A lane-level speed limit control method for construction zones in high-speed weaving sections in a connected vehicle environment

By dividing the grid, collecting traffic data and calculating traffic flow characteristics in the Internet of Vehicles environment, dynamically adjusting the lane speed limit solves the problem of speed limit in the construction zone of the interweaving section of the highway, improves traffic management efficiency, alleviates traffic congestion, and improves road safety. Network operating efficiency.

CN117012043BInactive Publication Date: 2024-10-08SHANDONG HI SPEED GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310775753.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-06-28
Publication Date
2024-10-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology cannot effectively solve the speed limit problem in the construction zone of the interwoven section of the highway, resulting in low traffic efficiency and traffic congestion, and cannot alleviate the traffic congestion in a timely manner.

Method used

Using the Internet of Vehicles environment to divide the grid, collect traffic characteristic data, calculate the traffic flow operating characteristics and diversion ratio, and dynamically adjust the lane speed limit through the lane-level speed limit control scheme to achieve uniform distribution of traffic flow and optimization of traffic management.

Benefits of technology

It improves the operating efficiency of highways, achieves efficient control of traffic management, alleviates traffic congestion, and improves the overall operating efficiency of the road network.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117012043B_ABST
    Figure CN117012043B_ABST
Patent Text Reader

Abstract

The present invention discloses a lane-level speed limit control method for a construction area of ​​a high-speed interweaving section in a vehicle networking environment, comprising: dividing the construction impact control area of ​​a high-speed interweaving section in a vehicle networking environment into grids and numbering them; determining the grid area of ​​the construction impact control area; collecting traffic characteristic data of the construction impact control area of ​​the high-speed interweaving section; calculating the traffic flow operation characteristics in the traffic control grid area of ​​the construction impact control area, and calculating the traffic flow in the construction impact control area; determining the traffic flow allocation plan for the construction impact control area of ​​the high-speed interweaving section; determining the speed ranking of the guided traffic flow of each lane, and determining the lane-level speed limit control plan for the construction area of ​​the high-speed interweaving section. The present invention uses the convenience and reliability of the interaction of various types of traffic information in the vehicle networking environment to set a reasonable speed limit for each lane in the construction impact area of ​​the high-speed interweaving section in the vehicle networking environment, so as to achieve a uniform distribution of the road network traffic flow and improve the overall operation efficiency of the road network.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of intelligent traffic management and control systems, and in particular to a lane-level speed limit control method for construction zones in high-speed weaving sections of a vehicle-to-everything (V2X) environment. Background Technology

[0002] Despite the development of highways, traffic congestion remains a serious problem. Highway construction encroachments are potential bottlenecks. When vehicles encounter construction zones while traveling in sections of highways, they need to slow down and change lanes to minimize delays. Therefore, speed limits are a crucial component of travel services in highway construction zones. However, existing research on speed limits in highway construction zones is scarce, and most speed limit technologies are uniform static limits, failing to provide efficient technical support for traffic management and control schemes. This results in slow highway traffic flow, an inability to effectively alleviate traffic congestion, and a reduction in the overall operational efficiency of the road network. Summary of the Invention

[0003] Purpose of the invention: To address the above problems, the purpose of this invention is to provide a lane-level speed limit control method for construction areas in high-speed weaving sections within a vehicle-to-everything (V2X) environment. By leveraging the accuracy and reliability of data interaction in a V2X environment, this method determines the lane-level speed limit control method for construction areas in high-speed weaving sections, thereby improving the operational efficiency of the road network.

[0004] Technical solution: The present invention provides a lane-level speed limit control method for construction zones in high-speed weaving sections within a vehicle-to-everything (V2X) environment, comprising the following steps:

[0005] Step 1: Divide the construction impact control zone of the high-speed weaving section in the vehicle-to-everything (V2X) environment into grids and number each grid.

[0006] Step 2: Determine the grid area of ​​the construction impact control zone based on the vehicle's direction of travel and characteristics;

[0007] Step 3: Collect traffic characteristic data of the construction impact control area of ​​the expressway weaving section;

[0008] Step 4: Calculate the traffic flow characteristics within the traffic flow control grid area of ​​the construction impact control zone based on traffic characteristic data, and calculate the traffic flow in the construction impact control zone;

[0009] Step 5: Divert traffic flow in the construction-affected traffic area from the middle lane to the outer lane in sequence to determine the traffic flow distribution plan for the construction-affected control area of ​​the highway weaving section.

