A vertical pier breakwater with flow-through and silt-collecting properties

The permeable siltation type vertical wharf breakwater automatically adjusts the wave deflector and water flow direction, combined with a multi-level drainage system and solid-liquid separator, to solve the stability problems of the breakwater caused by water flow impact and sediment deposition, and achieves efficient siltation. management and water flow treatment, reducing maintenance costs and structural risks.

CN118668638BActive Publication Date: 2024-10-22TIANJIN RES INST FOR WATER TRANSPORT ENG M O T
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411166840.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-10-22
Estimated Expiration
2044-08-23

AI Technical Summary

Technical Problem

During the installation operation of vertical wharf breakwaters, when the water flow impact is too large, it will carry sediment and cause the front edge or bottom of the breakwater to gradually accumulate, increasing maintenance costs, and may reduce the water depth of the wharf, affecting the ship's entry and exit operations, and the continuous water flow impact And sedimentation will change the underwater topography, affect the stability of the breakwater, and even cause the structure to deform or collapse.

Method used

Adopt permeable sedimentation type vertical wharf breakwater design, including waterway side embankment, stone cushion, concrete base layer, guide wave board, lubricating mobile gate parts, arc trajectory chute, and inclined frame guide and sediment removal components , hydraulic rod, hydraulic push rod, multi-level drainage system and solid-liquid separator, by automatically adjusting the wave deflector and water flow direction, using the principle of gravity separation to remove suspended particles, forming a complete sludge treatment process, achieving automated operation and efficient drainage.

Benefits of technology

It effectively slows down water flow impact and sedimentation, reduces maintenance costs, improves the stability and management efficiency of breakwaters, ensures smooth drainage of water, avoids sediment accumulation, reduces the risk of structural damage, and adapts to the drainage needs of different areas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118668638B_ABST
    Figure CN118668638B_ABST
Patent Text Reader

Abstract

The invention discloses a flow-through silt-collecting upright dock breakwater, which relates to the technical field of breakwaters and comprises a waterway side embankment. The automatic adjustment of the guide wave-breaking board is achieved by cooperating with an inclined guide and silt-removing assembly, a hydraulic rod, a rotating shaft, a hydraulic push rod and a guide wave-breaking board to guide the direction and speed of the water flow. The staggered installation of the first water body and the second water body and the guide water tank arranged therebetween further optimize the water flow distribution, mitigate the impact of the water flow, promote the collection and discharge of sediments, and avoid the discharge of solid matter with the water. When the impact of the water flow is too large, the silt will be carried, resulting in the gradual accumulation of silt at the front edge or bottom of the breakwater, which increases the maintenance cost of the slope embankment, and may reduce the water depth of the dock over time, affecting the entry and exit operations of ships. The problem is effectively mitigated by the continuous impact of the water flow and the change of the surrounding underwater terrain by the sediment deposition, and the stability of the slope embankment is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of breakwaters, in particular to a flow-through and silt-collecting vertical dock breakwater. Background Art

[0002] Breakwaters are underwater structures built to block the impact of waves, protect harbors, maintain a stable water surface to protect harbors from bad weather, and allow ships to anchor and operate safely. Breakwaters can also prevent harbor siltation and wave erosion of the coastline. They are an important component of artificially protected coastal ports.

[0003] However, in the prior art, during the installation of vertical dock breakwaters, when the water flow impact is too large, it will carry mud and cause the mud to gradually accumulate at the front edge or bottom of the breakwater, increasing the maintenance cost of the slope breakwater, and may reduce the water depth of the dock over time, affecting the entry and exit operations of ships. In addition, continuous water flow impact and mud deposition may change the surrounding underwater terrain and affect the stability of the breakwater. In severe cases, it may cause structural deformation or collapse. Therefore, it is necessary to propose a permeable and silt-collecting vertical dock breakwater. Summary of the invention

