Construction management method of interlocking piles based on cloud computing
Through the cloud computing-based occlusion pile construction management method, real-time data monitoring and multiple linear regression models are used to dynamically adjust pile driving parameters, solving the deficiencies of data management and real-time control in traditional construction management, and achieving optimization of construction efficiency and quality.
Patent Information
- Application Number
- CN202410985453.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2044-07-23
AI Technical Summary
Traditional articulating pile construction management methods have deficiencies in informatization and data management, resulting in low data collection and processing efficiency and limited real-time data acquisition capabilities, which affects construction quality control and decision support.
The cloud computing-based construction management method of occlusal piles is used to predict soil changes and pile driving effects through real-time data monitoring, automatic parameter adjustment and multiple linear regression models, dynamically adjust pile driving speed and working parameters, and optimize construction control strategies.
It improves construction efficiency and structural quality, enhances the accuracy and response speed of construction management, ensures that the construction quality meets design requirements, and improves the overall effectiveness of construction management.
Smart Images

Figure CN118521186B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction management, and in particular to a method for managing interlocking pile construction based on cloud computing. Background Art
[0002] Interlocking piles are a widely used foundation reinforcement method in civil engineering, especially in construction projects with complex geological conditions or that need to bear heavy loads. Interlocking piles mechanically insert prefabricated concrete piles into the ground to form a tight fit with the surrounding soil, thereby enhancing the bearing capacity and overall stability of the foundation. At present, the construction management of interlocking piles mainly relies on traditional project management methods, involving on-site supervision, manual records, and post-data collation.
[0003] The prior art has the following deficiencies:
[0004] The traditional construction management method of interlocking piles has been effectively applied in many projects, but it has obvious deficiencies in informationization and data management. First, data collection and processing mostly rely on manual operations, which are prone to errors and inefficient. Second, on-site supervisors have limited ability to obtain real-time data related to interlocking piles, which to a certain extent affects the immediate control and adjustment of the construction quality of interlocking piles. In addition, project management lacks centralized and systematic information data processing, and cannot be combined with historical data for analysis, resulting in insufficient information data support in the decision-making process, which in turn affects the overall construction and use status of interlocking piles.
[0005] The above information disclosed in this Background section is only for enhancement of understanding of the background of the present disclosure and therefore it may contain information that does not constitute the prior art that is already known to one of ordinary skill in the art. Summary of the invention
[0006] The purpose of the present invention is to provide a cloud computing-based interlocking pile construction management method to address the deficiencies in the background technology.
[0007] In order to achieve the above object, the present invention provides the following technical solution: a cloud computing-based occlusal pile construction management method, comprising the following steps:
[0008] Collect relevant data during the construction of the interlocking pile and pre-process them, analyze the resistance peak and resistance gradient during the construction of the interlocking pile, calculate the resistance gradient between continuous depths, and predict soil changes;
[0009] According to the quality of the bite pile, determine the relationship between the pile driving speed and soil feedback, and adjust the working parameters of the pile driver according to the soil resistance data and the predetermined depth target;
[0010] A data-driven model based on multiple linear regression is used to predict the impact of different working parameters on the piling effect during the construction of interlocking piles. Adjustment strategies are automatically generated based on the model's prediction results and pre-set piling effect targets.
[0011] The effectiveness of the construction control strategy is analyzed based on the actual construction results and the model prediction results. The adaptation evaluation information generated by the interlocking piles during the construction control strategy is obtained to determine the adaptation effectiveness of the construction control strategy. The construction management of different interlocking piles is carried out according to the obtained adaptation results.
[0012] Preferably, relevant data during the construction of the interlocking piles are collected and preprocessed, the resistance peak and resistance gradient during the construction of the interlocking piles are analyzed, the resistance gradient between continuous depths is calculated, and soil changes are predicted, including:
[0013] The soil resistance data is collected by installing pressure sensors on the bite piles, recording the soil reaction force on the piles, the speed of the pile driver and the depth of each hit during each pile driving process;
[0014] Collect soil resistance data for each blow from the pressure sensor on the pile driver and group the data by each blow or each specific depth;
[0015] Conduct resistance peak analysis and resistance gradient calculation analysis to identify the peak value of soil resistance during pile driving;
[0016] Resistance peak analysis, detecting peaks in soil resistance data that are significantly higher than surrounding data and recording the depths at which these peaks occur;
[0017] Resistance gradient calculation and analysis, for continuous depth data points, calculate the gradient of soil resistance and predict changes in soil layers based on the gradient value.
