A jacking method and system for multi-tower construction

By classifying tower cranes and establishing safety identification zones, and by optimizing the jacking scheme using collision detection algorithms, the problems of time-consuming and labor-intensive jacking scheme formulation and high collision risk in multi-tower construction have been solved, achieving rapid and safe tower crane jacking.

CN117105099BActive Publication Date: 2026-11-17CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202310888787.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-19
Publication Date
2026-11-17
Estimated Expiration
2043-07-19

AI Technical Summary

Technical Problem

In existing technologies, the formulation of jacking operation plans for multi-tower construction is time-consuming and labor-intensive, and the lack of an effective scheduling system leads to a high risk of collisions during the jacking process.

Method used

By classifying tower cranes and establishing safety identification zones, and by using collision detection algorithms to optimize the jacking scheme, an automated tower crane jacking scheme is generated to avoid tower crane collisions.

Benefits of technology

It enables the rapid and safe generation of multi-tower jacking schemes, reduces the time required for scheme development, avoids tower crane collisions, and ensures construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117105099B_ABST
    Figure CN117105099B_ABST
Patent Text Reader

Abstract

This application relates to the field of construction equipment scheduling technology, specifically disclosing a jacking method and system for multi-tower construction. The jacking method for multi-tower construction includes: acquiring tower crane foundation information and tower crane construction safety indicators; establishing a safety identification zone by combining the tower crane foundation information with the tower crane construction safety indicators; classifying tower cranes into target tower cranes, anchored tower cranes, and free tower cranes; and adjusting free tower cranes within the safety identification zone of the target tower crane to outside the target tower crane's safety identification zone; step 6: using a collision detection algorithm to perform collision detection on the target tower crane, free tower crane, and anchored tower crane. If a collision is found, the data adjusted in step 5 is used as the initial data and repeated until no collision occurs, and then a jacking plan is derived. The purpose of this patent is to solve the problems of time-consuming and labor-intensive development of existing multi-tower jacking operation plans and the lack of a multi-tower jacking scheduling system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of construction equipment scheduling technology, and in particular to a jacking method and system for multi-tower construction. Background Technology

[0002] With the development of society and the economy, the number of large-scale public building projects is increasing, and the application of tower cranes is becoming more and more widespread. Tower cranes are also constantly changing in size and height. Tower crane operations have also shifted from single-tower operations to multi-tower operations. This has led to a sharp increase in the number of hazardous factors, bringing many difficulties to on-site safety management.

[0003] Currently, high-speed railway station construction often involves multiple sections and large areas of simultaneous construction. Cross-operation of tower cranes within and between construction units is unavoidable. As the building is constructed, the distance between the tower cranes and the building gradually decreases. When the distance is less than 10 meters, tower crane lifting becomes difficult and affects the lifting process. Therefore, the tower cranes must be raised again, using their own hydraulic systems to lift standard sections one by one—this is the tower crane jacking operation. Before the tower crane jacking operation, due to the cross-operation of tower cranes among various construction units, a tower crane jacking plan needs to be developed through coordination meetings. Because multiple tower cranes from multiple construction units are involved, and some tower cranes need to be kept at a certain height for construction requirements and cannot be adjusted, the tower crane jacking plan design process is complex. Furthermore, due to the lack of experimental simulation and verification, errors may occur during actual operation, and tower crane collisions are prone to occur during the jacking process, resulting in a high risk of implementing the jacking plan.

[0004] During peak construction of a high-speed railway station project, 55 tower cranes operate simultaneously, posing challenges to the development of collision avoidance and jacking strategies. Existing tower crane coordination systems primarily focus on optimizing the operating paths of the cranes to create a reasonable crane layout, without addressing adjustments or optimizations during jacking operations. Furthermore, current tower crane jacking control systems only manage the jacking of individual cranes, thus failing to optimize the scheduling of group jacking operations. Summary of the Invention

[0005] To address the shortcomings of existing technologies, the technical problem solved by this invention is to provide a jacking method and system for multi-tower construction, which solves the problems of time-consuming and labor-intensive formulation of existing multi-tower jacking operation plans and the lack of a multi-tower jacking scheduling system.

