Optimized dispatching method and device for electricity market, storage medium and computer equipment

By constructing and solving a two-stage robust optimization model, the problem of day-ahead-intraday economic dispatch in the intra-regional-inter-regional market is solved, and the economic dispatch effect under large uncertainties is achieved, combining the balance between safety and economy. .

CN118735152APending Publication Date: 2024-10-01EAST CHINA BRANCH OF STATE GRID CORP

Patent Information

Application Number
CN202410629046.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-21
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

It is difficult for the existing technology to effectively solve the day-ahead-day two-stage economic dispatch problem under the operation of the intra-regional and inter-regional two-level markets. Especially when the source-load uncertainty factors are large, the calculation results of the traditional stochastic optimization method are out of sample. Poor performance and inability to effectively coordinate economic dispatch in intra-regional markets.

Method used

By obtaining historical data sample sets of renewable energy units and loads, processing to obtain the value range of uncertainty parameters, constructing a two-layer day-ahead economic dispatch model and an intraday economic dispatch model, and using a robust optimization method to construct a two-stage robust optimization model. And solve it to achieve economic dispatch in the power market.

Benefits of technology

It has realized day-ahead and intra-day two-stage economic dispatch under the coordinated operation of inter-regional and intra-regional two-level markets. The clearing results comprehensively consider the balance between security and economy, and have strong ability to cope with source-load uncertainty, especially The performance is more significant when the prediction error is large.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735152A_ABST
    Figure CN118735152A_ABST
Patent Text Reader

Abstract

The invention discloses an optimal scheduling method and device for a power market, a storage medium and computer equipment, relates to the technical field of power system scheduling, and mainly aims to solve the problem of how to realize day-ahead and intra-day two-stage economic scheduling under intra-region and inter-region two-stage market operation. Comprising the steps of obtaining a historical data sample set of a renewable energy unit and a load, and performing data processing on the historical data sample set to obtain an uncertainty set; constructing a day-ahead economic dispatching double-layer model by taking the minimization of the market operation cost in the regions as a target and the minimization of the market electricity purchasing cost between the regions as a target; constructing an intra-day economic dispatching model by taking the minimization of the intra-region market rescheduling cost of the intra-day stage electricity purchasing region as a target; and constructing a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatching double-layer model and the intra-day economic dispatching model, and solving the two-stage robust optimization model to obtain a power market dispatching result.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power system dispatching, and in particular to an optimization dispatching method and device, storage medium, and computer equipment for a power market. Background Art

[0002] Since power resources and load demand are inversely distributed, not only intra-regional power dispatching but also inter-regional power dispatching has emerged in the power market. And with the construction of a unified power market, the need for coordinated operation of inter-regional and intra-regional markets has become more prominent. In addition, with the continuous increase in the proportion of renewable energy power generation and the large-scale access of emerging loads such as electric vehicles, the uncertainty factors of power supply and load will also have an impact on the economic dispatch decision-making process of the two-level operation of the regional power market and the inter-regional power market.

[0003] At present, although the uncertainty factors of power supply and load are taken into account in the formulation of power dispatching strategies, the traditional optimization method for source-load uncertainty factors is stochastic optimization (SO). However, stochastic optimization requires accurate acquisition of the probability distribution of random variables, and the out-of-sample performance of the calculation results is poor, and it cannot solve the two-stage economic dispatch problem of day-ahead and intraday under the operation of the intra-regional and inter-regional two-level markets. Summary of the invention

[0004] In view of this, the present invention provides an optimization dispatching method and device, storage medium, and computer equipment for the power market, the main purpose of which is to solve the problem of how to achieve two-stage economic dispatching of day-ahead and day-intraday under the operation of two-level markets within and between regions.

[0005] According to one aspect of the present invention, there is provided an optimization dispatching method for an electricity market, comprising:

[0006] Acquire a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of the renewable energy units and the load demand;

[0007] A two-layer model of day-ahead economic dispatch is constructed with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost.

[0008] An intraday economic dispatch model is constructed with the goal of minimizing the market redispatch cost in the intraday power purchasing area;

[0009] A two-stage robust optimization model is constructed based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, and the two-stage robust optimization model is solved to obtain a power market dispatch result.

[0010] Furthermore, the historical data sample set is processed to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units, including:

[0011] A Monte Carlo sampling method is used to extract multiple groups of sample data from the historical data sample set, and a prediction deviation scenario corresponding to the sample data is generated;

[0012] A K-means clustering method is used to perform scenario reduction processing on the prediction deviation scenario to obtain multiple typical prediction deviation scenarios;

[0013] An uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units is generated based on the typical prediction deviation scenario.

[0014] Furthermore, the two-layer model of day-ahead economic dispatching with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost includes:

[0015] The conventional unit output, upper reserve capacity, lower reserve capacity and inter-regional power purchase demand of each node in the region are determined as the upper decision variables in the first stage;

[0016] Determine the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost within the region;

[0017] The electric energy transmitted from the conventional units at each node in the power sales area to the power purchase area is determined as the lower decision variable in the first stage;

[0018] Determine the objective function of the lower model based on the lower decision variables with the goal of minimizing the inter-regional market electricity purchase cost;

[0019] Adding upper-level constraints to the upper-level model objective function, and adding lower-level constraints to the lower-level model objective function;

[0020] The day-ahead economic dispatch two-layer model is constructed based on the upper-layer model objective function, the upper-layer constraint conditions, the lower-layer model objective function and the lower-layer constraint conditions.

[0021] Furthermore, the intraday economic dispatch model is constructed with the goal of minimizing the intra-regional market redispatching cost of the intra-day power purchasing area, including:

[0022] The daily upward and downward output of conventional units at each node in the power purchasing area, the wind power curtailment amount of wind turbines, the light curtailment amount of photovoltaic units and the load reduction amount are determined as decision variables in the second stage;

[0023] Based on the decision variables in the second stage, the objective function of the second stage is determined with the goal of minimizing the intra-day market redispatch cost of the power purchasing area;

[0024] Intraday constraints are added to the objective function of the second stage, and the intraday economic scheduling model is constructed based on the objective function of the second stage and the intraday constraints.

[0025] Furthermore, before constructing the two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, the method further includes:

[0026] The Carlo-Kuhn-Tucker condition method is used to transform the lower model in the two-layer model of day-ahead economic dispatch into a set of constraint equations without a target;

[0027] Determine the constraint equation group as the additional conditions of the upper model to obtain the transformed single-layer model of day-ahead economic dispatch;

[0028] The penalty function method is used to transform the single-layer model of the day-ahead economic dispatch to obtain a single-layer mixed integer linear programming model of the day-ahead economic dispatch.

[0029] Furthermore, constructing a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model includes:

[0030] Taking the uncertainty prediction bias in the uncertainty set as a random variable;

[0031] Determining a feasible domain of decision variables in the intraday economic dispatch model based on the random variables and the decision variables in the day-ahead economic dispatch two-layer model;

[0032] The two-stage robust optimization model is constructed based on the upper and lower decision variables and the corresponding first-stage related parameters in the day-ahead economic dispatch model, the decision variables and the corresponding second-stage related parameters in the intraday economic dispatch model, and the feasible domain of the decision variables in the intraday economic dispatch model.

[0033] Further, solving the two-stage robust optimization model includes:

[0034] Determining the part of the two-stage robust optimization model related to the two-layer model of day-ahead economic dispatch as the main problem in the two-stage robust optimization problem;

[0035] Determining the portion of the two-stage robust optimization model related to the intraday economic dispatch model as a sub-problem in the two-stage robust optimization problem;

[0036] Solving the main problem to obtain a solution to the main problem; and solving the sub-problems to obtain solutions to the sub-problems;

[0037] Determine the solution result of the main problem as the lower bound of the two-stage robust optimization model; and determine the solution result of the sub-problem as the upper bound of the two-stage robust optimization model;

[0038] The solution process is continuously iterated, and the upper bound and the lower bound are continuously updated until the two-stage robust optimization model is in a convergence state, and the power market dispatch result is obtained.

