Mechanical processing flexible production management system and method based on MES system
By analyzing historical equipment usage data through the MES system, resources can be filtered and configured, resolving conflicts caused by insufficient equipment resources in machining and improving production efficiency and quality.
Patent Information
- Application Number
- CN202311583705.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-24
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2043-11-24
AI Technical Summary
During machining, the overlapping and uneven demand for equipment for different parts in different processes can lead to resource conflicts when equipment resources are insufficient, thus affecting the efficiency of parts processing and production.
The machine tooling flexible production management system based on MES collects historical and abnormal data on parts processing, analyzes equipment usage, identifies equipment to be added, and optimizes equipment resource allocation through a resource allocation model to reduce resource conflicts.
It improved the efficiency and quality of parts processing and production, reduced equipment resource conflicts, and lowered unnecessary production costs.
Smart Images

Figure CN117522067B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of machining production management, and in particular to a mechanical machining flexible production management system and method based on an MES system. Background Art
[0002] MES system is a computerized system used to monitor, track and control the production process in real time. MES system can integrate and configure the production process, resources and data on the production line. Its core functions include production scheduling, material management, quality management, equipment management, personnel management and data analysis. Applying MES system to flexible production management of mechanical processing, setting control ports for all processes of parts processing, monitoring the busy and idle conditions of equipment pools and personnel pools, etc., and allocating resources according to process needs and busy and idle conditions, enhances the flexibility of parts processing production, and can effectively improve production efficiency and quality;
[0003] However, different equipment or instruments are required to process parts in different processing steps. Since the processing content of some parts is overlapping, the same equipment may be used to process different types of parts. The number of parts of each type that need to be processed is different, and the parts may be in large quantities. When different types and large quantities of parts need to be processed by the same equipment at a similar or even the same time, if the equipment resources are insufficient, resource usage conflicts are likely to occur, resulting in delays in the processing of some parts in the process applied to the equipment, affecting the efficiency of parts processing and production. The existing technology has not taken this into consideration and has not pre-emptively added equipment to reduce resource usage conflicts and improve the efficiency of parts processing and production.
[0004] Therefore, people need a mechanical processing flexible production management system and method based on the MES system to solve the above problems. Summary of the invention
[0005] The purpose of the present invention is to provide a mechanical processing flexible production management system and method based on an MES system to solve the problems raised in the above background technology.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a mechanical processing flexible production management system based on an MES system, the system comprising: a processing and production data acquisition module, a data management center, a processing data analysis module, a screening object information analysis module and a processing and production management module;
[0007] The output end of the processing and production data acquisition module is connected to the input end of the data management center, the output end of the data management center is connected to the input ends of the processing data analysis module, the screening object information analysis module and the processing and production management module, the output end of the processing data analysis module is connected to the input end of the screening object information analysis module, and the output end of the screening object information analysis module is connected to the input end of the processing and production management module;
[0008] The processing and production data acquisition module is used to collect historical data and processing abnormality data of parts processing, and transmit all the collected data to the data management center;
[0009] The data management center is used to store and manage all received data;
[0010] The processing data analysis module is used to analyze the historical data of parts processing and preliminarily screen out the equipment to be added;
[0011] The screening object information analysis module is used to analyze the processing abnormality data when the equipment to be added is used for parts processing, and to secondary screen out the equipment that ultimately needs to be added;
[0012] The processing and production management module is used to establish a resource allocation model and perform equipment resource allocation for parts processing.
[0013] Furthermore, the processing and production data collection module includes a process information collection unit, an equipment usage data collection unit and a processing progress collection unit;
[0014] The output ends of the process information collection unit, the equipment usage data collection unit and the processing progress collection unit are connected to the input end of the data management center;
[0015] The process information collection unit is used to collect process information previously set when processing different parts, including process number information and planned processing time of each process;
[0016] The process number information refers to the process number set according to the processing steps. The process number of the first step of processing is 1;
[0017] The equipment usage data acquisition unit is used to collect information on the interval between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing;
[0018] All of the above parts have the same start time for processing;
[0019] The processing progress collection unit is used to collect the processing delay time information of the process when the same equipment was used to process different parts in the past.