[0006] To solve the above problems, the technical solution adopted by the present invention is: a jacking method for multi-tower construction, comprising the following steps;

[0007] Step 1: Obtain tower crane foundation information and tower crane construction safety indicators;

[0008] Step 2: Establish a safety identification zone by combining tower crane foundation information with tower crane construction safety indicators;

[0009] Step 3: Classify the tower cranes into target tower cranes, anchored tower cranes, and free tower cranes. Tower cranes that need to be lifted are marked as target tower cranes, tower cranes with fixed and non-adjustable heights are marked as anchored tower cranes, and tower cranes with adjustable heights are marked as free tower cranes. Number each type of tower crane sequentially, and associate the target tower crane with the corresponding lifting target height value according to the number.

[0010] Step 4: Perform jacking calculations on the target tower crane. The jacking calculations include the following steps:

[0011] Step 41: Adjust the current target tower crane to the target lifting height value, and use a collision detection algorithm to filter out tower cranes within the safety identification zone of the current target tower crane; Step 42: Determine whether there are anchored tower cranes or other target tower cranes within the safety identification zone of the current target tower crane. If so, modify the height of the current target tower crane and repeat Step 41; if not, proceed to Step 43; Step 43: Move the free tower cranes within the safety identification zone of the current target tower crane to outside the safety identification zone of the current target tower crane;

[0012] Step 5: Use a collision detection algorithm to perform collision detection on the target tower crane, free tower crane, and anchored tower crane. If a collision is found, use the data adjusted in step 43 as the initial data for the current target tower crane and repeat step 4; if there is no collision, increment the target tower crane number and repeat step 4.

[0013] Step 6: Generate a lifting plan after all target tower cranes have completed the lifting calculation.

[0014] The beneficial effects of this solution are as follows: Tower cranes are categorized based on their adjustability; a safety identification zone is established based on construction safety indicators, allowing for the selection of adjustable tower cranes within the zone that clearly require adjustment, thus narrowing the range of cranes needing adjustment and reducing the workload. Collision algorithms are used to detect adjusted tower crane data, enabling experimental simulation of the jacking scheme and ensuring the safety of the final jacking plan. By employing this method, only the tower crane foundation information and the expected jacking data of the target tower crane need to be collected beforehand; a tower crane jacking scheme can be quickly calculated based on the foundation information, eliminating the need for multiple coordination meetings and effectively shortening the customization time for the tower crane jacking scheme. Furthermore, simulation avoids collision hazards after jacking, ensuring the safety of the tower crane jacking process.

[0015] Furthermore, the adjustment of the free tower crane within the safety identification zone includes the following steps;

[0016] Step 431: Sort the free tower cranes in the safety identification zone according to the elevation of the tower crane cantilever;

[0017] Step 432: Based on the sorting results, adjust the free tower cranes in the safety identification zone section by section from high to low until there are no free tower cranes in the target tower crane's safety identification zone.

[0018] Adjustments should be made section by section according to height to avoid collisions with the tower crane during the adjustment process.

[0019] Furthermore, the tower crane foundation information includes the section height, cantilever slewing radius, tower crane coordinates, cantilever elevation, and cantilever upper and lower chord elevations.

[0020] Furthermore, the tower crane construction safety indicators include the radial intersection area between two adjacent tower crane cantilever arms and the height difference between the two cantilever arms. By setting safety indicators, it is ensured that the tower cranes comply with construction safety regulations after adjustment, thus preventing collisions and safety accidents that may occur after adjustment.

[0021] Furthermore, the tower crane foundation information also includes the minimum attachment height H3, the interval attachment height H4, and the first wall attachment height H5; step 6 also includes tower crane wall attachment calculation, which includes the following steps:

[0022] Step 61: Determine whether the height of the target tower crane and the free tower crane is greater than or equal to H3 according to the number. If not, output the jacking plan. If yes, proceed to step 62.

