A data processing method and system based on edge computing
By dynamically adjusting the data processing time and equipment allocation of edge computing nodes, the problem of inability to effectively distinguish and process data of different monitoring equipment in the prior art is solved, and reasonable resource allocation and computing intensity optimization of edge computing nodes is realized.
Patent Information
- Application Number
- CN202411036667.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-31
AI Technical Summary
Existing edge computing nodes cannot effectively distinguish and process data from different monitoring devices during data processing, resulting in the inability to highlight the data processing of key monitoring devices, and the data processing method is relatively solid and cannot be adjusted dynamically.
By uploading data based on the preset time, dynamically adjusting the duration according to the processing value of the edge computing node, marking the high-voltage computing nodes in real time, and allocating the excess equipment to other edge computing nodes, using feature analysis model and neural network model Perform data feature analysis and equipment allocation optimization.
The reasonable data processing and reasonable allocation of resources of edge computing nodes are realized, the data upload standards are dynamically adjusted, the calculation intensity of each edge computing node is optimized, and the equipment processing efficiency of high-voltage computing nodes is improved.
Smart Images

Figure CN118573686B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of edge computing technology, and more specifically, to a data processing method and system based on edge computing. Background Art
[0002] Edge computing is a distributed computing framework that allows IoT devices to quickly process and act on data at the edge of the network. Edge computing deploys edge servers with relatively low performance but capable of handling simple needs at the edge monitoring locations of the Internet, effectively saving network bandwidth and computing power. Currently, edge computing nodes are connected to multiple monitoring devices. Edge computing nodes determine the status of monitoring data by calculating and processing the data uploaded by the monitoring devices. At present, edge computing nodes calculate and process the data uploaded by monitoring devices in a preset period, and edge computing nodes can meet the periodic processing intensity. However, this data processing method is relatively rigid, maintaining a unified data upload and processing standard for each monitoring device, and cannot highlight the data processing of key monitoring devices. Summary of the invention
[0003] In view of the shortcomings of the prior art, the object of the present invention is to provide a data processing method and system based on edge computing.
[0004] To achieve the above object, the present invention provides the following technical solutions:
[0005] A data processing method based on edge computing includes the following steps:
[0006] Step 1: The monitoring device uploads monitoring data to the edge computing node based on the preset duration, and dynamically adjusts the preset duration based on the edge computing results;
[0007] Step 2: Obtain the edge processing value of the edge computing node in real time, and determine whether to mark the edge computing node as a high-voltage computing node based on the comparison result between the edge processing value and its threshold;
[0008] Step 3: Analyze the excess devices at the high-voltage computing nodes to determine whether the excess devices need to be allocated to the remaining edge computing nodes.
[0009] Further, a data processing system based on edge computing includes an edge computing module, a node analysis module, and a device allocation module;
[0010] The edge computing module controls the monitoring device to upload monitoring data to the edge computing node based on a preset duration, and dynamically adjusts the preset duration based on the edge computing result;
[0011] The node analysis module is used to obtain the edge processing value of the edge computing node in real time, and determine whether to mark the edge computing node as a high-voltage computing node based on the comparison result between the edge processing value and its threshold value;
[0012] The device allocation module analyzes the excess devices at the high-voltage computing node and determines whether the excess devices need to be allocated to the remaining edge computing nodes.
[0013] Furthermore, the monitoring device is controlled to upload monitoring data to the edge computing node based on a preset duration, and the fixed duration is dynamically adjusted based on the edge computing result. Specifically, every t duration, the monitoring device packages the monitoring data within t duration and uploads it to the nearest edge computing node. The edge computing node performs feature recognition on the packaged monitoring data to obtain monitoring data features, and uses the monitoring data features as input data of the feature analysis model. The feature analysis model outputs the monitoring feature analysis value, and generates a data processing record of the edge computing node.