[0004] The object of the present invention is to provide a flow-through and silt-collecting vertical dock breakwater to solve the problem proposed in the above-mentioned background technology that during the installation operation of the vertical dock breakwater, when the water flow impact is too large, it will carry mud and cause the mud to gradually accumulate at the front edge or bottom of the breakwater, increase the maintenance cost of the slope breakwater, and may reduce the water depth of the dock over time, affecting the entry and exit operations of ships, and the continuous water flow impact and mud deposition may change the surrounding underwater terrain, affect the stability of the breakwater, and in severe cases may cause structural deformation or collapse.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a permeable and silt-collecting vertical dock breakwater, comprising a waterway side embankment, a stone cushion layer is installed at the bottom of the waterway side embankment, a concrete foundation layer is installed at the bottom of the stone cushion layer, a rotating shaft column is installed at the top side end of the stone cushion layer, a guide wave-breaking plate is arranged outside the rotating shaft column, a side groove is opened at the bottom of the side end of the guide wave-breaking plate, a connecting bearing column is fastened to the bottom of the side groove, a lubricating movable gate is fastened to the bottom of the connecting bearing column, and two groups of arc-shaped blocks are symmetrically opened on the surface of the stone cushion layer. Track slide, the lubricating movable gate member drives the guide wave-breaking plate to adjust the internal displacement along the arc track slide in cooperation with the rotating shaft column, a side dike is arranged on the top of the waterway side dike, a side dike water guide slope is arranged on the side of the side dike, a vertical wharf is installed on the side of the side dike water guide slope, a treatment dam water tank overhead layer is installed on the side of the vertical wharf, a silt treatment chamber is installed on the side of the treatment dam water tank overhead layer, a bottom water inlet is installed between the height difference between the side dike water guide slope and the stone cushion layer, and an inclined frame guide desilting component is installed inside the treatment dam water tank overhead layer;

[0006] The inclined frame type guiding desilting assembly includes a bottom waterway, an inclined plate sedimentation tank is installed at the middle end inside the bottom waterway, a first water diversion body and a second water diversion body are respectively installed inside the bottom waterway, the first water diversion body and the second water diversion body are staggered, and a guiding water trough is arranged in the gap between the first water diversion body and the second water diversion body.

[0007] Preferably, the side of the waterway embankment is fastened with a slotted part, a rotating shaft is installed inside the slotted part, the side of the rotating shaft is fastened with a pushing side wing, the side of the pushing side wing is fastened with a hydraulic rod, the side end of the hydraulic rod is fastened to the surface of the waterway embankment, a hydraulic pushing rod is installed on the side of the rotating shaft, the pushing side wing is connected to the hydraulic pushing rod, and the side end of the hydraulic pushing rod is fastened to the guide wave-breaking plate.

[0008] Preferably, pressure relief holes are symmetrically provided on the surface of the side dike water diversion slope, a transverse drainage ditch is installed at the connection between the side dike water diversion slope and the vertical wharf, and a transverse drainage hydraulic gate is installed at the bottom of the transverse drainage ditch.

[0009] Preferably, a first hydraulic bottom drainage gate is installed inside the bottom water inlet, and a second hydraulic bottom drainage gate and a third hydraulic bottom drainage gate are installed in stages inside the overhead layer of the treatment dam water tank. The first hydraulic bottom drainage gate, the second hydraulic bottom drainage gate, the third hydraulic bottom drainage gate and the lateral drainage hydraulic gate are all connected to an external motion controller.

[0010] Preferably, the side of the second hydraulic bottom drainage gate is connected to the high entrance of the bottom waterway, a silt plate is installed at the bottom of the inclined plate sedimentation tank, an adsorption pre-buried pipe is installed on the surface of the silt plate, and the side end of the adsorption pre-buried pipe is connected to a solid-liquid separator.

[0011] Preferably, the side end of the solid-liquid separator is connected to a sludge conveying pipeline, and a pre-buried groove is opened on the outer peripheral side of the sludge conveying pipeline, and the pre-buried groove is opened inside the concrete base layer of the overhead layer of the treatment dam water tank.

[0012] Preferably, an oblique sludge discharge net is installed inside the sludge treatment chamber, and a hydraulically-propelled cleaning plate is installed on the side of the sludge treatment chamber through a fixed frame, and the hydraulically-propelled cleaning plate is connected to a built-in sludge detection sensor.

[0013] Preferably, a trough is provided on the inner side of the sludge treatment chamber, and the trough is located on the side of the oblique sludge discharge net. The side of the trough is connected to a centrifugal dehydrator through a sludge pump. The power generation of the centrifugal dehydrator can utilize the cooperation of a stress sensor group installed inside the guide wave-breaking plate to convert hydraulic potential energy into piezoelectric potential energy, and then drive the centrifugal dehydrator through a pre-buried generator.

[0014] Preferably, the top end of the centrifugal dehydrator is connected to a water suction pipeline, and the side end of the water suction pipeline is connected to a water suction guide.

