A TOUCH material processing method for bow, stern and bilge structures of a hull
By using TEST segment assist PILLAR in the AM12 system to simulate the shape of the circular tube at the transition of the large circular arc of the bow and stern junction part, the problem of inaccurate boundaries of TOUCH parts in the prior art is solved, and more efficient structural modeling and accuracy are achieved Processing improves work efficiency.
Patent Information
- Application Number
- CN202411158251.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-22
AI Technical Summary
When the prior art deals with the large arc transition point of the bow and stern of the hull, the boundary shape of the TOUCH section is inaccurate, resulting in increased working hours and difficulty in ensuring accuracy, which affects operating efficiency.
By using TEST segment assisted PILLAR in the AM12 system to form a circular tube, the true shape of the large arc transition of the bow and stern junction part is simulated, and the boundaries and bevels of the rib plate are adjusted to achieve accurate structural modeling.
It improves the internal structural accuracy and accuracy of the hull bow and stern junction structure, reduces the working hours of on-site processing, and improves the efficiency of technical and on-site operations.
Smart Images

Figure CN118683700B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of ship production design using an AM12 system to perform TOUCH component structure modeling of a bow and stern bilge of a hull, and in particular to a TOUCH component processing method of a bow and stern bilge structure of a hull. Background Art
[0002] The overall spatial orientation and plate curvature of the internal structure at the bow and stern of the hull bilge section are relatively complex (the overall orientation is reflected in the convergence to the centerline of the hull), and the inclined plate and inner bottom plate of the bottom tank internal structure are arc transitions. From the perspective of spatial position, the main plate of the bottom tank internal structure is obliquely intersected with each rib. During the biotech modeling operation, the plate boundary shape of the TOUCH of this plate was displayed as an arc transition on the entire rib section due to the AM12 system bug, rather than the elliptical arc transition of the actual section, resulting in errors in the material boundary at the TOUCH. In the past, the arc radius of the internal structure of the bow and stern bilge of the ship type was small, and the overall length of the contact surface between the TOUCH plate and the arc transition was short. Even if this situation is handled according to the ordinary manufacturing method, due to its small correction range, the groove change is relatively simple and easy to control, and it does not take a long time, the handling method is generally for the on-site production personnel to perform plate grinding, groove opening and other plate correction work.
[0003] However, with the update of ship types, structural optimization and changes in shipowners' needs, most current ship types use large arc transitions at the bow and stern. The contact area and length required for the TOUCH plate and the arc transition are much larger than before. If the TOUCH part of the arc transition is processed according to the original technical modeling method, a gap will be generated (see comparison). Figure 5 , Figure 6 , Figure 7 ), for the on-site staff, it takes much more time than the original ship type processing method to grind and correct the plate boundary, and it is difficult to ensure that its boundary shape is completely accurate. The current on-site processing method can no longer meet the requirements for the accuracy and precision of the internal structure. If a design processing solution is not proposed, it will greatly affect the operating efficiency of both technical operators and on-site operators and the subsequent processing of similar ship types. Summary of the invention
[0004] (I) Technical problems solved: In view of the deficiencies of the prior art, the present invention provides a TOUCH material processing method for the bow and stern bilge structure of a hull, which has the advantages of making an auxiliary PILLAR through TEST segments to form a circular tube and simulating the real shape of the rib position at the large arc transition of the bow and stern bilge with its outer surface, confirming the axis positioning and inputting specific parameters to make a circular tube, simulating the real shape of the rib position at the large arc transition of the bow and stern bilge with its outer surface, when making the rib plate, the curve formed by the circular tube is used as the boundary at the arc transition to make the real shape of the inner structure plate at the rib position, and finally the groove of the inner structure plate at the large arc transition is adjusted to finally make an accurate shape, and the technical problems are solved in the production design stage upstream of on-site production and manufacturing, etc., which solves the problem that the on-site processing method can no longer meet the requirements for the accuracy and precision of the internal structure, which greatly affects the working efficiency of both technical operators and on-site operators and the subsequent processing of similar ship types.
[0005] (II) Technical solution: To solve the above technical problems, the present invention provides the following technical solution: A method for processing TOUCH components of a bow and stern bilge structure of a hull, comprising the following steps:
[0006] S1. Define the coordinate system of the ship, with the length of the ship as the base point of the coordinate system;
[0007] S2. The BILGE HOPPER and INNER BOTTOM plates used in the hull structure can be located and manufactured from various cross-sections according to the structural design drawings, thus forming a basic structural form unique to the stern bilge inner structure - a sloping plate and a horizontal plate connected by two separate plates;
[0008] S3. In any panel, enter the PANEL creation interface, select the PILLAR option, select Type72, and enter the outer diameter of the round tube R+t. The tube wall thickness can be set at will.
