A method for laying submarine water pipeline under navigation conditions

Through the combination of pipeline launching slides and propelled traction equipment, combined with the use of buoys and nylon ropes, the problems of high investment and complex operation of submarine pipe laying equipment have been solved, and efficient submarine water pipeline laying under navigation conditions has been achieved, reducing costs Reduce costs and ensure stability and accessibility.

CN117869667BActive Publication Date: 2024-10-15SDC WATERWAY CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310842423.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-10
Publication Date
2024-10-15
Estimated Expiration
2043-07-10

AI Technical Summary

Technical Problem

The existing submarine pipe-laying boat method has high investment in equipment, complex operations and strict environmental requirements. It is difficult to efficiently lay submarine water pipelines under navigation conditions, affecting construction efficiency and cost.

Method used

Using a method that combines the pipeline water slide and the push-type traction equipment, the pipeline is pushed forward into the water through the downhill angle of the pipeline water slide and the push-type traction equipment, and the buoy and nylon rope are used to reduce friction, combined with traction The traction equipment provides traction and thrust respectively in the shoal area and deep water channel area to achieve stable laying.

Benefits of technology

It reduces construction costs, improves project progress, ensures the stability of submarine pipeline laying and accessibility under navigation conditions, and the pontoons can be recycled and reused.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117869667B_ABST
    Figure CN117869667B_ABST
Patent Text Reader

Abstract

The invention discloses a method for laying a submarine water pipeline under navigation conditions, comprising the following steps: firstly constructing a pipeline launching slideway on the pipeline starting shore; excavating a pipeline trench and driving a plurality of pairs of positioning piles at intervals along the pipeline submarine laying route axis; assembling the first section of the pipeline on the pipeline launching slideway; utilizing the downhill angle of the pipeline launching slideway and using a propulsion type traction device provided on the basis of the pipeline launching slideway to push the first section of the pipeline forward into the water; sequentially splicing the second section of the pipeline and the subsequent section of the pipeline at the tail end of the first section of the pipeline; when the towing pipe head at the front end of the first section of the pipeline is about to enter the deep-water channel area, water is injected from the tail end of the pipeline, and the pipeline is towed by the main tugboat for bottom towing and laying in the deep-water channel area; when the main tugboat travels to the shoal area close to the pipeline landing shore, the pulling type traction device provided on the pipeline landing shore controls the forward direction of the pipeline, and the main tugboat continues to provide traction. The invention can ensure the stability of pipeline laying.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a method for laying a submarine water pipeline under navigation conditions. Background Art

[0002] Submarine water pipelines are currently widely used in the development of marine resources. With the country's increased investment in ensuring people's livelihood in recent years, submarine pipe laying technology has gradually been applied to the water supply construction process between coastal land and islands, and has good application prospects. In the process of laying submarine water pipelines, it is necessary to select appropriate submarine laying methods according to different marine environmental conditions and the material and size of the pipeline, so as to achieve the purpose of reducing costs and improving construction efficiency.

[0003] Currently, the commonly used method for submarine pipe laying is mainly the pipe-laying vessel method.

[0004] A pipe-laying vessel is a ship equipped with a winch and a guide device. It lays pipes directly downward at sea and rolls the pipes directly from the ship to the seabed. It is a coastal pipe-laying device. Its main feature is that it can complete long pipe-laying operations on the sea surface at one time. It is more suitable for deep-sea areas and has high laying efficiency. It can complete a large number of pipe-laying works in a short time and can adapt to the complex seabed environment. However, in the process of using pipe-laying vessels, there are also the following limitations, namely, the equipment investment of pipe-laying vessels is large, the operation is relatively complex and delicate, and the environmental requirements are relatively high. Summary of the invention

[0005] The purpose of the present invention is to overcome the defects of the prior art and provide a method for laying a submarine water pipeline under navigation conditions, which not only does not affect the passage of the waterway, but also speeds up the project progress, reduces the construction cost, and effectively ensures the stability of the laying of the submarine water pipeline.

