A debris flow blocking device
Patent Information
- Application Number
- CN202410107357.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2026-11-03
- Estimated Expiration
- 2044-01-25
AI Technical Summary
Existing debris flow barriers cannot be opened after use, making cleanup work inconvenient and easily damaged by debris flow impacts.
Design an openable barrier and buffer mechanism. The barrier mechanism is equipped with water-permeable holes, and the buffer mechanism is located upstream to reduce the impact of debris flow. The barrier mechanism can be opened after the debris flow to facilitate cleanup.
It effectively reduces the chance of the barrier mechanism being damaged, facilitates the cleanup work after a mudslide, and avoids affecting the cleanup equipment.
Smart Images

Figure CN117661507B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of debris flow prevention and control technology, and in particular to a debris flow blocking device. Background Technology
[0002] Debris flows are special types of floods that occur in mountainous areas or other deep valleys and rugged terrain, triggered by torrential rains or other natural disasters, carrying large amounts of mud, sand, and rocks. Debris flows are characterized by their suddenness, high velocity, large volume, large material capacity, and strong destructive power.
[0003] Currently, the most common debris flow control measures involve using retaining structures, such as cable mesh dams, grid dams, sieve dams, comb-tooth dams, and permeable arch dams. Existing dam-type retaining structures are all fixed projects, meaning their operational state is the same after completion, with the dam body always in a retaining state. However, after use, these existing retaining structures are affected by upstream debris flow accumulation, making them impossible to reopen. Engineering equipment cannot pass through the retaining area from downstream, hindering post-debris flow cleanup efforts. Summary of the Invention
[0004] The purpose of this invention is to provide a debris flow blocking device to solve the problems existing in the prior art.
[0005] To achieve the above objectives, the present invention provides a debris flow interception device, comprising:
[0006] The structural body is a U-shaped structure, and the structural body is disposed in the groove and is arranged along the length direction of the groove.
[0007] A barrier mechanism is provided in the U-shaped groove of the structural body. The barrier mechanism is an openable and closable structure. The barrier mechanism is used to block the structural body. Water-permeable holes are provided on the barrier mechanism.
[0008] A buffer mechanism is provided upstream of the barrier mechanism and located in the middle of the structural body. The distance between the buffer mechanism and the side wall of the structural body is sufficient for the passage of the dredging equipment.
[0009] Preferably, the blocking mechanism includes:
[0010] Mounting columns are fixedly installed on opposite side walls of the structural body, and mounting positions are provided on the downstream side of the mounting columns.
[0011] A baffle plate is rotatably connected to the mounting column via the mounting position, and the water-permeable holes are opened on the baffle plate; when the two baffle plates are in the closed state, they form a V-shaped structure, and the included angle between the two baffle plates is 90°-150°;
[0012] A support assembly is fixedly mounted on the side wall of the structural body and located downstream of the mounting column. The support assembly is used to support the barrier plate in the closed state.
[0013] Preferably, the support component includes:
[0014] The mounting base is fixedly installed on the side wall of the structural body, and a horizontal angle is provided between the mounting base and the structural body. The top of the end of the mounting base away from the structural body is provided with a mounting groove.
[0015] A support rod, one end of which is disposed in the mounting groove and connected to the mounting base by a pin, and the other end of which is fixedly connected to a support plate. The support plate is in contact with the barrier plate, and the support rod is perpendicular to the barrier plate.
[0016] Preferably, the support component further includes:
[0017] An adjusting seat is slidably sleeved on the support rod, and the adjusting seat is fixedly connected to the support rod by a pin.
[0018] A movable plate is disposed on the side of the support plate near the barrier plate. An adjusting rod is slidably disposed on the support plate. One end of the adjusting rod is fixedly connected to the movable plate, and the other end of the adjusting rod abuts against the adjusting seat. The distance between the movable plate and the support plate is 10cm-15cm.
[0019] Preferably, an arc-shaped guide plate is fixedly provided on the side of the barrier plate away from the support component.
[0020] Preferably, the buffer mechanism includes:
[0021] The mounting plate is vertically fixedly installed on the bottom wall of the structure body, and the mounting plate has through holes.
[0022] A support beam is slidably installed in the through hole. A notch is provided on the side of the two baffles that are in contact. The notch on the baffle in the closed state forms a sliding hole. The support beam is slidably limited to the sliding hole.
[0023] An arc-shaped baffle is fixedly installed at the upstream end of the supporting crossbeam. A gap is provided between the bottom end of the arc-shaped baffle and the bottom wall of the structure body, and the distance between the arc-shaped baffle and the side wall of the structure body is sufficient for the passage of the dredging equipment.