[0015] Preferably, the side of the centrifugal dehydrator is connected to the sludge treatment tank on the side through an external sludge discharge pipeline.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] 1. In the present invention, the automatic adjustment of the guide wave-breaking board is realized by cooperating with the inclined frame type guide desilting assembly, the hydraulic rod, the rotating shaft, the hydraulic push rod and the guide wave-breaking board. The position and angle of the wave-breaking board can be dynamically adjusted according to the real-time water flow conditions, so as to effectively guide the direction and speed of the water flow and reduce the impact of floods. At the same time, the automatic operation is realized by using an external motion controller, which improves the response speed and management efficiency. The high entrance of the bottom waterway is installed on the side of the second hydraulic bottom drainage gate, so that the inclined plate sedimentation tank uses the gravity separation principle to effectively remove the suspended particles in the water, and the staggered first water body and the second water body The installation and the guide water trough set in between further optimize the water flow distribution, slow down the impact of water flow, and promote the collection and discharge of sediment, which helps to maintain the ideal water level and treatment efficiency in the inclined plate sedimentation tank, ensures the smooth discharge of water flow, and avoids the discharge of solid matter with the water, reduces the problem of excessive water flow impact, which will carry silt and cause the gradual accumulation of silt at the front edge or bottom of the breakwater, increase the maintenance cost of the slope embankment, and may reduce the water depth of the dock over time, affecting the ship's entry and exit operations, effectively slowing down the changes in the surrounding underwater terrain caused by continuous water flow impact and silt deposition, and increasing the stability of the slope embankment.

[0018] 2. In the present invention, a multi-level drainage system is formed by the cooperation of the first hydraulic bottom drainage gate, the second hydraulic bottom drainage gate, the third hydraulic bottom drainage gate and the lateral drainage hydraulic gate, which are installed in stages inside and on the sides of the overhead layer of the treatment dam water tank. Each level of the gate can be controlled by an external motion controller, so that the overall drainage can be centrally controlled and automated. That is, through a pre-set program or real-time monitoring data, the external motion controller can automatically adjust the opening degree of each level of the water gate according to the actual water conditions, ensuring efficient drainage while maintaining structural safety, reducing human intervention, and improving management efficiency. Independent adjustment can adapt to the specific drainage needs of different areas, increasing the flexibility and response speed of the system, forming a complete processing flow from primary sedimentation to final solid-liquid separation, ensuring the cleanliness of the waterway and the effective management of silt. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the main structure of a flow-through silt-collecting vertical dock breakwater of the present invention;

[0020] Figure 2 It is a schematic structural diagram of a side view of a flow-through silt-collecting vertical dock breakwater of the present invention;

[0021] Figure 3 The invention discloses a vertical pier breakwater of a flow-through silt-collecting type. Figure 1 A schematic diagram of the enlarged structure at point A;

[0022] Figure 4The invention discloses a vertical pier breakwater of a flow-through silt-collecting type. Figure 1 A schematic diagram of the enlarged structure at B;

[0023] Figure 5 It is a schematic diagram of the internal cross-sectional structure of the main body of a flow-through silt-collecting vertical dock breakwater of the present invention;

[0024] Figure 6 It is a structural schematic diagram of an inclined frame type guiding and desilting component in a permeable and silting-collecting vertical dock breakwater of the present invention;

[0025] Figure 7 The invention discloses a vertical pier breakwater of a flow-through silt-collecting type. Figure 5 Enlarged structural diagram at C.

[0026] In the figure: 1, waterway side bank; 2, concrete foundation layer; 3, stone cushion layer; 4, side bank; 5, wave guide plate; 6, rotating shaft column; 7, side bank water diversion slope; 8, bottom water inlet; 9, horizontal drainage groove; 10, vertical dock; 11, pressure relief hole; 12, arc track slide; 13, overhead layer of treatment dam water tank; 14, sludge treatment room; 15, hydraulic push cleaning plate; 16, centrifugal dehydrator; 17, water suction pipeline; 18, water suction guide; 19, oblique sludge discharge net; 20, third hydraulic bottom drainage gate; 21, hydraulic rod; 22 , pushing side wings; 23, slotted parts; 24, rotating shaft; 25, hydraulic push rod; 26, side grooves; 27, connecting bearing columns; 28, lubricating movable gate parts; 29, sludge conveying pipelines; 30, embedded grooves; 31, horizontal drainage hydraulic gate; 32, first hydraulic bottom drainage gate; 33, second hydraulic bottom drainage gate; 34, inclined frame guide desilting assembly; 341, bottom waterway; 342, inclined plate sedimentation tank; 343, first water diversion body; 344, second water diversion body; 345, guide water trough; 35, silt plate; 36, solid-liquid separator. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the implementation regulations described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] Reference Figure 1-Figure 7As shown: a permeable silt collection type vertical dock breakwater, including a waterway side bank 1, a stone cushion layer 3 is installed at the bottom of the waterway side bank 1, a concrete foundation layer 2 is installed at the bottom of the stone cushion layer 3, a rotating shaft column 6 is installed at the top side end of the stone cushion layer 3, a guide wave-breaking board 5 is arranged outside the rotating shaft column 6, a side groove 26 is opened at the bottom of the side end of the guide wave-breaking board 5, a connecting bearing column 27 is fastened to the bottom of the side groove 26, a lubricating moving gate 28 is fastened to the bottom of the connecting bearing column 27, two groups of arc track slide grooves 12 are symmetrically opened on the surface of the stone cushion layer 3, the lubricating moving gate 28 drives the guide wave-breaking board 5 to adjust its internal displacement along the arc track slide groove 12 with the cooperation of the rotating shaft column 6, a side bank 4 is arranged on the top of the waterway side bank 1, a side bank water guide slope 7 is arranged on the side of the side bank 4, and a side bank guide An upright wharf 10 is installed on the side of the water slope 7, a treatment dam water tank overhead layer 13 is installed on the side of the upright wharf 10, a sludge treatment chamber 14 is installed on the side of the treatment dam water tank overhead layer 13, a bottom water inlet 8 is installed between the height difference between the side dam water diversion slope 7 and the stone cushion layer 3, and an inclined frame guiding and desilting component 34 is installed inside the treatment dam water tank overhead layer 13; the inclined frame guiding and desilting component 34 includes a bottom waterway 341, an inclined plate sedimentation tank 342 is installed at the middle end of the bottom waterway 341, a first water diversion body 343 and a second water diversion body 344 are respectively installed inside the bottom waterway 341, the first water diversion body 343 and the second water diversion body 344 are staggered, and a guiding water tank 345 is arranged in the gap between the first water diversion body 343 and the second water diversion body 344.