[0006] The object of the present invention is achieved by: a method for laying a submarine water pipeline under navigation conditions, comprising the following steps:

[0007] Step 1: First, build a pipeline launching slide perpendicular to the shoreline on the pipeline starting shore, the pipeline launching slide includes several pairs of columns, several beams correspondingly connected between the tops of the several pairs of columns, two longitudinal beams connected between the two ends of the several beams, a head end V-shaped roller fixed on the top surface of the first beam, two horizontal rollers correspondingly fixed on the second beam and the third beam, and several rear V-shaped rollers correspondingly fixed on the fourth beam to the last beam; the head end V-shaped roller and the subsequent V-shaped rollers are made of rubber; the horizontal roller is made of polyurethane; the pipeline launching slide extends from the land into the sea at a downhill angle of 3 to 5 degrees to the beach near the pipeline starting shore; and then the launch slide foundation is built by pouring concrete at the bottom rear end of the pipeline launching slide;

[0008] Step 2: Prefabricate the pipeline segments on a site opened up on the pipeline departure shore, and excavate the pipeline trench in the shallow area near the pipeline departure shore and the shallow area near the pipeline landing shore;

[0009] Step 3, a plurality of pairs of positioning piles are placed at intervals along the pipeline seabed laying route axis;

[0010] Step 4: First, hoist the prefabricated pipeline segments onto the pipeline launch slideway to assemble the first section of the pipeline, then install the pipe drag head at the front end of the first section of the pipeline, and then weld a pair of lifting rings symmetrically at a certain distance on both sides of the outer surface of the first section of the pipeline, and then tie the buoys all the way to the top of the first section of the pipeline, and use nylon ropes to connect all the buoys in series;

[0011] Step 5: Setting a push-type traction device on the pipeline launching slideway and setting a pull-type traction device on the pipeline landing shore;

[0012] Step 6: Connect the pipe-pulling head to one end of the towing cable through a shackle, and connect the other end of the towing cable to an amphibious excavator in a shallow area close to the starting shore of the pipeline;

[0013] Step 7: First, using the downhill angle of the pipeline launching slideway, and using the propulsion traction device to push the first section of the pipeline forward into the water, the front of the first section of the pipeline falls between each pair of positioning piles in the shallow area close to the starting bank of the pipeline, and at the same time, the amphibious excavator adjusts the forward direction of the first section of the pipeline in the shallow area close to the starting bank of the pipeline by towing the steel cable;

[0014] Step 8: first, splice the second section of the pipeline at the tail end of the first section of the pipeline still on the pipeline water slide, and weld a pair of lifting rings symmetrically at a certain distance on both sides of the outer surface of the second section of the pipeline, and tie buoys all over the top of the second section of the pipeline, and connect the buoys on the second section of the pipeline in series with the buoys on the first section of the pipeline through nylon ropes; then continue to use the propulsion traction device and use the downhill angle of the pipeline water slide to push the second section of the pipeline forward into the water;

[0015] Step nine, repeat step eight until the subsequent sections of the pipe are spliced ​​and pushed into the water;

[0016] Step 10. As the length of the pipeline increases and the pipe-pulling head is about to enter the deep-water channel area, the other end of the towing steel cable is connected to the main tugboat in the deep-water channel area, and water is injected into the pipeline from the tail end of the pipeline still on the pipeline launching slideway to make the pipeline sink to the bottom of the water. After that, after each subsequent section of the pipeline is spliced ​​and pushed into the water, water is injected into the tail end of the subsequent section of the pipeline still on the pipeline launching slideway. At the same time, the pipeline is towed by the main tugboat for bottom towing and laying in the deep-water channel area, and the propulsion traction equipment installed on the basis of the pipeline launching slideway continues to provide the pushing force. When injecting water into the pipeline, it is necessary to ensure that the pipeline in the deep-water channel area sinks to the seabed, and to ensure that there is no water in the pipeline in the shallow area of ​​the pipeline starting bank and it floats on the water surface.