[0020] Furthermore, the processing data analysis module includes a usage time analysis unit and a to-be-added equipment screening unit;
[0021] The input end of the usage time analysis unit is connected to the output end of the data management center, and the output end of the usage time analysis unit is connected to the input end of the device screening unit to be added;
[0022] The usage time analysis unit is used to retrieve and compare the time interval information between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing;
[0023] The equipment screening unit to be added is used to classify parts according to the interval duration information, select the best classification result as reference data, analyze different equipment used in more than one part processing process, the interval duration information between the time of use and the start time of part processing, select reference data for different equipment, and screen out the equipment to be added based on the reference data.
[0024] Further, the screening object information analysis module includes a processing progress analysis unit and an additional equipment secondary screening unit;
[0025] The input end of the processing progress analysis unit is connected to the output end of the equipment screening unit to be added and the data management center, and the output end of the processing progress analysis unit is connected to the input end of the additional equipment secondary screening unit;
[0026] The processing progress analysis unit is used to retrieve the processing delay time information of the process that used the equipment to be added to process different parts in the past;
[0027] The process processing delay here refers to the process processing delay of using the equipment to be added to process a part. For example: if a part uses the equipment to be added when processing the second process, the delay at this time refers to the delay of the second process. If the original processing time of the second process is a, the actual processing time of the second process, that is, the time required to complete the second process, is extended to b, then the delay of the second process is ba;
[0028] The additional equipment secondary screening unit is used for secondary screening the equipment to be added to finally select the equipment that needs to be added in quantity from the equipment to be added according to the delay duration information.
[0029] Furthermore, the processing and production management module includes a resource allocation model establishment unit and an additional quantity planning unit;
[0030] The input end of the resource configuration model establishment unit is connected to the output end of the additional equipment secondary screening unit and the data management center, and the output end of the resource configuration model establishment unit is connected to the input end of the additional equipment quantity planning unit;
[0031] The resource allocation model establishment unit is used to count the number of installed devices with the number of additional devices required, and the number of parts that have been processed by different numbers of additional devices in the past, and establish a resource allocation model based on the statistical results;
[0032] The additional quantity planning unit is used to plan the number of additional devices that need to be added according to the resource allocation model.
[0033] The mechanical processing flexible production management method based on the MES system includes the following steps:
[0034] Z1: Collect historical data and abnormal processing data of parts processing;
[0035] Z2: Analyze the historical data of parts processing and preliminarily select the equipment to be added;
[0036] Z3: Analyze the abnormal processing data when the equipment to be added is used for parts processing, and select the equipment that needs to be added in the final number;
[0037] Z4: Establish a resource allocation model to configure equipment resources for parts processing.
[0038] Furthermore, in step Z1: the set of intervals between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing is collected as t={t1, t2, ..., t r}, where r represents the number of parts processed by the same equipment and with the same start time. The process information set in the past when processing different parts is collected, including the process number information and the planned processing time of each process. The process processing delay time information of the process that was processed by the same equipment in the past when processing different parts is collected.
[0039] Furthermore, in step Z2: the r parts are arranged in ascending order according to the interval duration in the set t, and the arranged r parts are divided into n categories, wherein the interval duration corresponding to all parts in the first category is smaller than that in the second category, and the mean set of interval duration corresponding to each category of parts in a random classification result is obtained as T={T1, T2, …, T n}, calculate the reference value of a random classification result according to the following formula:
[0040] ;
[0041] Among them, T iIt represents the mean interval duration corresponding to the i-th type of parts in n types in a random classification result. The reference degree of different classification results is calculated in the same way. The classification result with the largest reference degree is selected as the best classification result. The number of parts in each type in the best classification result is counted, and the number of parts in the largest type is L. j , according to the formula Estimate the common frequency W of a random device j , collect the time interval information between the time when m devices were used in the past part processing and the time when the parts started processing, and estimate the common frequency set of m devices in the same way as W={W1, W2, …, W j , …, W m}, set the general frequency threshold to , preliminarily screen out the devices whose general frequency exceeds the threshold as the devices to be added;
[0042] In order to reasonably allocate equipment resources, it is necessary to prioritize the equipment that needs to be added, and use big data technology to collect historical data from the past parts production and processing process. Although different parts may use the same equipment in different processes, the time used for the same equipment may be similar due to different process durations. In this case, if a large number of parts need to use the corresponding equipment, it may cause equipment resource usage conflicts, resulting in delays in the processing of some parts. The time interval between the time when the same equipment was used in the past during the parts processing process and the start time of different parts is collected, and the time collected is the same as the start time of the processing. parts data, so that the number of parts used in the corresponding equipment at similar or even the same time can be accurately analyzed through the difference in interval time, thereby improving the accuracy of part quantity analysis; at the same time, when counting the number of parts, by analyzing the interval time and classifying the parts according to the interval time, in order to distinguish the time when the parts are used in the corresponding equipment, the parts with similar interval time are grouped into one category, and the proportion of the number of parts in the largest category to the number of parts is used as the basis for preliminary screening of equipment. The higher the proportion, the more frequently the corresponding equipment is used for parts processing at similar or the same time, and the more necessary it is to increase the number of corresponding equipment, thereby improving the rationality and accuracy of the preliminary screening.
