Communication equipment installation monitoring management system and method

By designing a communication equipment installation monitoring and management system, including fan operation detection and temperature monitoring devices, the problem of slope monitoring and self-organizing network communication machine cooling process monitoring and fault diagnosis is solved, and intelligent monitoring management and fault handling of communication equipment are realized. , ensuring the reliability of monitoring results.

CN118590409BActive Publication Date: 2024-10-25SICHUAN JINYU TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411047131.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-10-25
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

After the existing slope monitoring self-organizing network communication machines are installed, there is a lack of monitoring and management solutions, which makes it impossible to monitor the heat dissipation process and fault causes of the fans in real time, affecting the smart monitoring and management of communication equipment.

Method used

Design a communication equipment installation monitoring and management system, including fan operation detection device, equipment temperature detection device, operating time recording device, operating power detection device, heat exhaust outlet wind speed detection device and main control device. Through the cooperation of these devices, the fan status can be monitored in real time. Operating status and heat dissipation process, and fault diagnosis and processing are performed through the air flow sensor matrix, heat sink plate displacement detection device, fan operation adjustment device, vibration generation device and water spray humidification device.

Benefits of technology

It realizes real-time and comprehensive monitoring and management of communication equipment, can promptly identify heat dissipation faults and fault types, ensures the reliability of monitoring results, and avoids invalid actions of too many detection devices through appropriate measures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118590409B_ABST
    Figure CN118590409B_ABST
Patent Text Reader

Abstract

The present invention relates to a communication equipment installation monitoring management system and method, and belongs to the field of electrical digital data processing technology. Aiming at defects such as "after a slope monitoring self-organizing network communication machine is installed, no relevant monitoring and management scheme is designed, such as: when a fan performs heat dissipation action, it is impossible to monitor the specific heat dissipation process, and if the heat dissipation progress fails, it is even more impossible to monitor the cause of the heat dissipation failure, etc., which is not conducive to the intelligent monitoring and management of the communication machine", a coordination scheme among a fan operation detection device, an equipment temperature detection device, an operation time recording device, an operation power detection device, a heat exhaust port wind speed detection device, and a main control device is designed, which can monitor and manage the communication machine in real time and comprehensively, especially whether there is a heat dissipation failure in the heat dissipation process of the communication equipment, and the type of failure; it is conducive to the intelligent monitoring and management of the communication machine; each detection link is carried out in an orderly manner, which can ensure the reliability of the monitoring result, and can also avoid too many detection devices from being ineffective for a long time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of electrical digital data processing, and in particular relates to a communication equipment installation monitoring management system and method. Background Art

[0002] A Chinese patent with publication number CN218178489U discloses a slope monitoring self-organizing network communication machine, including a bottom plate, a support frame fixedly installed on the top of the bottom plate, a mounting plate movably sleeved on the side surface of the support frame, a communication device fixedly installed on the left side of the mounting plate, and a protective shell fixedly sleeved on the side surface of the support frame. The slope monitoring self-organizing network communication machine is provided with a mounting plate, a protective shell, a sealing plate, a rotating drum, a telescopic spring and a telescopic rod. Since the surface of the support frame is threadedly connected to the inside of the rotating drum, when the rotating drum rotates downward, the mounting plate is driven to move downward on the surface of the support frame, so that the bottom ends of the two telescopic rods push the sealing plate to the left, so that the communication device can be moved downward from the protective shell, and the rotating drum is rotated upward to move the mounting plate upward into the protective shell and the sealing plate is moved to the right by the elastic force of the telescopic spring, so that the protective shell is sealed, thereby facilitating the protection and operation of the slope monitoring self-organizing network communication machine.

[0003] However, after the installation of this communication machine, no relevant monitoring and management plan was designed. For example, when the fan is performing heat dissipation, the specific heat dissipation process cannot be monitored. Moreover, if the heat dissipation progress fails, the cause of the heat dissipation failure cannot be monitored, which is not conducive to the intelligent monitoring and management of the communication machine.