[0018] Preferably, according to the quality of the interlocking pile, the relationship between the pile driving speed and the soil feedback is determined, and according to the soil resistance data and the predetermined depth target, the working parameters of the pile driver are adjusted. The specific steps include:
[0019] According to the pile driving quality requirements and soil resistance characteristics, the adjustment threshold of the pile driving speed is set, and an automatic adjustment mechanism is implemented during the control process to dynamically adjust the pile driving speed according to the real-time soil resistance data;
[0020] Determine the main control objectives of the pile driver and define the performance indicators to achieve the control objectives;
[0021] Based on historical data analysis, key features affecting pile driving performance are selected, and a multivariate linear regression model is used to predict the pile driving conditions under different working parameters and adjust the working parameters.
[0022] Preferably, a data-driven model based on multiple linear regression is used to predict the influence of different working parameters on the piling effect in the construction of interlocking piles. According to the prediction results of the model and the pre-set piling effect target, an adjustment strategy is automatically generated. The specific steps are as follows:
[0023] Obtain relevant data that has been preprocessed and select features related to the piling effect;
[0024] Variable definition, determine the dependent and independent variables, divide the data into training and test sets to train the multivariate linear regression model;
[0025] The prediction ability of the multivariate linear regression model was verified using the coefficient of determination and root mean square error;
[0026] Based on the prediction results of the multivariate linear regression model and the pre-set piling effect targets, adjustment suggestions are generated, and specific working parameter adjustment logic is formulated based on the prediction results and actual construction targets.
[0027] Preferably, the effectiveness of the construction control strategy is analyzed according to the actual construction results and the model prediction results, and the adaptation evaluation information generated by the occlusal piles during the construction control strategy is obtained. The specific steps are as follows:
[0028] Acquire the adaptation evaluation information generated by the occlusal pile during the construction control strategy, the adaptation evaluation information including construction adaptation information and construction quality information;
[0029] Construction adaptation information includes construction efficiency stability index, and construction quality information includes structural integrity index:
[0030] The construction efficiency stability index and the structural integrity index are normalized and combined to generate the construction management coefficient;
[0031] The construction efficiency stability index and structural integrity index are directly proportional to the construction management coefficient.
[0032] Preferably, the adaptation effectiveness of the construction control strategy is determined, and construction management of different interlocking piles is performed according to the obtained adaptation results. The specific steps include:
[0033] Compare the generated construction management coefficient with the construction strategy management threshold;
[0034] If the construction management coefficient is greater than the construction strategy management threshold, a management adaptation signal is generated without additional maintenance or processing;
[0035] If the construction management coefficient is less than or equal to the construction strategy management threshold, a management adaptation exception signal is generated to optimize the construction control strategy.
[0036] In the above technical solution, the technical effects and advantages provided by the present invention are:
[0037] The present invention effectively optimizes the construction process of interlocking piles by integrating real-time data monitoring, automatic parameter adjustment and data-driven prediction models, collects the operation data of the pile driver in real time, including soil resistance and pile driving depth, analyzes the resistance peak and the resistance gradient between continuous depths, and thus predicts soil layer changes. Through this analysis, the pile driving speed can be dynamically adjusted according to the soil resistance data and the predetermined depth target to optimize the construction efficiency and the structural quality of the pile.
[0038] The multivariate linear regression model is further used to predict the impact of different pile driver working parameters on the piling effect based on real-time monitoring data. The model automatically generates an adjustment strategy based on the prediction results and the preset piling effect targets, and automatically adjusts the operating parameters of the pile driver to ensure that the construction quality meets the design requirements. The effectiveness of the construction control strategy is evaluated by continuously comparing the actual construction results with the model prediction results, and the construction strategy is adjusted according to the adaptation evaluation information to improve the accuracy and response speed of bite pile construction management. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0040] Figure 1 The present invention is a flow chart of the interlocking pile construction management method based on cloud computing. DETAILED DESCRIPTION
[0041] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in a variety of forms and should not be construed as limited to the examples set forth herein; rather, these example embodiments are provided so that the description of the present disclosure will be more comprehensive and complete, and the concept of the example embodiments will be fully conveyed to those skilled in the art.
[0042] Embodiment 1: The present invention provides Figure 1 The cloud computing-based occlusal pile construction management method shown includes the following steps:
[0043] Collect relevant data during the construction of the interlocking pile and pre-process them, analyze the resistance peak and resistance gradient during the construction of the interlocking pile, calculate the resistance gradient between continuous depths, and predict soil changes;
[0044] According to the quality of the bite pile, determine the relationship between the pile driving speed and soil feedback, and adjust the working parameters of the pile driver according to the soil resistance data and the predetermined depth target;
[0045] A data-driven model based on multiple linear regression is used to predict the impact of different working parameters on the piling effect during the construction of interlocking piles. Adjustment strategies are automatically generated based on the model's prediction results and pre-set piling effect targets.