[0039] According to another aspect of the present invention, there is provided an optimization dispatching device for an electricity market, comprising:

[0040] An uncertainty analysis module is used to obtain a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of renewable energy units and load requirements;

[0041] The day-ahead model building module is used to build a two-layer model of day-ahead economic dispatch with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost;

[0042] The intraday model building module is used to build an intraday economic dispatch model with the goal of minimizing the intra-regional market redispatch cost of the power purchasing area during the intraday stage;

[0043] The robust optimization and solution module is used to construct a two-stage robust optimization model based on the uncertainty set, the two-layer model of day-ahead economic dispatch and the intraday economic dispatch model, and solve the two-stage robust optimization model to obtain the power market dispatch result.

[0044] Furthermore, the uncertainty analysis module is also used for:

[0045] A Monte Carlo sampling method is used to extract multiple groups of sample data from the historical data sample set, and a prediction deviation scenario corresponding to the sample data is generated;

[0046] A K-means clustering method is used to perform scenario reduction processing on the prediction deviation scenario to obtain multiple typical prediction deviation scenarios;

[0047] An uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units is generated based on the typical prediction deviation scenario.

[0048] Furthermore, the day-ahead model building module is also used to:

[0049] The conventional unit output, upper reserve capacity, lower reserve capacity and inter-regional power purchase demand of each node in the region are determined as the upper decision variables in the first stage;

[0050] Determine the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost within the region;

[0051] The electric energy transmitted from the conventional units at each node in the power sales area to the power purchase area is determined as the lower decision variable in the first stage;

[0052] Determine the objective function of the lower model based on the lower decision variables with the goal of minimizing the inter-regional market electricity purchase cost;

[0053] Adding upper-level constraints to the upper-level model objective function, and adding lower-level constraints to the lower-level model objective function;

[0054] The day-ahead economic dispatch two-layer model is constructed based on the upper-layer model objective function, the upper-layer constraint conditions, the lower-layer model objective function and the lower-layer constraint conditions.

[0055] Furthermore, the intraday model building module is also used for:

[0056] The daily upward and downward output of conventional units at each node in the power purchasing area, the wind power curtailment amount of wind turbines, the light curtailment amount of photovoltaic units and the load reduction amount are determined as decision variables in the second stage;

[0057] Based on the decision variables in the second stage, the objective function of the second stage is determined with the goal of minimizing the intra-day market redispatch cost of the power purchasing area;

[0058] Intraday constraints are added to the objective function of the second stage, and the intraday economic scheduling model is constructed based on the objective function of the second stage and the intraday constraints.

[0059] Furthermore, the device also includes a model conversion module, which is used to:

[0060] The Carlo-Kuhn-Tucker condition method is used to transform the lower model in the two-layer model of day-ahead economic dispatch into a set of constraint equations without a target;

[0061] Determine the constraint equation group as the additional conditions of the upper model to obtain the transformed single-layer model of day-ahead economic dispatch;

[0062] The penalty function method is used to transform the single-layer model of the day-ahead economic dispatch to obtain a single-layer mixed integer linear programming model of the day-ahead economic dispatch.

[0063] Furthermore, the robust optimization and solution module is also used for:

[0064] Taking the uncertainty prediction bias in the uncertainty set as a random variable;

[0065] Determining a feasible domain of decision variables in the intraday economic dispatch model based on the random variables and the decision variables in the day-ahead economic dispatch two-layer model;

[0066] The two-stage robust optimization model is constructed based on the upper and lower decision variables and the corresponding first-stage related parameters in the day-ahead economic dispatch model, the decision variables and the corresponding second-stage related parameters in the intraday economic dispatch model, and the feasible domain of the decision variables in the intraday economic dispatch model.

[0067] Furthermore, the robust optimization and solution module is also used for:

[0068] Determining the part of the two-stage robust optimization model related to the two-layer model of day-ahead economic dispatch as the main problem in the two-stage robust optimization problem;

[0069] Determining the portion of the two-stage robust optimization model related to the intraday economic dispatch model as a sub-problem in the two-stage robust optimization problem;

[0070] Solving the main problem to obtain a solution to the main problem; and solving the sub-problems to obtain solutions to the sub-problems;

[0071] Determine the solution result of the main problem as the lower bound of the two-stage robust optimization model; and determine the solution result of the sub-problem as the upper bound of the two-stage robust optimization model;

[0072] The solution process is continuously iterated, and the upper bound and the lower bound are continuously updated until the two-stage robust optimization model is in a convergence state, and the power market dispatch result is obtained.

[0073] According to another aspect of the present invention, a storage medium is provided, wherein the storage medium stores at least one executable instruction, wherein the executable instruction enables a processor to execute operations corresponding to the above-mentioned optimization scheduling method for the power market.

[0074] According to another aspect of the present invention, there is provided a computer device, comprising a processor, a memory, a communication interface and a communication bus, wherein the processor, the memory and the communication interface communicate with each other via the communication bus;

[0075] The memory is used to store at least one executable instruction, and the executable instruction enables the processor to perform operations corresponding to the above-mentioned optimization scheduling method for the power market.

[0076] By means of the above technical solution, the technical solution provided by the embodiment of the present invention has at least the following advantages:

[0077] The present invention provides an optimization dispatching method and device, storage medium, and computer equipment for an electric power market. Compared with the prior art, the present invention obtains a historical data sample set of renewable energy units and loads, and processes the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units; constructs a two-layer model of day-ahead economic dispatching with the goal of minimizing the intra-regional market operation cost and the inter-regional market power purchase cost; constructs an intra-day economic dispatching model with the goal of minimizing the intra-day market re-dispatch cost of the power purchase area; constructs a two-stage robust optimization model based on the uncertainty set, the two-layer model of day-ahead economic dispatching, and the intra-day economic dispatching model, and solves the two-stage robust optimization model to obtain the electric power market dispatching result, thereby realizing the day-ahead-intra-day two-stage economic dispatching under the coordinated operation of the inter-regional and intra-regional two-level markets. The present invention adopts a robust optimization method to add source-load uncertainty factors in the model, and solves the two-stage robust optimization model, effectively realizing the day-ahead-intra-day two-stage market collaborative clearing under the new power system. Its clearing result comprehensively considers the balance between safety and economy, and is the optimal day-ahead and intraday two-stage market clearing result under the worst source-load uncertainty scenario, which can be used as a reference for actual economic scheduling. When the prediction error increases, the advantages of the two-stage robust optimization method adopted by the present invention over the deterministic optimization method and the random optimization method will be more significant, and the obtained day-ahead and intraday scheduling scheme will be more capable of coping with source-load uncertainty.

[0078] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0079] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:

[0080] Figure 1 A schematic diagram of a flow chart of an optimization scheduling method for a power market provided by an embodiment of the present invention is shown;

[0081] Figure 2 A schematic diagram showing a flow chart of another method for optimizing scheduling of a power market provided by an embodiment of the present invention;

[0082] Figure 3 A schematic diagram showing a flow chart of another method for optimizing scheduling of a power market provided by an embodiment of the present invention;

[0083] Figure 4 A schematic diagram showing a flow chart of another method for optimizing scheduling of a power market provided by an embodiment of the present invention;

[0084] Figure 5 A schematic diagram showing a flow chart of another method for optimizing scheduling of a power market provided by an embodiment of the present invention;

[0085] Figure 6 A schematic diagram of a 5-region power system structure provided by an embodiment of the present invention is shown;

[0086] Figure 7 The inter-provincial power purchase amount and load curve diagram of power purchasing provinces A and B provided by the embodiment of the present invention are shown;

[0087] Figure 8 A comparison diagram of the inter-provincial purchase amount of power purchasing province B before and after the increase of ATC provided by an embodiment of the present invention is shown;

[0088] Fig. 9 A schematic diagram showing the structure of an optimization scheduling device for a power market provided by an embodiment of the present invention is shown;

[0089] Fig.10 A schematic structural diagram of a computer device provided by an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0090] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.

