A tunnel construction abnormality warning method and system based on multi-source data fusion

By interconnecting multiple monitoring devices with the system during tunnel construction, parallel and series risk coefficients are calculated in real time, and early warning signals are generated, which solves the delay and manual dependence problems of traditional tunnel construction abnormality early warning systems, and achieves high accuracy and rapid emergency response. Automated processing reduces the risk of construction accidents.

CN118333407BActive Publication Date: 2024-10-15JIANGXI SUPERMASTER TECH DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410756226.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-15
Estimated Expiration
2044-06-13

AI Technical Summary

Technical Problem

The traditional tunnel construction abnormality early warning system based on multi-source data fusion has delays in data collection and analysis and processing, low alarm accuracy, relies on manual operations, and lacks automated and intelligent processing processes, resulting in slow emergency response and high risk of construction accidents. .

Method used

Design a tunnel construction abnormality early warning method based on multi-source data fusion. By interconnecting tunnel peripheral displacement monitoring devices, internal settlement monitoring devices, environmental monitoring devices, video monitoring devices and multiple sensors with the system, multi-source acquisition modules and fusion analysis are used. module and early warning management and control module, which monitors and calculates parallel and series risk coefficients in real time, generates early warning signals and controls them, and realizes automated emergency response.

Benefits of technology

It improves the accuracy of early warning signals and emergency response speed, ensures the safety of tunnel construction and the automation of the construction process, and reduces the risk of construction accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118333407B_ABST
    Figure CN118333407B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of tunnel construction early warning analysis, and discloses a tunnel construction abnormal early warning method and system based on multi-source data fusion. The early warning system comprises a multi-source acquisition module, a fusion analysis module and an early warning management and control module. The early warning method comprises the following steps: step 1, interconnecting monitoring devices and sensors related to tunnel construction with the early warning system, and the multi-source acquisition module collects data sets according to different data sources; step 2, under the condition of limiting the time axis, arranging and sorting the monitoring parameters within the same time period to form a standard data group #imgabs0#, and calculating the parallel risk coefficient #imgabs1# and the series risk coefficient #imgabs2# according to different analysis methods, so that the real-time monitoring and early warning have high accuracy; step 3, the early warning management and control module determines and generates corresponding early warning signals, and manages and controls the safety issues related to tunnel construction and tunnel environment, so that the automated emergency response speed is fast and the safety is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel construction early warning analysis, and in particular to a tunnel construction abnormality early warning method and system based on multi-source data fusion. Background Art

[0002] With the continuous growth of traffic demand and the development of engineering technology, tunnels have become an indispensable part of the modern transportation network. Tunnel construction not only overcomes terrain obstacles, but also shortens travel time and promotes the rapid development of the regional economy. Before the construction of a tunnel, detailed planning and design work must be carried out. This includes the exploration of geological conditions, the assessment of environmental impacts, and the determination of tunnel specifications. Geological exploration is a crucial step that determines the selection of subsequent construction methods and the formulation of preventive measures. At the same time, the design stage also needs to consider the tunnel's ventilation, drainage, lighting, monitoring and other supporting facilities. According to the geological conditions and the scale of the tunnel, the construction technology can be divided into excavation method, shield method, immersed tube method, etc. Excavation method is often used in rock tunnels and is divided into traditional blasting excavation and mechanical excavation. The shield method is suitable for underground conditions with soft soil and more aquifers. This method uses a shield machine to support the surrounding rock while digging. The immersed tube method is mostly used in the construction of underwater tunnels, where prefabricated tunnel sections are sunk underwater and connected. Modern tunnel construction relies on advanced equipment and technology. For example, shield machines can quickly dig and support tunnel walls, and laser guidance systems ensure that the tunnel trajectory is accurate. In addition, new blasting technologies and mechanized construction equipment have greatly improved construction efficiency and safety. Safety is the primary consideration during tunnel construction. Construction workers need to follow strict safety regulations and use professional protective equipment. In addition, monitoring systems need to be set up at the construction site to monitor potential risks such as harmful gases and groundwater levels in real time. Evacuation routes and emergency plans in emergency situations must also be planned in advance. Environmental protection is also an important part of tunnel construction. Measures must be taken during construction to reduce the impact of noise and dust on the surrounding environment. In addition, the treatment and discharge of waste must meet environmental standards to avoid damage to the natural ecology. After the tunnel is built, its operation and maintenance are equally important. Regular inspections and maintenance can ensure the safety and functionality of the tunnel, including the inspection of structural integrity, ventilation systems, lighting facilities and monitoring systems. Cleaning work is also a necessary measure to keep the tunnel in good operating condition. Tunnel construction is a complex process that integrates engineering technology, safety management and environmental protection. From planning and design to construction and operation, every step needs to be carefully organized and efficiently executed. With the continuous advancement of technology, future tunnel construction will be more intelligent, environmentally friendly and safer, making greater contributions to the development of human society.