[0023] Step 62: Determine if the current tower crane has a first wall attachment. If not, add a wall attachment at a distance of H5 from the tower crane's elevation. If it does, add a wall attachment at every H4 height interval until the wall attachment calculations for all target tower cranes and free tower cranes are completed, and output the jacking plan.

[0024] By performing wall-attachment calculations on the tower cranes, the tower cranes that need to be attached to the wall and their attachment positions can be determined, thereby ensuring the installation temperature of the tower cranes after adjustment and ensuring safe construction of multiple tower cranes.

[0025] Furthermore, a jacking system for multi-tower construction includes a human-machine interaction unit, a data storage unit and a data processing unit, a collision detection unit and a scheme generation unit;

[0026] The human-machine interaction unit is used to interact with users. Users can import tower crane basic data, tower crane jacking data and tower crane type through the human-machine interaction unit. Tower crane types include target tower crane, free tower crane and anchored tower crane.

[0027] The data storage unit is used to store tower crane foundation data, tower crane jacking data, and tower crane height adjustment data processed by the data processing unit.

[0028] The data processing unit is used to extract tower crane foundation data and tower crane jacking data from the data storage unit, and adjust the height of the free tower crane according to the tower crane jacking data;

[0029] The collision detection unit is used to extract tower crane foundation data and tower crane height adjustment data from the data storage unit, and to perform collision detection based on the tower crane foundation data and tower crane height adjustment data;

[0030] The scheme generation unit is used to generate a tower crane lifting scheme based on the collision detection results, using tower crane foundation data, tower crane lifting data, and tower crane height adjustment data.

[0031] The tower crane jacking system enables automated generation of jacking schemes and avoids collisions between tower cranes after adjustments through collision detection. The system can output a jacking scheme within a certain time. The jacking scheme exported from this system was verified in a high-speed railway station project. No collisions occurred during the jacking of the tower cranes. The system can be promoted and applied to the jacking operations of tower cranes in various large-scale projects.

[0032] Furthermore, the data processing unit includes a safety identification zone establishment module and a tower crane adjustment module; the safety identification zone is used to establish a safety identification zone based on the tower crane foundation data, tower crane jacking data and safety distance indicators of the target tower crane, and the tower crane adjustment module is used to detect the tower cranes within the safety identification zone and adjust the height of the free tower cranes within the safety identification zone. Attached Figure Description

[0033] Figure 1 This is a schematic diagram of the system modules of the present invention.

[0034] Figure 2 This is a system flowchart of Embodiment 1 of the present invention.

[0035] Figure 3 This is a system flowchart of Embodiment 2 of the present invention. Detailed Implementation

[0036] The following detailed description illustrates the specific implementation method:

[0037] Example 1 is as attached. Figure 2 As shown: A jacking method for multi-tower construction, comprising the following steps;

[0038] Step 1: Obtain tower crane foundation information, tower crane construction safety indicators, and target jacking height values ​​and form a database; tower crane foundation information can be collected offline or imported using a BIM system; tower crane foundation information includes tower crane model, jib size, counterweight size, section height, slewing radius, tower crane coordinates, and cantilever top and bottom chord elevations, including the jib top and bottom chord elevations and the horizontal jib top and bottom chord elevations;

[0039] Step 2: Combine the tower crane coordinates, the heights of the upper and lower chords of the jib and the upper and lower chords of the horizontal jib with the tower crane construction safety indicators to establish a safety identification zone. The safety identification zone is a cylindrical three-dimensional digital model. The tower crane construction safety indicators include the shortest distance H1 between two adjacent tower crane jibs and the height difference H2 between the lower chords of two adjacent tower crane jibs. The safety requirement range for H1 is 2-3m, preferably 2m in this embodiment; the safety requirement range for H2 is 6-7m, preferably 6m in this embodiment.

[0040] Step 3: Classify the tower cranes into target tower cranes, anchored tower cranes, and free tower cranes. Tower cranes requiring jacking are marked as target tower cranes, tower cranes with fixed, non-adjustable heights are marked as anchored tower cranes, and tower cranes with adjustable heights are marked as free tower cranes. Number the target tower cranes sequentially, starting from 1; number the anchored tower cranes sequentially, starting from 1; and number the free tower cranes sequentially, starting from 1. Then, associate each target tower crane with its corresponding jacking target height value according to its number.

