A mine irregular block filling frame and method
By using long baffles, folding partitions, and prestressed anchor cables to form stepped filling bodies in mines, the stability problem of mine filling bodies under vibration and impact was solved, and the safety and compressive strength of the mine filling area were improved.
Patent Information
- Application Number
- CN202311450234.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-02
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-11-02
AI Technical Summary
The existing mine filling methods do not have bonding and embedding effects between the filling bodies, resulting in poor stability under vibration and impact. They are prone to deformation and displacement, leading to safety hazards such as pressure deformation and collapse of the artificial false bottom.
A mine irregular block filling frame is adopted, including long strip baffles, folded partitions, prestressed anchor cables and filling components. By forming an irregular filling area in the mining area and applying prestress to the folded partitions using prestressed anchor cables, a stepped filling body is formed, which realizes the embedding and self-stabilization of the filling body.
It improves the compressive strength of the mine after backfilling, ensures the safety and stability of the backfilled area, avoids accidents such as collapse, and improves the overall safety of the backfilled area.
Smart Images

Figure CN117345332B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of mine filling technology, and in particular to a mine irregular block filling frame and method. Background Technology
[0002] Mining involves excavating underground ore bodies. During this process, voids are formed beneath the surface. If no support measures are taken, the risk of surface subsidence will increase as mining progresses, affecting the safety of open-pit and underground operations and hindering the maximum recovery of mineral resources. Therefore, during mining, it is necessary to simultaneously fill the mining area to improve the stress on the pillars and prevent subsidence.
[0003] Currently, the most common filling method in mine backfilling operations is layered full filling, which involves vertically dividing the area to be filled into several layers and filling each layer as a whole space to coordinate with the mining rhythm in the mine. In order to ensure the safety of the backfill, an artificial false bottom is often required at the bottom layer of the backfill. The pressure of the backfill is all vertically transmitted to the artificial false bottom. It can be seen that the backfill formed by the existing filling method has no bonding and embedding effect between the backfills, and its stability under vibration and impact is poor. It is prone to deformation and displacement during mining operations, which in turn causes the artificial false bottom to be subjected to great pressure and deformation, leading to accidents such as collapse, posing a significant safety hazard. Summary of the Invention
[0004] In view of the shortcomings of the prior art, the purpose of this application is to provide a mine irregular block filling frame and method to solve the problem that the filling bodies formed by the existing filling methods do not have bonding and embedding effects, have poor stability under vibration and impact, are prone to deformation and displacement during mining operations, and thus cause the artificial false bottom to be subjected to great pressure and deformation, leading to accidents such as collapse and other serious safety hazards.
[0005] To achieve the above and other related objectives, in a first aspect, this application provides a mine irregular block filling frame for filling mining areas, comprising:
[0006] Long strip baffles are vertically installed in the mining area and extend along a first direction. Multiple long strip baffles are arranged in parallel and at intervals.
[0007] A folding partition is disposed between two adjacent elongated baffles, and multiple partitions are arranged at intervals along the first direction. The two adjacent folding partitions and the elongated baffles enclose an irregularly shaped filling area. The folding partition is a stepped plate structure composed of at least three plates spliced together in sequence. The two adjacent plates of the same folding partition are folded at right angles. A filling port is provided on the folding partition.
[0008] One or more prestressed anchor cables are provided in each of the irregular filling areas. The two ends of the prestressed anchor cables are used to fasten to two adjacent folded partitions and penetrate the irregular filling area along the first direction.
[0009] A filling assembly includes a filling hose for insertion into the filling port to fill the irregular filling area with slurry.
[0010] Furthermore, the prestressed anchor cable includes a tensioning base plate, a tensioning face plate, a cable, and a cable sleeve. An anchor cable opening is provided on the folded partition plate. The folded partition plate includes a first partition plate and a second partition plate forming the same irregular filling area. The anchor cable opening on the first partition plate is positioned opposite to the anchor cable opening on the second partition plate. The tensioning base plate is attached to the outside of the first partition plate. The first end of the cable passes through the anchor cable opening of the first partition plate and connects to the tensioning base plate. The second end of the cable is used to pass through the anchor cable opening of the second partition plate and connect through the tensioning face plate to tighten within the irregular filling area. The cable sleeve is fitted onto the cable. The diameter of the cable sleeve is smaller than the diameter of the anchor cable opening, so that the cable sleeve can be pulled out from the irregular filling area before the second end of the cable is connected to the tensioning face plate.