[0024] A spring is disposed between the arc-shaped baffle and the mounting vertical plate, and the spring is slidably sleeved on the support beam. The two ends of the spring abut against the mounting vertical plate and the arc-shaped baffle, respectively.
[0025] Preferably, a fixing beam is fixedly connected to the top of the mounting vertical plate, and the two ends of the fixing beam are respectively fixedly connected to the two mounting columns, and the fixing beam is fixedly connected to the structural body.
[0026] Preferably, the buffer mechanism further includes an elastic support component disposed at the other end of the support beam. The elastic support component is fixedly installed on the structural body and is used to buffer the support beam.
[0027] Preferably, the elastic support component includes:
[0028] The column is located downstream of the supporting beam and is fixedly installed in the middle of the bottom wall of the structural body;
[0029] A support base is slidably sleeved on the support beam, and the support base and the support beam are in a limiting fit.
[0030] A guide post is fixedly installed on the column, and the support base is slidably sleeved on the guide post;
[0031] Spring 2 is disposed between the support base and the column, and spring 2 is slidably sleeved on the guide column. The two ends of spring 2 are in contact with the support base and the column, respectively.
[0032] Compared with the prior art, the present invention has the following advantages and technical effects:
[0033] This invention determines the number of retaining devices to be constructed based on the width of the trench. By setting a retaining mechanism within the main structure, the debris flow is blocked. By setting a buffer mechanism upstream of the retaining mechanism, the energy of the debris flow can be dissipated, reducing the impact of the debris flow on the retaining mechanism and thus lowering the probability of the retaining mechanism being damaged. Moreover, the retaining mechanism is designed to be openable and closable, allowing it to be reopened after the debris flow to facilitate dredging. The distance between the buffer mechanism and the side wall of the main structure is sufficient for the passage of dredging equipment, preventing dredging work from being affected. Attached Figure Description
[0034] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0035] Figure 1 This is a schematic diagram of the debris flow blocking device of the present invention;
[0036] Figure 2 This is a top view of the debris flow interception device of the present invention;
[0037] Figure 3 This is a schematic diagram of the debris flow interception device of the present invention installed in a relatively wide trench;
[0038] In the diagram: 1. Main structure; 2. Mounting column; 3. Barrier plate; 4. Mounting seat; 5. Support rod; 6. Support plate; 7. Adjusting seat; 8. Movable plate; 9. Adjusting rod; 10. Arc-shaped guide plate; 11. Mounting vertical plate; 12. Support beam; 13. Arc-shaped baffle; 14. Spring 1; 15. Fixed beam; 16. Column; 17. Support base; 18. Guide column; 19. Spring 2. Detailed Implementation
[0039] It should be noted that, unless otherwise specified, the embodiments and features described in this invention can be combined with each other. The described embodiments are merely some, not all, of the embodiments of this invention. All other embodiments obtained by those skilled in the art without inventive effort are within the scope of protection of this invention. The invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0040] This invention provides a debris flow interception device, comprising:
[0041] Structural body 1, structural body 1 is a U-shaped structure, structural body 1 is set in the trench and is set along the length of the trench;
[0042] The barrier mechanism is set in the U-shaped groove of the structure body 1. The barrier mechanism is an openable and closable structure. The barrier mechanism is used to block the structure body 1. Water-permeable holes are provided on the barrier mechanism.
[0043] A buffer mechanism is located upstream of the barrier mechanism and in the middle of the main body 1. The distance between the buffer mechanism and the side wall of the main body 1 is sufficient for the passage of the dredging equipment.
[0044] In use, this invention involves modifying a trench and constructing a structural body 1 within it. The number of structural bodies 1 constructed is determined by the width of the trench, and multiple structural bodies 1 can be constructed along the length of the trench. The structural bodies 1 are arranged correspondingly along the length of the trench. A barrier mechanism is then installed within the structural body 1 to block debris flows. A buffer mechanism is installed upstream of the barrier mechanism to dissipate energy from the debris flow, reducing its impact and thus lowering the likelihood of damage. Furthermore, the barrier mechanism is designed to be openable and closable, allowing it to be reopened after a debris flow to facilitate dredging. The distance between the buffer mechanism and the sidewall of the structural body 1 is sufficient for dredging equipment to pass through, preventing disruption to dredging operations.