[0017] Step 11: As the length of the pipeline increases and the main tugboat cannot tow the pipeline, an auxiliary tugboat is added in the deep-water channel area, and the auxiliary tugboat is connected to the lifting ring on the first section of the pipeline or the lifting ring on the subsequent section of the pipeline through the anchor chain. The auxiliary tugboat and the main tugboat jointly provide traction to the pipeline, so as to achieve the laying of the first section of the pipeline and the subsequent section of the pipeline in the deep-water channel area; when the main tugboat reaches the shallow area close to the pipeline landing shore and cannot move forward, the other end of the towing steel cable is replaced to be connected to the pulling traction equipment set on the pipeline landing shore, and the forward direction of the pipeline is controlled by the pulling traction equipment; the main tugboat returns to the deep-water channel area and is connected to the lifting ring on the subsequent section of the pipeline through the anchor chain, and provides traction together with the auxiliary tugboat, and the propulsion traction equipment set on the basis of the pipeline launching slideway continues to provide jacking force, so as to achieve the laying of the subsequent section of the pipeline in the deep-water channel area;

[0018] Step 12: After the pipeline is fully laid, divers will first go into the water to untie the buoys on the pipeline, and use the tied nylon ropes to recover all the buoys, and then conduct a water pressure test on the pipeline;

[0019] Step 13: First, the pipelines in the deep-sea channel area are buried by the post-trenching method, and then the pipelines located in the shallow area of ​​the pipeline starting bank and the pipelines located in the shallow area of ​​the pipeline landing bank are transported to the trench for burial by amphibious excavators or mud transporters.

[0020] In the above-mentioned method for laying a submarine water pipeline under navigation conditions, both ends of the second crossbeam and both ends of the fourth crossbeam in the pipeline launching slide are connected to a chain.

[0021] The above-mentioned method for laying a submarine water pipeline under navigation conditions is characterized in that, during step two, when excavating the trench, the position of the trench is released under the positioning of the DGPS navigation system, and an amphibious excavator is used to excavate the trench for areas with a water depth of more than 2m, and a dredger is used to excavate the trench for areas with a water depth of less than 2m; the silt excavated from the trench is transported to the shallow area by an amphibious excavator or a dredger and is regularly stacked and stored in an open area 15m away from the trench.

[0022] In the above-mentioned method for laying submarine water pipelines under navigation conditions, when performing step three, the spacing between each pair of positioning piles is 10m, a pair of positioning piles is set every 200m, and the depth of the positioning piles driven into the seabed is not less than 6m.

[0023] In the above-mentioned method for laying a submarine water pipeline under navigation conditions, when performing steps four and nine, the buoy is bound with iron sheets, and a rubber pad is arranged between the iron sheets and the outer surface of the buoy; the material of the buoy is high molecular polyethylene.

[0024] In the above-mentioned method for laying a submarine water pipeline under navigation conditions, when performing step five, the propulsion-type traction equipment uses a 35t winch; and the pulling-type traction equipment uses a 10t winch.

[0025] In the above-mentioned method for laying a submarine water pipeline under navigation conditions, when performing step thirteen, the post-trenching method adopts the gully laying method.

[0026] The method for laying a water pipeline under navigation conditions of the present invention has the following characteristics:

[0027] 1. The present invention takes into account that the pipeline water slide is tilted forward at a certain angle. When laying the pipeline, the front part of the pipeline water slide is subjected to greater force, which is very likely to cause damage to the rollers at the front part. Therefore, two horizontal rollers made of polyurethane are arranged at the front part of the pipeline water slide, and the remaining rollers are V-shaped rollers made of rubber. The horizontal rollers can better protect the pipeline, reduce damage to the remaining V-shaped rollers, and reduce the replacement cost of the rollers;