[0014] Set the monitoring feature analysis threshold. When the monitoring feature analysis value is greater than the monitoring feature analysis threshold, calculate the ratio of the monitoring feature analysis threshold to the monitoring feature analysis value to obtain the duration adjustment index and mark it as SC. The monitoring device is based on Duration, will The monitoring data within the time period is packaged and uploaded to the nearest edge computing node;
[0015] When the monitoring feature analysis value is less than or equal to the monitoring feature analysis threshold, the monitoring device maintains the time length t, packages the monitoring data within the time length t and uploads it to the nearest edge computing node.
[0016] Furthermore, the data processing record includes the monitoring equipment number and the data processing time.
[0017] Furthermore, the feature analysis model is obtained in the following manner: obtain multiple groups of monitoring data features, assign monitoring feature analysis values to the monitoring data features, use the monitoring data features as training data for the neural network model, divide the training data into a training set and a validation set by setting a ratio, and iteratively train the training data with the training set and the validation set to obtain the feature analysis model, wherein the value of the monitoring feature analysis value is greater than 0, and the larger the value of the monitoring feature analysis value, the more abnormal the monitoring data feature is.
[0018] Furthermore, the edge processing value of the edge computing node is obtained in the following way: obtain all data processing records of the edge computing node within T time before the current time of the system, mark the total number of data processing records as SJZ, obtain the monitoring device number of the data processing record, mark the data processing records of the monitoring device with the same number as the same-number device processing record, sort all the same-number device processing records in the order of data processing time, calculate the time difference between the data processing times of two adjacent same-number device processing records after sorting, and obtain the same-number processing time difference, sum up all the same-number processing time differences and take the average value, and obtain the same-number processing average time difference of the numbered monitoring device, set the same-number processing threshold average time difference, when the same-number processing average time difference is greater than or equal to the same-number processing threshold average time difference, do not do the corresponding processing, when the same-number processing average time difference is less than the same-number processing threshold average time difference, mark the numbered monitoring device as an excess number of devices, mark the total number of excess number of devices as TEP, and use the formula The edge processing value BYC of the edge computing node is obtained, where a1 is the coefficient of the total number of data processing records, and a2 is the coefficient of the total number of devices at the excess number.
[0019] Furthermore, based on the comparison result between the edge processing value and its threshold, it is determined whether to mark the edge computing node as a high-voltage computing node. Specifically, an edge processing threshold is set. When the edge processing value of the edge computing node is greater than or equal to the edge processing threshold, the edge computing node is marked as a high-voltage computing node. When the edge processing value of the edge computing node is less than the edge processing threshold, no corresponding processing is performed.
[0020] Further, the excess number of devices at the high-voltage computing node is analyzed to determine whether it is necessary to allocate the excess number of devices to the remaining edge computing nodes. Specifically, when the edge computing node is marked as a high-voltage computing node, a circle is drawn with the location of the excess number of devices as the center and a preset radius to obtain the edge allocation range, and all edge computing nodes within the edge allocation range are marked as preliminary allocation nodes, and the allocation processing value of the preliminary allocation node is obtained, and the allocation processing threshold is set. When the allocation processing value of the preliminary allocation node is greater than or equal to the allocation processing threshold, the preliminary allocation node is marked as a final allocation node. When the allocation processing value of the preliminary allocation node is less than the allocation processing threshold, no corresponding processing is performed, and the final allocation node with the largest allocation processing value is marked as the final allocation node. The excess number of devices will subsequently package the monitoring data and upload it to the final allocation node. At the same time, the final allocation node generates a device allocation record, and the device allocation record includes the device allocation time.
[0021] When there is no selected allocation node within the edge allocation range, the device at the excess number will continue to package the monitoring data and upload it to the nearest edge computing node.
[0022] Furthermore, the allocation processing value of the preliminary allocation node is obtained in the following way: obtain the edge processing value BYC of the preliminary allocation node, obtain all the equipment allocation records of the preliminary allocation node within p time periods before the current system time, mark the total number of equipment allocation records as FGH, sort all the equipment allocation records in the order of equipment allocation time, calculate the time difference between the equipment allocation times of the two adjacent equipment allocation records after sorting, and obtain the equipment allocation interval, sum up all the equipment allocation intervals and take the average, obtain the average equipment allocation interval, and mark it as PMZ, calculate the distance difference between the position of the preliminary allocation node and the position of the excess number of devices, obtain the allocation distance, and mark it as LSW, and use the formula The allocation processing value WAP of the preliminary allocation node is obtained, where b1 is the edge processing value coefficient, b2 is the total number of device allocation records coefficient, b3 is the average device allocation interval coefficient, and b4 is the allocation distance coefficient.