[0045] Furthermore, the barrier mechanism includes:
[0046] Mounting column 2 is fixedly installed on the opposite side walls of the structure body 1, and the mounting position is provided on the downstream side of the mounting column 2;
[0047] The baffle plate 3 is rotatably connected to the mounting column 2 via the mounting position, and the water permeable hole is opened on the baffle plate 3; when the two baffle plates 3 are in the closed state, they form a V-shaped structure, and the included angle between the two baffle plates 3 is 90°-150°.
[0048] The support assembly is fixedly installed on the side wall of the main structure 1 and located downstream of the mounting column 2. The support assembly is used to support the closed barrier plate 3.
[0049] By integrating the mounting column 2 with the main structure 1, the structural strength of the mounting column 2 can be improved, preventing damage to the mounting column 2 when impacted by debris flow, thus affecting the blocking effect of the barrier plate 3 on debris flow. Moreover, by limiting the angle between the two barrier plates 3, local damage to the barrier plate 3 due to concentrated force can be avoided after a debris flow. The barrier plate 3 is supported by the support components, which can prevent the barrier plate 3 from opening when impacted by debris flow.
[0050] Furthermore, to ensure that the installation of the support components does not affect the opening and closing of the barrier mechanism, the support components include:
[0051] Mounting base 4 is fixedly installed on the side wall of the structure body 1. There is a horizontal angle between the mounting base 4 and the structure body 1. The top of the end of the mounting base 4 away from the structure body 1 is provided with a mounting groove.
[0052] The support rod 5 has one end set in the mounting groove and connected to the mounting base 4 by a pin. The other end of the support rod 5 is fixedly connected to the support plate 6. The support plate 6 is in contact with the barrier plate 3, and the support rod 5 is set perpendicular to the barrier plate 3.
[0053] The support rod 5 is mounted on the mounting base 4 by a pin. When it is necessary to remove the support rod 5, simply remove the pin and take the support rod 5 out of the mounting slot.
[0054] Furthermore, the supporting components also include:
[0055] Adjusting seat 7 is slidably sleeved on support rod 5, and the adjusting seat 7 is connected and fixed to support rod 5 by a pin.
[0056] Movable plate 8 is located on the side of support plate 6 near barrier plate 3. Adjusting rod 9 is slidably installed on support plate 6. One end of adjusting rod 9 is fixedly connected to movable plate 8, and the other end of adjusting rod 9 abuts against adjusting seat 7. The distance between movable plate 8 and support plate 6 is 10cm-15cm.
[0057] After a debris flow occurs, the barrier plate 3 will adhere tightly to the support plate 6 under the impact of the debris flow, making it difficult to remove the support rod 5, thus affecting the opening of the barrier plate 3 and consequently the dredging work. Therefore, this invention uses a movable plate 8 to support the barrier plate 3 in the early stage. The movable plate 8 is limited by the adjusting rod 9 and the adjusting column, which can prevent the movable plate 8 from shifting when impacted by the debris flow. After the debris flow, the debris flow deposits upstream of the barrier plate 3 are less likely to deform after the water volume decreases. At this time, the pin on the adjusting seat 7 can be removed, and the position of the adjusting seat 7 can be changed to adjust the position of the movable plate 8, thus creating a certain gap between the movable plate 8 and the barrier plate 3. At this time, the position of the barrier plate 3 is not easily changed. At this time, simply rotating the support rod 5 can release the limitation between the support rod 5 and the barrier plate 3, making it convenient to open the barrier plate 3.
[0058] Furthermore, to improve the energy dissipation effect on debris flows, an arc-shaped guide plate 10 is fixedly installed on the side of the barrier plate 3 away from the support components, and the position of the arc-shaped guide plate 10 corresponds to that of the support components.
[0059] After the debris flow is first dissipated by the buffer mechanism, it impacts the barrier plates 3 from both sides of the buffer mechanism. Due to the inclined setting of the barrier plates 3, the barrier plates 3 can play a certain guiding role for the debris flow. Then, guided by the arc-shaped guide plate 10, the debris flow on the two barrier plates 3 can collide with each other to dissipate energy. Moreover, it can prevent the debris flow from directly impacting the joint of the two barrier plates 3, thus helping to maintain the stability of the barrier plates 3. In addition, the position of the arc-shaped guide plate 10 is set in correspondence with the support component, which can ensure the effective support of the support component for the barrier plates 3.
[0060] Furthermore, the buffer mechanism includes:
[0061] The mounting plate 11 is vertically fixed on the bottom wall of the structural body 1, and the mounting plate 11 has through holes.