[0003] At present, the traditional tunnel construction abnormal warning system based on multi-source data fusion has delays in data collection and analysis and processing, and the alarm accuracy is not high, which seriously affects the reliability of the warning signal. When an emergency occurs, the traditional warning system relies on manual operation and lacks automated and intelligent processing procedures. The emergency response speed is slow and the risk of construction accidents is high. Summary of the invention

[0004] 1. Technical issues to be resolved

[0005] In view of the shortcomings of the prior art, the present invention provides a method and system for abnormal early warning of tunnel construction based on multi-source data fusion, which has the advantages of high accuracy of real-time monitoring and early warning, fast automated emergency response speed and high safety. It solves the problem that the abnormal early warning system for tunnel construction based on multi-source data fusion has low alarm accuracy, and emergency situations rely on manual operation and lack of automated response speed and slow speed.

[0006] (II) Technical solution

[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a tunnel construction abnormality early warning method based on multi-source data fusion, the tunnel construction abnormality early warning method based on multi-source data fusion performs real-time monitoring through a tunnel construction abnormality early warning system based on multi-source data fusion, the tunnel construction abnormality early warning system based on multi-source data fusion includes a multi-source acquisition module, a fusion analysis module and an early warning control module, and the tunnel construction abnormality early warning method based on multi-source data fusion includes the following steps:

[0008] Step 1: interconnect the tunnel perimeter displacement monitoring device, tunnel internal settlement monitoring device, environmental monitoring device, video monitoring device and multiple sensors with the tunnel construction abnormality early warning system based on multi-source data fusion, and the multi-source acquisition module collects data sets according to different data sources;

[0009] Step 2: When the time axis is limited, the fusion analysis module arranges and organizes the monitoring parameters within the same time period to form a standard data set. , and calculate the risk coefficient according to different analysis methods, and generate the corresponding parallel risk coefficient and tandem risk factor , parallel risk factor Calculated and generated by multi-dimensional parallel risk factors, the risk coefficient is connected in series It is calculated from risk factors with causal relationships;

[0010] Step 3: Early warning control module based on parallel risk coefficient and tandem risk factor , judge and generate corresponding early warning signals, and manage safety issues related to tunnel construction and tunnel environment.

[0011] Preferably, a tunnel construction abnormality warning system based on multi-source data fusion includes a multi-source acquisition module, a fusion analysis module and a warning control module;

[0012] The multi-source acquisition module includes a peripheral monitoring unit, an internal monitoring unit, an environmental monitoring unit, a video monitoring unit and a sensor monitoring unit. The peripheral monitoring unit is connected to a displacement monitoring device through a network to collect a displacement data set, and transmits it to a fusion analysis module through the network. The internal monitoring unit is connected to a settlement monitoring device through a network to collect a settlement data set, and transmits it to a fusion analysis module through the network. The environmental monitoring unit is connected to an environmental monitoring device through a network to collect an environmental data set, and transmits it to a fusion analysis module through the network. The video monitoring unit is connected to a video monitoring device through a network to collect a video data set, and transmits it to a fusion analysis module through the network. The sensor monitoring unit is connected to multiple sensors through a network to collect a sensor data set, and transmits it to a fusion analysis module through the network. The multi-source acquisition module is connected to a fusion analysis module through a network.

