Device foundation bolt pre-burying method based on BIM and GIS technology

By constructing a 3D model using BIM and GIS technologies and utilizing a GIS positioning robot for the positioning and installation of pre-embedded bolts, the problem of low positioning accuracy of large factory equipment foundations was solved, achieving high-precision installation, cost reduction, and shortening the construction period.

CN118551444BActive Publication Date: 2025-11-28CHINA MCC22 GROUP CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410679141.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2025-11-28
Estimated Expiration
2044-05-29

AI Technical Summary

Technical Problem

Low positioning accuracy of pre-embedded bolts in the foundations of large factory equipment leads to installation deviations, causing rework and material waste, and affecting project progress and costs.

Method used

A three-dimensional information model was constructed using BIM and GIS technologies. A GIS positioning robot was used to locate and install the pre-embedded bolts, and the installation of the pre-embedded bolts was completed in conjunction with a grouting system.

Benefits of technology

This improved the installation accuracy of the pre-embedded bolts, reduced construction costs and rework rates, and shortened the construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118551444B_ABST
    Figure CN118551444B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of equipment civil foundation construction, and particularly relates to a device foundation bolt pre-embedding method based on BIM and GIS technology, actual data information of construction site topography and geomorphology generated by GIS technology is downloaded, and a model of construction content is established by using BIM technology; after fitting and rectifying the site model exported by the GIS system and the BIM model by means of Navisworks software, the GIS system is used to convert the coordinate information into the GIS positioning robot positioning system; the fixed anchor frame is used to fix the pre-embedded bolt, and the GIS positioning robot is used for positioning and installation; after the GIS positioning robot is positioned and installed, the grouting system is used for grouting, the fixed anchor frame is removed after grouting is completed, and the setting of the pre-embedded foundation bolt is completed. The present application greatly increases the installation and setting precision of the pre-embedded foundation bolt, reduces the construction cost and the rework rate, and shortens the construction period.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of equipment civil foundation construction, and particularly relates to a device foundation bolt pre-embedding method based on BIM and GIS technologies. BACKGROUND

[0002] The pre-embedded bolts on the foundation of large-scale factory equipment are numerous, widely distributed, and have corresponding specification requirements for the center point, verticality and spacing between the hole wall, etc., and need to be pre-embedded after the positioning position of the pre-embedded bolt on the equipment foundation is measured according to the drawings.

[0003] At present, the traditional method for setting the pre-embedded bolts of the foundation of large-scale factory equipment is as follows: the equipment foundation is constructed according to the drawings, a wooden formwork is erected, a settlement observation point or other permanent reference point is selected as a coordinate starting point, a total station or a theodolite combined level is used to measure the position of the anchor bolt after the wooden formwork is erected, a fixed wooden cross is erected, the anchor bolt is fixed on the fixed wooden cross by using an anchor frame and a tightening screw, and then the foundation is grouted for the second time, the anchor frame and the tightening screw are removed after the curing period of the concrete ends. This method for setting the pre-embedded bolts has a high degree of dependence on manpower, low positioning accuracy, and often causes the position of the pre-embedded anchor bolt to deviate, which often requires a large number of deviated pre-embedded anchor bolts to be removed and repositioned during the installation of the equipment, resulting in engineering rework, design changes and waste of construction materials, and adversely affecting the engineering progress and construction cost. SUMMARY

[0004] In order to solve the above technical problems, the present application provides a device foundation bolt pre-embedding method based on BIM and GIS technologies, which can improve the positioning accuracy, shorten the construction period and reduce the construction cost.

[0005] To achieve this technical purpose, the present application adopts the following solutions:

[0006] A device foundation bolt pre-embedding method based on BIM and GIS technologies is performed according to the following steps:

[0007] S1, download the actual data information of the topography of the construction site generated by the GIS technology, and use the BIM technology to establish a model of the construction content;

[0008] S2, fit and correct the site model exported from the GIS system and the BIM model by means of the Navisworks software, and then import the coordinate information converted from the GIS system into the positioning robot to form a GIS positioning robot positioning system;

[0009] S3, fix the pre-embedded bolt by using a fixed anchor frame, and install it by using the GIS positioning robot;

[0010] S4, after the GIS positioning robot is positioned and installed, grouting is carried out by using a grouting system, after grouting is completed, the fixed anchor frame is removed, and the setting of the embedded anchor bolt is completed.

