A boiler flue gas waste heat deep utilization system

The water vapor in the steam boiler flue gas is condensed into liquid water through the heat pump system and the third condenser, which solves the problem of unused waste heat of the flue gas and achieves energy saving and avoidance of 'white smoke'.

CN118328411BActive Publication Date: 2024-10-18SHANGHAI FANGKUAI BOILER CO LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410757291.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-18
Estimated Expiration
2044-06-13

AI Technical Summary

Technical Problem

Existing steam boiler technology fails to effectively utilize the waste heat of flue gas emitted by the boiler, resulting in energy waste and the generation of 'white smoke' phenomenon.

Method used

A heat pump system combined with a third condenser and a water tank is used to condense the high-temperature flue gas through the evaporator, reduce the temperature of the flue gas, condense the water vapor into liquid water, and use the heat to heat the supplementary cold water, saving gas use.

Benefits of technology

It effectively avoids the generation of white smoke, utilizes the heat in the flue gas, reduces the water vapor content in the flue gas, saves gas use, and improves energy utilization efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118328411B_ABST
    Figure CN118328411B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of steam boilers, and specifically discloses a system for deep utilization of waste heat of boiler flue gas, comprising a furnace body and a burner for heating the furnace body, a compressor being connected to a first condenser, the first condenser being connected to a second condenser, the second condenser being connected to an evaporator, the evaporator being connected to the compressor, an air outlet of the first condenser being connected to the burner, a smoke inlet of a third condenser being connected to a smoke exhaust port of the furnace body, a smoke exhaust port of the third condenser being connected to a smoke inlet of the evaporator, a water inlet of a first water tank being connected to a water outlet of the third condenser, a water outlet of the first water tank being connected to a water inlet of the second condenser, a water outlet of the second condenser being connected to a water inlet of the first water tank, and a water outlet of the second condenser being connected to a water inlet of the furnace body; the present invention can reduce the content of water vapor in the exhaust flue gas, can effectively avoid the generation of white smoke, and can also save the use of gas.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steam boilers, and in particular to a boiler flue gas waste heat deep utilization system. Background Art

[0002] A natural gas steam boiler is a type of gas steam boiler. A natural gas steam boiler is a heat energy conversion device that uses natural gas as fuel. The heat released by burning in the furnace heats the water in the furnace and vaporizes it into steam. The main component of natural gas is methane. The flue gas produced by combustion contains 15%-17% water vapor, and its condensation temperature is around 57°C. The latent heat of vaporization of water vapor accounts for about 11% of the low calorific value of the gas.

[0003] The patent document with publication number CN219140740U discloses a high-efficiency combustion system for a steam boiler, including a recirculation fan, an air preheater, a low-nitrogen burner, and a blower unit; the flue gas outlet at the tail of the boiler is connected to the inlet of the recirculation fan through pipeline 1, and the outlet of the recirculation fan is connected to the outlet hot air duct of the air preheater through pipeline 2, the end of the outlet hot air duct of the air preheater is connected to the low-nitrogen burner, and the outlet pipeline of the blower unit is connected to the air preheater; the natural gas transmission pipeline of the gas distribution station is connected to the low-nitrogen burner, and two sets of flow regulating valves are arranged in parallel on the natural gas transmission pipeline of the gas distribution station. This patent significantly improves the combustion efficiency of the steam boiler through a reasonable reactor arrangement, so that the exhaust flue gas of the steam boiler meets the emission standards.

[0004] The above technical solution only achieves the effect of reducing the content of harmful substances in the exhaust gas by improving the combustion efficiency, but does not take measures to recycle the waste heat in the flue gas discharged by the boiler, which will make it impossible for the exhaust temperature to drop to a very low level. Among the heat generated by the combustion of gas, a large amount of heat will be dissipated into the environment through the exhaust gas, causing energy waste and visual pollution of "white smoke". Among them, the white smoke phenomenon is a phenomenon formed when the moisture in the flue gas enters the atmosphere, which will increase the air humidity and cause life and safety impacts on surrounding electrical equipment. Summary of the invention

[0005] The present invention provides a boiler flue gas waste heat deep utilization system, aiming to solve the technical problem in the related technology that a large amount of heat is lost to the environment through exhaust smoke, causing energy waste and the phenomenon of "white smoke".