[0028] 2. The present invention realizes the sinking of the pipeline by injecting water into the pipeline. Compared with the prior art which uses concrete counterweights with higher costs, the present invention not only speeds up the project progress but also reduces the construction cost;

[0029] 3. The present invention achieves the purpose of reducing the friction between the pipeline and the seabed during bottom towing laying by tying buoys on the pipeline, which can not only reduce the traction during bottom towing, but also effectively ensure the stability of the submarine pipeline laying, and the buoys can be recycled and reused after the entire pipeline is laid;

[0030] 4. The construction method of the push-behind-pull method is adopted. The laying method of the present invention is divided into the following three stages:

[0031] In the shallow area near the starting bank of the pipeline: that is, a push-type traction device is set up on the starting bank of the pipeline and arranged at the rear end of the pipeline launch slide. When laying the pipeline in the shallow area, the push-type traction device is mainly used to provide the top thrust. The top thrust direction is controlled by positioning piles, and the direction of the pipeline is fine-tuned by a water excavator;

[0032] In the deep water area of ​​the main channel: To maintain the stability of pipe laying and minimize the impact on navigation, the bottom towing method is used for pipe laying, that is, water is injected into the pipeline to make it sink. At this time, the towing head at the front end of the pipe laying is connected to the main tugboat through the towing steel cable. The main tugboat provides traction, and the tugboat anchor chain and anchor winch are used for towing. The propulsion traction equipment on the pipeline departure shore continues to provide top thrust;

[0033] In the shallow area near the pipeline landing shore: When the tugboat tows to the shallow area near the pipeline landing shore, the main tugboat cannot continue to provide traction forward due to the shallow water depth. The pulling traction method is adopted. The pulling traction equipment is deployed on the pipeline landing shore, and the towing pipe head is connected to the pulling traction equipment through the towing steel cable. At this time, the pulling traction equipment mainly plays a guiding role. At this time, the main tugboat returns to the deep-water channel area and continues to rely on the lifting ring welded on the pipeline as a traction point to provide traction to the pipeline. The push-type traction equipment on the pipeline starting shore continues to provide top thrust. The three together provide thrust and traction for laying the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a perspective view of a pipeline launching slide constructed during step 1 of the method for laying a submarine water pipeline under navigation conditions of the present invention;

[0035] Figure 2 It is a plan view of the method for laying a submarine water pipeline under navigation conditions of the present invention when performing step eight;

[0036] Figure 2a It is an elevation view of the method for laying a submarine water pipeline under navigation conditions of the present invention when performing step eight;

[0037] Figure 3 It is a plan view of the method for laying a submarine water pipeline under navigation conditions of the present invention when step ten is performed;

[0038] Figure 3a It is an elevation view of the method for laying a submarine water pipeline under navigation conditions of the present invention when step ten is performed;

[0039] Figure 4 It is a plan view of the method for laying a submarine water pipeline under navigation conditions of the present invention when step 11 is performed;

[0040] Figure 4a It is a vertical view of the method for laying a submarine water pipeline under navigation conditions of the present invention when performing step eleven. DETAILED DESCRIPTION

[0041] The present invention will be further described below in conjunction with the accompanying drawings.

[0042] See also Figures 1 to 4a The method for laying a submarine water pipeline under navigation conditions of the present invention comprises the following steps:

[0043] Step 1: First, build a pipeline launching slide 10 perpendicular to the shoreline on the pipeline starting shore. The total length of the pipeline launching slide 10 in this embodiment is 96m; the pipeline launching slide 10 includes several pairs of columns 11, several beams 12 correspondingly connected between the tops of the several pairs of columns, two longitudinal beams 13 connected between the two ends of the several beams 12, a head end V-shaped roller 14 fixed on the top surface of the first beam, two horizontal rollers 15 correspondingly fixed on the second beam and the third beam, and several The rear V-shaped rollers 16 are fixed one by one on the fourth beam to the last beam; the material of the head V-shaped roller 14 and the subsequent V-shaped rollers 16 are both made of rubber; the material of the horizontal roller 15 is polyurethane; both ends of the second beam and the fourth beam are connected with a chain 16; the pipeline water slide 10 extends from the land into the sea at a downhill angle of 3 to 5 degrees to the beach near the starting shore of the pipeline; and then the water slide foundation 100 is built by pouring concrete at the bottom rear end of the pipeline water slide 10;