[0029] according to Figure 3 As shown, the side of the waterway bank 1 is fastened with a slotted member 23, a rotating shaft 24 is installed inside the slotted member 23, a pushing side wing 22 is fastened to the side of the rotating shaft 24, a hydraulic rod 21 is fastened to the side of the pushing side wing 22, a side end of the hydraulic rod 21 is fastened to the surface of the waterway bank 1, a hydraulic push rod 25 is installed on the side of the rotating shaft 24, the pushing side wing 22 is connected to the hydraulic push rod 25, a side end of the hydraulic push rod 25 is fastened to the guide wave-breaking board 5, the hydraulic rod 21 and the slotted member 23 are installed on the side of the waterway bank 1, when it is necessary to When guiding and protecting against water flow impact, the hydraulic rod 21 is started under the control and adjustment of an external motion controller (not shown in the figure), generating a driving force for the pushing wing 22, so that the pushing wing 22 drives the hydraulic pushing rod 25 to rotate on the outer peripheral side of the rotating shaft 24, thereby facilitating the hydraulic pushing rod 25 to drive the guiding wave-breaking board 5 to form an adjustment through the cooperation of the rotating shaft column 6 during operation, thereby adjusting the position or angle of the guiding wave-breaking board 5 in the waterway, dynamically adjusting the water flow direction and speed in the waterway, and possible wave behavior, so as to achieve flood control, protect the river bank or optimize the waterway flow.

[0030] according to Figure 1As shown, pressure relief holes 11 are symmetrically provided on the surface of the dike water diversion slope 7, a transverse drainage groove 9 is installed at the connection between the dike water diversion slope 7 and the vertical dock 10, and a transverse drainage hydraulic gate 31 is installed at the bottom of the transverse drainage groove 9. The pressure relief holes 11 are symmetrically provided on the surface of the dike water diversion slope 7, so that when the water level rises or the water flow pressure increases, excess water is allowed to form a vortex through these holes to flow into the internal waterway space of the treatment dam water tank overhead layer 13, so as to reduce the water pressure of the dike water diversion slope 7, prevent the structure from being damaged, and ensure the stability of the dike water diversion slope 7. In addition, with the cooperation of the transverse drainage groove 9 and the transverse drainage hydraulic gate 31, the step difference formed by the dike water diversion slope 7 and the stone cushion layer 3 can divert the water flow in the drainage. Diversion protection is carried out before the water flows out, so that the upper layer of water containing smaller particles of sediment can be discharged from the transverse drainage groove 9, and fall into the internal waterway space of the overhead layer 13 of the treatment dam water groove, and cooperate with the vortex flow formed by the pressure relief hole 11 to facilitate the above-mentioned smaller particles of sediment to be pulled in. During long-term use, smaller particles of sediment will not accumulate on the surface of the side embankment water guide slope 7, causing interference to the transverse drainage hydraulic gate 31. The transverse drainage hydraulic gate 31 is controlled by the hydraulic structure to open and close, so as to flexibly adjust the discharge amount of the upper water flow. When rapid drainage or water level control is required, the transverse drainage hydraulic gate 31 can be opened to increase the drainage capacity, and when it is necessary to maintain the water level or reduce water flow scouring, it can be appropriately closed.