[0004] Therefore, at this stage, it is necessary to design a communication equipment installation monitoring management system and method to solve the above problems. Summary of the invention

[0005] The purpose of the present invention is to provide a communication equipment installation monitoring and management system and method for solving the technical problems existing in the above-mentioned prior art. After the above-mentioned slope monitoring self-organizing network communication machine is installed, no relevant monitoring and management plan is designed. For example, when the fan is performing heat dissipation, the specific heat dissipation process cannot be monitored, and if the heat dissipation progress fails, the cause of the heat dissipation failure cannot be monitored, etc., which is not conducive to the intelligent monitoring and management of the communication machine.

[0006] To achieve the above object, the technical solution of the present invention is:

[0007] A communication equipment installation monitoring and management system, comprising a fan operation detection device, an equipment temperature detection device, an operation time recording device, an operation power detection device, a heat exhaust outlet wind speed detection device, and a main control device, wherein the main control device is respectively connected to the fan operation detection device, the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust outlet wind speed detection device;

[0008] The fan operation detection device is used to detect whether the heat dissipation fan is in operation;

[0009] The device temperature detection device is used to detect the real-time temperature of the communication device and determine whether the real-time temperature meets the preset temperature of the cooling fan start-up condition;

[0010] The operation time recording device is used to record the actual operation time of the cooling fan, and determine whether the actual operation time reaches the preset operation time corresponding to the completion of the heat dissipation of the communication device;

[0011] The operating power detection device is used to detect whether the operating power of the cooling fan is abnormal;

[0012] The heat exhaust outlet wind speed detection device is used to detect whether the wind speed of the heat exhaust outlet is abnormal;

[0013] Wherein, the main control device controls the initial state of the fan operation detection device to be normally open, and controls the initial state of the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust port wind speed detection device to be normally closed;

[0014] When the fan operation detection device detects that the cooling fan is in operation, the main control device controls the device temperature detection device to turn on;

[0015] When the equipment temperature detection device determines that the real-time temperature meets the preset temperature of the cooling fan start-up condition, the main control device controls the operation time recording device to start;

[0016] When the operation time recording device determines that the actual operation time reaches the preset operation time corresponding to the real-time temperature, and the real-time temperature has not yet completely dissipated heat, the main control device controls the operation power detection device to start;

[0017] When the operating power detection device detects that there is no abnormality in the operating power of the heat dissipation fan, the main control device controls the heat exhaust port wind speed detection device to turn on.

[0018] Furthermore, it also includes an airflow sensor matrix and a heat sink displacement detection device, and the main control device is connected to the airflow sensor matrix and the heat sink displacement detection device respectively;

[0019] The airflow sensor matrix is ​​used to detect whether the airflow at the position corresponding to the air hole on the heat sink is abnormal;

[0020] The heat sink displacement detection device is used to detect whether the heat sink has abnormal displacement;

[0021] Wherein, the main control device controls the initial state of the airflow sensor matrix and the heat sink displacement detection device to be normally closed;

[0022] When the heat exhaust outlet wind speed detection device detects that the wind speed of the heat exhaust outlet is abnormal, the main control device controls the heat sink displacement detection device to turn on;

[0023] When the heat sink displacement detection device detects that the heat sink has no abnormal displacement, the main control device controls the airflow sensor matrix to turn on.

[0024] Furthermore, it also includes a fan operation adjustment device, and the main control device is connected to the fan operation adjustment device;

[0025] The fan operation adjustment device is used to adjust the operating power of the heat dissipation fan;

[0026] Wherein, the main control device controls the initial state of the fan operation adjustment device to be normally closed;

[0027] When the airflow sensor matrix detects that the airflow at the positions corresponding to the air holes on the heat sink is abnormal, that is, some of the air holes are blocked, the main control device controls the fan operation adjustment device to increase the operating power of the heat dissipation fan.

[0028] Furthermore, it also includes a vibration generating device, and the main control device is connected to the vibration generating device;

[0029] The vibration generating device is used to make the heat sink vibrate slightly;

[0030] Wherein, the main control device controls the initial state of the vibration generating device to be normally closed;

[0031] When the airflow sensor matrix detects that some of the air holes are blocked and completely blocked, the main control device controls the vibration generating device to turn on.

[0032] Furthermore, it also includes a water spray humidification device, and the main control device is connected to the water spray humidification device;

[0033] The water spray humidification device is used to spray water to the air holes on the heat sink;

[0034] Wherein, the main control device controls the initial state of the water spray humidification device to be normally closed;

[0035] When the airflow sensor matrix detects that some of the air holes are blocked but not completely blocked, the main control device controls the water spray humidification device to turn on.