[0013] The fusion analysis module includes a preprocessing unit, a parallel evaluation unit and a series evaluation unit. The fusion analysis module collects a standard data set through a network connection database and caches it in the fusion analysis module. The preprocessing unit arranges the displacement data set, the settlement data set, the environmental data set, the video data set, the sensor data set and the standard data set to form a standard data set. and transmitted to the parallel evaluation unit and the series evaluation unit through the network. The parallel evaluation unit is based on the standard data set. and standard data set to calculate the parallel risk coefficient The series evaluation unit is based on the standard data set and standard data set to calculate the tandem risk coefficient , the fusion analysis module is connected to the early warning control module through the network;

[0014] The early warning control module is based on the parallel risk coefficient , tandem risk factor and standard data sets to determine and generate corresponding early warning signals, and to manage and control safety issues related to tunnel construction and tunnel environment.

[0015] Preferably, the displacement data set includes ground movement parameters around the tunnel, and the surrounding monitoring unit describes the parameters in the displacement data set as: , , ,..., , to Corresponding to the ground movement parameters monitored by the displacement monitoring device around the tunnel each time, the settlement data set includes the tunnel vault settlement and surface settlement parameters. The internal monitoring unit describes the parameters in the settlement data set as , , ,..., , represents the tunnel vault settlement parameter, Represents the surface settlement parameters inside the tunnel.

[0016] Preferably, the environmental data set includes temperature, humidity and ventilation parameters inside the tunnel, and the environmental monitoring unit describes the parameters in the environmental data set as , , ,..., , Indicates the temperature and humidity parameters inside the tunnel, represents the ventilation volume parameter inside the tunnel, the video data set includes monitoring segments of the traffic road and entrances and exits inside the tunnel, and the video monitoring unit describes the monitoring segments in the video data set as , , ,..., , to Corresponding to multiple groups of traffic roads and entrance and exit monitoring segments inside the tunnel, the sensor data set includes smoke concentration and oxygen concentration parameters inside the tunnel. The sensor monitoring unit describes the parameters in the sensor data set as , , ,..., , Indicates the smoke density parameter inside the tunnel, Represents the oxygen concentration parameter inside the tunnel.

[0017] Preferably, the standard data set consists of a standard time axis, a standard construction safety threshold, a standard environmental safety threshold, a standard parallel risk threshold and a standard series risk threshold. The fusion analysis module describes the standard data set as , , and , Specifically, it is the standard timeline used uniformly in the process of collecting data sets and analyzing data sets in the tunnel construction abnormal warning system. Specifically, they are the stratum movement sensitivity threshold, the vault settlement sensitivity threshold and the surface settlement sensitivity threshold. Specifically, they are temperature and humidity sensitivity thresholds, ventilation volume sensitivity thresholds, maximum traffic road load capacity, maximum number of vehicles entering and exiting, smoke concentration sensitivity thresholds, and oxygen concentration sensitivity thresholds. Specifically, it is the parallel risk coefficient corresponding to the safe state Sensitivity threshold, Specifically, the corresponding series risk coefficient under safe conditions Sensitivity threshold.

[0018] Preferably, the preprocessing unit arranges the displacement data set, the settlement data set, the environmental data set, the video data set, the sensor data set and the standard data set to form a standard data set. , and its arrangement algorithm is as follows:

[0019]

[0020] In the formula, represents a standard data set, It means that under the limited conditions of the standard time axis, the ground movement parameters around the tunnel, the vault settlement and surface settlement parameters inside the tunnel, the temperature, humidity and ventilation volume parameters inside the tunnel, the traffic roads and entrances and exits monitoring clips inside the tunnel, and the smoke concentration and oxygen concentration parameters inside the tunnel collected within a unified time period are arranged and sorted.