[0046] The effectiveness of the construction control strategy is analyzed based on the actual construction results and the model prediction results. The adaptation evaluation information generated by the interlocking piles during the construction control strategy is obtained to determine the adaptation effectiveness of the construction control strategy. The construction management of different interlocking piles is carried out according to the obtained adaptation results.
[0047] Cloud computing provides a centralized platform to store, access and manage large amounts of construction data, including real-time data, historical data, project files, etc. All relevant personnel can access this information from any location. This centralized management simplifies data processing and reduces the risk of data loss or data inconsistency.
[0048] Through the cloud platform, sensors installed at the construction site can upload data to the cloud server in real time, which makes it easier for the project management team to monitor the progress and quality of construction in real time and promptly discover and solve problems. For example, monitoring the driving depth and speed of the interlocking piles to ensure that all operations meet the design specifications. Cloud computing platforms usually include disaster recovery plans and data redundancy systems, which means that even in the event of hardware failure, natural disasters or other emergencies, project data can be protected and quickly restored.
[0049] In summary, cloud computing-based occlusal pile construction management not only improves the manageability and accessibility of data, but also enhances project transparency, collaboration efficiency, and overall risk management capabilities.
[0050] Select sensors suitable for interlocking pile construction, such as ground vibration sensors, depth and pressure sensors, to monitor the driving depth, speed and ground reaction of the pile in real time. Install sensors on the pile driving machinery to ensure stable data collection during the construction process. Configure IoT (Internet of Things) devices to directly upload data to cloud storage in real time for cloud computing and other analysis. Set up automatic synchronization to ensure timely data upload and backup;
[0051] Collect relevant data during the construction of the interlocking pile, including the working parameters of the pile driver (such as pile driving depth and speed) and environmental monitoring data (such as soil type and humidity);
[0052] It should be noted that the relevant data include data collected by various sensors and data related to the bite piles, such as soil resistance data, historical data, etc.
[0053] The pressure sensor installed on the bite pile collects soil resistance data, records the reaction force of the soil on the pile each time the pile is driven, monitors the speed of the pile driver and the depth of each hit, and records the data in real time;
[0054] Check the data integrity and remove or fill in missing values. For missing values, you can use the mean, median or forward and backward data interpolation method;
[0055] Identify and handle outliers, which may be caused by sensor failure or data entry errors. Common methods include standard deviation or IQR (interquartile range) based methods;
[0056] Create time window features (such as sliding mean, sliding standard deviation) to capture the trend and seasonal changes of the time series, and standardize or normalize the data to meet the model input requirements. The specific steps are as follows:
[0057] Create time window features, such as sliding average and sliding standard deviation , these features can help the model understand the trends and volatility in the data. The sliding average expression is: , the sliding standard deviation expression is: , where N is the window size, is a data point in the time series;
[0058] Apply data transformation to enhance the performance of the model, perform logarithmic transformation or Box-Cox transformation to handle non-normally distributed data, and standardize the data to eliminate the influence of features of different magnitudes, including Z-score standardization and Min-Max standardization;
[0059] Data anomaly detection is performed using historical and real-time data from the same construction environment, focusing on the piling depth, speed, and corresponding pressure readings. The isolation forest algorithm is applied to identify anomalies in the data. The isolation forest screens observations by randomly selecting features and randomly selecting split values. Abnormal points are usually points that are more easily isolated.
[0060] Perform characteristic calculations to calculate the average soil resistance at each depth or each blow and compare it with geological survey data to assess the uniformity and stability of the soil layer. The specific steps are as follows:
[0061] The soil resistance data for each blow is collected from the sensor on the pile driver, and the data is grouped per blow or per specific depth. The average soil resistance is calculated as: ,in, is the average soil resistance at depth d, is the soil resistance at the ith blow at depth d, and n is the number of blows at that depth;
[0062] Resistance peak analysis and resistance gradient calculation analysis are performed to identify the peaks of soil resistance during the pile driving process. These peaks usually indicate the presence of harder soil layers or obstacles. By calculating the resistance gradient between continuous depths, the changes in soil layers are predicted and the final depth of the pile is determined. The specific analysis steps are as follows:
[0063] Resistance peak analysis detects peaks in soil resistance data that are significantly higher than the surrounding data and records the depths at which these peaks occur. These may indicate a sudden change in soil hardness or an obstacle. The peak identification expression is: ,in, is the soil resistance at depth d, It is the threshold used to identify significant peaks, which can be determined based on experience or data distribution;
[0064] Resistance gradient calculation and analysis, for continuous depth data points, calculate the gradient of soil resistance to identify changes in soil properties, predict changes in soil layers by analyzing gradient values, and assist in determining the final depth of the pile or areas that require special treatment. Resistance gradient: , where is the soil resistance gradient at depth d, representing the resistance difference between adjacent depths;
[0065] If the soil layer shows relatively consistent resistance values and mild gradient changes over a long depth range, it indicates that the soil layer is relatively uniform. By analyzing the peak and gradient data, the stability of the soil can be evaluated. Frequent high peaks and high gradient changes may indicate that the soil structure is unstable, which may require additional reinforcement during construction;
[0066] Through these analysis steps and calculations, which are directly linked to the most critical soil-structure interaction during the construction process, the engineering team can better understand the geological conditions of the construction site and make more accurate construction decisions.
