfaces and permission management mechanisms to ensure data security and privacy protection. Provide data sharing and collaboration functions to facilitate data exchange and sharing between different users or systems.

[0036] In a preferred embodiment of the present invention, the data collection unit further includes a system monitoring and management subunit: implementing system performance monitoring and error log recording to promptly detect and resolve system faults. It also provides a system configuration and management interface to facilitate system maintenance and adjustments by administrators.

[0037] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0038] 1. In this invention, to improve the efficiency of short-term transaction organization, on a monthly basis, before the commencement of short-term transactions, the power grid company submits its intended short-term power transmission price and upper limit for power transmission, as well as its intended power purchase price and upper limit for power purchase, for the following month, according to peak, valley, and flat periods. The State Grid Corporation of China centrally matches the one-way power transmission price and one-way power purchase price submitted by each province (region). When multiple power purchase prices and power transmission prices can be matched, the transaction is cleared according to the bid matching method (high-low matching method). The power grid company can continuously adjust the intended power price and power volume within the month, and continuously clear the transaction.

[0039] 2. Optimize the acquisition of volume and price for each province: Each province submits the volume and price of one-way outbound power transmission and the volume and price of one-way power purchase to the system. After the administrator approves the submission, the other provinces can immediately obtain the corresponding latest price.

[0040] 3. Improved efficiency of centralized bidding and matching: The system performs centralized matching based on the one-way power transmission volume and price and one-way power purchase price declared by each province (region). When multiple power purchase prices and power transmission prices can be matched, they are cleared according to the bidding and matching method (high-low matching method) and sorted according to price priority. Attached Figure Description

[0041] Figure 1 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 1 ;

[0042] Figure 2 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 2 ;

[0043] Figure 3 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 3 ;

[0044] Figure 4 This is the declaration representation intent of the time-segmented continuous rolling clearing system for power grid transactions provided in this embodiment of the invention;

[0045] Figure 5 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 4 ;

[0046] Figure 6 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 5 ;

[0047] Figure 7 This is a schematic diagram of a non-trading transaction in the time-segmented continuous rolling clearing system for power grid transactions provided in this embodiment of the invention, using the price matching method (high-low matching method).

[0048] Figure 8 This is a schematic diagram of a bid-matching method (high-low matching method) transaction in a time-segmented continuous rolling clearing system for power grid trading provided in an embodiment of the present invention;

[0049] Figure 9 This is a flowchart of the time-segmented continuous rolling clearing system for power grid transactions provided in an embodiment of the present invention;

[0050] Figure 10 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 6 ;

[0051] Figure 11 This is the system block diagram of the time-segmented continuous rolling clearing system for power grid trading provided in this embodiment of the invention. Figure 7 . Detailed Implementation

[0052] To further understand the invention's content, features, and effects, the following embodiments are provided, and detailed descriptions are given in conjunction with the accompanying drawings.

[0053] The structure of the present invention will now be described in detail with reference to the accompanying drawings.

[0054] See Figure 1 The present invention provides a time-segmented continuous rolling clearing system for power grid transactions, comprising a central processing module, characterized in that the central processing module is signal-connected to a declaration and review module, a one-way bid matching and clearing module, and a monthly rolling clearing module;

[0055] Application and review module: Each regional power grid company submits its short-term intended power transmission price and upper limit for power transmission volume, as well as its intended power purchase price and upper limit for power purchase volume for the following month. The administrator reviews the application and marks it as approved once the data meets the specifications.

[0056] One-way bid matching and clearing module: After converting the bid prices from each province to the power purchaser node according to the power supply side price, the module uses a high-low matching method to match and trade the bids.

[0057] The monthly rolling clearing module: It conducts centralized bidding and matching based on the one-way power transmission price and one-way power purchase price adjusted by each province within the month, calculates the qualified trading parties according to the high-low matching method, prioritizes them according to price, and generates the latest transaction notification.

[0058] To improve the efficiency of short-term trading, a monthly basis is used. Before short-term trading begins, power grid companies (e.g., the Northwest Five Provinces (Regions) Power Grid Company) submit their intended short-term power transmission prices and upper limits for power transmission, as well as intended power purchase prices and upper limits for power purchase, for the following month, according to peak, valley, and flat periods. The State Grid (Northwest Branch) centrally matches the one-way power transmission and one-way power purchase prices submitted by each province (region). When multiple power purchase and transmission prices can be matched, the clearing is carried out according to the price matching method (high-low matching method). The Northwest Five Provinces (Regions) Power Grid Company can adjust the intended power prices and volumes on a rolling basis within the month, continuously clearing the market.