[0091] The embodiment of the present invention provides an optimization scheduling method for the power market, such as Figure 1 As shown, the method includes:

[0092] 101. Obtain a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of the renewable energy units and the load demand;

[0093] In an embodiment of the present invention, the current execution end obtains a historical data sample set of renewable energy units and loads, wherein the renewable energy units include wind turbines (hereinafter referred to as "wind turbines") and photovoltaic generators (hereinafter referred to as "photovoltaic generators"). The historical data sample set includes the actual output and predicted output of wind turbines, the actual output and predicted output of photovoltaic generators, the actual load and predicted load, etc., which are not specifically limited in the embodiment of the present invention. The current execution end processes the acquired historical data sample set to obtain an uncertainty set. Among them, the uncertainty set characterizes the value range of uncertainty parameters of the output and load demand of renewable energy units, such as the value range of the predicted deviation of the output of wind turbines, the value range of the predicted deviation of the output of photovoltaic generators, the value range of the predicted deviation of the load, etc., which are not specifically limited in the embodiment of the present invention.

[0094] 102. Construct a two-layer model of day-ahead economic dispatch with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost;

[0095] In an embodiment of the present invention, the current execution end constructs an upper model in the economic dispatch two-layer model with the goal of minimizing the market operation cost within the region; and then constructs a lower model in the economic dispatch two-layer model with the goal of minimizing the market electricity purchase cost between regions. The upper model and the lower model constructed above are combined to obtain the day-ahead economic dispatch two-layer model.

[0096] 103. Construct an intraday economic dispatch model with the goal of minimizing the market redispatching cost in the intraday power purchasing area;

[0097] In the embodiment of the present invention, the current execution end constructs an intraday economic dispatch model with the goal of minimizing the intra-day market redispatch cost of the power purchasing area. The intra-day market redispatch cost of the power purchasing area includes the upward adjustment cost and downward adjustment cost of the power purchasing area generator set during the intra-day period, and also includes the penalty cost of wind abandonment, solar abandonment, load reduction in the power purchasing area, etc., which is not specifically limited in the embodiment of the present invention.

[0098] 104. Construct a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, and solve the two-stage robust optimization model to obtain a power market dispatch result.

[0099] In an embodiment of the present invention, the current execution end constructs a two-stage robust optimization model based on an uncertainty set, a two-layer model of day-ahead economic dispatch, and an intraday economic dispatch model. In the above two-stage robust optimization model, the optimization of the two-layer model of day-ahead economic dispatch can be used as the optimization of the first stage, and the optimization of the intraday economic dispatch model can be used as the optimization of the second stage. It can also be adjusted as needed, etc., which is not specifically limited in the embodiment of the present invention. After constructing the above two-stage robust optimization model, the current execution end solves the two-stage robust optimization model to obtain the power market dispatch result. Among them, when solving the two-stage robust optimization model, the column and constraint generation algorithm (Column-and-Constraint Generation, C&CG) is preferred, which is not specifically limited in the embodiment of the present invention.

[0100] Furthermore, as a refinement and extension of the specific implementation methods of the above-mentioned embodiments, in order to obtain various typical scenarios that characterize the uncertainty factors of source-load and to specifically represent the adverse situations that require wind power abandonment, solar power abandonment and load reduction, another optimization scheduling method for the power market is provided, such as Figure 2 As shown, the step processes the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units, including:

[0101] 201. Using the Monte Carlo sampling method to extract multiple groups of sample data from the historical data sample set, and generating prediction deviation scenarios corresponding to the sample data;

[0102] In the embodiment of the present invention, it is first assumed that the forecast output of renewable energy units and the forecast deviation of load demand satisfy the normal distribution with a variance of Ω. Then, the Monte Carlo sampling method is used to extract multiple groups of sample data from the historical data sample set, and each group of sample data can be used to characterize different forecast deviation scenarios, such as using the forecast deviation of wind turbine output, the forecast deviation of photovoltaic unit output, and the forecast deviation of load to represent the forecast deviation scenario corresponding to each sample data, which is not specifically limited in the embodiment of the present invention.

[0103] 202. Perform scenario reduction processing on the prediction deviation scenario by using a K-means clustering method to obtain multiple typical prediction deviation scenarios;

[0104] In an embodiment of the present invention, after the current execution end obtains the prediction deviation scenario corresponding to the sample data, the K-means clustering method is used to first cluster the obtained prediction deviation scenario, and the obtained clustering result is determined as a typical prediction deviation scenario, that is, the screening and reduction of deviation scenarios is realized, so as to subsequently generate an uncertainty set.

[0105] 203. Generate an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of the renewable energy unit based on the typical prediction deviation scenario.

[0106] In the embodiment of the present invention, the current execution end generates an uncertainty set of uncertainty parameter value ranges that characterize the output and load demand of renewable energy units based on typical prediction deviation scenarios. Among them, the uncertainty set may include the deviation value range of wind turbine output prediction, the deviation value range of photovoltaic unit output prediction, the deviation value range of load prediction, etc., which are not specifically limited in the embodiment of the present invention. In the embodiment of the present invention, the K-means clustering method is used to reduce the scene to obtain N Γ Typical scenarios, based on N Γ The uncertainty set of each typical scenario is expressed as follows:

[0107]

[0108] in, and They represent the predicted positive deviation values ​​of wind turbine output, photovoltaic generator output and load in power purchasing area m at node n respectively; and They represent the minimum deviation of wind turbine output forecast, the minimum deviation of photovoltaic power generation output forecast and the minimum deviation of load forecast respectively; and is the predicted positive deviation value; α represents a 0-1 variable. If the 0-1 variable α is 1, the predicted positive deviation value of the wind turbine output is equal to the minimum deviation + 1× the predicted positive deviation, which means that the worst case of positive deviation has occurred; if the 0-1 variable α is 0, the predicted positive deviation value of the wind turbine output is equal to the minimum deviation + 0× the predicted positive deviation, that is, only the minimum deviation occurs, indicating that the worst case has not occurred.

[0109] Further, as a refinement and extension of the specific implementation of the above embodiment, in order to coordinate the day-ahead and intra-day power dispatch and enable the cleared inter-regional spot power transactions to be physically executed, another optimization dispatch method for the power market is provided, such as Figure 3 As shown in the figure, the steps to construct a two-layer model of day-ahead economic dispatch with the goal of minimizing the market operation cost within the region and minimizing the market purchase cost between regions include:

[0110] 301. The conventional unit output, upper reserve capacity, lower reserve capacity and inter-regional power purchase demand of each node in the region are determined as the upper decision variables in the first stage;

[0111] 302. Determine the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost within the region;

[0112] In the embodiment of the present invention, the current execution end determines the conventional unit output, upper spare capacity of the unit, lower spare capacity of the unit and regional power purchase demand of each node in the region as the upper decision variables in the first stage. Then, the current execution end determines the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost in the region. In the embodiment of the present invention, the upper model objective function is expressed by the formula as follows:

[0113]

[0114] Among them, the decision variable P n,m,t represents the power output of the conventional unit at the nth node in the mth power purchasing area in the tth period; the decision variable and They represent the upper and lower reserve capacities of the units at the nth node in the mth power purchasing area in the tth period respectively; the decision variables is the inter-regional power demand of the mth power purchasing area in the tth period. This model assumes that the inter-regional power purchase is connected from an equivalent node in the power purchasing area; T represents the set of time periods for optimal scheduling; M represents the set of power purchasing areas; N m represents the node set in the mth power purchasing area; subscript t represents the time period t; subscript m represents the power purchasing area m; subscript n represents the nth node in a power purchasing area; C n,m,P () represents the electric energy quotation function of the nth unit in the mth power purchasing area. In the embodiment of the present invention, a quadratic function is used as the unit quotation function; and Respectively represent the quotes for upper and lower reserves; It is the inter-regional electricity purchase price of the mth electricity purchase area in the tth period.