[0010] Step 6: Based on the traffic flow distribution plan for the construction impact control area, determine the speed order of the guided traffic flow in each lane, and determine the lane-level speed limit control plan for the construction area of ​​the highway weaving section.

[0011] Furthermore, step 1 specifically includes the following sub-steps:

[0012] Step 101, Determine the control starting point section

[0013] Based on the length L of the high-speed weaving section and the distance D between the starting section of the construction area and the starting section of the weaving section, determine the horizontal distance D between the control starting section and the starting section of the construction area. c The expression is as follows:

[0014]

[0015] Step 102: Divide the grid of the construction impact control zone in the high-speed weaving section under the vehicle-to-everything (V2X) environment.

[0016] The area enclosed from the starting section to the ending section of the weaving zone is divided into rectangular road grids, each grid having a length of l. g Width is l d ;

[0017] Step 103: Number the grid of the construction impact control zone in the high-speed weaving section under the vehicle-to-everything (V2X) environment.

[0018] Each grid is numbered sequentially according to the direction of traffic flow, and each grid number is denoted as G. ij , where j represents the j-th grid of the i-th lane.

[0019] Furthermore, step 2 specifically includes:

[0020] Based on the fact that the construction area is located in the Wth lane and the length of the construction area L W The area enclosed by the control start point and the construction zone end point of the lane is defined as the construction impact control zone grid area G. W , is represented as:

[0021] G W ={G W1 G W2 ,…,G WZ}

[0022] Where Z represents the number of grid cells occupied by the construction impact control zone, expressed as:

[0023]

[0024] Furthermore, step 3 includes collecting real-time traffic characteristic data and historical traffic characteristic data of the construction impact control area of ​​the highway weaving section:

[0025] When the vehicle passes the upstream section D of the control starting point section a At that time, the data acquisition and control starting point section is within a unit time period t. m Traffic flow Q in each lane i And the speed V of each vehicleQ_i ;

[0026] Collect characteristic data of each grid in the construction impact control area of ​​the highway weaving section under the vehicle-to-everything (V2X) environment during the h-hour period of historical time H, including the traffic flow distribution to the left lane. Traffic diversion to the right lane and traffic flow of each lane at the point section

[0027] Furthermore, step 4 specifically includes the following sub-steps:

[0028] Step 401: Calculate the interlaced operation characteristics of grid vehicles.

[0029] Based on the collected historical traffic characteristic data of the construction impact control area of ​​the expressway weaving section, the historical left-side traffic flow of each grid in the construction impact control area of ​​the expressway weaving section during the h-hour period of historical time H is calculated. Right-side flow distribution and total flow The expressions are as follows:

[0030]

[0031]

[0032]

[0033] Calculate the diversion ratio of the left lane of the grid based on historical diversion rates. Diversion ratio of right lane The interlacing operation characteristics of grid vehicles are obtained, and the expressions are as follows:

[0034]

[0035]

[0036] Step 402: Calculate the vehicle weaving operation characteristics in the grid area of ​​the construction impact control zone.

[0037] Based on the characteristics of interwoven vehicle traffic within the grid, the diversion ratio of the left lane in the grid within the construction impact control area is calculated. Diversion ratio of right lane The vehicle weaving operation characteristics of the grid area within the construction impact control zone are obtained, and the expressions are as follows:

[0038]

[0039]

[0040] In the formula, This indicates the diversion ratio of the left lane in the Ath grid of the construction impact control zone. This indicates the diversion ratio of the right lane in the Ath grid of the construction impact control zone;

[0041] Step 403: Calculate the traffic flow after the construction impact control zone intersects.

[0042] Based on the vehicle weaving operation characteristics of the grid area within the construction impact control zone, calculate the traffic flow flowing into the construction impact control zone from the left side of the zone. Traffic flow from the right side of the construction area into the construction impact control area Then calculate the traffic flow Q after the construction impact control area intersects. ′ W The expressions are as follows:

[0043]

[0044]

[0045]

[0046] In the formula, This indicates the right-side divergence ratio of lane W-1. Q represents the left-side divergence ratio of lane W+1. W This indicates the traffic flow before the construction impact control zone intersects.

[0047] Furthermore, step 5 specifically includes the following sub-steps:

[0048] Step 501: Calculate the lane diversion scheme for the construction impact control area.