[0059] The system performs centralized matching based on the one-way power transmission volume and price and one-way power purchase price declared by each province (region). When multiple power purchase prices and power transmission prices can be matched, the system clears the market according to the price matching method (high-low matching method) and sorts them according to price priority.

[0060] The system offers the following advantages: First, it eliminates the need for individual power grid companies to contact other power grid companies by phone or email to inquire about their quotations. Second, it enables timely access to the latest quotations from other power grid companies. Third, it eliminates the need for manual matching of quotations from various provincial companies, as the system automatically uses a quotation matching method to rank eligible trading parties and prioritizes them. Fourth, for intra-month quotation adjustments, the system automatically clears out the latest quotations based on the time frame upon approval, eliminating the need for manual matching and improving efficiency and automation.

[0061] It should be noted that each region can be a province, a city, or a district, thus this application has a wider scope of application.

[0062] See Figure 2 The application and review module includes a price transmission unit, a beginning-of-month application unit, and an application data review unit. The price transmission unit is used for price transmission between the power supply side and the load side. The beginning-of-month application unit submits the intended short-term power transmission price and the upper limit of the power transmission volume, as well as the intended power purchase price and the upper limit of the power purchase volume, for the following month according to the peak, valley, and flat periods, respectively, before the short-term trading begins. The application data review unit is used by the administrator to review and verify the intended short-term power transmission price and the upper limit of the power transmission volume, as well as the intended power purchase price and the upper limit of the power purchase volume, submitted by the power grid company for the following month. The data is marked as approved after it meets the specifications.

[0063] For example, the peak period is set to 7:00-9:00 and 18:00-22:00, the valley period is set to 10:00-16:00, and the flat period is set to the remaining time periods outside the peak and valley periods.

[0064] For further details, please refer to [link / reference]. Figure 3 The application and review module also includes a monthly rolling application unit, which flexibly adjusts the one-way power transmission price, one-way power purchase price, and power volume limit according to changes in supply and demand.

[0065] See Figure 4 , Figure 4 This is the declaration representation intent of the time-segmented continuous rolling clearing system for power grid transactions provided in the embodiments of the present invention.

[0066] See Figure 5 The application data review unit includes a data input and verification subunit, a rule verification subunit, a review processing subunit, a review operation subunit, a review record and notification subunit, and a data query and statistics subunit.

[0067] Data Input and Verification Subunit: Administrators input the short-term intended power transmission price and upper limit of power transmission volume, intended power purchase price and upper limit of power purchase volume for the following month submitted by the power grid company through the interface or API. The system verifies the format of the input data to ensure that it meets the specifications, such as data type and numerical range.

[0068] The rule verification subunit designs the rule verification logic, including regulations such as price range and power limit. It verifies whether the input data meets the requirements according to the rules. If it does not meet the rules, it returns an error message.

[0069] In the review and processing sub-unit, if the data meets the specifications, it is marked as pending review. Administrators can view the list of data pending review and perform review operations on each piece of data.

[0070] The review operation sub-unit allows administrators to review data according to customized review processes and rules. Review operations can include options such as approve, reject, or require modification. Administrators can select the appropriate operation and fill in their review comments.

[0071] Audit Record and Notification Sub-unit: The system records the audit results, auditors, and audit time information for each piece of data. Based on the audit results, the system can send a notification to the power grid company to inform them of the audit results and related comments.

[0072] Data Query and Statistics Sub-unit: Provides a query interface or API so that administrators can view the approved data, pending data, and approval records as needed. It supports the statistical analysis of the approved data, such as the approval rate and the distribution of approval time.

[0073] See Figure 6 The one-way quote matching and clearing module includes a first transaction judgment unit and a second transaction judgment unit;

[0074] For the first transaction judgment unit, please refer to... Figure 7 During peak, valley, and flat periods, the electricity sales price and the electricity purchase price are ranked separately according to price. If the electricity sales price is consistently higher than the electricity purchase price, no transaction will be made.