[0115] 303. The electric energy transmitted from the conventional units at each node in the power selling area to the power purchasing area is determined as the lower decision variable in the first stage;

[0116] 304. Determine the objective function of the lower model based on the lower decision variables with the goal of minimizing the inter-regional market electricity purchase cost;

[0117] In the embodiment of the present invention, the current execution end determines the electric energy transmitted by the conventional units at each node in the power sales area to the power purchase area as the lower-level decision variable in the first stage, and then the current execution end determines the lower-level model objective function based on the determined lower-level decision variables with the goal of minimizing the inter-regional market power purchase cost. In the embodiment of the present invention, the lower-level model objective function is expressed by the following formula:

[0118]

[0119] Among them, the decision variables represents the electric energy transmitted by the generator set of the nth node in the sth power sales area to the mth power purchase area in the tth period; S represents the set of power sales areas; N s represents the node set of the s-th power sales area; the subscript s represents the s-th power sales area; the subscript n represents the n-th node in a certain power sales area; c n,s,t represents the bid price of the unit at the nth node in the sth power sales area in the tth period; It represents the inter-regional transmission price for power transmission from the s-th power sales area to the m-th power purchase area during the t-th period.

[0120] 305. Adding an upper constraint condition to the upper model objective function, and adding a lower constraint condition to the lower model objective function;

[0121] In an embodiment of the present invention, the current execution end adds upper-level constraints to the upper-level model objective function, including power balance constraints in the day-ahead scheduling area, line ATC constraints, conventional generator output constraints, conventional generator set climbing constraints and conventional generator set spare capacity constraints, etc., which are not specifically limited in the embodiment of the present invention.

[0122] In the embodiment of the present invention, the power balance constraint in the day-ahead scheduling area is expressed by the following formula:

[0123]

[0124] Among them, the superscript W represents a wind turbine; the superscript PV represents a photovoltaic turbine; and represents the wind turbine output and photovoltaic power output of the nth node in the mth power purchasing area in the tth period; D n,m,t Indicates the nth electricity purchasing area in the mth electricity purchasing area in the tth period 个 The load on the node.

[0125] In the embodiment of the present invention, the line ATC constraint is expressed by the following formula:

[0126]

[0127] Among them, SF l,n,mrepresents the element in the lth row and nth column of the power transfer factor matrix; L m represents the set of key transmission lines in the mth power purchasing area; represents the maximum remaining available transmission capacity of the lth key transmission line in the mth power purchasing area, It is calculated by deducting the existing transaction volume, transmission reliability margin and capacity benefit margin from the maximum transmission capacity of line l, which will not be elaborated here; SF l,m Represents the power transfer factor of the purchased electricity from the mth power purchasing area to line l.

[0128] It should be noted that in order to ensure that the cleared inter-regional spot power transactions can be physically executed in the embodiment of the present invention, it is necessary to consider the Available Transfer Capacity (ATC) constraints of the inter-regional interconnection lines in the inter-regional economic dispatch model. That is, on the basis of the medium- and long-term transactions between regions and the medium- and long-term transactions within regions occupying part of the channel capacity, a unified economic dispatch is carried out that considers the needs of both the supply and demand sides and the remaining ATC of the inter-regional interconnection lines. Considering the ATC constraints in the model makes the clearing results meet the grid security constraints, and to a certain extent ensures that the transaction results are physically executed in real time, which can significantly reduce the subsequent adjustment of the transmission line flow.

[0129] In the embodiment of the present invention, the conventional generator output constraint is expressed by the following formula:

[0130]

[0131] in, and They respectively represent the upper and lower limits of the conventional unit output at the nth node in the mth power purchasing area.

[0132] In the embodiment of the present invention, the conventional generator set climbing constraint is expressed by the following formula:

[0133]

[0134] Among them, P n,m,U and P n,m,D They respectively represent the limits of the upward climbing rate and downward climbing rate of the conventional unit at the nth node in the mth electricity purchasing province.

[0135] In the embodiment of the present invention, the conventional generator set reserve capacity constraint is expressed by the following formula:

[0136]

[0137] In an embodiment of the present invention, the current execution end adds lower-level constraints to the objective function of the lower-level model, including inter-regional interconnection line transmission power constraints, inter-regional market unit capacity constraints, inter-regional market power balance constraints, etc., which are not specifically limited in the embodiment of the present invention.

[0138] In the embodiment of the present invention, the transmission power constraint of the inter-regional tie line is expressed by the following formula:

[0139]

[0140] Where L represents the set of inter-regional contact lines; the subscript l represents the lth inter-regional contact line; SF s,n,m,l represents the power flow impact factor on line l for the transaction pair in which the generator set at the nth node in the sth power sales area transmits power to the mth power purchase area. For a DC line, the power flow impact factor is 1 (in the embodiment of the present invention, it is assumed that the power flow direction is fixed, from the set power sales area to the power purchase area); P l ATC It represents the maximum remaining available transmission capacity of the inter-regional tie line, which is calculated by deducting the existing transaction volume, transmission reliability margin and capacity benefit margin from the maximum transmission capacity of line l, and will not be elaborated here; ω l,t represents the dual multiplier of this constraint.

[0141] In the embodiment of the present invention, the inter-regional market unit capacity constraint is expressed by the following formula:

[0142]

[0143] in, and Indicates the upper and lower limits of the output of the unit at the nth node in the sth power sales area; and represents the dual multiplier of this constraint.

[0144] In the embodiment of the present invention, the inter-regional market power balance constraint is expressed by the following formula:

[0145]

[0146] Among them, f n,s,m It represents the power transmission loss coefficient of the tie line between the nth node in the sth power sales area and the mth power purchase area. The power purchase price of power purchase area m in the inter-regional market in the tth period is It is the marginal price of the inter-regional market node, that is, the dual variable λ of this constraint m,t .

[0147] 306. Construct the day-ahead economic dispatch two-layer model based on the upper-layer model objective function, the upper-layer constraint conditions, the lower-layer model objective function, and the lower-layer constraint conditions.

[0148] In the embodiment of the present invention, the current execution end constructs a two-layer model of day-ahead economic dispatch based on the upper-layer model objective function, upper-layer constraint conditions, lower-layer model objective function and lower-layer constraint conditions. In the two-layer model of day-ahead economic dispatch, the upper-layer model converts the inter-regional electricity purchase demand into is passed to the lower model to guide the lower model to formulate the unit output plan; at the same time, the lower model can also m,t The information is passed to the upper model, thus affecting the clearing results in the upper model. In summary, the two-layer model is coupled with each other through the inter-regional electricity purchase demand and the inter-regional electricity purchase price.

[0149] Further, as a refinement and extension of the specific implementation methods of the above embodiment, in order to coordinate the power dispatching between the regional market and the regional market and improve the economic efficiency of dispatching, another optimization dispatching method for the power market is provided, such as Figure 4 As shown in the figure, the steps to construct an intraday economic dispatch model with the goal of minimizing the intra-regional market redispatch cost of the power purchasing area during the intraday stage include:

[0150] 401. Determine the daily upward and downward output of conventional units at each node in the power purchasing area, the wind power curtailment amount of wind turbines, the light curtailment amount of photovoltaic units and the load reduction amount as decision variables in the second stage;

[0151] 402. Determine the objective function of the second stage based on the decision variables in the second stage with the goal of minimizing the intra-regional market redispatch cost of the power purchasing area during the intra-day period;

[0152] In the embodiment of the present invention, the current execution end determines the daily upward and downward output of the conventional units at each node in the power purchasing area, the wind turbine abandoned wind volume, the photovoltaic abandoned light volume and the load reduction volume as the decision variables in the second stage. Then, the current execution end determines the objective function of the second stage based on the decision variables in the second stage with the goal of minimizing the regional market re-dispatch cost in the power purchasing area during the intraday stage. In the embodiment of the present invention, the objective function of the second stage is expressed by the formula as follows:

[0153]

[0154] Among them, the decision variables and They represent the upward and downward adjustment of the power output of the node n generator in the power purchasing area m during the day; the decision variables and They respectively represent the wind curtailment amount of wind turbines, photovoltaic curtailment amount and load reduction amount at node n in power purchasing area m. and The cost increase and cost decrease of the generating unit at node n in the power purchasing area m during the intraday period respectively; and They respectively represent the penalty cost coefficients for wind abandonment, solar abandonment and load reduction in power purchasing area m at node n.