[0006] A system for deep utilization of waste heat from boiler flue gas comprises a furnace body and a burner for heating the furnace body, and also comprises a heat pump system, a third condenser and a first water tank. The heat pump system comprises a compressor, an evaporator, a first condenser and a second condenser. The refrigerant outlet of the compressor is connected to the refrigerant inlet of the first condenser, the refrigerant outlet of the first condenser is connected to the refrigerant inlet of the second condenser, the refrigerant outlet of the second condenser is connected to the refrigerant inlet of the evaporator, and the refrigerant outlet of the evaporator is connected to the refrigerant inlet of the compressor. The first condenser also has an air inlet and an air outlet, the air outlet is connected to the burner, the smoke inlet of the third condenser is connected to the smoke exhaust port of the furnace body, the smoke exhaust port of the third condenser is connected to the smoke inlet of the evaporator, the water inlet of the third condenser can be connected to a cold water replenishing device, the water inlet of the first water tank is connected to the water outlet of the third condenser, the water outlet of the first water tank is connected to the water inlet of the second condenser through the first pump, the water outlet of the second condenser is connected to the water inlet of the first water tank, and the water outlet of the second condenser is also connected to the water inlet of the furnace body through the second pump.

[0007] The beneficial effects of the present invention are: the temperature of the flue gas discharged through the evaporator can be reduced to below the dew point, so that the water vapor in the flue gas can be fully condensed into liquid water, which can effectively avoid the generation of white smoke. At the same time, the heat in the high-temperature flue gas can be used to convert the supplementary cold water into high-temperature water, which can save the use of gas.

[0008] Preferably, a boiler economizer is provided on the furnace body, the smoke inlet of the third condenser is connected to the smoke exhaust port of the furnace body through the boiler economizer, and the water outlet of the second condenser is connected to the water inlet of the boiler economizer through a second pump, thereby achieving communication with the water inlet of the furnace body.

[0009] Preferably, it further comprises a water return machine, the water inlet of the water return machine is connected to the water return pipeline of the production line, and the water outlet of the water return machine is connected to the water inlet of the furnace body through the boiler economizer.

[0010] Preferably, the cold water replenishing device includes a second water tank and a third pump, and the water outlet of the second water tank is connected to the water inlet of the third condenser through the third pump.

[0011] Preferably, the evaporator has a drain outlet, which is connected to the second water tank. The effect is that in the evaporator, the heat exchange between the flue gas and the refrigerant can condense the water vapor in the flue gas, and the condensed water can enter the second water tank through the drain outlet to be used as cold water supplement.

[0012] Preferably, the evaporator includes a shell, in which a plurality of blowing plates are arranged along the width direction of the shell, and the length direction of the blowing plates is in the same direction as the length direction of the shell. One end of the blowing plate in the length direction is connected to the shell, and the other end is connected to the shell through a positioning assembly, so that when the blowing plate expands due to heat, the blowing plate can maintain a flat state in the length direction.

[0013] Preferably, the positioning assembly includes a first positioning member and a second positioning member connected to the blowing plate and the shell respectively, the first positioning member and the second positioning member can approach or move away from each other in the length direction of the shell, and the second positioning member is fixedly connected to a positioning frame, and a movable block and a sleeve having the same arrangement direction as the first positioning member and the second positioning member are provided in the positioning frame, one end of the movable block is movably inserted into the sleeve, and a first expansion block prepared by an expansion alloy is provided in the sleeve, the first expansion block is fixedly connected to the movable block, the sleeve is fixedly connected to the first positioning member, and the movable block is connected to the positioning frame through a non-return structure, so that after the movable block moves a set distance in the direction of the second positioning member, the movable block cannot be reset, and the effect is that when the blowing plate is heated and expanded, the positioning assembly can keep the blowing plate in a tensioned state in the length direction to facilitate the passage of flue gas, thereby ensuring the heat exchange effect.

[0014] Preferably, the non-return structure includes a first wedge block and a plurality of second wedge blocks arranged along the length direction of the shell, the first wedge block is connected to the movable block through the first elastic member, and the first wedge block can move in the up and down directions, the second wedge block is fixedly connected to the positioning frame, the first wedge block has a first inclined surface and a first vertical surface, the first inclined surface faces the second positioning member, and the first vertical surface faces away from the second positioning member, the second wedge block has a second inclined surface and a second vertical surface, the second inclined surface faces away from the second positioning member, and the second vertical surface faces the second positioning member, the first inclined surface and the second inclined surface are arranged opposite to each other, the effect of which is that when the blowing plate shrinks, the non-return structure can keep the blowing plate in a tensioned and flat state in the length direction.