[0021] Preferably, the parallel evaluation unit is based on a standard data set and standard data set to calculate the parallel risk coefficient , and its calculation formula is as follows:

[0022]

[0023] In the formula, represents the parallel risk factor, It represents the ratio of the actual ground movement parameters, vault settlement and surface settlement parameters in the standard data set to the standard construction safety threshold. It represents the ratio of the actual temperature and humidity, ventilation parameters, traffic road and entrance and exit monitoring segments, smoke concentration and oxygen concentration parameters in the standard data group to the standard environmental safety threshold.

[0024] Preferably, the series evaluation unit is based on a standard data set and standard data set to calculate the tandem risk coefficient , and its calculation formula is as follows:

[0025]

[0026] In the formula, represents the series risk coefficient, represents the weight index for the difference in tunnel construction safety parameters, Represents the weight index for the difference in tunnel environmental safety parameters, Indicates the difference between the actual tunnel construction parameters and the standard construction safety threshold, Indicates the difference between the actual tunnel environment parameters and the standard environment safety threshold. represents the total number of parameters involved in the calculation of the cascade risk coefficient, It represents the average risk factor calculated by connecting all monitoring parameters in series with different weights.

[0027] Preferably, the parallel risk coefficient Exceeding the standard parallel risk threshold When the early warning control module determines to generate a parallel early warning signal, the parallel risk coefficient The standard parallel risk threshold is not exceeded When no warning signal is generated, the series risk coefficient Exceeding standard tandem risk threshold When the early warning control module determines to generate a series warning signal, the series risk coefficient Standard tandem risk threshold not exceeded No warning signal is generated.

[0028] Preferably, the parallel warning signal has a higher priority than the series warning signal. The warning control module selects single ground displacement, vault settlement and surface settlement problems for control or single selects safety issues related to temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration for control according to the parallel warning signal. The warning control module comprehensively controls safety issues related to ground displacement, vault settlement, surface settlement, temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration caused by abnormal tunnel construction according to the series warning signal.

[0029] Compared with the prior art, the present invention provides a method and system for abnormal early warning of tunnel construction based on multi-source data fusion, which has the following beneficial effects:

[0030] 1. The present invention interconnects a tunnel perimeter displacement monitoring device, a tunnel internal settlement monitoring device, an environmental monitoring device, a video monitoring device and multiple sensors with a tunnel construction abnormality early warning system based on multi-source data fusion. The multi-source acquisition module is provided with a perimeter monitoring unit, an internal monitoring unit, an environmental monitoring unit, a video monitoring unit and a sensor monitoring unit. Displacement data sets, settlement data sets, environmental data sets, video data sets and sensor data sets are collected according to different data sources. The fusion analysis module is provided with a pre-processing unit, a parallel evaluation unit and a series evaluation unit. The pre-processing units are arranged to form a standard data set. , under the condition of limited time axis, the monitoring parameters within the same time period are arranged and sorted, and an information feedback mechanism is effectively established to avoid system judgment deviation caused by parameter delay, and the real-time monitoring and early warning are highly accurate.

[0031] 2. The present invention generates a parallel risk coefficient by calculating the parallel evaluation unit , multiple related detection parameters are analyzed in parallel, which effectively improves the efficiency of system analysis and judgment, and the series evaluation unit calculates and generates the series risk coefficient , comprehensively evaluate the abnormal status of multiple monitoring parameters, which is conducive to the subsequent rapid judgment of the safety of the overall construction of the tunnel. The early warning control module is based on the parallel risk coefficient , tandem risk factor and standard data sets, determine and generate parallel warning signals or series warning signals. The priority of parallel warning signals is higher than that of series warning signals. The warning control module selects single ground displacement, vault settlement and surface settlement problems for control or single selects temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration-related safety issues for control according to the parallel warning signals. The warning control module comprehensively controls the safety issues related to ground displacement, vault settlement, surface settlement, temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration caused by abnormal tunnel construction according to the series warning signals. The automated emergency response is fast and safe. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a step diagram of the method of the present invention;