[0044] Step 2: Prefabricate the pipeline segments on a site opened up on the pipeline departure shore, and excavate the trenches in the shallow areas near the pipeline departure shore and the shallow areas near the pipeline landing shore. When excavating the trenches, the position of the trenches is set under the positioning of the DGPS navigation system. The depth of the trenches must meet the design requirements. For areas with a water depth of more than 2m, amphibious excavators are used to excavate the trenches. For areas with a water depth of less than 2m, dredgers are used to excavate the trenches. The silt excavated from the trenches is transported to the shallow areas by amphibious excavators or mud transporters and is regularly stacked and stored in an open area 15m away from the trenches.

[0045] Step 3: a plurality of pairs of positioning piles 30 are installed at intervals along the pipeline seabed laying route axis; starting from the sea entry point of the pipeline starting shore to the landing point of the pipeline landing shore (the distance from the sea entry point to the landing point is 4500m); the spacing between each pair of positioning piles 30 is 10m, and a pair of positioning piles 30 is set every 200m, and the depth of the positioning piles 30 driven into the seabed is not less than 6m; the spacing of the positioning piles 30 can be appropriately adjusted according to the passage requirements of the waterway;

[0046] Step 4: First, use a crawler crane to hoist the prefabricated pipeline segment onto the pipeline launching slide 10 to assemble the first section of the pipeline 20 with a length of 96m. Then, install a conical pipe drag head 200 at the front end of the first section of the pipeline 20 by welding, and then weld a pair of lifting rings 20C symmetrically every 48m on both sides of the outer surface of the first section of the pipeline 20. Then, tie the buoy 20A all the way to the top of the first section of the pipeline 20, and use nylon ropes to connect all the buoys 20A in series to facilitate the untying of the buoys 20A in the future. When assembling the first section of the pipeline, the two chains 17 on the second beam 12 on the pipeline launching slide 10 and the two chains 17 on the fourth beam 12 correspond to each other. It is connected with two pairs of lifting rings 20C on the first section of the pipeline 20 to prevent the first section of the pipeline 20 on the pipeline launching slide 10 from sliding down with the tide when the tide is low; the material of the buoy 20A is high molecular polyethylene; the specifications of the buoy 20A are 90cm×60cm×60cm in length×width×height; the buoy 20A is tied with iron sheet 20B, and a rubber pad is arranged between the iron sheet 20B and the outer surface of the buoy 20A to prevent damage to the buoy 20A; the buoy 20A can ensure the stability of the pipeline when the pipeline is towed at the bottom, and can also reduce the traction force when the pipeline is towed at the bottom; the diameter and arrangement spacing of the buoy are calculated and determined according to the size of the pipeline, so that the friction between the pipeline and the seabed is reduced when the pipeline is towed at the bottom;

[0047] Step 5: a propulsion traction device 41 is installed on the pipeline launching slide foundation 100, and a 35t winch is used for the propulsion traction device 41; and a pulling traction device 42 is installed on the pipeline landing shore, and a 10t winch is used for the pulling traction device 42;

[0048] Step 6: The pipe-pulling head 200 is connected to one end of the towing cable through a shackle, and the other end of the towing cable is connected to an amphibious excavator in a shallow area close to the starting shore of the pipeline;