[0015] Preferably, the shell is provided with shafts at both ends in its length direction, the axial direction of the shaft is in the same direction as the width direction of the shell, a movable sleeve is provided on the shaft, the rod sleeve can slide in the axial direction of the shaft, one end of the blowing plate is fixedly connected to the rod sleeve, at the other end of the blowing plate, a second positioning member is fixedly connected to the rod sleeve, a second expansion block made of expansion alloy is provided at one end of the shaft, the two ends of the second expansion block are respectively connected to the shaft and the rod sleeve, a second elastic member is provided at the other end of the shaft, the two ends of the second elastic member are respectively fixedly connected to the shaft and the rod sleeve, the effect is: when the blowing plate expands and contracts, under the action of the second expansion block and the second elastic member, the blowing plate can always maintain a tensioned and flat state in the height direction.

[0016] By adopting the above technical solution, the beneficial effects of the present invention are as follows:

[0017] 1. It can reduce the temperature of the flue gas discharged through the evaporator to below the dew point, so that the water vapor in the flue gas can be fully condensed into liquid water, which greatly reduces the content of water vapor in the flue gas discharged, and can effectively avoid the generation of white smoke. At the same time, the heat in the high-temperature flue gas can be used to convert the supplementary cold water into high-temperature water, which can save the use of gas.

[0018] 2. When the blowing plate of the evaporator expands and contracts, under the action of the positioning assembly, the check structure, the rod sleeve, the second expansion block and the second elastic member, the blowing plate can be kept taut and flat in both the length and height directions, which is convenient for the flue gas to pass through and can ensure the heat exchange effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a structural schematic diagram of the present invention.

[0020] Figure 2 It is a structural schematic diagram of the evaporator of the present invention.

[0021] Figure 3 It is a schematic diagram of the installation structure of the blowing plate of the present invention.

[0022] Figure 4 for Figure 3 Schematic diagram of the enlarged structure at point A in the middle.

[0023] Figure 5 It is a structural schematic diagram of the movable block of the present invention.

[0024] Figure 6 It is a structural schematic diagram of the positioning frame of the present invention.

[0025] Figure 7 It is a schematic diagram of the installation structure of the second expansion block and the second elastic member of the present invention.

[0026] Figure 8 It is a schematic diagram of the installation structure of the first wedge block and the second wedge block of the present invention.

[0027] Reference numerals:

[0028] 11. Furnace body; 12. Burner; 13. Compressor; 14. Evaporator; 15. First condenser; 16. Second condenser; 17. Third condenser; 18. First water tank; 19. Second water tank; 20. Boiler economizer; 21. Return water machine; 22. Fan; 23. First pump; 24. Second pump; 25. Third pump; 26. Fourth pump;

[0029] 31. Shell; 32. Blowing plate; 33. Shaft; 34. Rod sleeve;

[0030] 41. first positioning member; 411. insertion rod; 42. second positioning member; 43. positioning frame; 431. mounting cavity; 44. movable block; 441. receiving groove; 45. sleeve;

[0031] 51, first wedge block; 511, first inclined surface; 512, first vertical surface; 52, second wedge block; 521, second inclined surface; 522, second vertical surface; 53, first elastic member;

[0032] 61. Second expansion block; 62. Second elastic member. DETAILED DESCRIPTION

[0033] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0034] like Figure 1 As shown, the boiler flue gas waste heat deep utilization system of the embodiment of the present invention includes a furnace body 11 and a burner 12 for heating the furnace body 11, and also includes a heat pump system, a third condenser 17 and a first water tank 18. The heat pump system includes a compressor 13, an evaporator 14, a first condenser 15 and a second condenser 16. The refrigerant outlet of the compressor 13 is connected to the refrigerant inlet of the first condenser 15, the refrigerant outlet of the first condenser 15 is connected to the refrigerant inlet of the second condenser 16, the refrigerant outlet of the second condenser 16 is connected to the refrigerant inlet of the evaporator 14, and the refrigerant outlet of the evaporator 14 is connected to the refrigerant inlet of the compressor 13.