[0067] Analyze the quality of the interlocking piles, determine the relationship between the pile driving speed and soil feedback, monitor the speed of the pile driver and the depth of each hit, record data in real time, dynamically adjust the pile driving speed based on the soil resistance data and the predetermined depth target, establish a relationship model between soil resistance and pile driving speed, and use statistical analysis methods such as regression analysis to determine the correlation and causal relationship between the two;
[0068] According to the pile driving quality requirements and soil resistance characteristics, set the adjustment threshold of the pile driving speed; for example, when the soil resistance suddenly increases, the pile driving speed may need to be reduced to avoid damage to the pile driver or cause pile quality problems;
[0069] Implementing an automatic adjustment mechanism in the control process enables the pile driving speed to be dynamically adjusted based on real-time soil resistance data. This may involve pre-programmed logic or more advanced algorithms, such as machine learning models, to predict the optimal pile driving speed.
[0070] Adaptive control is performed to adjust the working parameters of the pile driver according to real-time data to adapt to different soil conditions and optimize the piling speed and effect. Through continuous data collection and analysis, each step in the construction process is optimized and adjusted according to the results of the previous step. The specific steps are as follows:
[0071] Determine the main control objectives of the pile driver, such as optimal pile driving speed, best hitting force and maximum efficiency, while ensuring the quality and structural integrity of the pile;
[0072] Define performance indicators that control whether the objectives are achieved, such as through pile depth accuracy, soil resistance feedback and construction efficiency;
[0073] Based on historical data analysis, select key features that affect pile driving performance, such as soil resistance, pile driving speed, pile depth, etc.
[0074] Develop a data-driven model to predict the pile driving effect under different working parameters, use a multivariate linear regression model to learn from each operation and automatically optimize the adjustment parameters to improve future performance.
[0075] A data-driven model based on multivariate linear regression is used to predict the impact of different working parameters on the piling effect in the construction of interlocking piles, optimize the construction parameters and improve the construction quality. The specific steps are as follows:
[0076] Obtain and pre-process the data collected from the sensors and operation logs of the pile driver, and select or construct features that are closely related to the pile driving effect. Possible features include original features such as pile driving speed and force, and derived features such as the rate of change of soil resistance and the historical average pile driving speed.
[0077] Conduct model development, variable definition, and determine dependent and independent variables;
[0078] Dependent variable (y): pile driving effect, such as the percentage of expected depth, independent variables (X): pile driving speed, pile driving force, soil resistance, etc.;
[0079] Use the multiple linear regression formula to build a model: ,in, is the selected feature, are model parameters, is the error term;
[0080] Perform data segmentation and divide the data into training set and test set. The commonly used ratio is 80% training set and 20% test set.
[0081] Perform model training, using the training set data to train the model through statistical software or machine learning libraries (such as Python's scikit-learn);
[0082] Perform model validation and use the test set data to verify the model's predictive ability. The main evaluation indicators include R² (coefficient of determination), RMSE (root mean square error), etc.
[0083] The previously developed multivariate linear regression model was integrated into the construction control strategy. The model takes real-time input data as input variables and uses real-time input parameters such as soil resistance and pile driving speed to predict the pile driving effect, such as the expected pile driving depth and construction quality.
[0084] According to the model's prediction results and pre-set pile driving effect targets (such as depth, time efficiency), adjustment suggestions are automatically generated, and specific working parameter adjustment logic is formulated based on the prediction results and actual construction goals. For example: soil resistance adjustment, , when the measured resistance exceeds a predetermined threshold, the piling speed is reduced to prevent excessive stress on the machinery or the pile body;
[0085] Depth Adjustment: , when the predicted depth does not reach the target depth, the piling effort is increased to ensure that the required depth is reached, where k is the adjustment factor determined by historical data analysis;
[0086] Conduct feedback adjustments, monitor the effects of the adjustments in real time, and continue to optimize the adjustment strategy based on the feedback. If the adjusted parameters fail to achieve the expected results, the system will make further adjustments or remind the operator to intervene manually.