[0043] Further, in step Z3: k devices to be added are screened out, and the average delay time set of the process of processing different parts using k devices to be added is retrieved as B={B1, B2, ..., B k}, arrange the k devices to be added in descending order of average delay time, and divide the arranged devices to be added into f categories, where the average delay time corresponding to all devices to be added in the first category is greater than that in the second category, and obtain the sum of the average delay time corresponding to each type of devices to be added in f categories in a random classification result as U={U1, U2, …, U f}, calculate the difference degree E of the processing delay time of the process using the f type of equipment to be added in a random classification result according to the following formula:
[0044] ;
[0045] Among them, U c Indicates the sum of the average delay times corresponding to the c-th type of equipment to be added in the f category in a random classification result. The difference in the processing delay time of the process using the f-type equipment to be added in different classification results is calculated in the same way. The equipment to be added in the first category in the classification result with the largest difference is selected as the equipment that needs to be added in the final number.
[0046] In order to further improve the rationality and accuracy of the screening results, two equipment screening processes were carried out. Although the equipment to be added that was initially screened out was frequently used to process different parts at similar or the same time, it is not necessarily the case that all the equipment to be added is insufficient for the corresponding parts processing with the current installed quantity. Taking into account the current status of equipment resources, the equipment that needs to be added is finally screened out by analyzing the delay data of the equipment to be added that was initially screened out when it was used to process parts. The delay data can intuitively and truly reflect the usage of equipment resources, thereby improving the rationality and accuracy of the final screening results.
[0047] Further, in step Z4: retrieve the past usage data of the equipment that needs to be added in the final number: obtain the set of parts quantity that a random equipment that needs to be added in the final number has been used for processing in the past v times as G={G1, G2, ..., G v}, the corresponding number of equipment that needs to be added for processing is J={J1, J2, …, J v}, corresponding to v times of use, the corresponding number of additional equipment is required to process the parts without delay, for the data points {(G1, J1), (G2, J2), …, (G v , J v )} Perform straight line fitting and establish resource allocation model: , where D1 and D2 represent the fitting coefficients. It is found that H devices corresponding to the number of additional devices are currently installed. The corresponding number of additional devices are used to process N parts in the time period from P1 to P2. Substitute N into the resource allocation model: Let X=N, and the number of devices corresponding to the number of additional devices that should be installed is , select Add The corresponding number of equipment to be added;
[0048] After screening out the number of equipment that needs to be added, we further planned the number of equipment that needs to be added, achieved rational allocation of resources, and configured the right number of equipment. This can not only reduce the problem of conflicts in use when corresponding equipment needs to be used for processing different parts at similar or the same time, but also enhance the flexibility of part processing and production, improve the efficiency and quality of part processing and production, without adding too much equipment, and reduce unnecessary processing and production costs.