[0031] according to Figure 5 As shown, the first hydraulic bottom drainage gate 32 is installed inside the bottom water inlet 8, and the second hydraulic bottom drainage gate 33 and the third hydraulic bottom drainage gate 20 are installed in stages inside the overhead layer 13 of the dam water tank. The first hydraulic bottom drainage gate 32, the second hydraulic bottom drainage gate 33, the third hydraulic bottom drainage gate 20 and the lateral drainage hydraulic gate 31 are all connected to the external motion controller. With the cooperation of the bottom water inlet 8, the inflow and outflow of the bottom water flow can be controlled, so that the water flow containing large particles of sediment can be accurately controlled and introduced from the bottom of the dam. The first hydraulic bottom drainage gate 32, the second hydraulic bottom drainage gate 33, the third hydraulic bottom drainage gate 20 and the lateral drainage hydraulic gate 31 are all connected to the external motion controller. 3 and the third hydraulic bottom drainage gate 20 are installed in stages inside and on the side of the overhead layer 13 of the treatment dam water tank, together forming a multi-level drainage system. Each level of the gate can be controlled by an external motion controller, so that the overall drainage can be centrally controlled and automated. That is, through a pre-set program or real-time monitoring data, the external motion controller can automatically adjust the opening degree of each level of the water gate according to the actual water situation, ensuring efficient drainage while maintaining structural safety, reducing human intervention, improving management efficiency, and independently adjusting to meet the specific drainage needs of different areas, thereby increasing the flexibility and response speed of the system.

[0032] according to Figure 5As shown, the side of the second hydraulic bottom drainage gate 33 and the high entrance of the bottom waterway 341 are connected, a silt plate 35 is installed at the bottom of the inclined plate sedimentation tank 342, and an adsorption pre-buried pipe is installed on the surface of the silt plate 35. The side end of the adsorption pre-buried pipe is connected with a solid-liquid separator 36. The high entrance of the bottom waterway 341 is installed on the side of the second hydraulic bottom drainage gate 33, which helps to maintain the ideal water level and treatment efficiency in the inclined plate sedimentation tank 342, ensures smooth discharge of water, and avoids the discharge of solid matter with water, keeping the inside of the inclined plate sedimentation tank 342 clean. The silt plate 35 is set to facilitate the collection and temporary storage of the settled sludge, so that in cooperation with the solid-liquid separator 36, the adsorption pre-buried pipe is used to efficiently separate the water in the settled sludge, so that the dehydrated sludge is transported from the sludge conveying pipeline 29.

[0033] according to Figure 5 As shown, the side end of the solid-liquid separator 36 is connected to the sludge conveying pipeline 29, and a pre-buried groove 30 is opened on the outer peripheral side of the sludge conveying pipeline 29. The pre-buried groove 30 is opened inside the concrete base layer of the treatment dam water tank overhead layer 13. With the cooperation of the sludge conveying pipeline 29, the separated sludge is conveyed to the trough. The pre-buried groove 30 is opened inside the concrete base layer of the treatment dam water tank overhead layer 13, which can protect the sludge conveying pipeline 29 from damage by the external environment.

[0034] according to Figure 2 and Figure 5 As shown, an inclined sludge discharge net 19 is installed inside the sludge treatment chamber 14, and a hydraulically pushed cleaning plate 15 is installed on the side of the sludge treatment chamber 14 through a fixed frame. The hydraulically pushed cleaning plate 15 is connected to the built-in sludge detection sensor, and the inclined sludge discharge net 19 is installed inside the sludge treatment chamber 14. The inclined structure is utilized, so that during the drainage treatment process, when the water flow carries the silt, it helps the silt to naturally slide and gather on the surface of the inclined sludge discharge net 19 under the action of gravity, which is convenient for collection and subsequent treatment, and the inclined design reduces silt accumulation, improves discharge efficiency, and also reduces the energy consumption required for cleaning. Afterwards, with the cooperation of the silt detection sensor, the hydraulically pushed cleaning plate 15 can be indirectly started, which is convenient for pushing the accumulated silt into the chute.

[0035] according to Figure 2As shown, a trough is provided on the inner side of the sludge treatment chamber 14, and the trough is located on the side of the oblique sludge discharge net 19. The side of the trough is connected to a centrifugal dehydrator 16 through a sludge pump. The power generation of the centrifugal dehydrator 16 can convert hydraulic potential energy into piezoelectric potential energy with the cooperation of a stress sensor group installed inside the guide wave-breaking plate 5, and then drive the centrifugal dehydrator 16 through a pre-buried generator. A trough is provided on the inner side of the sludge treatment chamber 14, and its position is close to the oblique sludge discharge net 19, so that the sludge can slide naturally on the oblique sludge discharge net 19, and the sludge can be guided to the guide wave-breaking plate 5 by gravity. The trough is convenient for further processing, and the trough is connected to the centrifugal dehydrator 16 through a sludge pump. The sludge pump can be used to transport the sludge collected in the trough to the centrifugal dehydrator 16 for dehydration treatment, and the overall driving energy supply can utilize the stress sensor group installed inside the guide wave-breaking plate 5 to capture the kinetic energy of the water flow. When the water flows through the guide wave-breaking plate 5, the pressure and stress generated are sensed by the sensor group and converted into piezoelectric potential energy through a specific mechanism (such as piezoelectric material). Through the pre-buried generator, the piezoelectric potential energy is converted into electrical energy, which is directly used to drive the centrifugal dehydrator 16 or related structures that require energy supply.