[0011] Compared with the prior art, the present application has the beneficial effects that:

[0012] The present application uses BIM and GIS technology to construct a three-dimensional information composite model of the construction site topography, converts the coordinate information of the GIS system into the GIS positioning robot to form a GIS positioning robot positioning system, determines the motion trajectory of the positioning robot, realizes the installation and positioning of the embedded bolt, transmits the BIM model from the design end to the construction end, realizes data integration on the GIS platform based on the BIM model, realizes the integration of BIM model design and construction, thereby improving the construction quality and efficiency, greatly increasing the installation accuracy of the embedded bolt, avoiding positioning deviation caused by human factors, improving the installation accuracy of the embedded bolt, reducing the construction cost and rework rate, and shortening the construction period.

[0013] Further, the preferred scheme of the present application is:

[0014] In step 1, according to the design drawing, a 1:1 three-dimensional information model of the equipment foundation and the embedded bolt is established by using BIM technology.

[0015] In step 3, the magnetic chuck of the GIS positioning robot is powered on, and the initial coordinates are positioned on the intersection of the longitudinal and transverse center lines of the fixed anchor frame. After the fixed anchor frame is sucked, the GIS positioning robot reads the embedded bolt site coordinate positioning data information imported into its device, uses the infrared position scanner of the GIS positioning robot to walk for positioning, places the bolt at the positioning point, waits for grouting, and uses the total station to recheck and test. After the embedded bolt is fixed on the fixed anchor frame, it is transported to the installation position by the positioning robot, and the positioning accuracy is higher.

[0016] In step 4, the grouting system is composed of a grouting car and a wooden formwork, and after the embedded bolt is placed at the embedded bolt positioning point by the GIS positioning robot, grouting is carried out, and after the concrete performance is stable, the wooden formwork and the fixed anchor frame are removed. BRIEF DESCRIPTION OF DRAWINGS

[0017] Figure 1 is a flowchart of the present application;

[0018] Figure 2 is a system work diagram of the present application;

[0019] Figure 3 is a coordinate positioning principle of the GIS positioning robot and a foot bolt combination system schematic diagram;

[0020] Figure 4 is a grouting schematic diagram of the present application;

[0021] Figure 5 Figure is a schematic diagram of the wooden formwork and fixed anchor frame demolition of the present application;

[0022] In the figure: GIS positioning robot 1; embedded bolt combination system 2; grouting vehicle 3; infrared scanner 4; magnetic suction cup 5; fixed anchor frame 6; embedded bolt 7; wooden formwork 8; concrete 9. DETAILED DESCRIPTION

[0023] In order to fully understand the purpose, features and effects of the present application, the present application will be described in detail by the following specific embodiments, but the present application is not limited to this.

[0024] The building construction based on BIM and GIS technology can obtain the model and data of main elements such as construction site equipment, realize the integrated presentation of model scene and construction site, and thus proposes a device foundation bolt embedding method based on BIM and GIS technology, and the working principle is as follows: the GIS system exported site model and BIM model are fitted by means of Navisworks software, then the coordinate information converted by the GIS system is imported into the positioning robot, and the fixed anchor frame is driven to move to the installation position by the movement track determined by the positioning robot data acquisition, and the specific steps are as follows: as shown in Figures 1 to 5

[0025] S1, first download the actual data information of the construction site topography generated by the GIS technology, and at the same time, according to the CAD design drawing, establish the 1:1 three-dimensional information model of the equipment foundation and embedded bolt by using the BIM technology, and carry out the model establishment of the construction content, and the position of the BIM model of the embedded bolt is established according to the drawing given by the design institute (specification, positioning position, etc.).

[0026] S2, the engineering site uses GIS system to export site model and BIM model fitting by means of Navisworks software-computer automatic correction-renewed model after approval exports the final data, and the coordinate information converted by the GIS system is imported into the positioning robot to form a GIS positioning robot positioning system.