[0155] 403. Add intraday constraints to the objective function of the second stage, and construct the intraday economic scheduling model based on the objective function of the second stage and the intraday constraints.

[0156] In an embodiment of the present invention, the current execution end adds intraday constraints to the objective function of the above-mentioned second stage, including power balance constraints in the intraday scheduling stage, spare capacity constraints within the region in the intraday scheduling stage, unit output up and down adjustment and load reduction constraints within the region in the intraday scheduling stage, line ATC constraints within the region in the intraday scheduling stage, etc., which are not specifically limited in the embodiment of the present invention.

[0157] In the embodiment of the present invention, the power balance constraint in the intraday scheduling stage is expressed by the following formula:

[0158]

[0159] in, and They represent the predicted positive deviation values ​​of wind turbine output, photovoltaic power output and load in power purchasing area m at node n respectively; ε t is the dual multiplier of this constraint.

[0160] In the embodiment of the present invention, the reserve capacity constraint in the region during the intraday scheduling phase is expressed by the following formula:

[0161]

[0162] in, and is the dual multiplier of this constraint. The reserve capacity constraint in the region during the intraday dispatch stage indicates that the output adjustment of the units during the intraday dispatch stage is limited by the reserve reserved capacity during the day-ahead dispatch stage.

[0163] In the embodiment of the present invention, the constraints on the output adjustment and load reduction of the units in the region during the intraday scheduling phase are expressed by the following formula:

[0164]

[0165] Among them, η W , η PV and η LThey represent the maximum wind power abandonment ratio, the maximum solar power abandonment ratio and the maximum load reduction ratio respectively; and is the dual multiplier of this constraint.

[0166] In the embodiment of the present invention, the ATC constraint of the lines in the region during the intraday scheduling phase is expressed by the following formula:

[0167]

[0168] Among them, γ t,m,l is the dual multiplier of this constraint. Compared with the previous dispatching stage, the intraday dispatching stage is only carried out between the intra-regional markets in the receiving areas. A reserve sharing mechanism is introduced between the receiving areas, that is, all the reserve capacities are shared by all the areas. Under this mechanism, if there is a large deviation between the new energy and load forecasts in a certain receiving area, other receiving areas can transmit the excess reserve power in the area to it. Therefore, the reserve capacity of a single area can be less, and each area can jointly cope with the impact of the uncertainty of the deviation of the forecast of new energy output and load demand, thereby effectively reducing the total reserve capacity.

[0169] Further, as a refinement and extension of the specific implementation of the above embodiment, in order to simplify the model solution process, another optimization scheduling method for the power market is provided. Before constructing a two-stage robust optimization model based on the uncertainty set, the day-ahead economic scheduling two-layer model and the intraday economic scheduling model, the method further includes:

[0170] The Carlo-Kuhn-Tucker condition method is used to transform the lower model in the two-layer model of day-ahead economic dispatch into a set of constraint equations without a target;

[0171] Determine the constraint equation group as the additional conditions of the upper model to obtain the transformed single-layer model of day-ahead economic dispatch;

[0172] The penalty function method is used to transform the single-layer model of the day-ahead economic dispatch to obtain a single-layer mixed integer linear programming model of the day-ahead economic dispatch.

[0173] In the embodiment of the present invention, the current execution end uses the Karush-Kuhn-Tucker (KKT) condition method to transform the lower model in the two-layer model of day-ahead economic dispatch into a non-target constraint equation set. Among them, the KKT condition is a necessary condition for determining a point as an extreme point in nonlinear optimization. In fact, it transforms a constraint programming problem with a target into a non-target equation set. It should be noted that the application of the KKT condition needs to meet two conditions:

[0174] (1) The underlying model is a continuous linear convex optimization problem;

[0175] (2) The lower model satisfies the strong duality.

[0176] The intra-day inter-regional economic dispatch model constructed in the embodiment of the present invention satisfies the above two conditions, so the KKT condition can be applied to transform the lower-level intra-day economic dispatch model into the additional constraint condition of the upper-level model. The transformed additional constraint is shown in the following formula (17).

[0177]

[0178] In the embodiment of the present invention, the converted single-layer model of day-ahead economic dispatch is as follows:

[0179]

[0180]

[0181] In the above transformed single-layer model of day-ahead economic dispatch, the decision variable is P n,m,t , and and the dual variables in the original underlying model ω l,t and λ m,t Since the complementary constraints in the KKT condition are the products of decision variables, after the two-layer model is converted into a single-layer model using the KKT condition, the single-layer model is nonlinear and needs to be converted into a mixed integer linear programming problem by introducing auxiliary 0-1 variables using the penalty function method (also known as the big M method or the big number method).

[0182] In the embodiment of the present invention, the complementary constraint conditions are as follows:

[0183]

[0184]

[0185] For the above complementary constraints, introduce 0-1 auxiliary variables and And the maximum constant and The above constraints are transformed into the following:

[0186]

[0187]

[0188] In the embodiment of the present invention, after the transformation, a single-layer mixed integer linear programming model for day-ahead economic dispatch is obtained, as shown in the following equations (24) and (25):

[0189]

[0190]

[0191] Further, as a refinement and extension of the specific implementation of the above embodiment, in order to realize the problem of economic dispatch in two stages of day-ahead and day-intraday under the operation of two-level markets within and between regions while considering uncertainty factors, another optimization dispatch method for the power market is provided, and the steps of constructing a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model include:

[0192] Taking the uncertainty prediction bias in the uncertainty set as a random variable;

[0193] Determining a feasible domain of decision variables in the intraday economic dispatch model based on the random variables and the decision variables in the day-ahead economic dispatch two-layer model;

[0194] The two-stage robust optimization model is constructed based on the upper and lower decision variables and the corresponding first-stage related parameters in the day-ahead economic dispatch model, the decision variables and the corresponding second-stage related parameters in the intraday economic dispatch model, and the feasible domain of the decision variables in the intraday economic dispatch model.

[0195] In the embodiment of the present invention, the current execution end constructs a two-stage robust optimization model of the day-ahead and intraday based on the single-layer model transformed from the day-ahead economic dispatch model. and The robust optimization method is adopted, and the uncertainty set Γ that has been constructed to characterize the uncertainty parameter value range of renewable energy unit output and load demand is used. The uncertainty prediction deviation in the uncertainty set is used as a random variable to form a two-stage robust optimization model as shown in the following formula.

[0196]

[0197] stAy..d, (27)

[0198] Gx..h-Ey-Mu,u∈U (28)

[0199] Among them, x and y are the decision variables of the intraday scheduling stage and the day-ahead scheduling stage, respectively. The decision variables of the intraday scheduling stage include and The decision variables in the day-ahead scheduling phase include Pn,m,t, and c is the relevant parameters of the decision variables that have been determined in the day-ahead scheduling stage. b is the relevant parameters of the decision variables that have been determined in the intraday scheduling stage. u is the uncertainty parameter of the intraday stage, and its value range is characterized by the uncertainty set Γ. A and d are the parameter matrices of the day-ahead scheduling stage in the compact form, and G, h, E and M are the parameter matrices of the intraday scheduling stage in the compact form. F(y,u) is the feasible domain of x under the source-load prediction deviation. For the constraints, equation (27) corresponds to equation (25), and equation (28) corresponds to equations (13) to (16). Equations (26) to (28) are the two-stage robust optimization model in compact form.