[0049] The traffic flow in the construction impact control area is calculated by dividing the number of lanes in the construction area by the number of lanes in the left lane (W-1) and then by the number of lanes in the construction area (In(d)). W The proportion of ) is used to calculate the lane diversion scheme in the construction impact control area, and the expressions are as follows:

[0050]

[0051]

[0052] In the formula, ΔQ ( ′ W→(W-1)) This indicates the traffic flow diverted to the left lane from the construction impact control zone, ΔQ ( ′ W→(W+1)) This indicates the traffic flow being diverted to the right lane from the construction impact control zone;

[0053] Step 502, calculate lane-controlled traffic flow

[0054] Based on the unit time period t collected for each lane m Traffic flow Qi Calculate lane-controlled traffic flow The expression is:

[0055]

[0056] Step 503, calculate other lane diversion schemes

[0057] Based on lane-controlled traffic flow, traffic is diverted sequentially from the middle construction zone lanes to the outer lanes, with the diversion flow ΔQ calculated for each lane. ( ′ (W-f)→(W-f-1)) and the right lane split flow ΔQ ( ′ (u-W)→(u-W+1)) The expressions are as follows:

[0058]

[0059]

[0060] In the formula, Q ( ′ W-f) Q represents the traffic flow in lane Wf. ( ′ u-W) This indicates the traffic flow in lane uW.

[0061] Furthermore, step 6 specifically includes the following sub-steps:

[0062] Step 601: Calculate the control speed of the traffic flow in the left-hand diverging lane.

[0063] Sort the traffic speeds in lane Wf from lowest to highest to determine the traffic flow Rank(Q) that needs to be diverted. c((W-f)→(W-f-1)) ), calculate the vehicle speed corresponding to the lane, i.e., the traffic flow control speed V of lane Wf. c(W-f) The expression is:

[0064]

[0065] Step 602, calculate the traffic flow control speed of the right-hand diverging lane.

[0066] Sort the traffic flow in lane Wu according to its speed from smallest to largest, and determine the traffic flow that needs to be diverted (Rank(Q)). c((W-u)→(W-u+1)) ), calculate the vehicle speed corresponding to the lane, i.e., the traffic flow control speed V of lane Wu. c(W-u) The expression is:

[0067]

[0068] Step 603: Determine the lane-level speed limit control scheme.

[0069] Speed ​​limits are imposed on corresponding lanes based on traffic flow, with the innermost and outermost lanes maintaining their speed limits. Lanes in construction zones only have diversion signs. A lane-level speed limit control scheme is implemented based on the speed limits of each lane, and this is done every time interval t. m The speed limits for each lane will be dynamically updated based on the newly collected data.

[0070] Beneficial effects: Compared with the prior art, the significant advantages of this invention are: This invention provides a lane-level speed limit control method for construction areas in high-speed weaving sections under vehicle-to-everything (V2X) environments. By leveraging the convenience and reliability of various traffic information interactions under V2X environments, reasonable speed limits are set for each lane in the construction impact area of ​​high-speed weaving sections under V2X environments. This provides technical support for formulating reasonable and efficient traffic management and control schemes, achieving uniform distribution of traffic flow on the road network, and improving the overall operating efficiency of the road network. Attached Figure Description

[0071] Figure 1 This is a flowchart of the present invention;

[0072] Figure 2 This is a schematic diagram of the grid division of the construction impact zone in the high-speed intersecting section;

[0073] Figure 3 This is a schematic diagram showing the location of the construction impact control zone;

[0074] Figure 4 This is a schematic diagram illustrating the interwoven operation characteristics of grid vehicles;

[0075] Figure 5 This is a schematic diagram of the construction area of ​​the high-speed weaving section in the embodiment;

[0076] Figure 6 This is a schematic diagram of the grid division of the construction impact zone of the high-speed interlacing section in the embodiment. Detailed Implementation

[0077] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments.

[0078] like Figure 1 The flowchart shown is a method for lane-level speed limit control in a high-speed weaving section construction area in a vehicle-to-everything (V2X) environment, as described in this embodiment, including the following steps:

[0079] Step 1: Divide the construction impact control zone of the high-speed weaving section in the vehicle-to-everything (V2X) environment into grids and number each grid.

[0080] Specifically, step 1 includes the following sub-steps:

[0081] Step 101, Determine the control starting point section

[0082] Based on the length L of the high-speed weaving section and the distance D between the starting section of the construction area and the starting section of the weaving section, determine the horizontal distance D between the control starting section and the starting section of the construction area. c The expression is as follows:

[0083]

[0084] Step 102: Divide the grid of the construction impact control zone in the high-speed weaving section under the vehicle-to-everything (V2X) environment.