[0011] Furthermore, the filling assembly includes a three-way valve disposed on the filling hose and a storage bag connected to the three-way valve.
[0012] Furthermore, the multiple panels of the folding partition are hinged together, and two hinged panels are provided with right-angle fasteners at the joint edges. The right-angle fasteners are L-shaped and are connected to the two adjacent panels respectively by fasteners, so that the included angle between the two adjacent panels is a right angle.
[0013] Furthermore, the mine irregular block filling frame also includes a ground stabilization component, which includes a pressure plate that fits against the mine surface and a fixed wing that is vertically connected to the pressure plate. The fixed wing is used to connect to the bottom end of the elongated baffle or the folding partition.
[0014] Secondly, this application also provides a method for filling irregularly shaped blocks in a mine. Based on the same inventive concept, this method fills the mining area of the mine by constructing the irregularly shaped block filling framework as described above, to obtain several staggered stacked irregularly shaped block filling bodies. The method includes:
[0015] S1, In the filling area of the mining area, several long strip baffles are vertically installed to divide the filling area into several long strip-shaped filling areas, wherein the extension direction of the long strip baffles should be flush with the extension direction of the mining operation.
[0016] S2, in the elongated area to be filled, the folding partitions are fixed and spaced apart, so that at least two adjacent folding partitions and the elongated baffles enclose an irregular filling area;
[0017] S3, the prestressed anchor cable is installed in the irregular filling area;
[0018] S4, insert the filling hose into the irregular filling area through the filling port, fill the irregular filling area with slurry, and pull out the filling hose before the slurry solidifies. After the slurry solidifies, a stepped filling body is formed in the irregular filling area.
[0019] S5, prestress is applied to the folded partitions on both sides of the irregular filling area through the prestressed anchor cable.
[0020] Furthermore, when step S1 is executed for the first time, the ground of the area to be filled is used as the mounting base of the long strip baffle. After step S1-S5 is executed twice or more to obtain multiple stepped filling bodies arranged in a single layer, the top end face of the stepped filling body is used as the mounting base of the long strip baffle to fill the area above the formed stepped filling body.
[0021] The above-described irregular block filling frame and method for mines has at least the following advantages:
[0022] The irregularly shaped filling area enclosed by folded partitions allows for the formation of a stepped filling body after filling. The stepped filling bodies interlock and interlock to form an integral structure, which generates a self-stabilizing effect. This is beneficial for absorbing and transmitting pressure changes between the overlying ore body and the filling body, thereby dispersing the pressure evenly and effectively improving the mine's compressive strength after filling, ensuring the safety of operations under the filling area. Attached Figure Description
[0023] Figure 1 A schematic diagram of the structure of a mine irregular block filling frame shown as an exemplary embodiment of this application;
[0024] Figure 2 A schematic diagram showing the distribution of prestressed anchor cables in a first direction of a mine irregular block filling frame, as illustrated in another exemplary embodiment of this application;
[0025] Figure 3 This is a schematic diagram illustrating the disassembled structure of a prestressed anchor cable, as shown in an exemplary embodiment of this application.
[0026] Figure 4 This is a schematic diagram illustrating the unfolded structure of a folding partition as shown in an exemplary embodiment of this application;
[0027] Figure 5 This is a schematic cross-sectional view of a right-angle fastener as shown in an exemplary embodiment of this application;
[0028] Figure 6 This is a schematic diagram of the structure of a filling component shown in an exemplary embodiment of this application;
[0029] Figure 7 This is a schematic diagram of the structure of a ground-fixing component shown in an exemplary embodiment of this application.
[0030] Part Number Explanation
[0031] 1-Stepped filling body; 2-Long strip baffle; 3-Prestressed anchor cable; 31-Tightening base plate; 32-Cable; 33-Tightening face plate; 34-Cable sleeve; 4-Folding partition; 41-Hinge; 42-Filling port; 43-First mounting hole; 44-Second mounting hole; 45-Right angle fastener; 46-Ground stabilization component; 461-Fixing wing; 462-Pressure plate; 5-Filling component; 51-Filling hose; 52-Three-way valve; 53-Storage bag. Detailed Implementation
[0032] The following specific embodiments illustrate the implementation of this application. Those skilled in the art can easily understand other advantages and effects of this application from the content disclosed in this specification.