[0200] Furthermore, as a refinement and extension of the specific implementation of the above embodiment, in order to solve the two-stage robust optimization model and effectively realize the day-ahead and intraday two-stage market coordinated clearing under the new power system, another optimization scheduling method for the power market is provided, such as Figure 5 As shown, the steps for solving the two-stage robust optimization model include:

[0201] Determining the part of the two-stage robust optimization model related to the two-layer model of day-ahead economic dispatch as the main problem in the two-stage robust optimization problem;

[0202] Determining the portion of the two-stage robust optimization model related to the intraday economic dispatch model as a sub-problem in the two-stage robust optimization problem;

[0203] Solving the main problem to obtain a solution to the main problem; and solving the sub-problems to obtain solutions to the sub-problems;

[0204] Determine the solution result of the main problem as the lower bound of the two-stage robust optimization model; and determine the solution result of the sub-problem as the upper bound of the two-stage robust optimization model;

[0205] The solution process is continuously iterated, and the upper bound and the lower bound are continuously updated until the two-stage robust optimization model is in a convergence state, and the power market dispatch result is obtained.

[0206] In an embodiment of the present invention, the current execution end uses the column and constraint generation C&CG algorithm to solve the two-stage robust optimization model. The algorithm decomposes the original two-stage model into a master problem (Master Problem, MP) and a sub-problem (Sub Problem, SP). Specifically, the algorithm uses the day-ahead economic dispatch model of the day-ahead stage as MP, and the intraday economic dispatch model of the intraday stage as SP, and uses repeated iterations between MP and SP to solve the model. In each iteration process, the result of each solution to MP is used as the lower bound (LB) of the model, and the result of each solution to SP is used as the upper bound (UB) of the model. By continuously iterating this process, the upper and lower bounds of the model will continue to be improved, and the algorithm will eventually converge.

[0207] (1)MP

[0208]

[0209] 0≥b T x z (30)

[0210] Where θ represents the value of the second-stage objective function, and the superscript z represents the zth iteration. Solving MP yields the optimal decision y for the day-ahead scheduling stage. z+1 , and update the lower bound LB of the model:

[0211] LB z+1 =max(LB z , c Ty z+1 +θ) (31)

[0212] (2) SP

[0213]

[0214] In the iterative process, the optimal decision of the day-ahead stage is passed to the intraday stage model to solve the above SP. For the two-layer model of SP, the steps of converting the two-layer model into a single-layer model are also carried out using the KKT condition. I will not repeat them here, and directly give the converted single-layer SP as follows:

[0215]

[0216]

[0217]

[0218]

[0219]

[0220]

[0221]

[0222]

[0223]

[0224]

[0225]

[0226]

[0227]

[0228]

[0229]

[0230] Wherein, Ε represents the set of all dual multipliers in the constraints of the intraday scheduling optimization model; and v t,m,l They represent the 0-1 auxiliary variables introduced to linearize the nonlinear optimization model; and M t,m,l They represent the maximum constants introduced to linearize the nonlinear optimization model; SF l,n,m,W , SF l,n,m,PV and SF l,n,m,L They respectively represent the power transfer factor matrix related to wind turbines, the power transfer factor matrix related to photovoltaic turbines, and the power transfer factor matrix related to adjustable load reduction.

[0231] After solving equations (32) to (47), we can obtain the optimal decision x in the intraday scheduling stage: z+1 , and update the upper bound UB of the model:

[0232] UB z+1 =min(UB z , c T y z+1 +b T x z+1 ) (48)

[0233] It should be noted that in the embodiment of the present invention, the conservatism of the two-stage market collaborative optimization scheme can be flexibly adjusted by changing the robustness parameters in the model, which is conducive to the dispatcher to make reasonable decisions between costs and risks. Its clearing result comprehensively considers the balance between safety and economy, and is the optimal day-ahead-day two-stage market clearing result under the worst source-load uncertainty scenario, which can be used as a reference for actual economic dispatch.

[0234] In the embodiment of the present invention, a 5-zone system is adopted, such as Figure 6 As shown, each region can be a province in the country, where the power purchasing province adopts the IEEE 9-node system and the 30-node system, and the inter-provincial tie line access nodes are node 5 and node 8 respectively. In addition, the conventional unit at node 3 of the power purchasing province A is replaced by a wind turbine unit, and the conventional unit at node 13 of the power purchasing province B is replaced by a photovoltaic unit. The capacity of the transmission lines within the province, the relevant data and quotation information of the conventional units refer to the standard data in MATPOWER. The renewable energy output, historical forecast data of the load, the line loss rate and transmission price of the inter-provincial tie line of the power purchasing province A and the power purchasing province B, as well as the unit capacity participating in the inter-provincial market refer to the document "The Optimal Power Purchasing Model of Inter-provincial Traders Taking Risk into Account in a Two-Level Electricity Market Environment". A single power selling province is regarded as a node.

[0235] The inter-provincial power purchasing behavior in the day-ahead stage is analyzed. According to the goal of maximizing social welfare in the two-level market model in the day-ahead stage, for power purchasing provinces A and B, inter-provincial power purchasing behavior will only occur when the inter-provincial power purchasing price is lower than the marginal power price of the units within the province and meets the constraints. The inter-provincial power purchasing volume and load curves of power purchasing provinces A and B are shown in Figure 2. Figure 7 As shown in the figure. When the 8-14h load demand increases, the inter-provincial purchase volume of the power purchasing province B also increases. At this time, the inter-provincial purchase price is lower than the marginal price of the units within the province. However, for the power purchasing province A, although its rising load demand can be met at the lowest cost by inter-provincial power, its inter-provincial purchase volume actually remains unchanged. This is because the existence of the provincial standby demand requires the output of the conventional units in the province to be maintained at a certain level.

[0236] In addition to the reserve demand within the province, the ATC constraints of key lines within the province and the capacity constraints of inter-provincial interconnection lines will impose restrictions on inter-provincial power purchases that can improve total social welfare. Figure 8 A comparison of the inter-provincial power purchase volume of power purchasing province B before and after the increase of ATC is given. It can be seen from the figure that when the ATC constraints are relaxed to a certain extent, the inter-provincial power purchase volume increases, and the total operating cost of the inter-provincial and intra-provincial markets also decreases from 7650.0874 (thousand yuan) to 5932.1526 (thousand yuan).

[0237] In addition, the dispatcher can adjust the tolerance for uncertainty volatility risks in the market clearing process by adjusting the robustness coefficient. Table 1 shows the relationship between the robustness coefficient and the total operating cost of the inter-provincial and intra-provincial markets. From the data analysis in the table, it can be seen that when the robustness coefficient increases, the system's consideration of the risk level is more stringent. At this time, more spare capacity will be prepared to resist source-load uncertainty. In addition, the redispatching cost in the intraday market also increases due to the increase in the severity of the uncertainty scenario. Therefore, the total cost of market operation increases with the increase of the robustness coefficient.