[0087] Through these steps, adaptive control can effectively use real-time data and advanced predictive models to optimize the working parameters of the pile driver, achieving more efficient and more reliable bite pile construction. In addition, the continuous learning and adjustment capabilities ensure that the construction process can adapt to various complex geological and environmental changes.
[0088] The effectiveness of the construction control strategy is evaluated by comparing the actual construction results with the model prediction results. The model parameters are adjusted or the control logic is improved according to the feedback results to continuously optimize the construction process of the interlocking piles. The specific steps are as follows;
[0089] Obtain the adaptation evaluation information generated by the interlocking piles during the construction control strategy process, analyze the adaptation evaluation information, determine the effect of optimizing the construction control strategy of the pile driver, and determine the adaptation effectiveness of the construction control strategy. Through this systematic evaluation and optimization process, the effectiveness of the construction control strategy can be continuously improved to ensure the efficiency and accuracy of the pile driver operation, thereby maintaining the best construction quality and efficiency in a constantly changing construction environment. The adaptation evaluation information includes construction adaptation information and construction quality information;
[0090] The construction adaptation information includes the construction efficiency stability index, and the construction quality information includes the structural integrity index. After collection, the construction efficiency stability index and the structural integrity index are calibrated as SGX and JGW respectively.
[0091] The construction efficiency stability index is used to measure the consistency and reliability of efficiency during the piling construction process. The construction efficiency stability index reflects the stability of various working parameters in the construction process in achieving the predetermined effects. It also measures the fluctuation range of these parameters over time and under different conditions. Through this construction efficiency stability index, it is possible to evaluate whether the overall efficiency of the construction process can remain consistent under different working conditions and determine whether it is necessary to further optimize the construction strategy and control method.
[0092] Identify the causes of inefficiency, such as improper operation, equipment failure or improper resource allocation, and make targeted improvements. By analyzing the stability of the construction process, predicting potential risks and problems, and intervening and adjusting in advance, by monitoring the construction efficiency stability index, the construction team can manage the project more effectively, ensuring that the construction process proceeds smoothly according to the established schedule and quality standards, and making timely adjustments when necessary. This not only improves the professionalism of project management, but also provides strong support for the successful completion of the project, which has an impact on the following aspects:
[0093] Cost control: The stability of construction efficiency directly affects the cost-effectiveness of the project. It can help monitor project costs and ensure the effective use of resources within the budget. By continuously monitoring and optimizing the construction process, it can reduce the waste of materials and time and improve resource utilization.
[0094] Quality Assurance: The Construction Efficiency Stability Index provides insights into construction quality control, ensuring that construction quality remains consistent throughout the project, in line with industry standards and customer expectations. By continuously monitoring and evaluating the stability of construction efficiency, the quality of construction and long-term safety of the structure can be indirectly ensured;
[0095] Data storage and management: The Construction Efficiency Stability Index helps optimize construction scheduling and ensure that all activities are completed on time by evaluating the stability of time management during the construction process. A stable efficiency index helps to foresee and prevent factors that may cause project delays, such as improper resource allocation or inefficient operations.
[0096] The logic for obtaining the construction efficiency stability index is as follows:
[0097] There are t time periods in the set unit time. In each time period, the actual time of piling completion is obtained. With scheduled time , calculate the time efficiency TE, the calculation expression is: , where exp is the natural exponential function, representing the exponential power of e; get the actual pile driving depth With the predetermined depth , calculate the depth accuracy efficiency DE: ; Get actual energy consumption Compared with the standard energy consumption under the same operating conditions , calculate the energy efficiency EE: ; Get the number of mechanical failures , get the total number of operations in the same period , calculate the mechanical operating efficiency ME: ;
[0098] Obtain the time efficiency, accuracy efficiency, average time efficiency and energy efficiency of each time period within a unit time, and establish corresponding sets , , , , i ranges from 1 to t, and the average time efficiency is obtained , Average Depth Accuracy Efficiency , average energy efficiency , average mechanical operating efficiency , calculate the construction efficiency stability index SGX, the calculation expression is: .
[0099] It should be noted that the size of the unit time is divided according to the actual situation. Similarly, the size of the time period is also determined according to the actual usage scenario.
[0100] The structural integrity index is used to measure the structural stability and integrity of the snap pile. This index can be used to evaluate and indicate the integrity, stability and safety of the pile structure during the construction of the snap pile. The structural integrity index reflects whether the pile can maintain its designed structural integrity after construction, including the absence of serious structural defects such as cracks, voids or corrosion, which may affect its long-term performance and safety and have an impact on the following aspects:
[0101] Risk Management: By providing an accurate assessment of the structural health of the pile, the Structural Integrity Index helps identify potential structural problems so that preventive or remedial measures can be taken to avoid future structural failures;
[0102] Data quality: By systematically analyzing the structural integrity index, the construction control strategy of the pile driver can be evaluated and optimized to ensure the efficiency and accuracy of the construction process and adapt to changing construction conditions.