[0075] For the second transaction judgment unit, please refer to... Figure 8 During peak, valley, and flat periods, the electricity sales price and purchase price are ranked according to their price range. When the purchase price is higher than the sales price, the purchaser with the highest price and the seller with the lowest price form a trading pair. The average price is the transaction price. The pairs are traded one by one in descending order of price difference. The trading stops when the price difference is less than zero. The transaction price is the purchaser's node price minus the transmission price to get the seller's price.

[0076] See Figure 9 This is a flowchart of an embodiment of a time-segmented continuous rolling clearing system for power grid transactions.

[0077] See Figure 10 It also includes a monitoring module for real-time monitoring of changes in the electricity market, participant bids and declarations, and the establishment of a management mechanism to review and verify participants' bids and declarations to ensure the reliability and standardization of the data.

[0078] See Figure 11 It also includes a data collection unit, which comprises a data source access subunit, a data acquisition subunit, a data processing subunit, a data storage and management subunit, a data analysis and mining subunit, a data access and sharing subunit, and a system monitoring and management subunit.

[0079] The data source access subunit supports access to various data sources (such as sensors, devices, databases, etc.) and provides adapters or interfaces to communicate and collect data from different types of data sources.

[0080] The data acquisition subunit collects data in real time and stores it in a specified storage medium (such as a database or file system). It supports batch acquisition and scheduled acquisition to meet the needs of different data sources.

[0081] Data processing subunit: Performs preprocessing operations such as cleaning, transformation, and standardization on the collected raw data. Supports data filtering, aggregation, calculation, and statistics to generate useful derived data.

[0082] Data storage and management subunit: Provides scalable data storage solutions, such as relational databases and distributed file systems. Designs data models and architectures to support the storage and retrieval of structured and unstructured data. Implements real-time data backup, disaster recovery, and security strategies to ensure data integrity and availability.

[0083] See Figure 11 The data collection unit further includes a data analysis and mining subunit and a data access and sharing subunit;

[0084] Data Analysis and Mining Subunit: Uses machine learning, statistical analysis, and data mining to perform data analysis and mining, and supports data visualization and report generation so that users can better understand and utilize data;

[0085] Data Access and Sharing Subunit: Design appropriate data access interfaces and permission management mechanisms to ensure data security and privacy protection. Provide data sharing and collaboration functions to facilitate data exchange and sharing between different users or systems.

[0086] See Figure 11 The data collection unit also includes a system monitoring and management subunit: implementing system performance monitoring and error logging to promptly detect and resolve system faults. It provides a system configuration and management interface for administrators to easily maintain and adjust the system.

[0087] Working principle of the invention:

[0088] To improve the efficiency of short-term trading organization, on a monthly basis, before short-term trading begins, the power grid company submits its intended export price and export volume limit, as well as its intended purchase price and purchase volume limit for the following month, according to peak, valley, and flat periods. The State Grid Corporation of China centrally matches the one-way export price and one-way purchase price submitted by each province (region). When multiple purchase prices and export prices can be matched, the clearing is carried out according to the bid-matching method (high-low matching method). The power grid company can adjust the intended price and volume on a rolling basis within the month, continuously clearing the market.

[0089] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.