[0049] Compared with the prior art, the beneficial effects achieved by the present invention are:
[0050] The present invention improves the efficiency of parts processing by applying the MES system to parts processing production management, performing data analysis and resource allocation;
[0051] In order to reasonably allocate equipment resources and prioritize the equipment that needs to be added, big data technology is used to collect historical data from the past parts production and processing process, and the interval between the time when the same equipment was used in the past parts processing process and the start time of processing different parts is collected. The data of parts with the same start time are collected. In this way, the number of parts used in the corresponding equipment at similar or even the same time can be accurately analyzed through the difference in interval time, which improves the accuracy of part quantity analysis; at the same time, when counting the number of parts, by analyzing the interval time and classifying the parts according to the interval time, in order to distinguish the time when the parts are used in the corresponding equipment, the parts with similar interval time are grouped into one category, and the proportion of the number of parts in the largest category to the number of parts is used as the basis for preliminary screening of equipment. The higher the proportion, the more frequently the corresponding equipment is used for parts processing at similar or the same time, and the more necessary it is to add the corresponding equipment, which improves the rationality and accuracy of preliminary screening;
[0052] After two equipment screening processes, although the equipment to be added that was initially screened out was frequently used to process different parts at similar or the same time, it is not necessarily the case that all the equipment to be added is insufficient for the corresponding parts processing with the current installed quantity. Considering the current status of equipment resources, the equipment that needs to be added is finally screened out by analyzing the delay data of the equipment to be added that was initially screened out when it was used to process parts. The delay data can intuitively and truly reflect the use of equipment resources, which improves the rationality and accuracy of the final screening results;
[0053] After screening out the number of equipment that needs to be added, we further planned the number of equipment that needs to be added, achieved rational allocation of resources, and configured the right number of equipment. This can not only reduce the problem of conflicts in use when corresponding equipment needs to be used for processing different parts at similar or the same time, but also enhance the flexibility of part processing and production, improve the efficiency and quality of part processing and production, without adding too much equipment, and reduce unnecessary processing and production costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0054] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0055] Figure 1 It is a structural diagram of the mechanical processing flexible production management system based on the MES system of the present invention;
[0056] Figure 2 It is a flow chart of the mechanical processing flexible production management method based on the MES system of the present invention. DETAILED DESCRIPTION
[0057] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0058] Combine the following Figure 1-Figure 2 The present invention is further described with reference to the accompanying drawings and specific embodiments. Embodiment 1:
[0059] like Figure 1 As shown, this embodiment provides a mechanical processing flexible production management system based on the MES system. The system includes: a processing and production data acquisition module, a data management center, a processing data analysis module, a screening object information analysis module and a processing and production management module. The processing and production data acquisition module is used to collect historical data and processing abnormality data of parts processing, and transmit all collected data to the data management center. The data management center is used to store and manage all received data. The processing data analysis module is used to analyze the historical data of parts processing and preliminarily screen out the equipment to be added. The screening object information analysis module is used to analyze the processing abnormality data when the equipment to be added is used for parts processing, and secondary screen out the equipment that ultimately needs to be added. The processing and production management module is used to establish a resource allocation model to perform equipment resource allocation for parts processing.
[0060] The processing and production data collection module includes a process information collection unit, an equipment usage data collection unit and a processing progress collection unit. The process information collection unit is used to collect process information previously set when processing different parts, including process number information and the planned processing time of each process. The process number information refers to the process number set according to the processing steps. The process number of the first step of processing is 1. The equipment usage data collection unit is used to collect the interval time information between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing;
[0061] All of the above parts have the same start processing time, and the processing progress collection unit is used to collect the processing delay time information of the process when the same equipment was used to process different parts in the past.
[0062] The processing data analysis module includes a usage time analysis unit and a to-be-added equipment screening unit. The usage time analysis unit is used to retrieve and compare the interval time information between the time when the same equipment was used in the previous part processing process and the start time of processing different parts. The to-be-added equipment screening unit is used to classify the parts according to the interval time information, select the best classification result as reference data, analyze different equipment used in more than one part processing process, the interval time information between the time when the equipment was used and the start time of processing the parts, select reference data for different equipment, and screen out the to-be-added equipment based on the reference data.
[0063] The screening object information analysis module includes a processing progress analysis unit and an additional equipment secondary screening unit. The processing progress analysis unit is used to retrieve the processing delay time information of the process that uses the equipment to be added for processing different parts in the past;
[0064] The process processing delay here refers to the process processing delay of using the equipment to be added to process a part. For example: if a part uses the equipment to be added when processing the second process, the delay at this time refers to the delay of the second process. If the original processing time of the second process is a, the actual processing time of the second process, that is, the time required to complete the second process, is extended to b, then the delay of the second process is ba;
[0065] The additional equipment secondary screening unit is used to secondary screen the equipment to be added to select the final number of equipment that needs to be added according to the delay duration information.