[0033] Figure 2 It is a schematic diagram of the system flow of the present invention. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] See also Figure 1-Figure 2 A tunnel construction abnormality early warning method based on multi-source data fusion, the tunnel construction abnormality early warning method based on multi-source data fusion performs real-time monitoring through a tunnel construction abnormality early warning system based on multi-source data fusion, the tunnel construction abnormality early warning system based on multi-source data fusion includes a multi-source acquisition module, a fusion analysis module and an early warning control module, and the tunnel construction abnormality early warning method based on multi-source data fusion includes the following steps:

[0036] Step 1: interconnect the tunnel perimeter displacement monitoring device, tunnel internal settlement monitoring device, environmental monitoring device, video monitoring device and multiple sensors with the tunnel construction abnormality early warning system based on multi-source data fusion. The multi-source acquisition module collects data sets according to different data sources and comprehensively collects detection parameters related to tunnel construction, so as to facilitate the subsequent rapid judgment and response to abnormal construction conditions.

[0037] Step 2: Under the condition of limited time axis, the fusion analysis module arranges and sorts the monitoring parameters within the same time period, effectively establishes an information feedback mechanism, and forms a standard data set. , and calculate the risk coefficient according to different analysis methods, and generate the corresponding parallel risk coefficient and tandem risk factor , real-time monitoring and early warning with high accuracy, parallel risk factor Calculated and generated by multi-dimensional parallel risk factors, the risk coefficient is connected in series It is calculated from risk factors with causal relationships;

[0038] Step 3: Early warning control module based on parallel risk coefficient and tandem risk factor , judge and generate corresponding early warning signals, and manage safety issues related to tunnel construction and tunnel environment. The automated emergency response is fast and safe.

[0039] A tunnel construction abnormality warning system based on multi-source data fusion, including a multi-source acquisition module, a fusion analysis module and a warning control module;

[0040] The multi-source acquisition module includes a perimeter monitoring unit, an internal monitoring unit, an environmental monitoring unit, a video monitoring unit and a sensor monitoring unit. The perimeter monitoring unit collects displacement data sets through a network connection to a displacement monitoring device and transmits them to a fusion analysis module through the network. The displacement data sets include the ground movement parameters around the tunnel. The perimeter monitoring unit describes the parameters in the displacement data sets as , , ,..., , to Corresponding to the ground movement parameters monitored by the displacement monitoring device around the tunnel each time, the internal monitoring unit collects the settlement data set through the network connection settlement monitoring device and transmits it to the fusion analysis module through the network. The settlement data set includes the tunnel vault settlement and surface settlement parameters. The internal monitoring unit describes the parameters in the settlement data set as , , ,..., , represents the tunnel vault settlement parameter, represents the surface settlement parameters inside the tunnel. The environmental monitoring unit collects the environmental data set through the network connection of the environmental monitoring device and transmits it to the fusion analysis module through the network. The environmental data set includes the temperature, humidity and ventilation parameters inside the tunnel. The environmental monitoring unit describes the parameters in the environmental data set as , , ,..., , Indicates the temperature and humidity parameters inside the tunnel, represents the ventilation volume parameter inside the tunnel. The video monitoring unit collects the video data set through the network connection video monitoring device and transmits it to the fusion analysis module through the network. The video data set includes the monitoring segments of the traffic road and entrances and exits inside the tunnel. The video monitoring unit describes the monitoring segments in the video data set as , , ,..., , to Corresponding to multiple groups of traffic roads and entrances and exits monitoring segments inside the tunnel, the sensor monitoring unit collects sensor data sets through network connection with multiple sensors and transmits them to the fusion analysis module through the network. The sensor data sets include smoke concentration and oxygen concentration parameters inside the tunnel. The sensor monitoring unit describes the parameters in the sensor data sets as , , ,..., , Indicates the smoke density parameter inside the tunnel, Indicates the oxygen concentration parameter inside the tunnel. The multi-source acquisition module is connected to the fusion analysis module through the network;