[0036] according to Figure 2 As shown, the top end of the centrifugal dehydrator 16 is connected to a water-drawing pipeline 17, and the side end of the water-drawing pipeline 17 is connected to a water-drawing guide 18. By connecting the top end of the centrifugal dehydrator 16 with the water-drawing pipeline 17, it is ensured that the water separated from the centrifugal dehydrator 16 can be effectively collected and transported to the water-drawing guide 18 through a pipeline, and the water is guided to the same discharge point as the inclined sludge discharge network 19 through the water-drawing guide 18.

[0037] according to Figure 2 As shown, the side of the centrifugal dehydrator 16 is connected to the sludge treatment tank on the side through an external silt discharge pipeline. With the cooperation of the sludge treatment tank and the external silt discharge pipeline, the sludge from which water has been removed can be collected and treated uniformly, and then the sludge can be buried on the side of the slope of the breakwater, thereby promoting the growth of the surrounding ecological chain.

[0038] The wiring diagram of the centrifugal dehydrator 16, water-drawing guide 18, solid-liquid separator 36, motion controller, sludge detection sensor and stress sensor group in the present invention is common knowledge in the field, and its working principle is a well-known technology. The model is selected according to the actual use, so the control method and wiring layout of the centrifugal dehydrator 16, water-drawing guide 18, solid-liquid separator 36, motion controller, sludge detection sensor and stress sensor group will not be explained in detail.