[0036] Furthermore, it also includes a wireless communication device and a remote intelligent terminal, and the main control device is connected to the remote intelligent terminal network through the wireless communication device.

[0037] The communication equipment installation monitoring and management method adopts the communication equipment installation monitoring and management system as mentioned above to perform communication equipment installation monitoring and management.

[0038] A storage medium stores a computer program, which executes the above-mentioned communication equipment installation monitoring and management method when executed.

[0039] Compared with the prior art, the present invention has the following beneficial effects:

[0040] One of the beneficial effects of this solution is that, in response to defects such as "after the installation of the above-mentioned slope monitoring self-organizing network communication machine, no relevant monitoring and management plan is designed, such as: when the fan is cooling, the specific cooling process cannot be monitored, and if the cooling progress fails, the cause of the cooling failure cannot be monitored, etc., which is not conducive to the intelligent monitoring and management of the communication machine", a coordination plan among the fan operation detection device, the equipment temperature detection device, the operation time recording device, the operation power detection device, the heat exhaust port wind speed detection device, and the main control device is designed, which can monitor and manage the communication machine in real time and comprehensively, especially whether there is a cooling failure in the cooling process of the communication equipment, and the type of failure; it is conducive to the intelligent monitoring and management of the communication machine; and each detection link is carried out in an orderly manner to ensure the reliability of the monitoring results, and to avoid too many detection devices from being ineffective for a long time. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 This is a schematic diagram of the system structure of the implementation scheme.

[0042] Figure 2 This is a schematic diagram of the system operation principle of the implementation scheme. DETAILED DESCRIPTION

[0043] like Figure 1 As shown, a communication equipment installation monitoring and management system is proposed, including a fan operation detection device, an equipment temperature detection device, an operation time recording device, an operation power detection device, a heat exhaust outlet wind speed detection device, and a main control device, wherein the main control device is respectively connected to the fan operation detection device, the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust outlet wind speed detection device;

[0044] The fan operation detection device is used to detect whether the heat dissipation fan is in operation;

[0045] The device temperature detection device is used to detect the real-time temperature of the communication device and determine whether the real-time temperature meets the preset temperature of the cooling fan start-up condition; that is, the cooling fan start-up condition is that the temperature of the communication device reaches the preset temperature.

[0046] The operating time recording device is used to record the actual operating time of the cooling fan, and determine whether the actual operating time reaches the preset operating time corresponding to the completion of the heat dissipation of the communication equipment; that is, when the actual operating time of the cooling fan reaches the preset operating time, the communication equipment should theoretically complete the heat dissipation. If not, it indicates that there is an abnormality in the heat dissipation process.

[0047] The operating power detection device is used to detect whether the operating power of the cooling fan is abnormal;

[0048] The heat exhaust outlet wind speed detection device is used to detect whether the wind speed of the heat exhaust outlet is abnormal;

[0049] Among them, Figure 2 As shown, the main control device controls the initial state of the fan operation detection device to be normally open, and controls the initial state of the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust port wind speed detection device to be normally closed; the operation of the cooling fan serves as the trigger condition for the entire system.

[0050] When the fan operation detection device detects that the cooling fan is in operation, the main control device controls the device temperature detection device to start; the real-time temperature of the communication device can be used to determine whether the cooling fan malfunctions.

[0051] When the equipment temperature detection device determines that the real-time temperature meets the preset temperature of the cooling fan start-up condition, the main control device controls the operation time recording device to start; after determining that the cooling fan is not malfunctioning, the cooling process of the cooling fan is judged whether it is abnormal through the cooling fan operation time.

[0052] When the operating time recording device determines that the actual operating time reaches the preset operating time corresponding to the real-time temperature, and the real-time temperature has not yet completed the heat dissipation, the main control device controls the operating power detection device to turn on; when the heat dissipation process of the heat dissipation fan is abnormal, it can be classified into whether the operating power of the heat dissipation fan is abnormal, and whether the heat dissipation component is abnormal.

[0053] When the operating power detection device detects that there is no abnormality in the operating power of the heat dissipation fan, the main control device controls the heat exhaust port wind speed detection device to turn on.