[0041] Step 4: Perform jacking calculations on the target tower crane. The jacking calculations include the following steps:

[0042] Step 41: Adjust the current target tower crane to the target lifting height value, and use the collision detection algorithm to filter out tower cranes within the safe identification zone of the current target tower crane;

[0043] Step 42: Determine if there is an anchored tower crane or other target tower crane within the safety identification zone. If so, modify the current target tower crane height and repeat step 41; otherwise, proceed to the next step.

[0044] Step 43: Move the free tower crane within the safety identification zone of the current target tower crane to outside the safety identification zone of the current target tower crane; the adjustment of the free tower crane within the safety identification zone includes the following steps;

[0045] Step 431: Sort the free tower cranes in the safety identification zone according to the elevation of the tower crane cantilever;

[0046] Step 432: Based on the sorting results, adjust the free tower cranes in the safety identification zone section by section from high to low until there are no free tower cranes in the safety identification zone of the target tower crane;

[0047] Step 5: Use a collision detection algorithm to perform collision detection on the target tower crane, free tower crane, and anchored tower crane. If a collision is found, use the data adjusted in step 43 as the initial data for the current target tower crane and repeat step 4; if there is no collision, increment the target tower crane number and repeat step 4.

[0048] Step 6: Once all target tower cranes have completed their lifting operations, a lifting plan is generated.

[0049] In step 42, the target tower crane is modified by gradually increasing its height until no fixed tower crane or other target tower cranes are detected within the safe range of the current target tower crane.

[0050] As attached Figure 1 As shown, a jacking system for multi-tower construction includes a human-machine interaction unit, a data storage unit and a data processing unit, a collision detection unit and a scheme generation unit.

[0051] The human-machine interface (HMI) unit is used for user interaction. Users can import tower crane foundation data, tower crane jacking data, and tower crane type through the HMI unit. Tower crane types include target tower crane, free tower crane, and anchored tower crane. Tower crane foundation data can be imported in tabular format, and the tower crane jacking data represents the planned jacking height of the target tower crane.

[0052] The data storage unit is used to store tower crane foundation data, tower crane jacking data, and tower crane height adjustment data processed by the data processing unit.

[0053] The data processing unit is used to extract tower crane foundation data and tower crane jacking data from the data storage unit, and adjust the height of the free tower crane according to the tower crane jacking data. The data processing unit includes a safety identification zone establishment module and a tower crane adjustment module. The safety identification zone is used to establish a safety identification zone based on the target tower crane's tower crane foundation data, tower crane jacking data, and safety distance indicators. The tower crane adjustment module is used to detect the free tower crane within the safety identification zone and adjust the cantilever height of the free tower crane within the safety identification zone.

[0054] The collision detection unit is used to extract tower crane foundation data and tower crane height adjustment data from the data storage unit, and to perform collision detection based on the tower crane foundation data and tower crane height adjustment data.

[0055] The scheme generation unit is used to generate a tower crane jacking scheme based on the collision detection results, using tower crane foundation data, tower crane jacking data, and tower crane height adjustment data. The jacking scheme is exported in tabular form, and includes the tower crane serial number, existing installation height, existing tower crane elevation, planned adjustment time, adjusted tower height, and adjusted tower height elevation. The units for existing installation height and adjusted tower height are the number of standard tower crane sections; the units for existing tower height elevation and adjusted tower height elevation are meters (m).

[0056] Example 2 Figure 3 As shown, the parts that are the same as in Example 1 will not be repeated here. The differences are as follows:

[0057] A jacking method for multi-tower construction includes the following steps;

[0058] Step 1: Obtain tower crane foundation information, tower crane construction safety indicators, and target jacking height values ​​and form a database; tower crane foundation information can be collected offline or imported using a BIM system; tower crane foundation information includes tower crane model, jib size, counterweight size, section height, slewing radius, tower crane coordinates, and cantilever top and bottom chord elevations, as well as minimum attachment height H3, interval attachment height H4, and first wall attachment height H5. Cantilever top and bottom chord elevations include the top and bottom chord elevations of the boom and the horizontal boom; H3 is 30-45m, preferably 40m in this embodiment; H4 is 18-25m, preferably 20m in this embodiment; H5 is 25-35m, preferably 30m in this embodiment.