[0085] The area enclosed from the starting section to the ending section of the weaving zone is divided into rectangular road grids, each grid having a length of l. g Width is l d ;

[0086] Step 103: Number the grid of the construction impact control zone in the high-speed weaving section under the vehicle-to-everything (V2X) environment.

[0087] Each grid is numbered sequentially according to the direction of traffic flow, and each grid number is denoted as G. ij , where j represents the j-th grid of the i-th lane.

[0088] In one example, such as Figure 2 The diagram shows the grid division of the construction impact zone of the highway weaving section. The area enclosed from the starting section to the ending section of the weaving zone is divided into rectangular road grids. The total length of the grid is L, and the length of each grid is l. g Generally, it is 10-20 meters long and the width is l. d Generally, the width of the lane is taken as the standard. The construction area is located inside the grid, and the entire grid includes a total of I lanes.

[0089] Step 2: Determine the grid area of ​​the construction impact control zone based on the vehicle's direction of travel and characteristics.

[0090] Specifically, step 2 above includes:

[0091] Based on the fact that the construction area is located in lane W and the length of the construction area L W The area enclosed by the control start point and the construction zone end point of the lane is defined as the construction impact control zone grid area G. W , is represented as:

[0092] G W ={G W1 G W2 ,…,G WZ}

[0093] Where Z represents the number of grid cells occupied by the construction impact control zone, expressed as:

[0094]

[0095] In one example, such as Figure 3 The diagram shows the location of the construction impact control zone. The area within the dashed box in the diagram represents the construction impact control zone.

[0096] Step 3: Collect traffic characteristic data of the construction impact control area of ​​the high-speed weaving section.

[0097] Specifically, step 3 above includes collecting real-time traffic characteristic data and historical traffic characteristic data of the control area affected by the construction of the high-speed weaving section. When a vehicle passes through the upstream section D of the control starting point... a At that time, the data acquisition and control starting point section is within a unit time period t. m Traffic flow Q in each lane i And the speed V of each vehicle Q_i The system collects characteristic data of each grid within the construction impact control area of ​​a highway weaving section under a vehicle-to-everything (V2X) environment during the h-hour period of historical time H, including the traffic flow distribution to the left lane. Traffic diversion to the right lane and traffic flow of each lane at the point section

[0098] In practical applications, the distance D a Generally, a distance of 10-20 kilometers is selected, and data collection begins with the aid of traffic detectors. The data collection control point is located within a unit time period t. m (Generally taken as 5-10 minutes) Traffic flow Q in each lane i The speed V of each vehicle Q_i The system collects characteristic data for each grid within the construction impact area of ​​a highway weaving section under a vehicle-to-everything (V2X) environment, during the h-hour period of historical time H. Historical time H is typically selected as 10-15 days. The characteristic data includes the traffic flow distribution to the left lane. Traffic diversion to the right lane Traffic flow of each lane at the data collection point cross-section

[0099] Step 4: Calculate the traffic flow characteristics within the traffic flow control grid area of ​​the construction impact control zone based on traffic characteristic data, and calculate the traffic flow in the construction impact control zone.

[0100] Specifically, step 4 above includes the following sub-steps:

[0101] Step 401: Calculate the interlaced operation characteristics of grid vehicles.

[0102] Based on the collected historical traffic characteristic data of the construction impact control area of ​​the expressway weaving section, the historical left-side traffic flow of each grid in the construction impact control area of ​​the expressway weaving section during the h-hour period of historical time H is calculated. Right-side flow distribution and total flow The expressions are as follows:

[0103]

[0104]

[0105]

[0106] Calculate the diversion ratio of the left lane of the grid based on historical diversion rates. Diversion ratio of right lane The interlacing operation characteristics of grid vehicles are obtained, and the expressions are as follows:

[0107]

[0108]

[0109] In one example Figure 4 This is a schematic diagram illustrating the interlacing operation characteristics of grid vehicles. This indicates that traffic flow in the construction impact control zone is diverting to the left. This indicates that traffic flow in the construction impact control zone is diverting to the right. This is used to indicate that the traffic flow in the j-th grid of the i-th lane is splitting to the left. This is used to indicate that the traffic flow in the j-th grid of the i-th lane is diverting to the right.