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] 1. The method of the present invention can ensure that the edge computing nodes rationally process the data of the monitoring equipment, and quickly arrange the excess number of devices at the high-voltage computing nodes to the appropriate edge computing nodes to ensure the reasonable allocation of edge computing;
[0025] 2. Set up an edge computing module to dynamically process the monitoring data uploaded by the monitoring equipment, dynamically formulate different data upload standards for different monitoring equipment, set up a node analysis module and a device allocation module, so as to obtain the edge processing value of the edge computing node in real time, and timely mark the high-voltage computing node based on the edge processing value, so as to optimize the edge computing intensity of each edge computing node. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a flowchart of the present invention;
[0027] Figure 2 A flowchart for determining whether to allocate excess devices to the remaining edge computing nodes. DETAILED DESCRIPTION
[0028] Example 1
[0029] Reference Figure 1 , a data processing method based on edge computing, comprising the following steps:
[0030] Step 1: The monitoring device uploads monitoring data to the edge computing node based on the preset duration, and dynamically adjusts the preset duration based on the edge computing results;
[0031] Step 2: Obtain the edge processing value of the edge computing node in real time, and determine whether to mark the edge computing node as a high-voltage computing node based on the comparison result between the edge processing value and its threshold;
[0032] Step 3: Analyze the excess devices at the high-voltage computing nodes to determine whether the excess devices need to be allocated to the remaining edge computing nodes.
[0033] Through the above method, it can be ensured that the edge computing nodes rationally process the data of the monitoring equipment, and at the same time, the excess equipment of the high-voltage computing nodes can be quickly arranged to the appropriate edge computing nodes to ensure the reasonable allocation of edge computing.
[0034] Example 2
[0035] Reference Figure 2 , a data processing system based on edge computing, including an edge computing module, a node analysis module, and a device allocation module.
[0036] Edge computing module: Every t time period, the monitoring device packages the monitoring data within t time period and uploads it to the nearest edge computing node. The edge computing node performs feature recognition on the packaged monitoring data (the feature recognition method corresponds to the monitoring data. For example, when the monitored data is visual image data, the SIFT algorithm, SURF algorithm, FAST corner detection algorithm, ORB algorithm, etc. can be used to extract key features in the visual image. For example, when the monitored data is voiceprint data, the characteristics of the voiceprint data can be obtained through the spectrum analysis method), obtains the monitoring data characteristics, and uses the monitoring data characteristics as the input data of the feature analysis model. The feature analysis model outputs the monitoring feature analysis value and generates the data processing record of the edge computing node. The data processing record includes the monitoring device number (the number of the monitoring device to which the packaged monitoring data belongs, and each monitoring device corresponds to a unique number) and the data processing time (that is, the time when the edge computing node processes the packaged monitoring data).
[0037] The feature analysis model is obtained in the following way: obtain multiple sets of monitoring data features. The authenticity of the monitoring data features is not the focus of this application. That is, it can be either simulated data or actual data. Assign monitoring feature analysis values to the monitoring data features, use the monitoring data features as training data for the neural network model, and divide the training data into a training set and a validation set by setting a ratio. The set ratio of the training set and the validation set is not the focus of this application. The set ratio can be adjusted according to actual needs. The training data is iteratively trained with the training set and the validation set to obtain the feature analysis model. Among them, the value of the monitoring feature analysis value is greater than 0. The larger the value of the monitoring feature analysis value, the more abnormal the monitoring data feature is.
[0038] Set the monitoring feature analysis threshold. The monitoring feature analysis threshold is the system setting threshold and can be modified according to actual needs.