[0066] The processing and production management module includes a resource allocation model establishment unit and an additional quantity planning unit. The resource allocation model establishment unit is used to count the number of installed equipment that needs to be added and the number of parts that have been processed in the past with different numbers of equipment that needs to be added, and to establish a resource allocation model based on the statistical results. The additional quantity planning unit is used to plan the number of additional equipment that needs to be added based on the resource allocation model. Embodiment 2:
[0067] like Figure 2 As shown, this embodiment provides a mechanical processing flexible production management method based on the MES system, which is implemented based on the production management system in the embodiment and specifically includes the following steps:
[0068] Z1: Collect historical data and abnormal processing data of parts processing, and collect the time interval between the time when the same equipment was used in the past parts processing and the time when different parts started processing, which is t={t1, t2, …, t r}, where r represents the number of parts processed by the same equipment and with the same start time. The process information set in the past when processing different parts is collected, including process number information and the planned processing time of each process. The process processing delay time information of the same equipment used in the past when processing different parts is collected.
[0069] For example, it is collected that in the past, during a random part processing, the equipment was used to process 15 parts in total and the processing start time of the 15 parts was the same. The interval time set from the time when the equipment was used to the time when the 15 parts started processing is t={t1, t2, t3, t4, t5, t6, t7, t8, t9, t 10 , t 11 , t 12 , t 13 , t 14 , t 15}={5, 6, 4, 11, 12, 10, 12.2, 11.6, 14, 15, 22, 20, 19, 20.5, 21.2}, unit: hour;
[0070] Z2: Analyze the historical data of parts processing, preliminarily select the equipment to be added, arrange the 15 parts in the order of the interval time in the set t from small to large, divide the arranged 15 parts into 3 categories, and obtain a random classification result: the interval time sets corresponding to the 3 categories of parts are {4, 5, 6, 10, 11}, {11.6, 12, 12.2} and {14, 15, 19, 20, 20.5, 21.2, 22} respectively, and the mean interval time set corresponding to each type of parts in the 3 categories in the corresponding classification results is T={T1, T2, T3}={7.2, 11.9, 18.8}. According to the formula The reference value of a random classification result is calculated to be 4.8, where T i represents the mean interval duration corresponding to the i-th type of parts in n types in a random classification result. The reference degree of different classification results is calculated in the same way. The classification result with the largest reference degree is selected as the best classification result. The best classification result is obtained: the interval duration sets corresponding to the three types of parts are {4, 5, 6}, {10, 11, 11.6, 12, 12.2, 14, 15} and {19, 20, 20.5, 21.2, 22} respectively. The number of parts in each type in the best classification result is counted, and the number of parts in the largest type is L j =7, according to the formula Estimate the common frequency W of a random device j =0.47, collect the time interval between the time when 10 devices were used in the past part processing and the time when the parts started to be processed, and estimate the common frequency set of 10 devices in the same way as W={W1, W2, W3, W4, W5, W6, W7, W8, W9, W 10}={0.47, 0.22, 0.82, 0.65, 0.77, 0.10, 0.83, 0.75, 0.90, 0.88}, set the general frequency threshold to , preliminarily screened out the devices with common frequencies exceeding the threshold as the devices to be added, and a total of 7 devices to be added were obtained;
[0071] Z3: Analyze the abnormal processing data when the equipment to be added is used for parts processing, and screen out the equipment that needs to be added in the end. A total of 7 equipment to be added are screened out. The average delay time set of the processing procedures using the 7 equipment to be added for processing different parts in the past is B={B1, B2, B3, B4, B5, B6, B7}={0.52, 0.10, 0.45, 0.05, 0.08, 0.04, 0.56}, in hours. The 7 equipment to be added Arrange the devices to be added in order of average delay from large to small, and divide them into three categories. Get a random classification result: the average delay sets corresponding to the three categories of devices to be added are {0.56, 0.52}, {0.45, 0.10, 0.08, 0.05} and {0.04} respectively. The sum of the average delays corresponding to each of the three categories of devices to be added in the corresponding classification results is U={U1, U2, U3}={1.08, 0.68, 0.04}. According to the formula Calculate the difference in the processing delay time of the process using the three types of equipment to be added in a random classification result. E≈0.18; among them, U crepresents the sum of the average delay durations corresponding to the c-th type of equipment to be added in the f-type in a random classification result. The difference in the processing delay durations of the processes using the three types of equipment to be added in different classification results is calculated in the same way. The classification result with the largest difference is obtained: the sets of average delay durations corresponding to the three types of equipment to be added are {0.56, 0.52, 0.45}, {0.10, 0.08} and {0.05, 0.04} respectively. The equipment to be added in the first category in the classification result with the largest difference is selected as the equipment that needs to be added in the final number, that is, the equipment to be added corresponding to the set {0.56, 0.52, 0.45};