[0103] The logic of obtaining the structural integrity index is as follows:
[0104] Obtain the reflected signal data inside the pile, including the intensity and time delay of the reflected signal, record the location, length, and width of each defect, record the diameter of the pile, and multiply the length and width of the defect to calculate the total defect area , obtain the theoretical cross-sectional area of the entire pile , calculate the structural defect value JQ, the calculation expression is: , calculate the depth SD of the defect from the pile surface to the defect through the time delay of the signal, and establish the depth set: , m is a positive integer, obtain the depth set mean SDavg, and calculate the defect risk value QD: , based on the defect risk value and the structural defect value, the structural integrity index JGW is calculated, and the calculation expression is: .
[0105] It should be noted that non-destructive testing techniques such as acoustic testing (such as acoustic transmission testing), ultrasonic testing or geological radar (GPR) are used to conduct a comprehensive inspection of the pile body. The test is evenly carried out over the entire length of the pile body to ensure that all possible defect areas are covered. From the acoustic or ultrasonic test, the depth, length, width, impact range, etc. of the defect are extracted. For example, changes in the reflected signal can indicate the location and possible size of the defect.
[0106] The obtained construction efficiency stability index and structural integrity index are normalized and calculated simultaneously to obtain the construction management coefficient, which is calibrated as , based on the formula: , where , are the preset proportional coefficients of the construction efficiency stability index and the structural integrity index, respectively, and , All are greater than 0;
[0107] It should be noted that the formula is obtained by technicians in this field by collecting multiple groups of sample data and setting corresponding preset proportional coefficients for each group of sample data. The specific calculation process is: substituting the obtained construction efficiency stability index and structural integrity index into the formula to form an equation group, and then screening and averaging the calculated preset proportional coefficients to obtain the preset proportional coefficients. Since each group of sample data is different, the specific values of the preset proportional coefficients under different sample data are also different.
[0108] From the formula, we can see that the larger the construction efficiency stability index and the larger the structural integrity index, that is, the larger the value of the construction management coefficient, it indicates that the construction process is not only efficient, but also that the construction project adheres to the schedule without sacrificing the quality of the project. It can effectively balance the construction efficiency and quality to ensure the successful completion of the project. When the construction control strategy of the pile driver is carried out, the better the optimization effect, the stronger the effectiveness of the construction control strategy, and the higher the efficiency and precision of the pile driver operation;
[0109] By effectively managing the operation of the pile driver and the construction control strategy, not only the construction efficiency is improved, but also the construction quality is guaranteed, because the optimization of the construction control strategy can ensure that each step of the operation is carried out according to the highest standards. This double guarantee enables the entire project to find the best balance between cost, time and quality;
[0110] The smaller the construction efficiency stability index and the structural integrity index, that is, the smaller the performance value of the construction management coefficient, indicates that there is instability in efficiency during the construction process, which may be caused by a variety of factors, such as unreasonable work arrangements, frequent equipment failures, improper resource allocation, or the mismatch between workers' skills and task requirements. Inefficiency usually leads to project delays and increases the operating costs of labor and equipment;
[0111] Low values of the structural integrity index indicate problems in the quality control strategy of the snap pile construction, which may be due to the use of low-quality materials, improper construction techniques or insufficient supervision. The poor structural quality of the snap piles may not only increase future maintenance costs, but also affect the safety and service life of the building.
[0112] By normalizing the construction efficiency stability index and the structural integrity index and calculating the construction management coefficient jointly, a comprehensive index can be obtained to quantify the overall performance of the bite pile in the construction management strategy analysis process. The smaller the construction management coefficient value, the worse the performance of the bite pile in the construction management strategy adaptation, and further optimization is needed to change the strategy or adjust the usage method.
[0113] The generated construction management coefficient is compared with the construction strategy management threshold, and different signals are generated according to the comparison result, that is, a management adaptation abnormality signal and a management adaptation signal are generated;
[0114] After obtaining the generated construction management coefficient, the generated construction management coefficient is compared with the construction strategy management threshold. If the construction management coefficient is greater than the construction strategy management threshold, a management adaptation signal is generated, indicating that the construction management measures are effective under the current circumstances and can maintain or improve the efficiency and quality of the construction process. Since the construction management coefficient exceeds the construction strategy management threshold, this indicates that the current construction control strategy, resource allocation and operating procedures are very suitable for the current construction environment and project requirements. Therefore, there is no urgent need to adjust or change the existing construction strategy.
[0115] A high construction management coefficient that exceeds the construction strategy management threshold and generates a management adaptation signal is a positive indicator, showing that the management, efficiency, and quality of the bite pile construction process are in good condition.