[0035] Among them, the refrigerant can be pentafluoropropane, code-named R245fa.

[0036] The first condenser 15 also has an air inlet and an air outlet. A fan 22 is connected to the air inlet of the first condenser 15 , and the air outlet of the first condenser 15 is in communication with the burner 12 .

[0037] The smoke inlet of the third condenser 17 is connected to the smoke exhaust port of the furnace body 11, and the smoke exhaust port of the third condenser 17 is connected to the smoke inlet of the evaporator 14. The flue gas after heat exchange with the refrigerant in the evaporator 14 will be discharged externally, and the water inlet of the third condenser 17 can be connected to the cold water replenishing device. In the third condenser 17, the replenished cold water can exchange heat with the flue gas. The water inlet of the first water tank 18 is connected to the water outlet of the third condenser 17, and the water outlet of the first water tank 18 is connected to the water inlet of the second condenser 16 through the first pump 23, and the water outlet of the second condenser 16 is connected to the water inlet of the first water tank 18, and the water outlet of the second condenser 16 is also connected to the water inlet of the furnace body 11 through the second pump 24.

[0038] During the operation of the steam boiler, the condensed water and remaining steam generated after the steam releases heat to the production line will be reused as boiler feed water. Due to the loss of the production line, a certain amount of cold water is usually required as a supplement.

[0039] When the steam boiler is working, the refrigerant compressed and heated by the compressor 13 will first enter the first condenser 15. In the first condenser 15, the air sent into the first condenser 15 by the fan 22 will exchange heat with the high-temperature refrigerant, so that the air temperature is increased. When the gas in the burner 12 is mixed with the heated air and burned, the combustion effect can be improved and the use of gas can be saved. In addition, the refrigerant after heat exchange in the first condenser 15 will enter the second condenser 16.

[0040] The high-temperature flue gas discharged from the furnace body 11 can be passed into the third condenser 17. In the third condenser 17, the cold water introduced into the third condenser 17 through the cold water replenishing device can exchange heat with the high-temperature flue gas, the flue gas temperature will decrease, and the cold water temperature will increase. The heated replenishing water will enter the first water tank 18 for storage, and the water in the first water tank 18 can enter the second condenser 16 through the first pump 23, and then return to the first water tank 18. In this cycle, the heated replenishing water will exchange heat with the refrigerant in the second condenser 16. The temperature of the replenishing water can be further increased by absorbing heat from the refrigerant, so that the temperature of the water in the first water tank 18 can be gradually increased. At this time, in the second condenser 16, the temperature of the refrigerant will be further reduced. When the production line return water in the furnace body 11 is insufficient and water replenishment is required, the high-temperature water after heat exchange in the second condenser 16 can be pumped into the furnace body 11 through the second pump 24. At this time, the replenishment of high-temperature water can save the use of gas.

[0041] The flue gas after heat exchange with cold water in the third condenser 17 will be discharged after entering the evaporator 14. The refrigerant whose temperature is further reduced in the second condenser 16 will absorb heat from the flue gas after entering the evaporator 14, which can reduce the temperature of the discharged flue gas to below the dew point. In this process, the water vapor in the flue gas can be fully condensed into liquid water, thereby greatly reducing the water vapor content in the discharged flue gas, thereby achieving full utilization of the heat in the high-temperature flue gas and avoiding the generation of white smoke.

[0042] In addition, this steam boiler can be used for return water of different proportions and temperatures in different industries, and has a wide range of applications.

[0043] In some embodiments, Figure 1As shown, the boiler flue gas waste heat deep utilization system also includes a water return machine 21, the water inlet of the water return machine 21 is connected to the production line return pipe, a boiler economizer 20 is provided on the furnace body 11, and the smoke inlet of the third condenser 17 is connected to the smoke exhaust port of the furnace body 11 through the boiler economizer 20. Specifically, the smoke inlet of the boiler economizer 20 is connected to the smoke exhaust port of the furnace body 11, and the smoke exhaust port of the boiler economizer 20 is connected to the smoke inlet of the third condenser 17.

[0044] The water outlet of the second condenser 16 is connected to the water inlet of the boiler economizer 20 through the second pump 24, and the water outlet of the return water machine 21 is connected to the water inlet of the furnace body 11 through the boiler economizer 20. Specifically, the water outlet of the return water machine 21 is connected to the water inlet of the boiler economizer 20 through the fourth pump 26, and the water outlet of the boiler economizer 20 is connected to the water inlet of the furnace body 11.