[0072] Z4: Establish a resource allocation model, configure equipment resources for parts processing, and retrieve the previous usage data of the equipment that will eventually need to be added: Get a random set of parts that were used for processing by a random equipment that needs to be added three times, which is G={G1, G2, G3}={50, 62, 73}, and the corresponding set of equipment that needs to be added for processing is J={J1, J2, J3}={5, 7, 8}. The corresponding equipment that needs to be added is used three times to ensure that there is no delay in the process of part processing. Perform linear fitting on the data points {(G1, J1), (G2, J2), (G3, J3)} to establish a resource allocation model: , where D1 and D2 represent the fitting coefficients, and the calculation results are , ,get , we get that H=8 devices corresponding to the number of additional devices are currently installed, and the corresponding number of additional devices are used to process N=82 parts in the time period from P1 to P2. Substitute N into the resource allocation model: Let X=N=82, and we get that the number of devices corresponding to the number of additional devices that should be installed is , select Add The corresponding number of devices needs to be added.
[0073] Finally, it should be noted that the above description is only a preferred example of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. The mechanical processing flexible production management method based on MES system is characterized by: The following steps are involved: Z1: Collect historical data and abnormal processing data of parts processing; Z2: Analyze the historical data of parts processing and preliminarily select the equipment to be added; Z3: Analyze the abnormal processing data when the equipment to be added is used for parts processing, and select the equipment that needs to be added in the final number; Z4: Establish resource allocation model to configure equipment resources for parts processing; In step Z1: the time interval between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing is collected as t={t1, t2, ..., t r }, where r represents the number of parts processed by the same equipment and with the same start time. The process information set in the past when processing different parts is collected, including process number information and the planned processing time of each process. The process processing delay time information of the same equipment used in the past when processing different parts is collected. In step Z2: Arrange the r parts in the order of the interval duration in the set t from small to large, and divide the arranged r parts into n categories, where the interval durations of all parts in the first category are smaller than those in the second category, and obtain the mean interval duration set of each type of parts in the n categories in a random classification result as T={T1, T2, …, T n }, calculate the reference value of a random classification result according to the following formula: ; Among them, T i It represents the mean interval duration corresponding to the i-th type of parts in n types in a random classification result. The reference degree of different classification results is calculated in the same way. The classification result with the largest reference degree is selected as the best classification result. The number of parts in each type in the best classification result is counted, and the number of parts in the largest type is L. j , according to the formula Estimate the common frequency W of a random device j , collect the time interval information between the time when m devices were used in the past part processing and the time when the parts started processing, and estimate the common frequency set of m devices in the same way as W={W1, W2, …, W j , …, W m }, set the general frequency threshold to , preliminarily screen out the devices whose general frequency exceeds the threshold as the devices to be added; In step Z3: k equipment to be added are screened out, and the average delay time set of the process of processing different parts using k equipment to be added is retrieved as B={B1, B2, …, B k }, arrange the k devices to be added in descending order according to the average delay time, divide the arranged devices to be added into f categories, and obtain the sum of the average delay time corresponding to each type of devices to be added in f categories in a random classification result as U={U1, U2, …, U f }, calculate the difference degree E of the processing delay time of the process using the f type of equipment to be added in a random classification result according to the following formula: ; Among them, U c Indicates the sum of the average delay times corresponding to the c-th type of equipment to be added in the f category in a random classification result. The difference in the processing delay time of the process using the f-type equipment to be added in different classification results is calculated in the same way. The equipment to be added in the first category in the classification result with the largest difference is selected as the equipment that needs to be added in the final number. In step Z4: retrieve the past usage data of the equipment that needs to be added in the final number: obtain the set of parts quantity that a random equipment that needs to be added in the final number has been used for processing in the past v times, which is G={G1, G2, ..., G v }, the corresponding number of equipment that needs to be added for processing is J={J1, J2, …, J v }, corresponding to v times of use, the corresponding number of additional equipment is required to process the parts without delay, for the data points {(G1, J1), (G2, J2), …, (G v , J v )} Perform straight line fitting and establish resource allocation model: , where D1 and D2 represent the fitting coefficients. It is found that H devices corresponding to the number of additional devices are currently installed. The corresponding number of additional devices are used to process N parts in the time period from P1 to P2. Substitute N into the resource allocation model: Let X=N, and the number of devices corresponding to the number of additional devices that should be installed is , select Add The corresponding number of devices needs to be added.