[0238] Table 1 Relationship between robustness coefficient and total market operation cost

[0239] Robustness coefficient 5 7 9 11 13 15 Market operation costs in the day-ahead phase 7350.59 7374.67 7401.04 7422.28 7453.08 7474.14 Intraday market redispatch costs 90.00 126.00 162.00 198.00 234.00 270.00 Total cost of market operation 7440.59 7500.67 7563.04 7620.28 7687.08 7744.14

[0240] The embodiment of the present invention provides an optimization dispatching method for the power market. Compared with the prior art, the present invention obtains a historical data sample set of renewable energy units and loads, and processes the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units; constructs a two-layer model of day-ahead economic dispatching with the goal of minimizing the intra-regional market operation cost and the inter-regional market power purchase cost; constructs an intra-day economic dispatching model with the goal of minimizing the intra-day stage power purchase market re-dispatch cost; constructs a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatching two-layer model and the intra-day economic dispatching model, and solves the two-stage robust optimization model to obtain the power market dispatching result, realizing the day-ahead-intra-day two-stage economic dispatching under the coordinated operation of the inter-regional and intra-regional two-level markets. The present invention adopts a robust optimization method to add source-load uncertainty factors in the model, and solves the two-stage robust optimization model, effectively realizing the day-ahead-intra-day two-stage market collaborative clearing under the new power system. Its clearing result comprehensively considers the balance between safety and economy, and is the optimal day-ahead and intraday two-stage market clearing result under the worst source-load uncertainty scenario, which can be used as a reference for actual economic scheduling. When the prediction error increases, the advantages of the two-stage robust optimization method adopted by the present invention over the deterministic optimization method and the random optimization method will be more significant, and the obtained day-ahead and intraday scheduling scheme will be more capable of coping with source-load uncertainty.

[0241] As the above Figure 1 The implementation of the method shown in the figure, the embodiment of the present invention provides an optimization scheduling device for the power market, such as Fig. 9 As shown, the device comprises:

[0242] The uncertainty analysis module 61 is used to obtain a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of the renewable energy units and the load requirements;

[0243] A day-ahead model building module 62, for building a day-ahead economic dispatch double-layer model with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost;

[0244] Intraday model building module 63, used to build an intraday economic dispatch model with the goal of minimizing the intra-regional market re-dispatch cost of the power purchasing area during the intraday stage;

[0245] The robust optimization and solution module 64 is used to construct a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, and solve the two-stage robust optimization model to obtain the power market dispatch result.

[0246] Furthermore, the uncertainty analysis module 61 is also used for:

[0247] A Monte Carlo sampling method is used to extract multiple groups of sample data from the historical data sample set, and a prediction deviation scenario corresponding to the sample data is generated;

[0248] A K-means clustering method is used to perform scenario reduction processing on the prediction deviation scenario to obtain multiple typical prediction deviation scenarios;

[0249] An uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units is generated based on the typical prediction deviation scenario.

[0250] Furthermore, the day-ahead model building module 62 is also used for:

[0251] The conventional unit output, upper reserve capacity, lower reserve capacity and inter-regional power purchase demand of each node in the region are determined as the upper decision variables in the first stage;

[0252] Determine the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost within the region;

[0253] The electric energy transmitted from the conventional units at each node in the power sales area to the power purchase area is determined as the lower decision variable in the first stage;

[0254] Determine the objective function of the lower model based on the lower decision variables with the goal of minimizing the inter-regional market electricity purchase cost;

[0255] Adding upper-level constraints to the upper-level model objective function, and adding lower-level constraints to the lower-level model objective function;

[0256] The day-ahead economic dispatch two-layer model is constructed based on the upper-layer model objective function, the upper-layer constraint conditions, the lower-layer model objective function and the lower-layer constraint conditions.

[0257] Furthermore, the intraday model building module 63 is also used for:

[0258] The daily upward and downward output of conventional units at each node in the power purchasing area, the wind power curtailment amount of wind turbines, the light curtailment amount of photovoltaic units and the load reduction amount are determined as decision variables in the second stage;

[0259] Based on the decision variables in the second stage, the objective function of the second stage is determined with the goal of minimizing the intra-day market redispatch cost of the power purchasing area;

[0260] Intraday constraints are added to the objective function of the second stage, and the intraday economic scheduling model is constructed based on the objective function of the second stage and the intraday constraints.

[0261] Furthermore, the device also includes a model conversion module, which is used to:

[0262] The Carlo-Kuhn-Tucker condition method is used to transform the lower model in the two-layer model of day-ahead economic dispatch into a set of constraint equations without a target;

[0263] Determine the constraint equation group as the additional conditions of the upper model to obtain the transformed single-layer model of day-ahead economic dispatch;

[0264] The penalty function method is used to transform the single-layer model of the day-ahead economic dispatch to obtain a single-layer mixed integer linear programming model of the day-ahead economic dispatch.

[0265] Furthermore, the robust optimization and solution module 64 is also used for:

[0266] Taking the uncertainty prediction bias in the uncertainty set as a random variable;

[0267] Determining a feasible domain of decision variables in the intraday economic dispatch model based on the random variables and the decision variables in the day-ahead economic dispatch two-layer model;

[0268] The two-stage robust optimization model is constructed based on the upper and lower decision variables and the corresponding first-stage related parameters in the day-ahead economic dispatch model, the decision variables and the corresponding second-stage related parameters in the intraday economic dispatch model, and the feasible domain of the decision variables in the intraday economic dispatch model.

[0269] Furthermore, the robust optimization and solution module 64 is also used for:

[0270] Determining the part of the two-stage robust optimization model related to the two-layer model of day-ahead economic dispatch as the main problem in the two-stage robust optimization problem;

[0271] Determining the portion of the two-stage robust optimization model related to the intraday economic dispatch model as a sub-problem in the two-stage robust optimization problem;

[0272] Solving the main problem to obtain a solution to the main problem; and solving the sub-problems to obtain solutions to the sub-problems;

[0273] Determine the solution result of the main problem as the lower bound of the two-stage robust optimization model; and determine the solution result of the sub-problem as the upper bound of the two-stage robust optimization model;

[0274] The solution process is continuously iterated, and the upper bound and the lower bound are continuously updated until the two-stage robust optimization model is in a convergence state, and the power market dispatch result is obtained.

[0275] The embodiment of the present invention provides an optimization dispatching device for the power market. Compared with the prior art, the present invention obtains a historical data sample set of renewable energy units and loads, and processes the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units; constructs a two-layer model of day-ahead economic dispatch with the goal of minimizing the intra-regional market operation cost and the inter-regional market power purchase cost; constructs an intra-day economic dispatching model with the goal of minimizing the intra-day market re-dispatch cost of the power purchase area; constructs a two-stage robust optimization model based on the uncertainty set, the two-layer model of day-ahead economic dispatching and the intra-day economic dispatching model, and solves the two-stage robust optimization model to obtain the power market dispatching result, thereby realizing the day-ahead and intra-day two-stage economic dispatching under the coordinated operation of the inter-regional and intra-regional two-level markets. The present invention adopts a robust optimization method to add source-load uncertainty factors in the model, and solves the two-stage robust optimization model, effectively realizing the day-ahead and intra-day two-stage market collaborative clearing under the new power system. Its clearing result comprehensively considers the balance between safety and economy, and is the optimal day-ahead and intraday two-stage market clearing result under the worst source-load uncertainty scenario, which can be used as a reference for actual economic scheduling. When the prediction error increases, the advantages of the two-stage robust optimization method adopted by the present invention over the deterministic optimization method and the random optimization method will be more significant, and the obtained day-ahead and intraday scheduling scheme will be more capable of coping with source-load uncertainty.

[0276] According to one embodiment of the present invention, a storage medium is provided, wherein the storage medium stores at least one executable instruction, and the computer executable instruction can execute the optimization scheduling method for the power market in any of the above method embodiments.

[0277] Fig.10 A schematic diagram of the structure of a computer device provided according to an embodiment of the present invention is shown. The specific embodiment of the present invention does not limit the specific implementation of the computer device.

[0278] like Fig.10As shown, the computer device may include: a processor (processor) 702 , a communication interface (Communications Interface) 704 , a memory (memory) 706 , and a communication bus 708 .

[0279] The processor 702 , the communication interface 704 , and the memory 706 communicate with each other via a communication bus 708 .

[0280] The communication interface 704 is used to communicate with other devices such as clients or other servers.

[0281] The processor 702 is used to execute the program 710, and specifically can execute the relevant steps of the above-mentioned optimization scheduling method for the power market.

[0282] Specifically, the program 710 may include program codes, which include computer operation instructions.