[0033] It should be understood that the structures, proportions, sizes, etc., illustrated in the accompanying drawings of this specification are merely for illustrative purposes to aid those skilled in the art and are not intended to limit the scope of this application. Therefore, they have no substantial technical significance. Any modifications to the structure, changes in proportions, or adjustments to size, without affecting the effectiveness and purpose of this application, should still fall within the scope of the technical content disclosed in this application. Furthermore, the terms such as "upper," "lower," "left," "right," "middle," "first," and "second" used in this specification are merely for clarity and are not intended to limit the scope of this application. Changes or adjustments to their relative relationships, without substantially altering the technical content, should also be considered within the scope of this application.
[0034] In one embodiment, this application exemplarily illustrates the structure of a mine irregular block filling frame, which is used to fill the mining area of a mine. In this embodiment, the mine irregular block filling frame includes a long strip baffle 2, a folding partition 4, a prestressed anchor cable 3, and a filling component 5, wherein:
[0035] The long strip baffle 2 is vertically set in the mining area and extends along the first direction. Multiple long strip baffles 2 are set in parallel and at intervals. It should be understood that the purpose of mine backfilling is to prevent the empty area after mining from collapsing due to the pressure of the rock and soil above as mining progresses. Therefore, the direction of backfilling should coincide with the direction of mining. In this embodiment, backfilling needs to be carried out along the extension direction of the long strip baffle 2. Therefore, the first direction here refers to the mining direction in the mine, that is, the extension direction of the area in the mine that needs to be filled.
[0036] Folding partitions 4 are arranged between two adjacent long strip baffles 2, and multiple partitions are arranged at intervals along the first direction. The two adjacent folding partitions 4 and the long strip baffles 2 enclose an irregular filling area. The folding partition 4 is a stepped plate structure composed of at least three plates spliced together in sequence. The two adjacent plates of the same folding partition 4 are folded at right angles. A filling port 42 is provided on the folding partition 4 for filling slurry into the irregular filling area to form a filling body.
[0037] One or more prestressed anchor cables 3 are provided in each irregular filling area, for example, in this embodiment, please refer to Figure 1 Each panel is connected to four prestressed anchor cables 3. In another embodiment, please refer to... Figure 2 Each plate is connected to two prestressed anchor cables 3. The two ends of the prestressed anchor cables 3 are used to fasten to two adjacent folded partitions 4 and penetrate the irregular filling area along the first direction.
[0038] The filling assembly 5 includes a filling hose 51, which is inserted into the filling port 42 to fill the irregular filling area with slurry. Specifically, in this embodiment, please refer to... Figure 6 The filling assembly 5 also includes a three-way valve 52 disposed on the filling hose 51 and a storage bag 53 connected to the three-way valve 52. The storage bag 53 can store more slurry under the control of the three-way valve 52. The storage bag 53 can be reused during the filling process. For example, when filling other irregular filling areas, the storage bag 53 can be removed and installed on the corresponding three-way valve 52 so that the slurry stored in the storage bag 53 can be used for filling.
[0039] The above-described irregular block filling frame for mines, through the irregular filling area enclosed by folded partitions 4, forms a stepped filling body 1 arranged in succession after filling. The stepped filling bodies 1 are staggered and interlocked to form an integral structure, which generates a self-stabilizing effect. This is beneficial for absorbing and transmitting pressure changes between the overlying ore rock mass and the filling body, thereby evenly dispersing the pressure, effectively improving the mine's compressive strength after filling, and ensuring the safety of operations under the filling area.
[0040] In this embodiment, please refer to Figure 3The prestressed anchor cable 3 includes a tensioning base plate 31, a tensioning face plate 33, a cable 32, and a cable sleeve 34. An anchor cable opening is provided on the folding partition 4. The folding partition 4 includes a first partition and a second partition forming the same irregular filling area. The anchor cable openings on the first partition are positioned opposite to those on the second partition. The tensioning base plate 31 is attached to the outside of the first partition. The first end of the cable 32 passes through the anchor cable opening of the first partition and connects to the tensioning base plate 31. The second end of the cable 32 is used to pass through the anchor cable opening of the second partition. The cable 32 is connected to the tensioning plate 33 to tighten it within the irregular filling area. The cable sleeve 34 is fitted onto the cable 32 to prevent the cable 32 from being wrapped by the grout during the filling process, which would affect the effect of applying prestress through the cable 32. The diameter of the cable sleeve 34 is smaller than the diameter of the anchor cable opening so that the cable sleeve 34 can be pulled out from the irregular filling area before the second end of the cable 32 is connected to the tensioning plate 33, so that the cable sleeve 34 can be reused. The cable 32 and the tensioning plate 31 can be connected by hooks or other means.