[0009] S4. Obtain accurate Y value: The Z value of the center of the tube is fixed, and the Z value is kept unchanged so that the PILLAR is close to the outside of the ship. The Y value of point p1 is adjusted until the elliptical arc and the inclined plate have a tangent point, and then the cross section where the rib is located is cut perpendicular to KL. At the direction of the inclined plate near the stern of the ship, the above operation is repeated to obtain the three-dimensional coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the tube;
[0010] S5. In the inner panel where the PILLAR is needed, it needs to be made into CUR first;
[0011] S6. After the creation, the groove of the inner plate edge is edited.
[0012] Preferably, in step S1, the coordinate system of the hull is clarified, with the length of the ship as the base point of the coordinate system, the base point direction as the X-axis, the width of the ship as the Y-axis, and the height of the ship as the Z-axis.
[0013] Preferably, in step S2, BILGE HOPPER plates and INNER BOTTOM plates used in the hull internal structure can be located and manufactured from various cross-sectional views according to the structural design drawings, thereby forming a basic structural form unique to the stern bilge internal structure - two sub-plates, an inclined plate and a horizontal plate, are connected, and the two plates are formed into a bent plate using the KNUCKLED command according to the arc transition radius R indicated by the structural design drawings. At this time, the main frame of the bilge internal structure is modeled.
[0014] Preferably, in step S3, in any plate, enter the PANEL creation interface, select the PILLAR option, select Type72, input the outer diameter R+t of the round tube, at this time the tube wall thickness can be set at will, click the "Byendpoints" option in MOULD LINE, and input the coordinates of the two points p1 and p2 in the two input boxes at END1 and END2.
[0015] Preferably, in step S4, an accurate Y value is obtained: the Z value of the center of the circular tube is fixed, and the Z value is kept unchanged so that the manufactured PILLAR is brought closer to the outside of the ship, and the Y value of point p1 is adjusted until a tangent point appears between the elliptical arc and the inclined plate, and then a section where the rib position is located is cut out perpendicular to KL at the direction of the inclined plate near the stern of the ship, and the above-mentioned method is repeated to obtain the three-dimensional coordinates of point P2, and the spatial straight line connecting points P1 and P2 is the axis of the circular tube.
[0016] Preferably, in step S5, in the inner plate that needs to use the PILLAR, a CUR needs to be created first, wherein the SCHEME statement is as follows: CUR, "H1", "FD2-UD-1", PI3, SID=FOR, DIR=BOT.
[0017] Preferably, in step S6, the inner plate edge is beveled after completion, and the bevel is in a gradual state and needs to be processed using a gradual bevel.
[0018] Compared with the prior art, the present invention provides a TOUCH material processing method for the bow, stern and bilge structure of a hull, which has the following beneficial effects:
[0019] The present invention makes auxiliary PILLAR in sections through TEST to form a circular tube and simulates the real shape of the rib position at the large arc transition of the bow and stern bilge with its outer surface; after confirming the axis positioning and inputting specific parameters, a circular tube is made, and the real shape of the rib position at the large arc transition of the bow and stern bilge is simulated with its outer surface; when making the rib plate, the curve formed by the circular tube at the arc transition is used as the boundary to make the real shape of the inner structure plate at the rib position; finally, the groove of the inner structure plate at the large arc transition is adjusted to finally make an accurate shape, thereby solving technical problems in the production design stage upstream of on-site production and manufacturing. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a three-dimensional schematic diagram of the PILLAR and the segments of the present invention;
[0021] Figure 2 This is a schematic diagram of the BILGE HOPPER of the present invention;
[0022] Figure 3 It is a schematic cross-sectional view of the rib position of the bent plate in the bow direction of the present invention;
[0023] Figure 4 It is a schematic cross-sectional view of the rib position of the bent plate in the present invention at the stern direction;
[0024] Figure 5 A schematic diagram showing a before-and-after comparison of the biotechnology modeling treatment method of the present invention;
[0025] Figure 6 A schematic diagram comparing the correct and incorrect methods of large arc transition in the present invention;
[0026] Figure 7 for Figure 6 Enlarged schematic diagram of part A in the middle. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] See also Figure 1-7 A TOUCH material processing method for a bow and stern bilge structure of a hull comprises the following steps:
[0029] S1. Clarify the coordinate system of the hull, and take the direction of the ship length as the base point of the coordinate system. In step S1, the coordinate system of the hull is clarified, and the direction of the ship length is the base point of the coordinate system, the base point direction is the X-axis, the ship width direction is the Y-axis, and the ship height direction is the Z-axis. Before processing the TOUCH material at the large arc transition, the base point of the hull's coordinate system needs to be determined first, so as to facilitate the subsequent calculation of the X point, Y point and Z point of the coordinate system based on the base point of the coordinate system;
[0030] S2. The BILGE HOPPER and INNER BOTTOM plates used in the internal structure of the hull can be located and manufactured from various cross-sectional drawings according to the structural design drawings, thereby forming a basic structural form unique to the internal structure of the stern bilge - a slanted plate and a horizontal plate are connected. In step S2, the BILGE HOPPER and INNER BOTTOM plates used in the internal structure of the hull can be located and manufactured from various cross-sectional drawings according to the structural design drawings, thereby forming a basic structural form unique to the internal structure of the stern bilge - a slanted plate and a horizontal plate are connected. The two plates are formed into a bent plate according to the arc transition radius R indicated by the structural design drawing using the KNUCKLED command. At this time, the main frame of the bilge internal structure is modeled. Use the section call command to cut out the section where the rib is located at the direction of the bow of the bent plate. According to the structural design drawing and biotechnical debugging, the transition arc radius R+t of the two plates is obtained, and a parallel to the INNER is made with this as the spacing. A straight line at BOTTOM, at this time, the height value Z of the INNER BOTTOM board is determined;
[0031] S3. In any board, enter the PANEL creation interface, select the PILLAR option, select Type72, and enter the outer diameter of the tube R+t. The tube wall thickness can be set at will. In step S3, in any board, enter the PANEL creation interface, select the PILLAR option, select Type72, and enter the outer diameter of the tube R+t. The tube wall thickness can be set at will. Click the "By endpoints" option in MOULDLINE, and enter the coordinates of the two points p1 and p2 in the two input boxes at END1 and END2 to create PILLAR.
[0032] S4. Obtaining the accurate Y value: The Z value of the center of the circular tube is fixed, and the Z value is kept unchanged so that the PILLAR that has been made is close to the outside of the ship. The Y value of point p1 is adjusted until the elliptical arc and the inclined plate have a tangent point, and then the cross section where the rib position is located is cut out perpendicular to KL at the direction of the inclined plate near the stern of the ship. The above method is repeated to obtain the three-dimensional coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the circular tube. In step S4, obtaining the accurate Y value: The Z value of the center of the circular tube is fixed, and the Z value is kept unchanged so that the PILLAR that has been made is close to the outside of the ship. The Y value of point p1 is adjusted until the elliptical arc and the inclined plate have a tangent point. At this time, the Y value of p1 is determined. With the drawing selected, use the point coordinate display command to find the 3D coordinates of the center of the circle in the drawing, named P1, and then cut the section where the rib is located at the stern direction of the inclined plate perpendicular to KL. Repeat the above operation to obtain the 3D coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the circular tube.
[0033] S5. In the inner plate that needs to use the PILLAR, a CUR needs to be created first. In step S5, in the inner plate that needs to use the PILLAR, a CUR needs to be created first, where the SCHEME statement is as follows: CUR, "H1", "FD2-UD-1", PI3, SID=FOR, DIR=BOT;
[0034] S6. After the production, the groove of the inner plate edge using the PILLAR is edited. In step S6, after the production, the groove of the inner plate edge is edited. The groove is in a gradual state and needs to be processed with a gradual groove. After the editing is completed, the processing of the TOUCH material at the large arc transition is completed. The auxiliary PILLAR is produced in sections through TEST to form a circular tube and its outer surface simulates the real shape of the rib position at the large arc transition of the bow and stern bilge (the spatial position is the oblique intersection of the rib position and the circular tube). After confirming the axis positioning and entering the specific parameters, a circular tube is produced, and its outer surface simulates the real shape of the rib position at the large arc transition of the bow and stern bilge. When the rib plate is produced, the curve formed by this circular tube at the arc transition is used as the boundary to produce the real shape of the inner plate at the rib position. Finally, the groove of the inner plate at the large arc transition is adjusted to finally make it into an accurate shape, solving technical problems in the production design stage upstream of on-site production and manufacturing.