[0049] Step 7: First, the downhill angle of the pipeline launching slide 10 is utilized, and the first section of the pipeline 20 is pushed forward into the water by the propulsion traction device 41, so that the front of the first section of the pipeline falls between each pair of positioning piles 30 in the shallow area close to the pipeline starting bank, and at the same time, the amphibious excavator adjusts the forward direction of the first section of the pipeline 20 in the shallow area close to the pipeline starting bank by towing the steel cable;

[0050] Step eight, first splice a second section of pipeline with a length of 96m at the tail end of the first section of pipeline 20 still on the pipeline launching slide 10, and weld a pair of lifting rings 20C symmetrically at intervals of 48m on both sides of the outer surface of the second section of pipeline, and tie buoys all over the top of the second section of pipeline, and connect the buoys on the second section of pipeline in series with the buoys on the first section of pipeline through nylon ropes; when splicing the second section of pipeline, the two chains on the second crossbeam 12 on the pipeline launching slide 10 are connected to the lifting rings 20C on the first section of pipeline 20 to prevent the first section of pipeline 20 on the pipeline launching slide 10 from sliding down with the tide when the tide falls, affecting the splicing of the second section of pipeline; after the splicing of the second section of pipeline is completed, continue to use the propulsion traction device 41 and use the downhill angle of the pipeline launching slide 10 to push the second section of pipeline forward into the water (see Figure 2 and Figure 2a );

[0051] Step nine, repeat step eight until the subsequent sections of the pipe are spliced ​​and pushed into the water;

[0052] Step 10. As the length of the pipeline increases, the pipeline enters the water for a certain distance (700m). When the pipe-pulling head 200 is about to enter the deep-water channel area, it becomes more difficult for the amphibious excavator to adjust the direction of pipeline laying. In order to further stabilize the forward direction of the pipeline and reduce the impact on the passage of the channel, the other end of the towing cable is connected to the main tugboat 40 in the deep-water channel area, and water is injected into the pipeline from the tail end of the pipeline still on the pipeline launching slide 10. The water injected into the pipeline is the tap water to be transported by the pipeline, so that the pipeline sinks to the bottom of the water. After that, after each subsequent section of the pipeline is spliced ​​and pushed into the water, water is injected into the tail end of the subsequent section of the pipeline still on the pipeline launching slide 10. At the same time, the pipeline is towed by the main tugboat 40 for bottom towing and laying in the deep-water channel area, and the propulsion traction device 41 provided on the pipeline launching slide foundation 100 continues to provide the thrust (see FIG. Figure 3 and Figure 3a ); When injecting water into the pipeline, ensure that the pipeline in the deep-water channel area sinks to the seabed, and ensure that there is no water in the pipeline in the shallow area of ​​the pipeline departure shore and it floats on the water surface, so as to reduce the friction resistance of the pipeline during bottom drag laying;

[0053] Step 11: As the length of the pipeline increases, when the main tugboat 40 cannot tow the pipeline, an auxiliary tugboat (not shown) is added in the deep-water channel area, and the auxiliary tugboat is connected to the lifting ring on the first section of the pipeline or the lifting ring on the subsequent section of the pipeline through an anchor chain, and the auxiliary tugboat and the main tugboat 40 jointly provide traction to the pipeline to achieve the laying of the pipeline in the deep-water channel area; the auxiliary tugboat is appropriately added according to the length of the pipeline and the size of the required traction force; when the main tugboat 40 travels to the shallow area close to the pipeline landing shore (500m away from the pipeline landing shore) and cannot travel forward, the other end of the towing steel cable is replaced to be connected to the pulling traction force device 42 set on the pipeline landing shore, and the pulling traction force device 42 controls the forward direction of the pipeline; the main tugboat 40 returns to the deep-water channel area and is connected to the lifting ring on the subsequent section of the pipeline through an anchor chain, and provides traction together with the auxiliary tugboat, and the propulsion traction force device 41 set on the pipeline launching slide foundation 10 continues to provide top thrust to achieve the laying of the subsequent section of the pipeline in the deep-water channel area (see Figure 4 and Figure 4a ); Similarly, when the auxiliary tugboat reaches the shallow area near the pipeline landing shore and cannot move forward, it returns to the deep-water channel area and connects with the lifting ring on the subsequent section of the pipeline through the anchor chain, and continues to provide traction together with the main tugboat;