[0039] The method of use and working principle of the device are as follows: first, the stone cushion layer 3 and the concrete foundation layer 2 at the bottom of the waterway embankment 1 are used to form an integral waterway, and the embankment 4 and the embankment water diversion slope 7 at the top of the waterway embankment 1, as well as the vertical dock 10 and the overhead layer 13 of the dam water tank are set to optimize the direction of water flow and reduce the direct impact of water flow on the embankment. At the same time, the setting of the vertical dock 10 is convenient for ships to dock and maintain operations. Then, the hydraulic rod 21 and the slotted member 23 are installed on the side of the waterway embankment 1. When it is necessary to guide and protect the impact of water flow, the hydraulic rod 21 is started under the control and adjustment of the external motion controller to generate a driving force for the pushing side wing 22, so that the pushing side wing 22 drives the hydraulic pushing rod 25 around the outer periphery of the rotating shaft 24. The hydraulic push rod 25 is rotated sideways, so that it is convenient for the hydraulic push rod 25 to drive the guide wave-breaking board 5 to form an adjustment under the cooperation of the rotating shaft column 6 during operation. At the same time, the lubricating movable gate member 28 drives the guide wave-breaking board 5 to adjust the internal displacement of the arc track slide groove 12 under the cooperation of the rotating shaft column 6, so as to adjust the position or angle of the guide wave-breaking board 5 in the waterway, dynamically adjust the water flow direction and speed in the waterway, as well as possible wave behavior, so as to achieve flood prevention, protect the river bank or optimize the waterway flow. At the same time, the pressure relief holes 11 are symmetrically opened on the surface of the side dike water guide slope 7, so that when the water level rises or the water flow pressure increases, excess water is allowed to form a vortex through these holes to flow into the internal waterway space of the treatment dam water tank overhead layer 13, so as to reduce the water pressure on the side dike water guide slope 7 and prevent The structure is damaged, ensuring the stability of the dike water diversion slope 7, and with the cooperation of the transverse drainage groove 9 and the transverse drainage hydraulic gate 31, the step difference formed by the dike water diversion slope 7 and the stone cushion layer 3 can divert the water flow before discharge, so that the upper layer of water containing smaller particles of sediment can be discharged from the transverse drainage groove 9, and it is convenient to fall into the internal waterway space of the water tank overhead layer 13 of the treatment dam, and the vortex flow formed by the pressure relief hole 11 is convenient to pull the above-mentioned smaller particles of sediment into it, and smaller particles of sediment will not accumulate on the surface of the dike water diversion slope 7 during long-term use, causing interference to the transverse drainage hydraulic gate 31. The transverse drainage hydraulic gate 31 is controlled by the hydraulic structure to open and close it, so as to flexibly adjust the discharge amount of the upper water flow, and when needed When it is necessary to drain water quickly or control the water level, the lateral drainage hydraulic gate 31 can be opened to increase the drainage capacity. When it is necessary to maintain the water level or reduce the scouring of water flow, it can be appropriately closed. In cooperation with the bottom water inlet 8, the inlet and outlet of the bottom water flow can be controlled, so that the water flow containing large particles of sediment can be accurately regulated and introduced from the bottom of the dam. The first hydraulic bottom drainage gate 32, the second hydraulic bottom drainage gate 33 and the third hydraulic bottom drainage gate 20 are installed in stages inside and on the side of the overhead layer 13 of the dam water tank, forming a multi-level drainage system. Each level of the gate can be controlled by an external motion controller, so that the overall drainage can be centrally controlled and automated, that is, it can be operated through a pre-set program or real-time monitoring data.The external motion controller can automatically adjust the opening degree of each level of water gates according to the actual water conditions, ensuring efficient drainage while maintaining structural safety, reducing human intervention, and improving management efficiency. Independent adjustment can adapt to the specific drainage needs of different areas, increasing the flexibility and response speed of the system, and installing the high entrance of the bottom waterway 341 on the side of the second hydraulic bottom drainage gate 33, so that the inclined plate sedimentation tank 342 uses the principle of gravity separation to effectively remove suspended particles in the water, and the staggered installation of the first water body 343 and the second water body 344, as well as the guide water tank 345 arranged therebetween, further optimizes the water flow distribution, slows down the impact of the water flow, and promotes the collection and discharge of sediments, which helps to maintain the inclined plate sedimentation. The ideal water level and treatment efficiency in the pool 342 ensure smooth discharge of water flow, while avoiding the discharge of solid matter with the water, keeping the interior of the inclined plate sedimentation pool 342 clean, and the setting of the silt plate 35 is convenient for collecting and temporarily storing the settled silt, so that in cooperation with the solid-liquid separator 36, the setting of the adsorption pre-buried pipeline is used to efficiently separate the water in the settled silt, solid impurities and liquid, so that the dehydrated silt is transported from the silt conveying pipeline 29, and the separated silt is transported to the trough with the cooperation of the silt conveying pipeline 29, and then the inclined silt discharge net 19 is installed inside the silt treatment chamber 14, using the inclined structure, so that in the drainage treatment process, the water flow carries the silt. During the discharge, it helps the silt to naturally slide and gather on the surface of the inclined silt discharge net 19 under the action of gravity, which is convenient for collection and subsequent treatment. The inclined design reduces silt accumulation, improves discharge efficiency, and also reduces the energy consumption required for cleaning. Afterwards, with the cooperation of the silt detection sensor, the hydraulic pressure can push the cleaning plate 15 to form an indirect start, which is convenient for pushing the accumulated silt into the trough. The silt collected in the trough can be transported to the centrifugal dehydrator 16 for dehydration by using the silt pump, and the overall driving energy supply can utilize the stress sensor group installed inside the guide wave-breaking plate 5 to capture the kinetic energy of the water flow. When the water flows through the guide wave-breaking plate 5, the pressure and stress generated are sensed by the sensor group, and It is converted into piezoelectric potential energy through a specific mechanism (such as piezoelectric materials), and then converted into electrical energy through a pre-buried generator, which is directly used to drive the centrifugal dehydrator 16 or related structures that require energy supply. Secondly, by connecting the top of the centrifugal dehydrator 16 to the water-drawing pipeline 17, it is ensured that the water separated from the centrifugal dehydrator 16 can be effectively collected and transported to the water-drawing guide 18 through a pipeline, and the water is guided to the same discharge point as the oblique sludge discharge network 19 through the water-drawing guide 18. With the cooperation of the sludge treatment tank and the external sludge discharge pipeline, it is convenient to uniformly collect and treat the dehydrated sludge, and then the sludge can be buried on the side of the slope of the breakwater, so as to promote the growth of the surrounding ecological chain.