[0110] Step 402: Calculate the vehicle weaving operation characteristics in the grid area of ​​the construction impact control zone.

[0111] Based on the characteristics of interwoven vehicle traffic within the grid, the diversion ratio of the left lane in the grid within the construction impact control area is calculated. Diversion ratio of right lane The vehicle weaving operation characteristics of the grid area within the construction impact control zone are obtained, and the expressions are as follows:

[0112]

[0113]

[0114] In the formula, This indicates the diversion ratio of the left lane in the Ath grid of the construction impact control zone. This indicates the diversion ratio of the right lane in the Ath grid of the construction impact control zone;

[0115] Step 403: Calculate the traffic flow after the construction impact control zone intersects.

[0116] Based on the vehicle weaving operation characteristics of the grid area within the construction impact control zone, calculate the traffic flow flowing into the construction impact control zone from the left side of the zone. Traffic flow from the right side of the construction area into the construction impact control area Then calculate the traffic flow Q after the construction impact control area intersects. ′ W The expressions are as follows:

[0117]

[0118]

[0119]

[0120] In the formula, This indicates the right-side divergence ratio of lane W-1. Q represents the left-side divergence ratio of lane W+1. W This indicates the traffic flow before the construction impact control zone intersects.

[0121] Step 5: Divert traffic flow in the construction-affected traffic area from the middle lane to the outer lane in sequence to determine the traffic flow distribution plan for the construction-affected control area of ​​the highway weaving section.

[0122] Specifically, step 5 above includes the following sub-steps:

[0123] Step 501: Calculate the lane diversion scheme for the construction impact control area.

[0124] The traffic flow in the construction impact control area is calculated by dividing the number of lanes in the construction area by the number of lanes in the left lane (W-1) and then by the number of lanes in the construction area (In(d)). W The proportion of ) is used to calculate the lane diversion scheme in the construction impact control area, and the expressions are as follows:

[0125]

[0126]

[0127] In the formula, ΔQ ( ′ W→(W-1)) This indicates the traffic flow diverted to the left lane from the construction impact control zone, ΔQ ( ′ W→(W+1)) This indicates the traffic flow being diverted to the right lane from the construction impact control zone;

[0128] Step 502, calculate lane-controlled traffic flow

[0129] Based on the unit time period t collected for each lane m Traffic flow Q i Calculate lane-controlled traffic flow The expression is:

[0130]

[0131] Step 503, calculate other lane diversion schemes

[0132] Based on lane-controlled traffic flow, traffic is diverted sequentially from the middle construction zone lanes to the outer lanes, with the diversion flow ΔQ calculated for each lane. ( ′ (W-f)→(W-f-1)) and the right lane split flow ΔQ ( ′ (u-W)→(u-W+1)) The expressions are as follows:

[0133]

[0134]

[0135] In the formula, Q ( ′ W-f) Q represents the traffic flow in lane Wf. ( ′ u-W) This indicates the traffic flow in lane uW.

[0136] Step 6: Based on the traffic flow distribution plan for the construction impact control area, determine the speed order of the guided traffic flow in each lane, and determine the lane-level speed limit control plan for the construction area of ​​the highway weaving section.

[0137] Specifically, step 6 above includes the following sub-steps:

[0138] Step 601: Calculate the control speed of the traffic flow in the left-hand diverging lane.

[0139] Sort the traffic speeds in lane Wf from lowest to highest to determine the traffic flow Rank(Q) that needs to be diverted. c((W-f)→(W-f-1)) ), calculate the vehicle speed corresponding to the lane, i.e., the traffic flow control speed V of lane Wf. c(W-f) The expression is:

[0140]

[0141] Step 602, calculate the traffic flow control speed of the right-hand diverging lane.

[0142] Sort the traffic flow in lane Wu according to its speed from smallest to largest, and determine the traffic flow that needs to be diverted (Rank(Q)). c((W-u)→(W-u+1)) ), calculate the vehicle speed corresponding to the lane, i.e., the traffic flow control speed V of lane Wu. c(W-u) The expression is:

[0143]

[0144] Step 603: Determine the lane-level speed limit control scheme.

[0145] Speed ​​limits are imposed on corresponding lanes based on traffic flow, with the innermost and outermost lanes maintaining their speed limits. Lanes in construction zones only have diversion signs. A lane-level speed limit control scheme is implemented based on the speed limits of each lane, and this is done every time interval t. m The speed limits for each lane will be dynamically updated based on the newly collected data.