[0045] Through the fourth pump 26 and the second pump 24, the production line return water in the return water machine 21 and the make-up water heated by the second condenser 16 can be pumped into the boiler economizer 20, and then enter the furnace body 11 through the boiler economizer 20. In the boiler economizer 20, the high-temperature flue gas discharged from the furnace body 11 can exchange heat with the production line return water and the make-up water, so that the temperature of the water entering the furnace body 11 is increased, and the temperature of the flue gas can be reduced at the same time, thereby realizing the utilization of the waste heat of the flue gas and reducing the use of gas in the burner 12.

[0046] In some embodiments, Figure 1 As shown, the cold water replenishing device includes a second water tank 19 and a third pump 25. The water outlet of the second water tank 19 is communicated with the water inlet of the third condenser 17 through the third pump 25. The evaporator 14 has a drain port, which is communicated with the second water tank 19. Specifically, the second water tank 19 can store cold water for supplying to the first water tank 18. The cold water in the second water tank 19 can be pumped into the third condenser 17 through the third pump 25, and then into the first water tank 18. In the evaporator 14, the heat exchange between the flue gas and the refrigerant can fully condense the water vapor in the flue gas. The condensed water can enter the second water tank 19 through the drain port to be used for cold water replenishment.

[0047] It should be noted that the flue gas emitted by the boiler contains NO X , CO, CO2 and SO2, etc., a neutralization mechanism can be set between the drain port of the evaporator 14 and the second water tank 19, and the water condensed in the evaporator 14 is neutralized and then passed into the second water tank 19, and in the process of condensation of water vapor in the evaporator 14, NO X Gases such as CO, CO2 and SO2 can be dissolved in condensed water, which can reduce air pollution.

[0048] In some embodiments, Figures 1 to 8As shown, the evaporator 14 includes a shell 31, and a plurality of blowing plates 32 are arranged in the shell 31. The plurality of blowing plates 32 are evenly spaced apart along the width direction of the shell 31, and the length direction of the blowing plates 32 is in the same direction as the length direction of the shell 31. For ease of understanding, the width direction of the shell 31 can be defined as the left-right direction, and the length direction of the shell 31 can be defined as the front-to-back direction, that is, the plurality of blowing plates 32 are evenly spaced apart along the left-to-right direction in the shell 31, and the length direction of the blowing plates 32 is set along the front-to-back direction. When working, the flue gas discharged by the boiler passes through the gap between two adjacent blowing plates 32, and the blowing plates 32 are provided with channels for the flow of refrigerant.

[0049] Thus, when the flue gas passes through the gap between two adjacent blowing plates 32, it can exchange heat with the refrigerant in the channel on the blowing plate 32. Currently, the common blowing plates 32 are mostly made of thin aluminum plates. Based on the principle of thermal expansion and contraction, when the evaporator 14 exchanges heat between the high-temperature flue gas and the refrigerant, the high-temperature flue gas will cause the blowing plate 32 to expand and deform irregularly. The deformed blowing plate 32 will increase the resistance of the flue gas when it passes through, which will further affect the heat exchange effect. Therefore, a blowing plate 32 installation structure is required so that when the blowing plate 32 is heated and expanded, the flatness of the blowing plate 32 can continue to be maintained to facilitate the passage of flue gas.

[0050] like Figures 2 to 4 As shown, two shaft rods 33 are fixedly installed at both ends of the shell 31 in the length direction. The two shaft rods 33 located at the same end are distributed on the upper and lower sides of the shell 31. The axial direction of the shaft rod 33 is in the same direction as the width direction of the shell 31. A rod sleeve 34 is movably sleeved on the shaft rod 33. The rod sleeve 34 can slide in the axial direction of the shaft rod 33. One end of the blowing plate 32 in the length direction is fixedly connected to the rod sleeve 34, and the upper and lower sides of the other end are respectively connected to the rod sleeve 34 through positioning components.

[0051] The positioning assembly includes a first positioning member 41 and a second positioning member 42, which are fixedly connected to the blowing plate 32 and the rod sleeve 34 respectively. A slot is provided on one of the first positioning member 41 and the second positioning member 42, and an insertion rod 411 is fixedly connected to the other. The insertion rod 411 is movably inserted in the slot, so that the first positioning member 41 and the second positioning member 42 can approach or move away from each other in the length direction of the shell 31.