[0041] In some embodiments, in addition to the filling component 5 being reusable for filling different areas, devices and components such as the long strip baffle 2, the folded closing plate, and the prestressed cable 32 can also be recycled for reuse after filling an irregularly shaped filling area, so as to save costs and improve the economy of filling.
[0042] In this embodiment, please refer to Figure 4 and Figure 5 The multiple panels of the folding partition 4 are hinged together by hinges 41. Two hinged panels have first mounting holes 43 at their joint edges for mounting right-angle fasteners 45. The right-angle fasteners 45 are L-shaped and have holes that mate with the first mounting holes 43. The right-angle fasteners 45 are connected to two adjacent panels by fasteners such as bolts passing through the holes and the first mounting holes 43 of the panels, so that the included angle between the two adjacent panels is a right angle. When not filled, the right-angle fasteners 45 can be removed and the folding partition 4 can be folded together by hinges 41 for easy transport and storage.
[0043] In this embodiment, the mine irregular block filling frame also includes a ground stabilization component 46, please refer to... Figure 7The ground stabilization component 46 includes a pressure plate 462 that fits against the mine surface and a fixing wing 461 that is vertically connected to the pressure plate 462. The fixing wing 461 is used to connect to the bottom end of the long strip baffle 2 or the folding partition 4. The connection can be made by setting through holes to allow bolts or other connecting parts to pass through. For example, in some embodiments, the folding partition 4 has a second mounting hole 44, and the fixing wing 461 has a hole that matches the second mounting hole 44, so that the end of the folding partition 4 and the fixing wing 461 can be connected by bolts or other connecting parts, and a weight can be pressed on the pressure plate 462 to firmly support the folding partition 4.
[0044] In another embodiment, this application also provides a method for filling irregularly shaped blocks in a mine. Based on the same inventive concept, this method fills the mining area of a mine by constructing the irregularly shaped block filling framework provided in this application, so as to obtain a plurality of staggered stacked irregularly shaped block filling bodies. The irregularly shaped block filling framework here can be the irregularly shaped block filling framework shown in the foregoing embodiment. The method specifically includes the following steps:
[0045] S1, In the filling area of the mining area, several long strip baffles are vertically installed to divide the filling area into several long strip-shaped filling areas. The extension direction of the long strip baffles should be flush with the extension direction of the mining operation.
[0046] S2, in the long strip-shaped area to be filled, the folding partitions are fixed and spaced apart, so that at least two adjacent folding partitions and the long strip baffles enclose an irregular filling area.
[0047] S3, Prestressed anchor cables are installed in the irregular filling area;
[0048] S4. Insert the filling hose into the irregular filling area through the filling port, fill the irregular filling area with slurry, and pull out the filling hose before the slurry solidifies. After the slurry solidifies, a stepped filling body is formed in the irregular filling area.
[0049] S5, prestress is applied to the folded partitions on both sides of the irregular filling area through prestressed anchor cables.
[0050] In some implementations, when step S1 is executed for the first time, the ground of the area to be filled is used as the mounting base for the long strip baffle. After step S1-S5 is executed twice or more to obtain multiple stepped filling bodies arranged in a single layer, the top end face of the stepped filling body is used as the mounting base for the long strip baffle to fill the area above the formed stepped filling body. Through the above implementation, the self-stabilizing characteristics between filling bodies can be further improved. By forming a multi-layered stepped filling body that is interlocked with each other, the filling reliability can be further improved.
[0051] The above-described method of irregular block backfilling in mines, through the irregular backfilling area enclosed by folded partitions, forms a stepped backfill body arranged in successive layers after backfilling. The stepped backfill bodies interlock and are interlocked to form an integral structure, which generates a self-stabilizing effect. This is beneficial for absorbing and transmitting pressure changes between the overlying ore body and the backfill body, thereby evenly dispersing the pressure and effectively improving the mine's compressive strength after backfilling, ensuring the safety of operations under the backfill area.