[0090] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A time-segmented continuous rolling clearing system for power grid transactions, comprising a central processing module, characterized in that, The central processing module is signal-connected to the declaration review module, the one-way quotation matching and clearing module, and the monthly rolling clearing module. In the application and review module, each regional power grid company submits its short-term intended power transmission price and upper limit for power transmission, as well as its intended power purchase price and upper limit for power purchase for the following month. The administrator reviews the application and marks it as approved once the data meets the specifications. The one-way bid matching and clearing module converts the bid prices submitted by each province to the power purchaser node according to the power supply side price and then uses the high-low matching method to match and trade. The monthly rolling clearing module conducts centralized bidding and matching based on the one-way power transmission price and one-way power purchase price adjusted by each province within the month. It calculates the eligible trading parties according to the high-low matching method, prioritizes them according to price, and generates the latest transaction notification. The application review module includes an electricity price transmission unit, an initial month application unit, and an application data review unit; Electricity price transmission unit, used for electricity price transmission between the power supply side and the load side; At the beginning of the month, before the commencement of short-term transactions, the reporting units shall submit their intended short-term power transmission price and upper limit for power transmission, as well as their intended power purchase price and upper limit for power purchase, for the following month, according to peak, valley, and flat periods respectively. In the data review unit, the administrator reviews and verifies the short-term intended power transmission price and upper limit of power transmission volume, as well as the intended power purchase price and upper limit of power purchase volume submitted by the power grid company for the following month. Once the data meets the specifications, it is marked as approved. The peak periods are defined as 7:00-9:00 and 18:00-22:00, the valley periods are defined as 10:00-16:00, and the flat periods are defined as the remaining time periods outside the peak and valley periods. The application and review module also includes a monthly rolling application unit, which flexibly adjusts the one-way power transmission price, one-way power purchase price and power volume limit according to changes in supply and demand. The data review unit includes a data input and verification subunit, a rule verification subunit, a review processing subunit, a review operation subunit, a review record and notification subunit, and a data query and statistics subunit. Data Input and Verification Subunit: Administrators input the short-term intended power transmission price and upper limit of power transmission volume, intended power purchase price and upper limit of power purchase volume for the following month submitted by the power grid company through the interface or API, and perform format verification on the input data to ensure that it meets the specifications. The rule verification subunit designs the rule verification logic, including the regulations on price range and power limit. It verifies whether the input data meets the requirements according to the rules. If it does not meet the rules, it returns an error message. In the review and processing sub-unit, if the data meets the specifications, it is marked as pending review. Administrators can view the list of data pending review and perform review operations on each piece of data. In the review operation sub-unit, the administrator reviews the data to be reviewed according to the customized review process and rules. The review operation includes options such as pass, reject, or require modification. The administrator can select the appropriate operation and fill in the review comments. Audit Record and Notification Sub-unit: The system records the audit results, auditors, and audit time information for each piece of data. Based on the audit results, the system can send a notification to the power grid company to inform them of the audit results and related comments. Data Query and Statistics Sub-unit: Provides a query interface or API so that administrators can view the approved data, pending data and approval records as needed, and support the statistics and analysis of the approved data; The one-way quote matching and clearing module includes a first transaction judgment unit and a second transaction judgment unit; In the first transaction judgment unit, the electricity sales price and the electricity purchase price are ranked according to price in the peak, valley and flat periods. When the electricity sales price is always higher than the electricity purchase price, no transaction is made. In the second transaction judgment unit, during peak, valley, and flat periods, the electricity sales price and purchase price are ranked according to price from highest to lowest. When the purchaser's price is higher than the seller's price, the highest-priced purchaser and the lowest-priced seller form a transaction pair. The average price quoted is the transaction price. Transactions are completed pair by pair in descending order of price difference. Transactions stop when the price difference is less than zero. The transaction price is the purchaser's node price minus the transmission price to obtain the seller's price. It also includes a monitoring module for real-time monitoring of changes in the electricity market, participant bids and declarations, and the establishment of a management mechanism to review and verify participants' bids and declarations to ensure the reliability and standardization of the data.

2. The time-segmented continuous rolling clearing system for power grid transactions as described in claim 1, characterized in that: It also includes a data collection unit, which comprises a data source access subunit, a data acquisition subunit, a data processing subunit, a data storage and management subunit, a data analysis and mining subunit, a data access and sharing subunit, and a system monitoring and management subunit. The data source access subunit supports access to multiple data sources and provides adapters or interfaces to communicate and collect data from different types of data sources. The data acquisition subunit collects data in real time and stores it in a specified storage medium. It supports batch acquisition and timed acquisition to meet the needs of different data sources. Data processing subunit: performs cleaning, transformation, and standardization preprocessing operations on the collected raw data; Data storage and management subunit: Provides scalable data storage solutions.

3. The time-segmented continuous rolling clearing system for power grid transactions as described in claim 2, characterized in that: The data collection unit also includes a data analysis and mining subunit and a data access and sharing subunit; Data Analysis and Mining Subunit: Uses machine learning, statistical analysis, and data mining to perform data analysis and mining, and supports data visualization and report generation so that users can better understand and utilize data; Data Access and Sharing Subunit: Design appropriate data access interfaces and permission management mechanisms to ensure data security and privacy protection, provide data sharing and collaboration functions, and facilitate data exchange and sharing between different users or systems.

4. The time-segmented continuous rolling clearing system for power grid transactions as described in claim 3, characterized in that: The data collection unit also includes a system monitoring and management subunit: implementing system performance monitoring and error log recording, timely detection and resolution of system faults, and providing a system configuration and management interface to facilitate administrators in maintaining and adjusting the system.

Citation Information

Patent Citations

  • Time-phased transaction system supporting medium and long term continuous market opening

    CN115482064A