[0146] The method for lane-level speed limit control in a high-speed weaving section construction area in a vehicle-to-everything (V2X) environment according to the present invention will be further illustrated by an example. Figure 5 The diagram shows a construction area in a highway weaving section. The construction area is 200 meters long, occupying the third lane. The entire weaving section is 1995 meters long, and each lane is 3.75 meters wide. Based on the vehicle-to-everything (V2X) environment highway weaving section construction area lane-level speed limit control method of this invention, the speed limit control scheme for each lane in the affected area of ​​the highway weaving section construction is calculated. The specific steps are as follows:

[0147] S1: Divide and number the grid of the construction impact control zone in the high-speed weaving section under the vehicle-to-everything (V2X) environment:

[0148] S11: Based on the interlacing zone length L being 1995m, the distance D between the starting section of the construction zone and the starting section of the interlacing zone is 1395m. Control the horizontal distance D between the starting section and the starting section of the construction zone. c The calculation results are as follows:

[0149]

[0150] S12: Based on the fact that each grid is 20m long and 3.75m wide, the lanes in the construction impact control area of ​​the highway weaving section are divided into 100 grids.

[0151] S13: The 100 grids in the construction impact control area of ​​the high-speed weaving section are numbered sequentially, with the first lane grid numbered G according to lane order. 1j The second lane grid number is G. 2j Construction area lane grid number G 3j Fourth lane grid number G 4j Fifth lane, grid number G 5j , where j∈Z, j=1,2,3,…,100.

[0152] S2: Determine the grid area of ​​the construction impact control zone:

[0153] Based on the fact that the construction area is located in the 3rd lane, the calculation results of the number of grids occupied by the construction impact control zone are as follows:

[0154]

[0155] S3: Collect traffic characteristic data of the control area affected by construction on highway weaving sections under a vehicle-to-everything (V2X) environment.

[0156] S31: Combination Figure 6 As shown, a data collection point was set up 10 kilometers upstream of the control starting point section. When a vehicle passed the observation section, the detector began to collect the traffic flow and speed of each vehicle per unit time period. The detection time was selected during the morning peak period on weekdays (8:00-8:10). The current traffic characteristics data of the construction impact area of ​​the highway weaving section are shown in Table 1 (partial data is listed).

[0157] Table 1

[0158]

[0159] Note: " / " indicates that the vehicle does not exist in this lane.

[0160] S32: Traffic characteristic data for a unit time period of 8:00-8:10 for a historical period of 10 days were collected 10 kilometers upstream of the control starting point section. The historical traffic characteristic data of the control area affected by the construction of the expressway weaving section is shown in Table 2 (partial data is listed), and the historical traffic flow of each lane section in the control area affected by the construction of the expressway weaving section is shown in Table 3.

[0161] Table 2

[0162]

[0163] Note: " / " indicates that the vehicle traffic characteristics of this lane are not considered.

[0164] Table 3

[0165]

[0166]

[0167] Note: " / " indicates that the vehicle traffic characteristics of this lane are not considered.

[0168] Based on the calculated historical left-side traffic flow, historical right-side traffic flow, and historical total traffic flow of the lane sections, the calculation results of the left-side lane diversion ratio and right-side lane diversion ratio of the grid in the construction impact area of ​​the expressway weaving section are shown in Table 4 (partial data is listed).

[0169] Table 4

[0170] Grid number Left lane diversion ratio Right lane diversion ratio <![CDATA[G 1,1 ]]> / 0.004 … … … <![CDATA[G 1,70 ]]> / 0.002 <![CDATA[G 2,1 ]]> 0.027 0.005 … … … <![CDATA[G 2,70 ]]> 0.017 0.006 <![CDATA[G 3,1 ]]> 0.014 0.015 … … … <![CDATA[G 3,70 ]]> 0.007 0.007 <![CDATA[G 4,1 ]]> 0.009 0.024 … … … <![CDATA[G 4,70 ]]> 0.005 0.013 <![CDATA[G 5,1 ]]> 0.002 / … … … <![CDATA[G 5,70 ]]> 0.006 /

[0171] Note: " / " indicates that the vehicle traffic characteristics of this lane are not considered.