[0054] Step 12: After the pipeline is fully laid, divers will first go into the water to untie the buoys on the pipeline, and use the tied nylon ropes to recover all the buoys, and then conduct a water pressure test on the pipeline;

[0055] Step 13. When all pipelines have been laid, the pipelines in the deep-sea channel area are first buried using the post-trenching method, that is, high-pressure water jets are used to impact the sand under the pipelines, thereby forming a trench at the bottom of the pipelines. The pipelines sink into the trenches under the action of their own gravity, and then amphibious excavators or mud transporters are used to transport the mud and sand stored during trench excavation to the pipelines in the shallow areas of the pipeline starting bank and the pipelines in the shallow areas of the pipeline landing bank to transport the mud and sand stored during trench excavation to the trenches for landfill.

[0056] The above embodiments are only used to illustrate the present invention, rather than to limit the present invention. Those skilled in the relevant technical field may make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalent technical solutions should also belong to the scope of the present invention and should be defined by the claims.

Claims

1. A method for laying a submarine water pipeline under navigation conditions, characterized in that: The laying method comprises the following steps: Step 1: First, build a pipeline launching slide perpendicular to the shoreline on the pipeline starting shore, the pipeline launching slide includes several pairs of columns, several beams correspondingly connected between the tops of the several pairs of columns, two longitudinal beams connected between the two ends of the several beams, a head end V-shaped roller fixed on the top surface of the first beam, two horizontal rollers correspondingly fixed on the second beam and the third beam, and several rear V-shaped rollers correspondingly fixed on the fourth beam to the last beam; the head end V-shaped roller and the subsequent V-shaped rollers are made of rubber; the horizontal roller is made of polyurethane; the pipeline launching slide extends from the land into the sea at a downhill angle of 3 to 5 degrees to the beach near the pipeline starting shore; and then the launch slide foundation is built by pouring concrete at the bottom rear end of the pipeline launching slide; Step 2: Prefabricate the pipeline segments on a site opened up on the pipeline departure shore, and excavate the pipeline trench in the shallow area near the pipeline departure shore and the shallow area near the pipeline landing shore; Step 3, a plurality of pairs of positioning piles are driven at intervals along the pipeline seabed laying route axis; Step 4: First, hoist the prefabricated pipeline segments onto the pipeline launch slideway to assemble the first section of the pipeline, then install the pipe drag head at the front end of the first section of the pipeline, and then weld a pair of lifting rings symmetrically at a certain distance on both sides of the outer surface of the first section of the pipeline, and then tie the buoys all the way to the top of the first section of the pipeline, and use nylon ropes to connect all the buoys in series; Step 5: Setting a push-type traction device on the pipeline launching slideway and setting a pull-type traction device on the pipeline landing shore; Step 6: Connect the pipe-pulling head to one end of the towing cable through a shackle, and connect the other end of the towing cable to an amphibious excavator in a shallow area close to the starting shore of the pipeline; Step 7: First, using the downhill angle of the pipeline launching slideway, and using the propulsion traction device to push the first section of the pipeline forward into the water, the front of the first section of the pipeline falls between each pair of positioning piles in the shallow area close to the starting bank of the pipeline, and at the same time, the amphibious excavator adjusts the forward direction of the first section of the pipeline in the shallow area close to the starting bank of the pipeline by towing the steel cable; Step 8: first, splice the second section of the pipeline at the tail end of the first section of the pipeline still on the pipeline water slide, and weld a pair of lifting rings symmetrically at a certain distance on both sides of the outer surface of the second section of the pipeline, and tie buoys all over the top of the second section of the pipeline, and connect the buoys on the second section of the pipeline in series with the buoys on the first section of the pipeline through nylon ropes; then continue to use the propulsion traction device and use the downhill angle of the pipeline water slide to push the second section of the pipeline forward into the