2. The mechanical processing flexible production management system based on the MES system is applied to the mechanical processing flexible production management method based on the MES system as claimed in claim 1, characterized in that: The system includes: a processing and production data acquisition module, a data management center, a processing data analysis module, a screening object information analysis module and a processing and production management module; The output end of the processing and production data acquisition module is connected to the input end of the data management center, the output end of the data management center is connected to the input ends of the processing data analysis module, the screening object information analysis module and the processing and production management module, the output end of the processing data analysis module is connected to the input end of the screening object information analysis module, and the output end of the screening object information analysis module is connected to the input end of the processing and production management module; The processing and production data acquisition module is used to collect historical data and processing abnormality data of parts processing, and transmit all the collected data to the data management center; The data management center is used to store and manage all received data; The processing data analysis module is used to analyze the historical data of parts processing and preliminarily screen out the equipment to be added; The screening object information analysis module is used to analyze the processing abnormality data when the equipment to be added is used for parts processing, and to secondary screen out the equipment that ultimately needs to be added; The processing and production management module is used to establish a resource allocation model and perform equipment resource allocation for parts processing.
3. The mechanical processing flexible production management system based on the MES system according to claim 2 is characterized in that: The processing and production data collection module includes a process information collection unit, an equipment usage data collection unit and a processing progress collection unit; The output ends of the process information collection unit, the equipment usage data collection unit and the processing progress collection unit are connected to the input end of the data management center; The process information collection unit is used to collect process information previously set when processing different parts, including process number information and planned processing time of each process; The equipment usage data acquisition unit is used to collect information on the interval between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing; The processing progress collection unit is used to collect the processing delay time information of the process when the same equipment was used to process different parts in the past.
4. The mechanical processing flexible production management system based on the MES system according to claim 2 is characterized in that: The processing data analysis module includes a usage time analysis unit and a to-be-added equipment screening unit; The input end of the usage time analysis unit is connected to the output end of the data management center, and the output end of the usage time analysis unit is connected to the input end of the device screening unit to be added; The usage time analysis unit is used to retrieve and compare the time interval information between the time when the same equipment was used in the past during the parts processing and the time when different parts started processing; The equipment screening unit to be added is used to classify parts according to the interval duration information, select the best classification result as reference data, analyze different equipment used in more than one part processing process, the interval duration information between the time of use and the start time of part processing, select reference data for different equipment, and screen out the equipment to be added based on the reference data.
5. The mechanical processing flexible production management system based on the MES system according to claim 4 is characterized in that: The screening object information analysis module includes a processing progress analysis unit and an additional equipment secondary screening unit; The input end of the processing progress analysis unit is connected to the output end of the equipment screening unit to be added and the data management center, and the output end of the processing progress analysis unit is connected to the input end of the additional equipment secondary screening unit; The processing progress analysis unit is used to retrieve the processing delay time information of the process that used the equipment to be added to process different parts in the past; The additional equipment secondary screening unit is used for secondary screening the equipment to be added to finally select the equipment that needs to be added in quantity from the equipment to be added according to the delay duration information.
6. The mechanical processing flexible production management system based on the MES system according to claim 5 is characterized in that: The processing and production management module includes a resource allocation model establishment unit and an additional quantity planning unit; The input end of the resource configuration model establishment unit is connected to the output end of the additional equipment secondary screening unit and the data management center, and the output end of the resource configuration model establishment unit is connected to the input end of the additional equipment quantity planning unit; The resource allocation model establishment unit is used to count the number of installed devices with the number of additional devices required, and the number of parts that have been processed by different numbers of additional devices in the past, and establish a resource allocation model based on the statistical results; The additional quantity planning unit is used to plan the number of additional devices that need to be added according to the resource allocation model.