[0059] Step 2: Combine the tower crane coordinates, the heights of the upper and lower chords of the jib and the upper and lower chords of the horizontal jib with the tower crane construction safety indicators to establish a safety identification zone. The safety identification zone is a cylindrical three-dimensional digital model. The tower crane construction safety indicators include the shortest distance H1 between two adjacent tower crane jibs and the height difference H2 between the lower chords of two adjacent tower crane jibs. The safety requirement range for H1 is 2-3m, preferably 2m in this embodiment; the safety requirement range for H2 is 6-7m, preferably 6m in this embodiment.

[0060] Step 3: Classify the tower cranes into target tower cranes, anchored tower cranes, and free tower cranes. Tower cranes that need to be lifted are marked as target tower cranes; tower cranes with fixed and non-adjustable heights are marked as anchored tower cranes; tower cranes with adjustable heights are marked as free tower cranes; number the classified tower cranes sequentially, and associate the target tower cranes with the corresponding lifting target height values ​​in sequence according to the numbers;

[0061] Step 4: Perform jacking calculations on the target tower crane. The jacking calculations include the following steps:

[0062] Step 41: Adjust the current target tower crane to the target lifting height value, and use the collision detection algorithm to filter out tower cranes within the safe identification zone of the current target tower crane;

[0063] Step 42: Determine if there are anchored tower cranes or other target tower cranes within the safety identification zone. If so, increase the height of the current target tower crane section by section; otherwise, proceed to the next step.

[0064] Step 43: Move the free tower crane within the target tower crane's safety identification zone to outside the target tower crane's safety identification zone; the adjustment of the free tower crane within the safety identification zone includes the following steps;

[0065] Step 431: Sort the free tower cranes in the safety identification zone according to the elevation of the tower crane cantilever;

[0066] Step 432: Based on the sorting results, adjust the free tower cranes in the safety identification zone section by section from high to low until there are no free tower cranes in the safety identification zone of the target tower crane;

[0067] Step 5: Use a collision detection algorithm to perform collision detection on the target tower crane, free tower crane, and anchored tower crane. If a collision is found, use the data adjusted in step 43 as the initial data for the current target tower crane and repeat step 4; if there is no collision, increment the target tower crane number and repeat step 4.

[0068] Step 6: Continue the tower crane attachment calculation until all target tower cranes have completed the lifting calculation;

[0069] Step 61: Determine whether the height of the target tower crane and the free tower crane is greater than or equal to H3 according to their numbers. If not, output the jacking plan; if yes, proceed to the next step.

[0070] Step 62: Determine if the current tower crane has a first wall attachment. If not, add a wall attachment at a distance of H5 from the tower crane's elevation. If it does, add a wall attachment at every H4 height interval until the wall attachment calculations for all target tower cranes and free tower cranes are completed, and output the jacking plan.

[0071] The above descriptions are merely embodiments of the present invention, and common knowledge regarding specific structures and characteristics is not elaborated upon here. It should be noted that those skilled in the art can make various modifications and improvements without departing from the structure of the present invention, and these should also be considered within the scope of protection of the present invention. These modifications and improvements will not affect the effectiveness of the present invention or the practicality of the patent. The scope of protection claimed in this application should be determined by the content of its claims, and the specific embodiments described in the specification can be used to interpret the content of the claims.