[0039] When the monitoring feature analysis value is greater than the monitoring feature analysis threshold, the monitoring feature analysis threshold is calculated as a ratio to the monitoring feature analysis value to obtain the duration adjustment index, which is marked as SC. Duration, will The monitoring data within the time period is packaged and uploaded to the nearest edge computing node.
[0040] When the monitoring feature analysis value is less than or equal to the monitoring feature analysis threshold, the monitoring device maintains the time length t, packages the monitoring data within the time length t and uploads it to the nearest edge computing node.
[0041] Set up an edge computing module to dynamically process the monitoring data uploaded by the monitoring equipment, and dynamically formulate different data uploading standards for different monitoring equipment.
[0042] Node analysis module; obtain the edge processing value of the edge computing node in real time, set the edge processing threshold, the edge processing threshold is the system setting threshold, which can be modified according to actual needs. When the edge processing value of the edge computing node is greater than or equal to the edge processing threshold, the edge computing node is marked as a high-voltage computing node. When the edge processing value of the edge computing node is less than the edge processing threshold, no corresponding processing is performed.
[0043] The edge processing value of the edge computing node is obtained in the following way: obtain all data processing records of the edge computing node within T time before the current time of the system, mark the total number of data processing records as SJZ, obtain the monitoring device number of the data processing record, mark the data processing records of the monitoring device with the same number as the same-number device processing record, sort all the same-number device processing records in the order of data processing time, calculate the time difference between the data processing times of the two adjacent same-number device processing records after sorting, and obtain the same-number processing time difference, sum up all the same-number processing time differences and take the average, and obtain the same-number processing average time difference of the monitoring device with this number, set the same-number processing threshold average time difference, and the same-number processing threshold average time difference is the system setting threshold, which can be modified according to actual needs. When the same-number processing average time difference is greater than or equal to the same-number processing threshold average time difference, no corresponding processing is performed. When the same-number processing average time difference is less than the same-number processing threshold average time difference, the monitoring device with this number is marked as an excess number of devices, and the total number of excess number of devices is marked as TEP. Using the formula The edge processing value BYC of the edge computing node is obtained, where a1 is the coefficient of the total number of data processing records, a2 is the coefficient of the total number of devices at the excess number, the value of a1 is 0.63, and the value of a2 is 0.98.
[0044] Equipment allocation module: When the edge computing node is marked as a high-voltage computing node, a circle is drawn with the location of the excess number of devices as the center and a preset radius (the preset radius can be modified according to actual needs) to obtain the edge allocation range, and all edge computing nodes within the edge allocation range are marked as preliminary allocation nodes. The allocation processing value of the preliminary allocation node is obtained, and the allocation processing threshold is set. The allocation processing threshold is a system-set threshold and can be modified according to actual needs. When the allocation processing value of the preliminary allocation node is greater than or equal to the allocation processing threshold, the preliminary allocation node is marked as a final allocation node. When the allocation processing value of the preliminary allocation node is less than the allocation processing threshold, no corresponding processing is performed, and the final allocation node with the largest allocation processing value is marked as the final allocation node. The excess number of devices will subsequently package the monitoring data and upload it to the final allocation node. At the same time, the final allocation node generates an equipment allocation record, and the equipment allocation record includes the equipment allocation time (i.e., the time when the excess number of devices is allocated to the final allocation node).
[0045] When there is no selected allocation node within the edge allocation range, the device at the excess number will continue to package the monitoring data and upload it to the nearest edge computing node.
[0046] The allocation processing value of the preliminary allocation node is obtained in the following way: obtain the edge processing value BYC of the preliminary allocation node, obtain all the equipment allocation records of the preliminary allocation node within p time length before the current time of the system, mark the total number of equipment allocation records as FGH, sort all the equipment allocation records in the order of equipment allocation time, calculate the time difference between the equipment allocation time of the two adjacent equipment allocation records after sorting, and obtain the equipment allocation interval, sum up all the equipment allocation intervals and take the average, obtain the average equipment allocation interval, and mark it as PMZ, calculate the distance difference between the position of the preliminary allocation node and the position of the excess number of devices, obtain the allocation distance, and mark it as LSW, and use the formula The allocation processing value WAP of the preliminary allocation node is obtained, where b1 is the edge processing value coefficient, b2 is the total number of device allocation records coefficient, b3 is the average device allocation interval coefficient, and b4 is the allocation distance coefficient. The value of b1 is 0.79, the value of b2 is 0.86, the value of b3 is 0.63, and the value of b4 is 0.52.