[0041] The fusion analysis module includes a preprocessing unit, a parallel evaluation unit and a series evaluation unit. The fusion analysis module collects standard data sets through a network connection database and caches them in the fusion analysis module. The standard data set consists of a standard time axis, a standard construction safety threshold, a standard environmental safety threshold, a standard parallel risk threshold and a standard series risk threshold. The fusion analysis module describes the standard data sets as , , and , Specifically, it is the standard timeline used uniformly in the process of collecting data sets and analyzing data sets in the tunnel construction abnormal warning system. Specifically, they are the stratum movement sensitivity threshold, the vault settlement sensitivity threshold and the surface settlement sensitivity threshold. Specifically, they are temperature and humidity sensitivity thresholds, ventilation volume sensitivity thresholds, maximum traffic road load capacity, maximum number of vehicles entering and exiting, smoke concentration sensitivity thresholds, and oxygen concentration sensitivity thresholds. Specifically, it is the parallel risk coefficient corresponding to the safe state Sensitivity threshold, Specifically, the corresponding series risk coefficient under safe conditions Sensitive threshold, the preprocessing unit arranges the displacement data set, settlement data set, environmental data set, video data set, sensor data set and standard data set to form a standard data set , and transmitted to the parallel evaluation unit and the series evaluation unit through the network. The arrangement algorithm is as follows:

[0042]

[0043] In the formula, represents a standard data set, It means that under the limited conditions of the standard time axis, the ground movement parameters around the tunnel, the vault settlement and surface settlement parameters inside the tunnel, the temperature, humidity and ventilation parameters inside the tunnel, the traffic roads and entrances and exits monitoring clips inside the tunnel, and the smoke concentration and oxygen concentration parameters inside the tunnel are arranged and sorted in a unified time period. , avoiding the system judgment deviation caused by parameter delay, and the real-time monitoring and early warning are highly accurate;

[0044] Evaluation units connected in parallel according to standard data sets and standard data set to calculate the parallel risk coefficient , and its calculation formula is as follows:

[0045]

[0046] In the formula, represents the parallel risk factor, It represents the ratio of the actual ground movement parameters, vault settlement and surface settlement parameters in the standard data set to the standard construction safety threshold. It represents the ratio of the actual temperature and humidity, ventilation parameters, traffic road and entrance and exit monitoring segments, smoke concentration and oxygen concentration parameters in the standard data group to the standard environmental safety threshold, according to the parallel risk coefficient , multiple related detection parameters are analyzed in parallel, which effectively improves the efficiency of system analysis and judgment;

[0047] Series evaluation unit according to standard data set and standard data set to calculate the tandem risk coefficient , the fusion analysis module is connected to the early warning control module through the network, and its calculation formula is as follows:

[0048]

[0049] In the formula, represents the series risk coefficient, represents the weight index for the difference in tunnel construction safety parameters, Represents the weight index for the difference in tunnel environmental safety parameters, Indicates the difference between the actual tunnel construction parameters and the standard construction safety threshold, Indicates the difference between the actual tunnel environment parameters and the standard environment safety threshold. represents the total number of parameters involved in the calculation of the cascade risk coefficient, It indicates the average risk coefficient calculated by connecting all monitoring parameters in series under different weights. , comprehensively evaluate the abnormal status of multiple monitoring parameters, which is conducive to the subsequent rapid judgment of the safety of the overall tunnel construction;

[0050] The early warning control module is based on the parallel risk coefficient , tandem risk factor and standard data sets, judge and generate corresponding early warning signals, and control the safety issues related to tunnel construction and tunnel environment, and parallel risk coefficients Exceeding the standard parallel risk threshold When the parallel data of stratum displacement, vault settlement and surface settlement, as well as ambient temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration are abnormal, the abnormal range is small, and the tunnel construction is dangerous. The early warning control module generates a parallel warning signal and the parallel risk coefficient The standard parallel risk threshold is not exceeded When the warning signal is not generated, the risk factor is connected in series Exceeding standard tandem risk threshold When the alarm is raised, it indicates that the overall monitoring parameters are abnormal, the abnormal range is large, and the tunnel construction risk is very high. The early warning control module determines and generates a series of early warning signals, and the series risk coefficient Standard tandem risk threshold not exceeded When the warning signal is generated, the parallel warning signal has a higher priority than the serial warning signal. The warning control module selects the ground displacement, vault settlement and surface settlement problems for control or selects the temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration-related safety issues for control according to the parallel warning signal. The warning control module comprehensively controls the safety issues related to ground displacement, vault settlement, surface settlement, temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration caused by tunnel construction abnormalities according to the serial warning signal. The automated emergency response has fast speed and high safety.