[0116] If the construction management coefficient is less than or equal to the construction strategy management threshold, a management adaptation exception signal is generated, indicating that the construction control strategy needs to be adjusted. A construction management coefficient below the threshold may indicate that there are efficiency and quality problems in the construction process, which may be caused by inappropriate resource allocation, inefficient workflow, technical or methodological defects, or mismatch between employee skills and task requirements. The generated management adaptation exception signal prompts the project management team to re-evaluate the current construction control strategy, which may involve re-planning the construction process, including but not limited to improving work scheduling, optimizing resource allocation, or introducing new technologies and tools to improve efficiency and output quality. That is, after the management adaptation exception signal is generated, the following measures can be taken:
[0117] Adjust the construction control strategy of the pile driver based on the analysis results, such as modifying the piling parameters, optimizing the operation plan or improving safety measures, implement a continuous improvement mechanism, regularly review the effectiveness of the construction control strategy, and make necessary adjustments based on the project progress and external conditions, re-check all relevant operating data and quality inspection results to confirm the specific scope and nature of the problem, and use the root cause analysis (RCA) method to determine the cause behind the problem, which may be operating errors, equipment failures, unsuitable operating conditions or construction material problems;
[0118] Based on the diagnosis results of the problem, adjust the working parameters of the pile driver. If the problem is related to the piling speed or force, these parameters can be appropriately adjusted to adapt to the soil conditions or design requirements. Adjust the piling depth setting to ensure that each pile can reach the required design depth.
[0119] Through these comprehensive measures, not only can current construction problems be solved, but the overall performance of future projects can also be improved, ensuring the efficient and high-quality completion of the construction process.
[0120] It should be noted that the relevant threshold information in this embodiment is pre-set by professionals and will not be explained in detail here.
[0121] The present invention effectively optimizes the construction process of interlocking piles by integrating real-time data monitoring, automatic parameter adjustment and data-driven prediction models, collects the operation data of the pile driver in real time, including soil resistance and pile driving depth, analyzes the resistance peak and the resistance gradient between continuous depths, and thus predicts soil layer changes. Through this analysis, the pile driving speed can be dynamically adjusted according to the soil resistance data and the predetermined depth target to optimize the construction efficiency and the structural quality of the pile.
[0122] The multivariate linear regression model is further used to predict the impact of different pile driver working parameters on the piling effect based on real-time monitoring data. The model automatically generates an adjustment strategy based on the prediction results and the preset piling effect targets, and automatically adjusts the operating parameters of the pile driver to ensure that the construction quality meets the design requirements. The effectiveness of the construction control strategy is evaluated by continuously comparing the actual construction results with the model prediction results, and the construction strategy is adjusted according to the adaptation evaluation information to improve the accuracy and response speed of bite pile construction management.
[0123] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0124] The above description is only by way of illustration of certain exemplary embodiments of the present invention. It is undoubted that those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
[0125] It should be noted that, in this article, if there are relational terms such as first and second, etc., they are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0126] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A cloud computing-based occlusal pile construction management method, characterized in that: The steps include: Collect relevant data during the construction of the interlocking pile and pre-process them, analyze the resistance peak and resistance gradient during the construction of the interlocking pile, calculate the resistance gradient between continuous depths, and predict soil changes; According to the quality of the bite pile, determine the relationship between the pile driving speed and soil feedback, and adjust the working parameters of the pile driver according to the soil resistance data and the predetermined depth target; A data-driven model based on multiple linear regression is used to predict the impact of different working parameters on the piling effect during the construction of interlocking piles. Adjustment strategies are automatically generated based on the model's prediction results and pre-set piling effect targets. Analyze the effectiveness of the construction control strategy based on the actual construction results and the model prediction results, obtain the adaptation evaluation information generated by the occlusal piles during the construction control strategy, determine the adaptation effectiveness of the construction control strategy, and manage the construction of different occlusal piles based on the obtained adaptation results; The effectiveness of the construction control strategy is analyzed based on the actual construction results and the model prediction results, and the adaptation evaluation information generated by the occlusal piles during the construction control strategy is obtained. The specific steps are as follows: Acquire the adaptation evaluation information generated by the occlusal pile during the construction control strategy, the adaptation evaluation information including construction adaptation information and construction quality information; Construction adaptation information includes construction efficiency stability index, and construction quality information includes structural integrity index: The construction efficiency stability index and the structural integrity index are normalized and combined to generate the construction management coefficient; The construction efficiency stability index and structural integrity index are directly proportional to the construction management