[0062] The support beam 12 is slidably installed in the through hole. There is a notch on the side where the two baffles 3 are in contact. The notch on the baffle 3 in the closed state forms a sliding hole. The support beam 12 is slidably limited to the sliding hole.
[0063] An arc-shaped baffle 13 is fixedly installed at the upstream end of the supporting beam 12. A gap is provided between the bottom end of the arc-shaped baffle 13 and the bottom wall of the structure body 1, and the distance between the arc-shaped baffle 13 and the side wall of the structure body 1 is sufficient for the passage of the dredging equipment.
[0064] Spring 14 is disposed between the arc-shaped baffle 13 and the mounting vertical plate 11, and spring 14 is slidably sleeved on the supporting crossbeam 12. The two ends of spring 14 abut against the mounting vertical plate 11 and the arc-shaped baffle 13 respectively.
[0065] The arc-shaped baffle 13 is installed by mounting a vertical plate 11 and a supporting horizontal beam 12. The supporting horizontal beam 12 is aligned and limited by the barrier plate 3, which can ensure the stability of the supporting horizontal beam 12. The supporting horizontal beam 12 will not affect the opening and closing of the barrier plate 3. When the arc-shaped baffle 13 is impacted by a debris flow, it will dissipate energy by compression through spring 14, thus preventing the arc-shaped baffle 13 from being damaged by the impact. Moreover, under the weight of the supporting horizontal beam 12, the friction between the supporting horizontal beam 12 and the mounting vertical plate 11 and the barrier plate 3 can also achieve a certain energy dissipation effect.
[0066] Furthermore, to ensure the structural strength of the mounting vertical plate 11, a fixing beam 15 is fixedly connected to the top of the mounting vertical plate 11. The two ends of the fixing beam 15 are fixedly connected to the two mounting columns 2 respectively, and the fixing beam 15 is fixedly connected to the structural body 1.
[0067] Furthermore, to improve the buffering effect against debris flows, the buffering mechanism also includes an elastic support component disposed at the other end of the supporting beam 12. The elastic support component is fixedly installed on the structural body 1 and is used to buffer the supporting beam 12. The elastic support component includes:
[0068] Column 16 is located downstream of the supporting beam 12 and is fixedly installed in the middle of the bottom wall of the structural body 1.
[0069] The support base 17 is slidably sleeved on the support beam 12, and the support base 17 and the support beam 12 are in a limiting fit.
[0070] Guide post 18 is fixedly installed on column 16, and support base 17 is slidably sleeved on guide post 18;
[0071] Spring 19 is disposed between the support base 17 and the column 16, and spring 19 is slidably sleeved on the guide column 18. The two ends of spring 19 are in contact with the support base 17 and the column 16 respectively.
[0072] After the arc-shaped baffle 13 is impacted, the supporting beam 12 moves downstream. At this time, the supporting base 17 installed on the supporting beam 12 will move towards the column 16 under the action of the guide column 18, thereby compressing the second spring 19. Therefore, after the arc-shaped baffle 13 is impacted by the debris flow, both the first spring 14 and the second spring 19 will be compressed, thereby improving the buffering and energy dissipation effect of the debris flow.
[0073] The debris flow interception device provided by this invention operates as follows: After a debris flow occurs, the debris flow flows along the ditch into the structural body 1, first impacting the arc-shaped baffle 13. Springs 14 and 19 are used for buffering and energy dissipation. The arc-shaped baffle 13 also guides the debris flow, directing it to both sides. The channel within the structural body 1 narrows under the action of the arc-shaped baffle 13, causing the debris flow to become congested and reducing its velocity. The debris flow then impacts the interception plate 3, which is supported by a support assembly. The interception plate 3 and the arc-shaped guide plate 10 guide the debris flow, changing the direction of the debris flow on both sides, causing them to collide and dissipate energy, further reducing the velocity of the debris flow. Finally, the debris flow accumulates at the interception plate 3, thus blocking the debris flow. When dredging is required, simply adjust the position of the movable plate 8 to separate the movable plate 8 from the barrier plate 3, thereby facilitating the removal or rotation of the support rod 5, opening the barrier plate 3, allowing the dredging equipment to pass through, and facilitating the cleanup work after the mudslide.
[0074] The above are merely preferred embodiments of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.