[0172] S42: Based on the calculated grid vehicle weaving operation characteristics, the calculation results of the left lane divergence ratio and right lane divergence ratio of the grid in the construction impact control area are as follows:

[0173]

[0174]

[0175] S43: Based on the calculated vehicle weaving characteristics of the grid area within the construction impact control zone, calculate the traffic flow from the left side of the construction impact control zone to the construction impact control zone, and the traffic flow from the right side of the construction impact control zone to the construction impact control zone. The calculation results are as follows:

[0176]

[0177]

[0178] Furthermore, the traffic flow after the construction impact control zone intersects was calculated, and the results are as follows:

[0179]

[0180] S5: Determine the traffic flow distribution plan for the construction impact area of ​​the high-speed weaving section:

[0181] S51: Based on the fact that there are 2 left-hand lanes in the construction area and 4 lanes in the construction area, the calculation results of the lane diversion scheme in the construction impact control area are as follows:

[0182]

[0183]

[0184] S52: Based on the traffic flow collected per unit time period for each lane, the lane control traffic flow calculation results are as follows:

[0185]

[0186] S53: Based on the calculated lane control traffic flow, traffic is diverted sequentially from the middle construction zone lanes to the outer lanes. The calculation results for the diversion flow of the left and right lanes are as follows:

[0187]

[0188]

[0189] S6: Determine the lane-level speed limit control scheme for the construction area of ​​the high-speed weaving section:

[0190] S61: Sort the speed of traffic flow in lane 2 from smallest to largest. The sorting results are shown in Table 5 (partial data is listed).

[0191] Table 5

[0192] Speed ​​sequence number Vehicle speed (km / h) 1 96 2 96 … … 299 104 300 105 … … 349 116

[0193] Based on the speed ranking of traffic flow in lane 2, the calculated speed control for lane 2 is as follows:

[0194] V c2 = 105 (km / h)

[0195] S62: Sort the speeds of traffic in lane 4 from smallest to largest, as shown in Table 6.

[0196] Table 6

[0197] Speed ​​sequence number Vehicle speed (km / h) 1 86 2 86 … … 299 100 300 101 … … 350 110

[0198] Based on the speed ranking of traffic flow in lane 4, the calculated speed control for lane 4 is as follows:

[0199] V c4 = 101 (km / h)

[0200] S63: The speed control of each lane is determined by the calculated traffic flow. The calculation results of the speed limit control scheme for each lane are shown in Table 7.

[0201] Table 7

[0202]

[0203]

[0204] Note: " / " indicates that there is no speed limit for this lane.