coefficient; The logic for obtaining the construction efficiency stability index is as follows: There are t time periods in the set unit time. In each time period, the actual time of piling completion is obtained. With scheduled time , calculate the time efficiency TE, the calculation expression is: , where exp is the natural exponential function, representing the exponential power of e; get the actual pile driving depth With the predetermined depth , calculate the depth accuracy efficiency DE: ; Get actual energy consumption Compared with the standard energy consumption under the same operating conditions , calculate the energy efficiency EE: ; Get the number of mechanical failures , get the total number of operations in the same period , calculate the mechanical operating efficiency ME: ; Obtain the time efficiency, accuracy efficiency, average time efficiency and energy efficiency of each time period within a unit time, and establish corresponding sets , , , , i ranges from 1 to t, and the average time efficiency is obtained , Average Depth Accuracy Efficiency , average energy efficiency , average mechanical operating efficiency , calculate the construction efficiency stability index SGX, the calculation expression is: ; The logic of obtaining the structural integrity index is as follows: Obtain the reflected signal data inside the pile, including the intensity and time delay of the reflected signal, record the location, length, and width of each defect, record the diameter of the pile, and multiply the length and width of the defect to calculate the total defect area , obtain the theoretical cross-sectional area of the entire pile , calculate the structural defect value, the calculation expression is: , calculate the depth SD of the defect from the pile surface to the defect through the time delay of the signal, and establish the depth set: , m is a positive integer, obtain the depth set mean SDavg, and calculate the defect risk value: , based on the defect risk value and the structural defect value, the structural integrity index JGW is calculated, and the calculation expression is: .
2. The cloud computing-based occlusal pile construction management method according to claim 1 is characterized in that: Collect relevant data during the construction of the bite pile and pre-process it, analyze the resistance peak and resistance gradient during the construction of the bite pile, calculate the resistance gradient between continuous depths, and predict soil changes, including: The soil resistance data is collected by installing pressure sensors on the bite piles, recording the soil reaction force on the piles, the speed of the pile driver and the depth of each hit during each pile driving process; Collect soil resistance data for each blow from the pressure sensor on the pile driver and group the data by each blow or each specific depth; Conduct resistance peak analysis and resistance gradient calculation analysis to identify the peak value of soil resistance during pile driving; Resistance peak analysis, detecting peaks in soil resistance data that are significantly higher than surrounding data and recording the depths at which these peaks occur; Resistance gradient calculation and analysis, for continuous depth data points, calculate the gradient of soil resistance and predict changes in soil layers based on the gradient value.
3. The cloud computing-based occlusal pile construction management method according to claim 2 is characterized in that: According to the quality of the bite pile, determine the relationship between the pile driving speed and soil feedback, and adjust the working parameters of the pile driver according to the soil resistance data and the predetermined depth target. The specific steps include: According to the pile driving quality requirements and soil resistance characteristics, the adjustment threshold of the pile driving speed is set, and an automatic adjustment mechanism is implemented during the control process to dynamically adjust the pile driving speed according to the real-time soil resistance data; Determine the main control objectives of the pile driver and define the performance indicators to achieve the control objectives; Based on historical data analysis, key features affecting pile driving performance are selected, and a multivariate linear regression model is used to predict the pile driving conditions under different working parameters and adjust the working parameters.
4. The cloud computing-based occlusal pile construction management method according to claim 3 is characterized in that: The data-driven model based on multivariate linear regression predicts the impact of different working parameters on the piling effect in the construction of interlocking piles. According to the prediction results of the model and the pre-set piling effect goals, the adjustment strategy is automatically generated. The specific steps are as follows: Obtain relevant data that has been preprocessed and select features related to the piling effect; Variable definition, determine the dependent and independent variables, divide the data into training and test sets to train the multivariate linear regression model; The prediction ability of the multivariate linear regression model was verified using the coefficient of determination and root mean square error; Based on the prediction results of the multivariate linear regression model and the pre-set piling effect targets, adjustment suggestions are generated, and specific working parameter adjustment logic is formulated based on the prediction results and actual construction targets.
5. The cloud computing-based occlusal pile construction management method according to claim 4 is characterized in that: Determine the adaptability effectiveness of the construction control strategy and carry out construction management of different interlocking piles according to the adaptation results. The specific steps include: Compare the generated construction management coefficient with the construction strategy management threshold; If the construction management coefficient is greater than the construction strategy management threshold, a management adaptation signal is generated without additional maintenance or processing; If the construction management coefficient is less than or equal to the construction strategy management threshold, a management adaptation exception signal is generated to optimize the construction control strategy.
Citation Information
Patent Citations
Automatic piling control method
CN113093552A
Intelligent pile foundation construction control method and system
CN113869680A
Visual engineering supervision system
CN114819628A
Intelligent control system and control method for cement mixing pile construction
CN117090206A
Structure construction management method
JP2017117147A