Claims
1. A debris flow interception device, characterized in that, include: The structural body (1) is a U-shaped structure and is disposed in the groove and along the length direction of the groove. The barrier mechanism is set in the U-shaped groove of the structure body (1). The barrier mechanism is an openable and closable structure. The barrier mechanism is used to block the structure body (1). The barrier mechanism is provided with water-permeable holes. A buffer mechanism is provided upstream of the barrier mechanism and located in the middle of the structure body (1). The distance between the buffer mechanism and the side wall of the structure body (1) is sufficient for the passage of the dredging equipment. The blocking mechanism includes: Mounting column (2), the mounting column (2) is fixedly installed on the opposite side walls of the structure body (1), and the mounting column (2) is provided with a mounting position on the downstream side; The baffle plate (3) is rotatably connected to the mounting column (2) through the mounting position, and the water-permeable hole is opened on the baffle plate (3); when the two baffle plates (3) are in the closed state, they form a V-shaped structure, and the included angle between the two baffle plates (3) is 90°-150°. A support assembly is fixedly disposed on the side wall of the structure body (1) and disposed downstream of the mounting column (2). The support assembly is used to support the barrier plate (3) in the closed state. The support components include: Mounting base (4), the mounting base (4) is fixedly installed on the side wall of the structural body (1), the mounting base (4) and the structural body (1) are provided with a horizontal angle, and the top of the end of the mounting base (4) away from the structural body (1) is provided with a mounting groove; Support rod (5), one end of the support rod (5) is set in the mounting groove and connected to the mounting base (4) by a pin, and the other end of the support rod (5) is fixedly connected to a support plate (6), the support plate (6) is in contact with the baffle plate (3), and the support rod (5) is perpendicular to the baffle plate (3); Adjustment seat (7), the adjustment seat (7) is slidably sleeved on the support rod (5), and the adjustment seat (7) is connected and fixed to the support rod (5) by a pin; A movable plate (8) is provided on the side of the support plate (6) near the barrier plate (3). An adjusting rod (9) is slidably provided on the support plate (6). One end of the adjusting rod (9) is fixedly connected to the movable plate (8), and the other end of the adjusting rod (9) abuts against the adjusting seat (7). The distance between the movable plate (8) and the support plate (6) is 10cm-15cm. The buffer mechanism includes: Mounting vertical plate (11) is vertically fixedly installed on the bottom wall of the structural body (1), and the mounting vertical plate (11) has through holes; A support beam (12) is slidably installed in the through hole. A notch is provided on the side where the two baffles (3) are in contact. The notch on the baffle (3) in the closed state forms a sliding hole. The support beam (12) is slidably limited to the sliding hole. An arc-shaped baffle (13) is fixedly installed at the upstream end of the supporting beam (12). A gap is provided between the bottom end of the arc-shaped baffle (13) and the bottom wall of the structure body (1), and the distance between the arc-shaped baffle (13) and the side wall of the structure body (1) is sufficient for the passage of the dredging equipment. Spring 1 (14) is disposed between the arc-shaped baffle (13) and the mounting vertical plate (11), and the spring 1 (14) is slidably sleeved on the support beam (12). The two ends of the spring 1 (14) abut against the mounting vertical plate (11) and the arc-shaped baffle (13) respectively.
2. The debris flow blocking device according to claim 1, characterized in that, An arc-shaped guide plate (10) is fixedly provided on the side of the barrier plate (3) away from the support component.
3. The debris flow blocking device according to claim 1, characterized in that, The top end of the mounting plate (11) is fixedly connected to a fixing beam (15), the two ends of the fixing beam (15) are fixedly connected to the two mounting columns (2) respectively, and the fixing beam (15) is fixedly connected to the structural body (1).
4. The debris flow blocking device according to claim 1, characterized in that, The buffer mechanism also includes an elastic support component disposed at the other end of the support beam (12). The elastic support component is fixedly installed on the structural body (1) and is used to buffer the support beam (12).
5. The debris flow blocking device according to claim 4, characterized in that, The elastic support component includes: The column (16) is located downstream of the supporting beam (12) and is fixedly installed in the middle of the bottom wall of the structural body (1). A support base (17) is slidably sleeved on the support beam (12), and the support base (17) and the support beam (12) are in a limiting fit. Guide post (18), the guide post (18) is fixedly installed on the column (16), and the support base (17) is slidably sleeved on the guide post (18); Spring 2 (19) is disposed between the support base (17) and the column (16), and the spring 2 (19) is slidably sleeved on the guide column (18). The two ends of the spring 2 (19) are in contact with the support base (17) and the column (16) respectively.
Citation Information
Patent Citations
Debris flow blocking prevention and control method
CN115354620A