[0054] In the above scheme, in response to defects such as "after the installation of the above-mentioned slope monitoring self-organizing network communication machine, no relevant monitoring and management plan was designed, such as: when the fan is performing heat dissipation, the specific heat dissipation process cannot be monitored, and if the heat dissipation progress fails, the cause of the heat dissipation failure cannot be monitored, etc., which is not conducive to the intelligent monitoring and management of the communication machine", a coordination scheme is designed among the fan operation detection device, the equipment temperature detection device, the operation time recording device, the operation power detection device, the heat exhaust port wind speed detection device, and the main control device, which can monitor and manage the communication machine in real time and comprehensively, especially whether there is a heat dissipation failure in the heat dissipation process of the communication equipment, and the type of failure; it is conducive to the intelligent monitoring and management of the communication machine; and each detection link is carried out in an orderly manner to ensure the reliability of the monitoring results, and to avoid too many detection devices from being ineffective for a long time.

[0055] Furthermore, it also includes an airflow sensor matrix and a heat sink displacement detection device, and the main control device is connected to the airflow sensor matrix and the heat sink displacement detection device respectively;

[0056] The airflow sensor matrix is ​​used to detect whether the airflow at the position corresponding to the air hole on the heat sink is abnormal;

[0057] The heat sink displacement detection device is used to detect whether the heat sink has abnormal displacement;

[0058] Wherein, the main control device controls the initial state of the airflow sensor matrix and the heat sink displacement detection device to be normally closed;

[0059] When the heat exhaust outlet wind speed detection device detects that the wind speed of the heat exhaust outlet is abnormal, the main control device controls the heat sink displacement detection device to turn on;

[0060] When the heat sink displacement detection device detects that the heat sink has no abnormal displacement, the main control device controls the airflow sensor matrix to turn on.

[0061] In the above scheme, considering that the wind speed at the heat exhaust port is abnormal, it should be the heat exhaust component that has failed, but the details of the failure are still unclear; therefore, an airflow sensor matrix and a heat sink displacement detection device are designed to clearly classify the above failures.

[0062] Furthermore, it also includes a fan operation adjustment device, and the main control device is connected to the fan operation adjustment device;

[0063] The fan operation adjustment device is used to adjust the operating power of the heat dissipation fan;

[0064] Wherein, the main control device controls the initial state of the fan operation adjustment device to be normally closed;

[0065] When the airflow sensor matrix detects that the airflow at the positions corresponding to the air holes on the heat sink is abnormal, that is, some of the air holes are blocked, the main control device controls the fan operation adjustment device to increase the operating power of the heat dissipation fan.

[0066] In the above solution, if the heat sink is abnormal and the pores are blocked, the problem can be overcome by increasing the operating power of the heat dissipation fan.

[0067] Furthermore, it also includes a vibration generating device, and the main control device is connected to the vibration generating device;

[0068] The vibration generating device is used to make the heat sink vibrate slightly;

[0069] Wherein, the main control device controls the initial state of the vibration generating device to be normally closed;

[0070] When the airflow sensor matrix detects that some of the air holes are blocked and completely blocked, the main control device controls the vibration generating device to turn on.

[0071] In the above scheme, considering that some pores are in a completely blocked state, they can only be unblocked by vibrating the heat sink, so a vibration generating device is designed to overcome the above defects.

[0072] Furthermore, it also includes a water spray humidification device, and the main control device is connected to the water spray humidification device;

[0073] The water spray humidification device is used to spray water to the air holes on the heat sink;

[0074] Wherein, the main control device controls the initial state of the water spray humidification device to be normally closed;

[0075] When the airflow sensor matrix detects that some of the air holes are blocked but not completely blocked, the main control device controls the water spray humidification device to turn on.

[0076] In the above scheme, considering that some pores are not completely blocked, the airflow passing through the pores is just lower than the normal level. Therefore, a water spray humidification device can be designed to clear them. If the airflow can pass through, it means that the water can also pass through, and water will not accumulate in the pores and cause further blockage.

[0077] Furthermore, it also includes a wireless communication device and a remote intelligent terminal, and the main control device is connected to the remote intelligent terminal network through the wireless communication device to achieve remote data interaction.

[0078] The communication equipment installation monitoring and management method adopts the communication equipment installation monitoring and management system as mentioned above to perform communication equipment installation monitoring and management.