[0052] The above embodiments are merely illustrative of the principles and effects of this application and are not intended to limit this application. Any person skilled in the art can modify or alter the above embodiments without departing from the spirit and scope of this application. Therefore, all equivalent modifications or alterations made by those skilled in the art without departing from the spirit and technical concept disclosed in this application should still be covered by the claims of this application.
Claims
1. A mine shaped block filling frame for filling a mine excavation area, characterised in that, include: Long strip baffles are vertically installed in the mining area and extend along a first direction. Multiple long strip baffles are arranged in parallel and at intervals. A folding partition is disposed between two adjacent elongated baffles, and multiple partitions are arranged at intervals along the first direction. The two adjacent folding partitions and the elongated baffles enclose an irregularly shaped filling area. The folding partition is a stepped plate structure composed of at least three plates spliced together in sequence. The two adjacent plates of the same folding partition are folded at right angles. A filling port is provided on the folding partition. One or more prestressed anchor cables are provided in each of the irregular filling areas. The two ends of the prestressed anchor cables are used to fasten to two adjacent folded partitions and penetrate the irregular filling area along the first direction. A filling assembly includes a filling hose for insertion into the filling port to fill slurry into the irregular filling region; The prestressed anchor cable includes a tensioning base plate, a tensioning face plate, a cable, and a cable sleeve. An anchor cable opening is provided on the folded partition. The folded partition includes a first partition and a second partition forming the same irregular filling area. The anchor cable openings on the first partition are positioned opposite to those on the second partition. The tensioning base plate is attached to the outside of the first partition. The first end of the cable passes through the anchor cable opening in the first partition and connects to the tensioning base plate. The second end of the cable passes through the anchor cable opening in the second partition and connects to the tensioning face plate for tensioning within the irregular filling area. The cable sleeve... The tube is sleeved on the cable, and the diameter of the cable sleeve is smaller than the diameter of the anchor cable opening, so that the cable sleeve can be pulled out from the irregular filling area before the second end of the cable is connected to the tensioning plate; the filling assembly includes a three-way valve disposed on the filling hose and a storage bag connected to the three-way valve; the multiple plates of the folding partition are hinged together, and two plates that are hinged together are provided with right-angle fasteners at the joint edges. The right-angle fasteners are L-shaped sheet structures, and the right-angle fasteners are connected to the two adjacent plates respectively by fasteners, so that the included angle between the two adjacent plates is a right angle.
2. A mine blockfilling framework according to claim 1, characterised in that, It also includes a ground stabilization component, which includes a pressure plate that adheres to the mine surface and a fixed wing vertically connected to the pressure plate. The fixed wing is used to connect to the bottom end of the elongated baffle or the folding partition.
3. A method of mine block filling with irregular shapes, characterized by, By constructing a mine irregular block filling framework as described in any one of claims 1-2, the mining area is filled to obtain several staggered stacked irregular block filling bodies, the method comprising: S1, In the filling area of the mining area, several long strip baffles are vertically installed to divide the filling area into several long strip-shaped filling areas, wherein the extension direction of the long strip baffles should be flush with the extension direction of the mining operation. S2, in the elongated area to be filled, the folding partitions are fixed and spaced apart, so that at least two adjacent folding partitions and the elongated baffles enclose an irregular filling area; S3, the prestressed anchor cable is installed in the irregular filling area; S4, insert the filling hose into the irregular filling area through the filling port, fill the irregular filling area with slurry, and pull out the filling hose before the slurry solidifies. After the slurry solidifies, a stepped filling body is formed in the irregular filling area. S5, prestress is applied to the folded partitions on both sides of the irregular filling area through the prestressed anchor cable.
4. The method of mine block filling with irregular shapes according to claim 3, characterized in that, When step S1 is executed for the first time, the ground of the area to be filled is used as the mounting base of the long strip baffle. After step S1-S5 is executed twice or more to obtain multiple stepped filling bodies arranged in a single layer, the top end face of the stepped filling body is used as the mounting base of the long strip baffle to fill the area above the formed stepped filling body.
Citation Information
Patent Citations
Gob-side entry retaining reinforcing filling body structure and construction method thereof
CN101975085A
Prefabricated forming assembly type concrete structure and construction method of concrete wall
CN116696392A
Can found bagging apparatus that fills of mould fast
CN205172632U