[0052] A positioning frame 43 is fixedly connected to one side of the second positioning member 42, and a mounting cavity 431 is provided in the positioning frame 43. A movable block 44 and a sleeve 45 are provided at the mounting cavity 431. The arrangement direction of the movable block 44 and the sleeve 45 is in the same direction as the arrangement direction of the first positioning member 41 and the second positioning member 42. The sleeve 45 can move in the length direction of the shell 31. The movable block 44 has a plug-in end, and the plug-in end is movably plugged into the sleeve 45, and the other end is abutted against the side wall of the mounting cavity 431 in the initial state. A first expansion block (not shown in the figure) made of expansion alloy is provided in the sleeve 45. The first expansion block is fixedly connected to the movable block 44, and the sleeve 45 is fixedly connected to the first positioning member 41. The upper and lower sides of the movable block 44 are connected to the positioning frame 43 through a non-return structure, so that after the movable block 44 moves a set distance in the direction of the second positioning member 42, the movable block 44 cannot be reset.

[0053] The first expansion block can be formed by Cu60Zn40 having a high expansion coefficient, and a hollow structure is provided on the sleeve 45 so that the first expansion block can be better heated.

[0054] like Figures 2 to 6 as well as Figure 8 As shown, the non-return structure includes a first wedge block 51 and a plurality of second wedge blocks 52 arranged along the length direction of the housing 31 .

[0055] The first wedge block 51 is connected to the movable block 44 through the first elastic member 53. Specifically, the upper and lower sides of the movable block 44 are provided with receiving grooves 441. The first wedge blocks 51 in the two non-return structures slide up and down and fit in the two receiving grooves 441 respectively. The first elastic member 53 is arranged in the receiving groove 441 and connected to the first wedge block 51, and can elastically push the first wedge block 51 upward or downward. The multiple second wedge blocks 52 that cooperate with the first wedge block 51 are fixedly installed on the upper side wall or the lower side wall of the installation cavity 431, wherein the first elastic member 53 can be a spring.

[0056] The first wedge block 51 has a first inclined surface 511 and a first vertical surface 512, the first inclined surface 511 faces the second positioning member 42, and the first vertical surface 512 faces away from the second positioning member 42. The second wedge block 52 has a second inclined surface 521 and a second vertical surface 522, the second inclined surface 521 faces away from the second positioning member 42, and the second vertical surface 522 faces the second positioning member 42. The first inclined surface 511 and the second inclined surface 521 are arranged opposite to each other.

[0057] When the high-temperature flue gas enters the evaporator 14 and the blowing plate 32 expands and deforms in the length direction, the first expansion block will also expand due to the heat. Since the positioning frame 43 is fixedly connected to the second positioning member 42, the movable block 44 is stopped against the side wall of the installation cavity 431, and the positions of the positioning frame 43 and the movable block 44 remain stationary, so that when the first expansion block expands due to the heat, it will push the sleeve 45 to move in the direction of the second positioning member 42. Since the sleeve 45 is fixedly connected to the first positioning member 41, and the first positioning member 41 is fixedly connected to the end of the blowing plate 32, when the sleeve 45 moves in the direction of the second positioning member 42, it can drive the end of the blowing plate 32 in the process of expansion and deformation to move in the direction of the second positioning member 42, so that the blowing plate 32 is always kept in a tensioned state in the length direction, thereby reducing the deformation of the blowing plate 32 when heated, facilitating the passage of flue gas, and ensuring the heat exchange effect.

[0058] In addition, after the evaporator 14 is used for a long time, when the blowing plate 32 shrinks, it will be deformed and become wrinkled and bent because it cannot return to its initial state. For this reason, a non-return structure is provided so that when the blowing plate 32 shrinks, it can continue to maintain a tensioned state in the length direction. Specifically, when shrinking occurs, due to the high expansion coefficient characteristic of the first expansion block, the first expansion block can return to its initial size. At this time, the end of the blowing plate 32 close to the second positioning member 42 is limited in the distance it moves away from the second positioning member 42, that is, the sleeve 45 cannot move away from the second positioning member 42 to the initial position, which is the position when the blowing plate 32 is first used and the expansion is deformed. The sleeve 45 is located in the flat state before the first expansion block is shaped, so that when the first expansion block is reduced, the movable block 44 will be driven to move toward the second positioning member 42. At this time, through the cooperation of the first inclined surface 511 and the second inclined surface 521, the first wedge block 51 will move downward at the same time when moving toward the second positioning member 42 until it passes over one or more second wedge blocks 52. After the first expansion block is restored to its initial size, the first vertical surface 512 of the first wedge block 51 will stop against the second vertical surface 522 of one of the second wedge blocks 52. At this time, the movable block 44 will also stop the sleeve 45, so that the blowing plate 32 can always remain in a tensioned and flat state in the length direction.