[0047] By setting up the node analysis module and the equipment allocation module, the edge processing value of the edge computing node can be obtained in real time, and the high-voltage computing node can be marked in time based on the edge processing value to optimize the edge computing intensity of each edge computing node.
[0048] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0049] The above embodiments can be implemented in whole or in part by software, hardware, firmware or any other combination. When implemented by software, the above embodiments can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions or computer programs. When the computer instructions or computer programs are loaded or executed on a computer, the process or function described in the embodiment of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from one website site, computer, server or data center to another website site, computer, server or data center by wired or wireless (e.g., infrared, wireless, microwave, etc.). The computer-readable storage medium can be any available medium that a computer can access or a data storage device such as a server or data center that contains one or more available media sets. The available medium can be a magnetic medium (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a semiconductor medium. The semiconductor medium can be a solid-state hard disk.
[0050] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0051] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0052] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0053] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0054] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in the various embodiments of the present application. The aforementioned storage media include: various media that can store program codes, such as USB flash drives, mobile hard disks, read-only memories (ROM), random access memories (RAM), magnetic disks or optical disks.
[0055] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A data processing method based on edge computing, It is characterized in that The steps include: Step 1: The monitoring device uploads monitoring data to the edge computing node based on the preset duration, and dynamically adjusts the preset duration based on the edge computing results; Step 2: Obtain the edge processing value of the edge computing node in real time, and determine whether to mark the edge computing node as a high-voltage computing node based on the comparison result between the edge processing value and its threshold; Step 3: Analyze the excess devices at the high-voltage computing nodes to determine whether the excess devices need to be allocated to the remaining edge computing nodes; The monitoring device uploads monitoring data to the edge computing node based on the preset duration, and dynamically adjusts the preset duration based on the edge computing result. Specifically, every t duration, the monitoring device packages the monitoring data within t duration and uploads it to the nearest edge computing node. The edge computing node performs feature recognition on the packaged monitoring data to obtain the monitoring data features, and uses the monitoring data features as the input data of the feature analysis model. The feature analysis model outputs the monitoring feature analysis value, and generates the data processing record of the edge computing node. Among them, the value of the monitoring characteristic analysis value is greater than 0. The larger the value of the monitoring characteristic analysis value is, the more abnormal the monitoring data characteristics are; Set the monitoring feature analysis threshold. When the monitoring feature analysis value is greater than the monitoring feature analysis threshold, calculate the ratio of the monitoring feature analysis threshold to the monitoring feature analysis value to obtain the duration adjustment index and mark it as SC. The monitoring device is based on Duration, will The monitoring data within the time period is packaged and uploaded to the nearest edge computing node; When the monitoring feature analysis value is less than or equal to the monitoring feature analysis threshold, the monitoring device maintains the time length t, packages the monitoring data within the time length t and uploads it to the nearest edge computing node; The edge processing value of the edge computing node is obtained in the following way: obtain all data processing records of the edge computing node within T time before the current time of the system, mark the total number of data processing records as SJZ, obtain the monitoring device number of the data processing record, mark the data processing records of the monitoring device with the same number as the same-number device processing record, sort all the same-number device processing records in the order of data processing time, calculate the time difference between the data processing times of the two adjacent same-number device processing records after sorting, and obtain the same-number processing time difference, sum up all the same-number processing time differences and take the average, and obtain the same-number processing average time difference of the numbered monitoring device, set the same-number processing threshold average time difference, when the same-number processing average time difference is greater than or equal to the same-number processing threshold average time difference, no corresponding processing is performed, when the same-number processing average time difference is less than the same-number processing threshold average time difference, mark the numbered monitoring device as an excess number of devices, and mark the total number of excess number of devices as TEP, using the formula The edge processing value BYC of the edge computing node is obtained, where a1 is the coefficient of the total number of data processing records, and a2 is the coefficient of the total number of devices at the excess number.