[0283] The processor 702 may be a central processing unit (CPU), or an application-specific integrated circuit (ASIC), or one or more integrated circuits configured to implement the embodiments of the present invention. The one or more processors included in the computer device may be processors of the same type, such as one or more CPUs; or may be processors of different types, such as one or more CPUs and one or more ASICs.

[0284] The memory 706 is used to store the program 710. The memory 706 may include a high-speed RAM memory, and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.

[0285] The program 710 may be specifically configured to enable the processor 702 to perform the following operations:

[0286] Acquire a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of the renewable energy units and the load demand;

[0287] A two-layer model of day-ahead economic dispatch is constructed with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost.

[0288] An intraday economic dispatch model is constructed with the goal of minimizing the market redispatch cost in the intraday power purchasing area;

[0289] A two-stage robust optimization model is constructed based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, and the two-stage robust optimization model is solved to obtain a power market dispatch result.

[0290] Obviously, those skilled in the art should understand that the above modules or steps of the present invention can be implemented by a general computing device, they can be concentrated on a single computing device, or distributed on a network composed of multiple computing devices, and optionally, they can be implemented by a program code executable by a computing device, so that they can be stored in a storage device and executed by the computing device, and in some cases, the steps shown or described can be executed in a different order than here, or they can be made into individual integrated circuit modules, or multiple modules or steps therein can be made into a single integrated circuit module for implementation. Thus, the present invention is not limited to any specific combination of hardware and software.

[0291] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An optimization dispatching method for an electric power market, characterized in that: include: Acquire a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of the renewable energy units and the load demand; A two-layer model of day-ahead economic dispatch is constructed with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost. An intraday economic dispatch model is constructed with the goal of minimizing the market redispatch cost in the intraday power purchasing area; A two-stage robust optimization model is constructed based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, and the two-stage robust optimization model is solved to obtain a power market dispatch result.

2. The method according to claim 1, characterized in that The historical data sample set is processed to obtain an uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units, including: A Monte Carlo sampling method is used to extract multiple groups of sample data from the historical data sample set, and a prediction deviation scenario corresponding to the sample data is generated; A K-means clustering method is used to perform scenario reduction processing on the prediction deviation scenario to obtain multiple typical prediction deviation scenarios; An uncertainty set of uncertainty parameter value ranges characterizing the output and load demand of renewable energy units is generated based on the typical prediction deviation scenario.

3. The method according to claim 1, characterized in that The two-layer model for constructing day-ahead economic dispatch with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost includes: The conventional unit output, upper reserve capacity, lower reserve capacity and inter-regional power purchase demand of each node in the region are determined as the upper decision variables in the first stage; Determine the upper model objective function based on the upper decision variables with the goal of minimizing the market operation cost within the region; The electric energy transmitted from the conventional units at each node in the power sales area to the power purchase area is determined as the lower decision variable in the first stage; Determine the objective function of the lower model based on the lower decision variables with the goal of minimizing the inter-regional market electricity purchase cost; Adding upper-level constraints to the upper-level model objective function, and adding lower-level constraints to the lower-level model objective function; The day-ahead economic dispatch two-layer model is constructed based on the upper-layer model objective function, the upper-layer constraint conditions, the lower-layer model objective function and the lower-layer constraint conditions.

4. The method according to claim 1, characterized in that: The intraday economic dispatch model constructed with the goal of minimizing the intra-day market redispatching cost in the intra-day power purchasing area includes: The daily upward and downward output of conventional units at each node in the power purchasing area, the wind power curtailment amount of wind turbines, the light curtailment amount of photovoltaic units and the load reduction amount are determined as decision variables in the second stage; Based on the decision variables in the second stage, the objective function of the second stage is determined with the goal of minimizing the intra-day market redispatch cost of the power purchasing area; Intraday constraints are added to the objective function of the second stage, and the intraday economic scheduling model is constructed based on the objective function of the second stage and the intraday constraints.

5. The method according to claim 1, characterized in that Before constructing the two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model, the method further includes: The Carlo-Kuhn-Tucker condition method is used to transform the lower model in the two-layer model of day-ahead economic dispatch into a set of constraint equations without a target; Determine the constraint equation group as the additional conditions of the upper model to obtain the transformed single-layer model of day-ahead economic dispatch; The penalty function method is used to transform the single-layer model of the day-ahead economic dispatch to obtain a single-layer mixed integer linear programming model of the day-ahead economic dispatch.

6. The method according to claim 1, characterized in that The constructing of a two-stage robust optimization model based on the uncertainty set, the day-ahead economic dispatch two-layer model and the intraday economic dispatch model includes: Taking the uncertainty prediction bias in the uncertainty set as a random variable; Determining a feasible domain of decision variables in the intraday economic dispatch model based on the random variables and the decision variables in the day-ahead economic dispatch two-layer model; The two-stage robust optimization model is constructed based on the upper and lower decision variables and the corresponding first-stage related parameters in the day-ahead economic dispatch model, the decision variables and the corresponding second-stage related parameters in the intraday economic dispatch model, and the feasible domain of the decision variables in the intraday economic dispatch model.

7. The method according to any one of claims 1 to 6, characterized in that: The solving of the two-stage robust optimization model includes: Determining the part of the two-stage robust optimization model related to the two-layer model of day-ahead economic dispatch as the main problem in the two-stage robust optimization problem; Determining the portion of the two-stage robust optimization model related to the intraday economic dispatch model as a sub-problem in the two-stage robust optimization problem; Solving the main problem to obtain a solution to the main problem; and solving the sub-problems to obtain solutions to the sub-problems; Determine the solution result of the main problem as the lower bound of the two-stage robust optimization model; and determine the solution result of the sub-problem as the upper bound of the two-stage robust optimization model; The solution process is continuously iterated, and the upper bound and the lower bound are continuously updated until the two-stage robust optimization model is in a convergence state, and the power market dispatch result is obtained.

8. An optimization dispatching device for an electric power market, characterized in that: include: An uncertainty analysis module is used to obtain a historical data sample set of renewable energy units and loads, and perform data processing on the historical data sample set to obtain an uncertainty set of uncertainty parameter value ranges that characterize the output of renewable energy units and load requirements; The day-ahead model building module is used to build a two-layer model of day-ahead economic dispatch with the goal of minimizing the intra-regional market operation cost and minimizing the inter-regional market power purchase cost; The intraday model building module is used to build an intraday economic dispatch model with the goal of minimizing the intra-regional market redispatch cost of the power purchasing area during the intraday stage; The robust optimization and solution module is used to construct a two-stage robust optimization model based on the uncertainty set, the two-layer model of day-ahead economic dispatch and the intraday economic dispatch model, and solve the two-stage robust optimization model to obtain the power market dispatch result.

9. A storage medium, wherein at least one executable instruction is stored in the storage medium, and the executable instruction executes an operation corresponding to the optimization scheduling method for the power market as described in any one of claims 1 to 7.

10. A computer device, comprising a processor, a memory, a communication interface and a communication bus, wherein the processor, the memory and the communication interface communicate with each other via the communication bus; The memory is used to store at least one executable instruction, and the executable instruction enables the processor to perform operations corresponding to the optimization scheduling method for the power market according to any one of claims 1-7.

Citation Information

Patent Citations

  • Virtual power plant day-ahead scheduling method for aggregating multiple types of electric vehicles

    CN112865082A

  • Micro-grid multi-time-stage economic dispatching method and system based on new energy uncertainty

    CN115912506A

  • Scheduling method and device of pumped storage power station, storage medium and computer equipment

    CN116404702A

  • Island power grid energy storage system hierarchical control method for ameliorating new energy power generation fluctuation

    WO2021114849A1

  • Flexibility demand quantification and coordination optimization method for wind-solar-water multi-energy complementary system

    WO2023065113A1

Cited By

  • Power transmission network expansion planning method and system based on improved large M method

    CN119784113A

  • Shared energy storage configuration method and apparatus for micro-energy network, and storage medium

    WO2026102940A1