[0059] In some embodiments, Figure 2 , Figure 3 and Figure 7As shown, at both ends of the shaft rod 33 on the upper side of the shell 31, a second expansion block 61 made of expansion alloy is provided at one end, and a second elastic member 62 is provided at the other end. The two ends of the second expansion block 61 are respectively connected to the shaft rod 33 and the rod sleeve 34. The second expansion block 61 can be made of Cu60Zn40 with a high expansion coefficient. The two ends of the second elastic member 62 are respectively fixedly connected to the shaft rod 33 and the rod sleeve 34. The second elastic member 62 can be a spring.

[0060] When the high-temperature flue gas enters the evaporator 14 and the blowing plate 32 expands and deforms in the height direction, the second expansion block 61 will also expand due to the heat, thereby driving the rod sleeve 34 installed at the upper end of the blowing plate 32 and the upper end of the blowing plate 32 to move toward the end direction of the shaft rod 33 provided with the second elastic member 62, wherein the upper end of the blowing plate 32 is the upper side end in the height direction of the blowing plate 32, and the second elastic member 62 will be compressed. At this time, the blowing plate 32 is inclined. Under the action of the second expansion block 61 and the second elastic member 62, the blowing plate 32 can be kept in a tensioned state in the height direction, reducing the deformation of the blowing plate 32 when heated, so as to facilitate the passage of flue gas and ensure the heat exchange effect. Similarly, when cold shrinkage occurs, under the action of the second expansion block 61 and the second elastic member 62, the blowing plate 32 can also be kept in a tensioned state in the height direction.

[0061] As can be seen from the above, when the blowing plate 32 is heated and expanded, the flatness of the blowing plate 32 can be ensured by keeping the blowing plate 32 in a tensioned state in both the length direction and the height direction.

[0062] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. A boiler flue gas waste heat deep utilization system, comprising a furnace body (11) and a burner (12) for heating the furnace body (11), characterized in that: Also includes: A heat pump system, the heat pump system comprising a compressor (13), an evaporator (14), a first condenser (15) and a second condenser (16), the refrigerant outlet of the compressor (13) being in communication with the refrigerant inlet of the first condenser (15), the refrigerant outlet of the first condenser (15) being in communication with the refrigerant inlet of the second condenser (16), the refrigerant outlet of the second condenser (16) being in communication with the refrigerant inlet of the evaporator (14), the refrigerant outlet of the evaporator (14) being in communication with the refrigerant inlet of the compressor (13), the first condenser (15) further comprising an air inlet and an air outlet, the air outlet being in communication with the burner (12); a third condenser (17), wherein a smoke inlet of the third condenser (17) is connected to a smoke exhaust port of the furnace body (11), a smoke exhaust port of the third condenser (17) is connected to a smoke inlet of the evaporator (14), and a water inlet of the third condenser (17) can be connected to a cold water replenishing device; A first water tank (18), a water inlet of the first water tank (18) is connected to a water outlet of the third condenser (17), a water outlet of the first water tank (18) is connected to a water inlet of the second condenser (16) via a first pump (23), a water outlet of the second condenser (16) is connected to a water inlet of the first water tank (18), and a water outlet of the second condenser (16) is also connected to a water inlet of the furnace body (11) via a second pump (24).

2. The boiler flue gas waste heat deep utilization system according to claim 1 is characterized in that: A boiler economizer (20) is provided on the furnace body (11); a smoke inlet of the third condenser (17) is connected to a smoke exhaust port of the furnace body (11) via the boiler economizer (20); a water outlet of the second condenser (16) is connected to a water inlet of the boiler economizer (20) via a second pump (24), thereby achieving communication with the water inlet of the furnace body (11).