2. A data processing system based on edge computing, applied to the data processing method based on edge computing described in claim 1, It is characterized in that Includes edge computing module, node analysis module, and device allocation module; The edge computing module controls the monitoring device to upload monitoring data to the edge computing node based on a preset duration, and dynamically adjusts the preset duration based on the edge computing result; The node analysis module is used to obtain the edge processing value of the edge computing node in real time, and determine whether to mark the edge computing node as a high-voltage computing node based on the comparison result between the edge processing value and its threshold value; The device allocation module analyzes the excess devices at the high-voltage computing node and determines whether the excess devices need to be allocated to the remaining edge computing nodes.
3. According to the data processing system based on edge computing in claim 2, It is characterized in that Data processing records include monitoring equipment number and data processing time.
4. A data processing system based on edge computing according to claim 2, It is characterized in that The feature analysis model is obtained in the following way: obtain multiple sets of monitoring data features, assign monitoring feature analysis values to the monitoring data features, use the monitoring data features as training data for the neural network model, divide the training data into a training set and a validation set by setting a ratio, and iteratively train the training data using the training set and the validation set to obtain the feature analysis model.
5. The data processing system based on edge computing according to claim 2, It is characterized in that Based on the comparison result of the edge processing value and its threshold, determine whether to mark the edge computing node as a high-voltage computing node. Specifically, set the edge processing threshold. When the edge processing value of the edge computing node is greater than or equal to the edge processing threshold, mark the edge computing node as a high-voltage computing node. When the edge processing value of the edge computing node is less than the edge processing threshold, no corresponding processing is performed.
6. A data processing system based on edge computing according to claim 2, It is characterized in that Analyze the excess number of devices at the high-voltage computing node to determine whether the excess number of devices needs to be allocated to the remaining edge computing nodes. Specifically, when the edge computing node is marked as a high-voltage computing node, draw a circle with a preset radius with the location of the excess number of devices as the center to obtain the edge allocation range, mark all edge computing nodes within the edge allocation range as preliminary allocation nodes, obtain the allocation processing value of the preliminary allocation node, set the allocation processing threshold, and when the allocation processing value of the preliminary allocation node is greater than or equal to the allocation processing threshold, mark the preliminary allocation node as the final allocation node. When the allocation processing value of the preliminary allocation node is less than the allocation processing threshold, no corresponding processing is performed, and the final allocation node with the largest allocation processing value is marked as the final allocation node. The excess number of devices will subsequently package the monitoring data and upload it to the final allocation node. At the same time, the final allocation node generates a device allocation record, and the device allocation record includes the device allocation time. When there is no selected allocation node within the edge allocation range, the device at the excess number will continue to package the monitoring data and upload it to the nearest edge computing node.
7. A data processing system based on edge computing according to claim 6, It is characterized in that The allocation processing value of the preliminary allocation node is obtained in the following way: obtain the edge processing value BYC of the preliminary allocation node, obtain all the equipment allocation records of the preliminary allocation node within p time length before the current time of the system, mark the total number of equipment allocation records as FGH, sort all the equipment allocation records in the order of equipment allocation time, calculate the time difference between the equipment allocation time of the two adjacent equipment allocation records after sorting, and obtain the equipment allocation interval, sum up all the equipment allocation intervals and take the average, obtain the average equipment allocation interval, and mark it as PMZ, calculate the distance difference between the position of the preliminary allocation node and the position of the excess number of devices, obtain the allocation distance, and mark it as LSW, and use the formula The allocation processing value WAP of the preliminary allocation node is obtained, where b1 is the edge processing value coefficient, b2 is the total number of device allocation records coefficient, b3 is the average device allocation interval coefficient, and b4 is the allocation distance coefficient.