water; Step nine, repeat step eight until the subsequent sections of the pipe are spliced ​​and pushed into the water; Step 10. As the length of the pipeline increases and the pipe-pulling head is about to enter the deep-water channel area, the other end of the towing steel cable is connected to the main tugboat in the deep-water channel area, and water is injected into the pipeline from the tail end of the pipeline still on the pipeline launching slideway to make the pipeline sink to the bottom of the water. After that, after each subsequent section of the pipeline is spliced ​​and pushed into the water, water is injected into the tail end of the subsequent section of the pipeline still on the pipeline launching slideway. At the same time, the pipeline is towed by the main tugboat for bottom towing and laying in the deep-water channel area, and the propulsion traction equipment installed on the basis of the pipeline launching slideway continues to provide the pushing force. When injecting water into the pipeline, it is necessary to ensure that the pipeline in the deep-water channel area sinks to the seabed, and to ensure that there is no water in the pipeline in the shallow area of ​​the pipeline starting bank and it floats on the water surface. Step 11: As the length of the pipeline increases and the main tugboat cannot tow the pipeline, an auxiliary tugboat is added in the deep-water channel area, and the auxiliary tugboat is connected to the lifting ring on the first section of the pipeline or the lifting ring on the subsequent section of the pipeline through the anchor chain. The auxiliary tugboat and the main tugboat jointly provide traction to the pipeline, so as to achieve the laying of the first section of the pipeline and the subsequent section of the pipeline in the deep-water channel area; when the main tugboat reaches the shallow area close to the pipeline landing shore and cannot move forward, the other end of the towing steel cable is replaced to be connected to the pulling traction equipment set on the pipeline landing shore, and the forward direction of the pipeline is controlled by the pulling traction equipment; the main tugboat returns to the deep-water channel area and is connected to the lifting ring on the subsequent section of the pipeline through the anchor chain, and provides traction together with the auxiliary tugboat, and the propulsion traction equipment set on the basis of the pipeline launching slideway continues to provide jacking force, so as to achieve the laying of the subsequent section of the pipeline in the deep-water channel area; Step 12: After the pipeline is fully laid, divers will first go into the water to untie the buoys on the pipeline, and use the tied nylon ropes to recover all the buoys, and then conduct a water pressure test on the pipeline; Step 13: First, the pipelines in the deep-sea channel area are buried by the post-trenching method, and then the pipelines located in the shallow area of ​​the pipeline starting bank and the pipelines located in the shallow area of ​​the pipeline landing bank are transported to the trench for burial by amphibious excavators or mud transporters.

2. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: Both ends of the second cross beam and both ends of the fourth cross beam in the pipeline water slide are connected with a chain.

3. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: In step two, when excavating the trench, the position of the trench is released under the positioning of the DGPS navigation system. For areas with a water depth of more than 2m, an amphibious excavator is used to excavate the trench, and for areas with a water depth of less than 2m, a dredger is used to excavate the trench; the silt excavated from the trench is transported to the shallow area by an amphibious excavator or a dredger and regularly stacked and stored in an open area 15m away from the trench.

4. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: When performing step three, the spacing between each pair of positioning piles is 10m, a pair of positioning piles is set every 200m, and the depth of the positioning piles driven into the seabed is not less than 6m.

5. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: When performing step 4 and step 8, the buoy is bound with iron sheets, and a rubber pad is arranged between the iron sheets and the outer surface of the buoy; the material of the buoy is high molecular polyethylene.

6. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: When performing step five, the push-type traction equipment uses a 35t winch; the pulling-type traction equipment uses a 10t winch.

7. The method for laying a submarine water pipeline under navigation conditions according to claim 1, characterized in that: When performing step thirteen, the post-trenching method adopts the ditch-laying pipe method.