3. The boiler flue gas waste heat deep utilization system according to claim 2 is characterized in that: It also includes a water return machine (21), the water inlet of the water return machine (21) being in communication with the water return pipeline of the production line, and the water outlet of the water return machine (21) being in communication with the water inlet of the furnace body (11) via the boiler economizer (20).

4. The boiler flue gas waste heat deep utilization system according to claim 1 is characterized in that: The cold water replenishing device comprises a second water tank (19) and a third pump (25), and the water outlet of the second water tank (19) is connected to the water inlet of the third condenser (17) through the third pump (25).

5. The boiler flue gas waste heat deep utilization system according to claim 4 is characterized in that: The evaporator (14) has a drain port, and the drain port is in communication with the second water tank (19).

6. The boiler flue gas waste heat deep utilization system according to claim 1, characterized in that: The evaporator (14) comprises a shell (31), wherein a plurality of blowing plates (32) are arranged in the shell (31), wherein the plurality of blowing plates (32) are arranged along the width direction of the shell (31), wherein the length direction of the blowing plates (32) is in the same direction as the length direction of the shell (31), wherein one end of the blowing plates (32) in the length direction is connected to the shell (31), and the other end is connected to the shell (31) via a positioning assembly, so that when the blowing plates (32) are heated and expanded, the blowing plates (32) can maintain a flat state in the length direction.

7. The boiler flue gas waste heat deep utilization system according to claim 6, characterized in that: The positioning assembly comprises a first positioning member (41) and a second positioning member (42) respectively connected to the inflation plate (32) and the shell (31); the first positioning member (41) and the second positioning member (42) can move closer to or farther from each other in the length direction of the shell (31); a positioning frame (43) is fixedly connected to the second positioning member (42); a movable block (44) and a sleeve (45) having the same arrangement direction as the first positioning member (41) and the second positioning member (42) are arranged in the positioning frame (43); one end of the movable block (44) is movably inserted into the sleeve (45); a first expansion block formed by an expansion alloy is arranged in the sleeve (45); the first expansion block is fixedly connected to the movable block (44); the sleeve (45) is fixedly connected to the first positioning member (41); the movable block (44) is connected to the positioning frame (43) via a non-return structure, so that after the movable block (44) moves a set distance in the direction of the second positioning member (42), the movable block (44) cannot be reset.

8. The boiler flue gas waste heat deep utilization system according to claim 7, characterized in that: The non-return structure comprises a first wedge block (51) and a plurality of second wedge blocks (52) arranged along the length direction of the housing (31); the first wedge block (51) is connected to the movable block (44) via a first elastic member (53), and the first wedge block (51) is movable in the up-down direction; the second wedge block (52) is fixedly connected to the positioning frame (43); the first wedge block (51) has a first inclined surface (511) and a first vertical surface (512); the first inclined surface (511) faces the second positioning member (42), and the first vertical surface (512) faces away from the second positioning member (42); the second wedge block (52) has a second inclined surface (521) and a second vertical surface (522); the second inclined surface (521) faces away from the second positioning member (42), and the second vertical surface (522) faces the second positioning member (42); the first inclined surface (511) and the second inclined surface (521) are arranged opposite to each other.

9. The boiler flue gas waste heat deep utilization system according to claim 8, characterized in that: A shaft (33) is provided at both ends of the housing (31) in the longitudinal direction thereof. The axial direction of the shaft (33) is in the same direction as the width direction of the housing (31). A rod sleeve (34) is provided on the shaft (33) in a movable sleeve. The rod sleeve (34) can slide in the axial direction of the shaft (33). One end of the inflation plate (32) is fixedly connected to the rod sleeve (34). At the other end of the inflation plate (32), a second positioning member (42) is fixedly connected to the rod sleeve (34). At one end of the shaft (33), a second expansion block (61) formed of an expansion alloy is provided. Two ends of the second expansion block (61) are respectively connected to the shaft (33) and the rod sleeve (34). At the other end of the shaft (33), a second elastic member (62) is provided. Two ends of the second elastic member (62) are respectively fixedly connected to the shaft (33) and the rod sleeve (34).

Citation Information

Patent Citations

  • High-efficiency combustion system of steam boiler

    CN219140740U

  • Flue gas total-heat recovery device of gas boiler

    CN101769594A

  • Energy -efficient gas boiler central heating system

    CN208703993U