[0035] When using, the coordinate system of the hull is clear, with the length direction as the base point of the coordinate system, the base point direction as the X axis, the width direction as the Y axis, and the height direction as the Z axis. Before processing the TOUCH part of the large arc transition, the base point of the hull's coordinate system needs to be determined first, so that the X, Y and Z points of the coordinate system can be calculated based on the base point of the coordinate system. The BILGE HOPPER plate and INNER used in the hull's structural members are The BOTTOM plate can be located and made from each section according to the structural design drawing, thus forming a basic structural form unique to the stern bilge inner structure - a slanted plate and a horizontal plate are connected, and the two plates are formed into a bent plate by the KNUCKLED command according to the arc transition radius R indicated in the structural design drawing. R is the arc radius that can be connected with the arc R in the middle of the ship with less error after debugging. At this time, the main frame of the bilge inner structure is modeled. Use the section call command to cut out the section where the rib is located at the bow direction of the bent plate. According to the structural design drawing and biotechnical debugging, the transition arc radius R+t of the two plates is obtained, and a straight line parallel to the INNER BOTTOM is made with this as the spacing. At this time, the height value Z of the INNER BOTTOM plate is determined. In any plate, enter the PANEL creation interface, select the PILLAR option, select Type72, and enter the outer diameter R+t of the round tube. At this time, the tube wall thickness can be set at will, MOULD LINEClick the "Byendpoints" option, enter the coordinates of the two points p1 and p2 in the END1 and END2 input boxes to make a PILLAR. The Z value of the center of the tube is fixed. Keeping the Z value unchanged, the PILLAR will be closer to the outside of the ship. Adjust the Y value of point p1 until the elliptical arc and the inclined plate have a tangent point. At this time, the Y value of p1 is determined. With the drawing selected, use the point coordinate display command to find out the 3D coordinates of the center of the circle in the drawing, named P1, and then cut out the section where the rib is located at the stern direction of the inclined plate perpendicular to KL. Repeat the above operation to obtain the 3D coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the circular tube. In the internal structure plate that needs to use the PILLAR, it is necessary to create a CUR first, where the SCHEME statement is as follows: CUR, "H1", "FD2-UD-1", PI3, SID=FOR, DIR=BOT. After it is created, the edge of the internal structure plate that uses the PILLAR is beveled and edited. The bevel is in a gradual state and needs to be processed with a gradual bevel. After the editing is completed, the TOUCH component at the large arc transition is processed.
[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A TOUCH material processing method for a bow, stern and bilge structure of a hull, comprising the following steps: S1. Define the coordinate system of the ship, with the length of the ship as the base point of the coordinate system; S2. The BILGE HOPPER and INNER BOTTOM plates used in the hull structure can be located and manufactured from various cross-sections according to the structural design drawings, thus forming a basic structural form unique to the stern bilge inner structure - a sloping plate and a horizontal plate connected by two separate plates; S3. In any panel, enter the PANEL creation interface, select the PILLAR option, select Type72, and enter the outer diameter of the round tube R+t. The tube wall thickness can be set at will. S4. Obtain accurate Y value: The Z value of the center of the tube is fixed, and the Z value is kept unchanged so that the PILLAR is close to the outside of the ship. The Y value of point p1 is adjusted until the elliptical arc and the inclined plate have a tangent point, and then the cross section where the rib is located is cut perpendicular to KL. At the direction of the inclined plate near the stern of the ship, the above operation is repeated to obtain the three-dimensional coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the tube; S5. In the inner panel where the PILLAR is needed, it needs to be made into CUR first; S6. After the creation, the groove of the inner plate edge is edited.
2. A TOUCH material processing method for a bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S1, the coordinate system of the hull is clarified, with the length of the ship as the base point of the coordinate system, the base point direction as the X-axis, the width of the ship as the Y-axis, and the height of the ship as the Z-axis.
3. A TOUCH material processing method for a bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S2, the BILGE HOPPER plate and INNER BOTTOM plate used in the hull internal structure can be located and manufactured from various cross-sectional views according to the structural design drawings, thereby forming a basic structural form unique to the stern bilge internal structure - a slanted plate and a horizontal plate are connected to each other, and the two plates are formed into a bent plate using the KNUCKLED command according to the arc transition radius R indicated by the structural design drawings. At this time, the main frame of the bilge internal structure is modeled.
4. A TOUCH material processing method for a bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S3, in any board, enter the PANEL creation interface, select the PILLAR option, select Type72, enter the outer diameter of the tube R+t, and the tube wall thickness can be set at will. Click the "By endpoints" option in MOULD LINE, and enter the coordinates of the two points p1 and p2 in the END1 and END2 input boxes.
5. The TOUCH material processing method for the bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S4, the accurate Y value is obtained: the Z value of the center of the circular tube is fixed, and the Z value is kept unchanged so that the PILLAR that has been made is close to the outside of the ship. The Y value of point p1 is adjusted until the elliptical arc and the inclined plate have a tangent point, and then the cross section where the rib position is located is cut at a point perpendicular to KL. At the direction of the inclined plate near the stern of the ship, the above method is repeated to obtain the three-dimensional coordinates of point P2. The spatial straight line connecting points P1 and P2 is the axis of the circular tube.
6. A TOUCH material processing method for a bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S5, in the inner plate that needs to use the PILLAR, CUR needs to be created first, where the SCHEME statement is as follows: CUR,"H1","FD2-UD-1",PI3,SID=FOR,DIR=BOT.
7. The TOUCH material processing method for the bow, stern and bilge structure of a hull according to claim 1, characterized in that: In step S6, after the inner plate edge is made, the groove is edited, and the groove is in a gradual state, and a gradual groove processing is required.