[0079] A storage medium stores a computer program, which executes the above-mentioned communication equipment installation monitoring and management method when executed.

Claims

1. Communication equipment installation monitoring and management system, characterized in that: It includes a fan operation detection device, an equipment temperature detection device, an operation time recording device, an operation power detection device, a heat exhaust outlet wind speed detection device, and a main control device, and the main control device is connected to the fan operation detection device, the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust outlet wind speed detection device respectively; The fan operation detection device is used to detect whether the heat dissipation fan is in operation; The device temperature detection device is used to detect the real-time temperature of the communication device and determine whether the real-time temperature meets the preset temperature of the cooling fan start-up condition; The operation time recording device is used to record the actual operation time of the cooling fan, and determine whether the actual operation time reaches the preset operation time corresponding to the completion of the heat dissipation of the communication device; The operating power detection device is used to detect whether the operating power of the cooling fan is abnormal; The heat exhaust outlet wind speed detection device is used to detect whether the wind speed of the heat exhaust outlet is abnormal; Wherein, the main control device controls the initial state of the fan operation detection device to be normally open, and controls the initial state of the equipment temperature detection device, the operation time recording device, the operation power detection device, and the heat exhaust port wind speed detection device to be normally closed; When the fan operation detection device detects that the cooling fan is in operation, the main control device controls the device temperature detection device to turn on; When the equipment temperature detection device determines that the real-time temperature meets the preset temperature of the cooling fan start-up condition, the main control device controls the operation time recording device to start; When the operation time recording device determines that the actual operation time reaches the preset operation time corresponding to the real-time temperature, and the real-time temperature has not yet completely dissipated heat, the main control device controls the operation power detection device to start; When the operating power detection device detects that the operating power of the heat dissipation fan is not abnormal, the main control device controls the heat exhaust outlet wind speed detection device to turn on; It also includes an airflow sensor matrix and a heat sink displacement detection device, and the main control device is connected to the airflow sensor matrix and the heat sink displacement detection device respectively; The airflow sensor matrix is ​​used to detect whether the airflow at the position corresponding to the air hole on the heat sink is abnormal; The heat sink displacement detection device is used to detect whether the heat sink has abnormal displacement; Wherein, the main control device controls the initial state of the airflow sensor matrix and the heat sink displacement detection device to be normally closed; When the heat exhaust outlet wind speed detection device detects that the wind speed of the heat exhaust outlet is abnormal, the main control device controls the heat sink displacement detection device to turn on; When the heat sink displacement detection device detects that the heat sink has no abnormal displacement, the main control device controls the airflow sensor matrix to turn on; It also includes a fan operation adjustment device, and the main control device is connected to the fan operation adjustment device; The fan operation adjustment device is used to adjust the operating power of the heat dissipation fan; Wherein, the main control device controls the initial state of the fan operation adjustment device to be normally closed; When the airflow sensor matrix detects that the airflow at the positions corresponding to the air holes on the heat sink is abnormal, that is, some of the air holes are blocked, the main control device controls the fan operation adjustment device to increase the operating power of the heat dissipation fan; It also includes a vibration generating device, and the main control device is connected to the vibration generating device; The vibration generating device is used to make the heat sink vibrate slightly; Wherein, the main control device controls the initial state of the vibration generating device to be normally closed; When the airflow sensor matrix detects that some of the air holes are blocked and completely blocked, the main control device controls the vibration generating device to turn on; It also includes a water spray humidification device, and the main control device is connected to the water spray humidification device; The water spray humidification device is used to spray water to the air holes on the heat sink; Wherein, the main control device controls the initial state of the water spray humidification device to be normally closed; When the airflow sensor matrix detects that some of the air holes are blocked but not completely blocked, the main control device controls the water spray humidification device to turn on; It also includes a wireless communication device and a remote intelligent terminal, and the main control device is connected to the remote intelligent terminal network through the wireless communication device.

2. A communication equipment installation monitoring and management method, characterized in that: The communication equipment installation monitoring and management system as claimed in claim 1 is used to carry out communication equipment installation monitoring and management.

3. A storage medium, characterized in that: The storage medium stores a computer program, which, when executed, executes the communication equipment installation monitoring and management method according to claim 2.