[0040] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A vertical pier breakwater with flow-through and silt-collecting function. Features: The invention comprises a waterway bank (1), wherein a stone cushion layer (3) is installed at the bottom of the waterway bank (1), a concrete foundation layer (2) is installed at the bottom of the stone cushion layer (3), a rotating shaft column (6) is installed at the top side end of the stone cushion layer (3), a guide wave-breaking plate (5) is arranged outside the rotating shaft column (6), a side groove (26) is provided at the bottom of the side end of the guide wave-breaking plate (5), a connecting bearing column (27) is fastened to the bottom of the side groove (26), a lubricating movable gate member (28) is fastened to the bottom of the connecting bearing column (27), two groups of arc-shaped track slide grooves (12) are symmetrically provided on the surface of the stone cushion layer (3), and the lubricating movable gate member (28) drives the guide wave-breaking plate (5) to move along the guide wave-breaking plate (5). The wave plate (5) is adjusted along the internal displacement of the arc track chute (12) in cooperation with the rotating shaft column (6); a side bank (4) is arranged on the top of the waterway side bank (1); a side bank water guide slope (7) is arranged on the side of the side bank (4); a vertical dock (10) is installed on the side of the side bank water guide slope (7); a treatment dam water tank overhead layer (13) is installed on the side of the vertical dock (10); a silt treatment chamber (14) is installed on the side of the treatment dam water tank overhead layer (13); a bottom water inlet (8) is installed between the height difference between the side bank water guide slope (7) and the stone cushion layer (3); and an inclined frame type guide and silt removal component (34) is installed inside the treatment dam water tank overhead layer (13); The inclined frame type guiding and desilting assembly (34) comprises a bottom waterway (341), an inclined plate sedimentation tank (342) is installed at the middle end of the bottom waterway (341), a first water diversion body (343) and a second water diversion body (344) are installed inside the bottom waterway (341), the first water diversion body (343) and the second water diversion body (344) are installed in a staggered manner, and a guiding water trough (345) is provided at the gap between the first water diversion body (343) and the second water diversion body (344); The side of the waterway bank (1) is fastened with a slotted member (23), a rotating shaft (24) is installed inside the slotted member (23), the side of the rotating shaft (24) is fastened with a pushing wing (22), the side of the pushing wing (22) is fastened with a hydraulic rod (21), the side end of the hydraulic rod (21) is fastened to the surface of the waterway bank (1), a hydraulic pushing rod (25) is installed on the side of the rotating shaft (24), the pushing wing (22) and the hydraulic pushing rod (25) are connected, and the side end of the hydraulic pushing rod (25) is fastened to the guide wave-breaking plate (5).

2. The flow-through silt-collecting vertical pier breakwater according to claim 1, Features: Pressure relief holes (11) are symmetrically provided on the surface of the side dike water diversion slope (7), a transverse drainage groove (9) is installed at the connection between the side dike water diversion slope (7) and the vertical dock (10), and a transverse drainage hydraulic gate (31) is installed at the bottom of the transverse drainage groove (9).

3. The flow-through silt-collecting vertical pier breakwater according to claim 1, Features: A first hydraulic bottom drainage gate (32) is installed inside the bottom water inlet (8), and a second hydraulic bottom drainage gate (33) and a third hydraulic bottom drainage gate (20) are installed in stages inside the overhead layer (13) of the treatment dam water tank. The first hydraulic bottom drainage gate (32), the second hydraulic bottom drainage gate (33), the third hydraulic bottom drainage gate (20) and the lateral drainage hydraulic gate (31) are all connected to an external motion controller.

4. The flow-through silt-collecting vertical pier breakwater according to claim 3, Features: The side of the second hydraulic bottom drainage gate (33) is connected to the high entrance of the bottom waterway (341), a silt plate (35) is installed at the bottom of the inclined plate sedimentation tank (342), an adsorption pre-buried pipe is installed on the surface of the silt plate (35), and the side end of the adsorption pre-buried pipe is connected to a solid-liquid separator (36).

5. The flow-through silt-collecting vertical pier breakwater according to claim 4, Features: The side end of the solid-liquid separator (36) is connected to a sludge conveying pipeline (29), and a pre-buried groove (30) is provided on the outer peripheral side of the sludge conveying pipeline (29). The pre-buried groove (30) is provided inside the concrete base layer of the overhead layer (13) of the treatment dam water tank.

6. The flow-through silt-collecting vertical pier breakwater according to claim 1, Features: An oblique sludge discharge net (19) is installed inside the sludge treatment chamber (14), and a hydraulically driven cleaning plate (15) is installed on the side of the sludge treatment chamber (14) via a fixed frame, and the hydraulically driven cleaning plate (15) is connected to a built-in sludge detection sensor.

7. The flow-through silt-collecting vertical pier breakwater according to claim 1, Features: A trough is provided on the inner side of the sludge treatment chamber (14), and the trough is located on the side of the oblique sludge discharge net (19). The side of the trough is connected to a centrifugal dehydrator (16) via a sludge pump. The power generation of the centrifugal dehydrator (16) can utilize the cooperation of a stress sensor group installed inside the guide wave-breaking plate (5) to convert hydraulic potential energy into piezoelectric potential energy, and then drive the centrifugal dehydrator (16) through a pre-buried generator.

8. The flow-through silt-collecting vertical pier breakwater according to claim 7, Features: The top end of the centrifugal dehydrator (16) is connected to a water-drawing pipeline (17), and the side end of the water-drawing pipeline (17) is connected to a water-drawing guide (18).

9. The flow-through silt-collecting vertical pier breakwater according to claim 7, Features: The side of the centrifugal dehydrator (16) is connected to a sludge treatment tank on the side through an external sludge discharge pipeline.