[0027] ​S3, utilize the fixed anchor frame 6 and bolt gasket fixed embedded bolt 7, fixed embedded bolt 7 is fixed on the four top corners of fixed anchor frame 6, make it constitute stable embedded bolt combination system 2, then positioning installation by means of GIS positioning robot 1: the infrared scanner 4 of GIS positioning robot 1 scans, determines the center coordinates of fixed anchor frame 6, and the intersection of fixed anchor frame longitudinal and horizontal center lines is the center point of fixed anchor frame, the coordinate here is the center coordinate, then the magnetic force suction disc 5 of GIS positioning robot 1 is placed in the middle of fixed anchor frame 6, and the initial coordinates of GIS positioning robot 1 are positioned on the center coordinates of fixed anchor frame 6, after coordinate positioning is completed, the magnetic force suction disc 5 holds fixed anchor frame 6, the initial coordinates of GIS positioning robot 1 are subtracted from the center coordinates of the installation position of embedded bolt site fixed anchor frame 6 by GIS positioning robot 1 reading imported embedded bolt site positioning data information, the motion trajectory of GIS positioning robot 1 is determined, GIS positioning robot 1 is positioned and walks, and after embedded bolt 7 is placed in the positioning point, grouting is waited, and rechecking is carried out using a total station, if the placement position of embedded bolt 7 is unqualified, manual calibration or deviation coordinate modification is needed until rechecking is qualified.

[0028] S4, after GIS positioning robot 1 is positioned and installed, grouting is carried out using a grouting system, and the grouting system is composed of a grouting vehicle 3 and a wood formwork 8, after embedded bolt 7 is stably placed in the embedded bolt positioning point by GIS positioning robot 1, grouting is carried out, and after concrete 9 is stably fixed, the wood formwork 8 and fixed anchor frame 6 are removed, and the setting of embedded anchor bolt is completed.

[0029] The embedded bolt is positioned and installed by means of the positioning robot by establishing a 1:1 three-dimensional information model of equipment foundation and embedded bolt through BIM technology, downloading construction site topography by GIS technology, fitting the two by means of Navisworks software, automatically correcting deviation by computer, reconfirming model-derived data imported into the positioning robot, and positioning and installing the embedded bolt by means of the positioning robot, so that the installation and setting precision of embedded anchor bolt is greatly increased, construction cost and rework rate are reduced, and construction period is shortened.

[0030] Finally, it should be noted that: the above-mentioned is only the preferred embodiment of the present application, of course, the person skilled in the art can modify and change the present application, if these modifications and changes belong to the scope of the claims of the present application and its equivalent technology, they should be considered as the protection scope of the present application.

Claims

1. A method for pre-embedding bolts for equipment foundations based on BIM and GIS technologies, comprising the following steps: S1. Download the actual topographic data of the construction site generated by GIS technology, and use BIM technology to build a model of the construction content; Its features are: S2. After fitting and correcting the site model exported from the GIS system and the BIM model using Navisworks software, the coordinate information converted from the GIS system is imported into the positioning robot to form a GIS positioning robot positioning system. S3. Use a fixed anchor frame to fix the pre-embedded bolts, and use a GIS positioning robot for positioning and installation; Power on the magnetic chuck of the GIS positioning robot, initially position it at the intersection of the longitudinal and transverse center lines of the fixed anchor frame. After attracting the fixed anchor frame, the GIS positioning robot reads the site coordinate positioning data of the pre-embedded bolts imported into its device, uses the infrared position scanner of the GIS positioning robot for positioning and movement, places the bolts at the positioning point and waits for grouting, and uses a total station for verification and inspection. After the S4 GIS positioning robot is installed, grouting is performed using a grouting system. Once grouting is complete, the fixed anchor frame is removed, and the pre-embedded anchor bolts are installed.

2. The method for pre-embedding equipment foundation bolts based on BIM and GIS technology according to claim 1, characterized in that: In step 1, based on the design drawings, a 1:1 three-dimensional information model of the equipment foundation and pre-embedded bolts is established using BIM technology.

3. The method for pre-embedding equipment foundation bolts based on BIM and GIS technology according to claim 1, characterized in that: In step 4, the grouting system consists of a grouting truck and wooden formwork. After the pre-embedded bolts are placed at the pre-embedded bolt positioning points by a GIS positioning robot and stabilized, grouting is carried out. After the concrete performance is stable, the wooden formwork and fixed anchor frame are removed.

Citation Information

Patent Citations

  • Two-step construction method of electrical equipment foundation

    CN111287212A

  • BIM-based soft foundation road segment query method and system

    CN111427987A