Claims

1. A lane-level speed limit control method for a construction zone in a high-speed weaving section in a connected vehicle environment. It is characterized in that The following steps are involved: Step 1: Divide the construction impact control area of ​​the high-speed interweaving section in the vehicle networking environment into grids, and number each grid; Step 2: Determine the grid area of ​​the construction impact control area based on the vehicle running direction and characteristics; Step 3, collecting traffic characteristic data of the control area affected by the construction of the high-speed interweaving section; Step 4: Calculate the traffic flow characteristics in the traffic control grid area of ​​the construction impact control area based on the traffic characteristic data, and calculate the traffic flow in the construction impact control area; Step 5: Divert the traffic flow in the construction-affected traffic area from the middle lane to the outer lanes in sequence, and determine the traffic flow allocation plan for the construction-affected control area of ​​the high-speed interweaving section; Step 6: According to the traffic flow allocation plan of the construction impact control area, determine the speed sequence of the guided traffic flow in each lane, and determine the lane-level speed limit control plan of the construction area of ​​the high-speed interweaving section; Step 1 specifically includes the following sub-steps: Step 101: Determine the control starting point section According to the length L of the high-speed weaving section and the distance D between the starting section of the construction area and the starting section of the weaving area, determine the horizontal distance D between the starting section of the control area and the starting section of the construction area. c , the expression is as follows: Step 102: Divide the grid of the construction impact control area of ​​the high-speed interweaving section in the vehicle networking environment The enclosed area from the control starting section to the end section of the interweaving area is divided into rectangular road grids, each grid length is l g , width is l d ; Step 103: numbering the grids of the construction impact control area of ​​the high-speed interweaving section in the vehicle networking environment Number each grid in turn according to the direction of traffic flow, and record each grid number as G ij , represents the jth grid of the i-th lane; Step 2 specifically includes: According to the construction area being located in the Wth lane and the length of the construction area L W , determine the area enclosed by the lane from the control starting point to the end point of the construction area as the construction impact control area grid area G W , expressed as: G W ={G W1 ,G W2 ,…,G WZ } Where Z represents the number of grids occupied by the construction impact control area, and the expression is: Step 3 includes collecting real-time traffic characteristic data and historical traffic characteristic data of the control area affected by the construction of the high-speed interweaving section: When the vehicle passes the upstream D of the control starting section a When the acquisition control starting point section is in unit time period t m The traffic volume Q in each lane i and the speed V of each vehicle Q_i ; Collect characteristic data of each grid in the construction control area of ​​the high-speed interweaving section under the vehicle networking environment during the h period of historical time H, including the left lane flow diversion Right lane flow diversion And the traffic flow of each lane at the point section Step 4 specifically includes the following sub-steps: Step 401, calculating grid vehicle interweaving operation characteristics Based on the collected historical traffic characteristics data of the high-speed interweaving section construction impact control area, calculate the historical left-side flow distribution of each grid in the high-speed interweaving section construction impact control area during the h period of historical time H Right side flow and total flow The expressions are: Calculate the diversion ratio of the left lane of the grid based on the historical diversion volume and right lane split ratio The grid vehicle interweaving operation characteristics are obtained, and the expressions are: Step 402: Calculate the vehicle interweaving characteristics in the grid area of ​​the construction impact control area Calculate the diversion ratio of the left lane of the grid in the construction impact control area based on the interweaving characteristics of grid vehicles and right lane split ratio The vehicle interweaving operation characteristics of the grid area of ​​the construction impact control area are obtained, and the expressions are: In the formula, It represents the diversion ratio of the left lane of the Ath grid in the construction impact control area. It represents the diversion ratio of the right lane of the Ath grid in the construction impact control area; Step 403: Calculate the traffic flow after the construction impact control area is intertwined According to the vehicle interweaving characteristics of the construction impact control area grid area, calculate the vehicle flow from the left area of ​​the construction impact control area into the construction impact control area and the traffic flow from the right side of the construction area into the construction impact control area Then calculate the traffic flow Q after the construction impact control area is intertwined ′ W , the expressions are: In the formula, represents the right diversion ratio of lane W-1, represents the left diversion ratio of the W+1 lane, Q W Indicates that the construction affects the traffic flow before the intersection of the control area; Step 5 specifically includes the following sub-steps: Step 501: Calculate the lane diversion plan for the construction impact control area The traffic flow in the construction affected control area is divided into the number of lanes in the construction area In (d W ) ratio, calculate the lane diversion plan for the construction impact control area, and the expressions are: In the formula, ΔQ′ (W→(W-1)) Indicates the traffic flow diversion from the construction control area to the left lane, ΔQ′ (W→(W+1)) Indicates that the construction affects the control area and diverts traffic to the right lane; Step 502: Calculate lane control traffic flow According to the collected unit time period t of each lane m The traffic volume Q i , calculate lanes to control traffic flow The expression is: Step 503: Calculate other lane diversion solutions According to the lane control traffic flow, the traffic is diverted from the middle construction area lane to the outer lanes in sequence, and the diversion volume ΔQ′ of the left lane is calculated respectively. ((W-f)→(W-f-1)) and the right lane split flow ΔQ′ ((u-W)→(u-W+1)) , the expressions are: In the formula, Q′ (W-f) represents the traffic flow of lane Wf, Q′ (u-W) represents the traffic flow in the uW lane; Step 6 specifically includes the following sub-steps: Step 601: Calculate the vehicle speed control of the left diversion lane Sort the speed of the traffic in lane Wf from small to large, and determine the Rank (Q c((W-f)→(W-f-1)) ), calculate the speed corresponding to the vehicle, that is, the traffic control speed V of lane Wf c(W-f) , the expression is: Step 602: Calculate the vehicle speed control of the right diverging lane Sort the speed of the traffic in lane Wu from small to large, and determine the Rank (Q c((W-u)→(W-u+1)) ), calculate the speed corresponding to the vehicle, that is, the traffic flow control speed V of lane Wu c(W-u) , the expression is: Step 603: Determine lane-level speed limit control scheme The speed limit of the corresponding lane is set according to the traffic flow control speed of each lane. The speed limit of the innermost and outermost lanes remains unchanged. The construction area lane is only equipped with a diversion sign. The lane-level speed limit control plan is set according to the speed limit of each lane, and every time period t m The speed limit for each lane is dynamically updated based on the newly collected data.