Claims

1. A jacking method for group tower construction, characterized by: Includes the following steps, Step 1: Obtain tower crane foundation information and tower crane construction safety indicators; Step 2: Establish a safety identification zone by combining tower crane foundation information with tower crane construction safety indicators; Step 3: Classify tower cranes into target tower cranes, anchored tower cranes, and free tower cranes. Tower cranes that need to be lifted are marked as target tower cranes; tower cranes with fixed and non-adjustable heights are marked as anchored tower cranes; tower cranes with adjustable heights are marked as free tower cranes; and then associate the target tower cranes with the corresponding lifting target height values ​​in sequence. Step 4: Perform jacking calculations on the target tower crane sequentially. The jacking calculation includes the following steps: Step 41: Adjust the current target tower crane to the target lifting height value, and use the collision detection algorithm to filter out tower cranes within the safe identification zone of the current target tower crane; Step 42: Determine if there is an anchored tower crane or other target tower crane within the safety identification zone. If so, modify the current target tower crane height and repeat step 41; otherwise, proceed to the next step. Step 43: Move the free tower crane within the safety identification zone of the current target tower crane to outside the safety identification zone of the current target tower crane; Step 431: Sort the free tower cranes in the safety identification zone according to the elevation of the tower crane cantilever; Step 432: Based on the sorting results, adjust the free tower cranes in the safety identification zone section by section from high to low until there are no free tower cranes in the safety identification zone of the target tower crane; Step 5: Use a collision detection algorithm to perform collision detection on the target tower crane, free tower crane, and anchored tower crane. If a collision is found, use the data adjusted in step 43 as the initial data for the current target tower crane and repeat step 4. Step 6: Once all target tower cranes have completed the jacking calculation, a jacking plan is generated; Step 6 also includes tower crane wall attachment calculation; the tower crane basic information also includes the minimum attachment height H3, interval attachment height H4, and first wall attachment height H5; the tower crane wall attachment calculation includes the following steps: Step 61: Determine whether the height of the target tower crane and the free tower crane is greater than or equal to H3 according to their numbers. If not, output the jacking plan; if yes, proceed to the next step. Step 62: Determine if the current tower crane has a first wall attachment. If not, add a wall attachment at a distance of H5 from the tower crane's elevation. If it does, add a wall attachment at every H4 height interval until the wall attachment calculations for all target tower cranes and free tower cranes are completed, and output the jacking plan.

2. The jacking method for multi-tower construction according to claim 1, characterized in that: The tower crane foundation information includes the section height, cantilever slewing radius, tower crane coordinates, cantilever elevation, and cantilever top and bottom chord elevations.

3. The jacking method for multi-tower construction according to claim 1, characterized in that: The tower crane construction safety indicators include the radius intersection area between two adjacent tower crane cantilever arms and the height difference between the two cantilever arms.

4. A jacking system for multi-tower construction, the system being used to implement the method described in any one of claims 1-3, characterized in that: It includes a human-computer interaction unit, a data storage unit and a data processing unit, a collision detection unit and a solution generation unit; The human-machine interaction unit is used to interact with users. Users can import tower crane basic data, tower crane jacking data and tower crane type through the human-machine interaction unit. Tower crane types include target tower crane, free tower crane and anchored tower crane. The data storage unit is used to store tower crane foundation data, tower crane jacking data, and tower crane height adjustment data processed by the data processing unit. The data processing unit is used to extract tower crane foundation data and tower crane jacking data from the data storage unit, and adjust the height of the free tower crane according to the tower crane jacking data; The collision detection unit is used to extract tower crane foundation data and tower crane height adjustment data from the data storage unit, and to perform collision detection based on the tower crane foundation data and tower crane height adjustment data; The scheme generation unit is used to generate a tower crane lifting scheme based on the collision detection results, using tower crane foundation data, tower crane lifting data, and tower crane height adjustment data.

5. The jacking system for multi-tower construction according to claim 4, characterized in that: The data processing unit includes a safety identification zone establishment module and a tower crane adjustment module. The safety identification zone is used to establish a safety identification zone based on the tower crane foundation data, tower crane jacking data and safety distance indicators of the target tower crane. The tower crane adjustment module is used to detect the tower cranes within the safety identification zone and adjust the height of the free tower cranes within the safety identification zone.

Citation Information

Patent Citations

  • Method for calculating installation height of group of towers and computer readable storage medium

    CN113378271A