[0051] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A tunnel construction abnormality warning system based on multi-source data fusion, Features: Including multi-source acquisition module, fusion analysis module and early warning control module; The multi-source acquisition module includes a perimeter monitoring unit, an internal monitoring unit, an environmental monitoring unit, a video monitoring unit and a sensor monitoring unit. The perimeter monitoring unit collects a displacement data set through a network connection to a displacement monitoring device and transmits the data to a fusion analysis module through the network. The displacement data set includes ground movement parameters around the tunnel. The perimeter monitoring unit describes the parameters in the displacement data set as , , ,..., , to Corresponding to the ground movement parameters monitored by the displacement monitoring device around the tunnel each time; The internal monitoring unit collects the settlement data set through the network connection settlement monitoring device and transmits it to the fusion analysis module through the network. The settlement data set includes the tunnel vault settlement and surface settlement parameters. The internal monitoring unit describes the parameters in the settlement data set as , , ,..., , represents the tunnel vault settlement parameter, Indicates the surface settlement parameters inside the tunnel; The environmental monitoring unit collects environmental data sets through a network connection to the environmental monitoring device, and transmits the environmental data sets to the fusion analysis module through the network. The environmental data sets include the temperature, humidity and ventilation parameters inside the tunnel. The environmental monitoring unit describes the parameters in the environmental data sets as , , ,..., , Indicates the temperature and humidity parameters inside the tunnel, Indicates the ventilation volume parameter inside the tunnel; The video monitoring unit collects video data sets through a network connection with a video monitoring device and transmits the video data sets to a fusion analysis module through the network. The video monitoring unit describes the monitoring segments in the video data sets as , , ,..., , to Corresponding to multiple groups of traffic roads and entrances and exits monitoring clips inside the tunnel; The sensor monitoring unit collects sensor data sets through network connection with multiple sensors and transmits them to the fusion analysis module through the network. The sensor data sets include smoke concentration and oxygen concentration parameters inside the tunnel. The sensor monitoring unit describes the parameters in the sensor data sets as , , ,..., , Indicates the smoke density parameter inside the tunnel, Indicates the oxygen concentration parameter inside the tunnel, the multi-source acquisition module is connected to the fusion analysis module through a network; The fusion analysis module includes a preprocessing unit, a parallel evaluation unit and a series evaluation unit. The fusion analysis module collects a standard data set through a network connection database and caches it in the fusion analysis module. The standard data set consists of a standard time axis, a standard construction safety threshold, a standard environmental safety threshold, a standard parallel risk threshold and a standard series risk threshold. The fusion analysis module describes the standard data set as , , and , Specifically, it is the standard timeline used uniformly in the process of data collection and data analysis of the tunnel construction abnormal warning system. Specifically, they are the stratum movement sensitivity threshold, the vault settlement sensitivity threshold and the surface settlement sensitivity threshold. Specifically, they are temperature and humidity sensitivity thresholds, ventilation volume sensitivity thresholds, maximum traffic road load capacity, maximum number of vehicles entering and exiting, smoke concentration sensitivity thresholds, and oxygen concentration sensitivity thresholds. Specifically, it is the parallel risk coefficient corresponding to the safe state Sensitivity threshold, Specifically, the corresponding series risk coefficient under safe conditions The preprocessing unit arranges the displacement data set, the settlement data set, the environmental data set, the video data set, the sensor data set and the standard data set to form a standard data set. , and transmitted to the parallel evaluation unit and the series evaluation unit through the network. The arrangement algorithm is as follows: In the formula, represents a standard data set, It means that under the limited conditions of the standard time axis, the ground movement parameters around the tunnel, the vault settlement and surface settlement parameters inside the tunnel, the temperature, humidity and ventilation parameters inside the tunnel, the monitoring clips of the traffic roads and entrances and exits inside the tunnel, and the smoke concentration and oxygen concentration parameters inside the tunnel collected within a unified time period are arranged and sorted; The parallel evaluation unit is based on a standard data set and standard data set to calculate the parallel risk coefficient , and its calculation formula is as follows: In the formula, represents the parallel risk factor, It represents the ratio of the actual ground movement parameters, vault settlement and surface settlement parameters in the standard data set to the standard construction safety threshold. It indicates the ratio of the actual temperature and humidity, ventilation parameters, traffic road and entrance and exit monitoring segments, smoke concentration and oxygen concentration parameters in the standard data set to the standard environmental safety threshold; The series evaluation unit is based on the standard data set and standard data set to calculate the tandem risk coefficient , and its calculation formula is as follows: In the formula, represents the series risk coefficient, represents the weight index for the difference in tunnel construction safety parameters, Represents the weight index for the difference in tunnel environmental safety parameters, Indicates the difference between the actual tunnel construction parameters and the standard construction safety threshold, Indicates the difference between the actual tunnel environment parameters and the standard environment safety threshold. represents the total number of parameters involved in the calculation of the cascade risk coefficient, It represents the average risk factor calculated by connecting all monitoring parameters in series under different weights; The fusion analysis module is connected to the early warning control module via a network; The early warning control module is based on the parallel risk coefficient , tandem risk factor and standard data sets, judge and generate corresponding early warning signals, and correspondingly control safety issues related to tunnel construction and tunnel environment. The parallel risk coefficient Exceeding the standard parallel risk threshold When the early warning control module determines to generate a parallel early warning signal, the parallel risk coefficient The standard parallel risk threshold is not exceeded When no warning signal is generated, the series risk coefficient Exceeding standard tandem risk threshold When the early warning control module determines to generate a series warning signal, the series risk coefficient Standard tandem risk threshold not exceeded When the warning signal is not generated, the priority of the parallel warning signal is higher than that of the series warning signal. The warning control module selects the ground displacement, vault settlement and surface settlement problems for control or selects the temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration-related safety problems for control according to the parallel warning signal. The warning control module controls the ground displacement, vault settlement, surface settlement, temperature and humidity, ventilation volume, traffic status, smoke concentration and oxygen concentration-related safety problems caused by abnormal tunnel construction in an integrated manner according to the series warning signal; The tunnel construction abnormality early warning method based on multi-source data fusion performs real-time monitoring through a tunnel construction abnormality early warning system based on multi-source data fusion. The tunnel construction abnormality early warning system based on multi-source data fusion includes a multi-source acquisition module, a fusion analysis module and an early warning control module. The tunnel construction abnormality early warning method based on multi-source data fusion includes the following steps: Step 1: interconnect the tunnel perimeter displacement monitoring device, tunnel internal settlement monitoring device, environmental monitoring device, video monitoring device and multiple sensors with the tunnel construction abnormality early warning system based on multi-source data fusion, and the multi-source acquisition module collects data sets according to different data sources; Step 2: When the time axis is limited, the fusion analysis module arranges and organizes the monitoring parameters within the same time period to form a standard data set. , and calculate the risk coefficient according to different analysis methods, and generate the corresponding parallel risk coefficient and tandem risk factor , parallel risk factor Calculated and generated by multi-dimensional parallel risk factors, the risk coefficient is connected in series It is calculated from risk factors with causal relationships; Step 3: Early warning control module based on parallel risk coefficient and tandem risk factor , judge and generate corresponding early warning signals, and manage safety issues related to tunnel construction and tunnel environment.