Automatic pipe joint assembling equipment
By designing automatic assembly equipment for pipe joints, using a turntable and multiple assembly mechanisms to automatically install rubber rings, plastic rings, and steel rings at the same location, the problems of low work efficiency and low automation in the existing technology are solved, and efficient Pipe joint assembly.
Patent Information
- Application Number
- CN202410815788.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-10-08
AI Technical Summary
The existing pipe joint assembly equipment has low working efficiency and a low degree of automation. A technical solution is needed to complete the installation of the pipe joints at one time and improve efficiency and automation.
An automatic pipe joint assembly equipment is designed, including a turntable and multiple assembly mechanisms. Rubber rings, plastic rings and steel rings are automatically installed at the same working position through rotating clamps and assembly mechanisms. This is achieved by using the cooperation of multiple assembly mechanisms and clamps. Automated assembly.
The product assembly efficiency and qualification rate are improved through automated assembly, which is highly practical and enables efficient installation of pipe joint parts at the pipe end.
Smart Images

Figure CN118744330A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of pipe joint equipment, and more specifically, to an automatic assembly equipment for pipe joints. Background Art
[0002] In the prior art, pipe joints are used to connect pipelines, and are generally two-way or three-way joints. Each joint part of the pipe joint needs to be installed with multiple rubber rings, plastic rings, steel rings, etc. The existing assembly equipment can only assemble the parts of one joint part at a time. A pipe joint needs to be inserted multiple times for assembly before the parts required for each joint part can be installed. The work efficiency is low and the degree of automation is not high. Therefore, a technical solution is needed to solve the above problems. Summary of the invention
[0003] The purpose of the present invention is to overcome the above-mentioned shortcomings of the prior art, so that the pipe joint can be installed in one time, so as to improve the working efficiency and the degree of automation, and provide an automatic assembly device for the pipe joint.
[0004] In order to achieve the above object, the present invention adopts the following technical solution:
[0005] The present invention discloses an automatic assembly device for a pipe joint, comprising a rotating disk, wherein the rotating disk comprises a first circular plate capable of rotating, a plurality of clamping assemblies are arranged in the circumference of the first circular plate, the clamping assemblies comprise a rotatable clamp, the clamp can clamp the pipe joint, the pipe joint comprises a plurality of pipe ends facing in different directions, a feeding mechanism, a plastic ring assembly mechanism, a rubber ring assembly mechanism, a steel ring assembly mechanism, and a material taking mechanism are arranged along the rotation direction of the first circular plate, the pipe joint is moved to the clamp by the feeding mechanism, a plastic ring is arranged in the plastic ring assembly mechanism, the plastic ring is sleeved on each of the pipe ends by rotating the plastic ring assembly mechanism and the clamp, a rubber ring is arranged in the rubber ring assembly mechanism, the rubber ring is sleeved on each of the pipe ends by rotating the rubber ring assembly mechanism and the clamp, a steel ring is arranged in the steel ring assembly mechanism, the steel ring is sleeved on each of the pipe ends by rotating the steel ring assembly mechanism and the clamp, and the assembled pipe joint can be removed from the clamp by the material taking mechanism.
[0006] Furthermore, the feeding mechanism includes a supporting device and a first feeding device, the supporting device includes a translation track and a pallet that moves along the translation track, the pipe joint is placed in the pallet, the first feeding device is located above the pallet, the first feeding device includes a first transverse device, a first lifting device, and a first clamp, the first lifting device can move along the first transverse device, the first clamp can be lifted and lowered along the first lifting device, and the first clamp can clamp the pipe joint from the pallet and clamp the pipe joint to the fixture.
[0007] Furthermore, the turntable includes a second circular plate, which is fixed relative to the first circular plate, and the second circular plate is located at the center of the upper end surface of the first circular plate. A plurality of driving components are arranged in the circumference of the second circular plate, and the driving component includes a feed cylinder and a rotating cylinder. The feed cylinder drives the rotating cylinder to approach or move away from the clamping component, and the rotating cylinder is provided with a rotatable positioning block, and the rotating axis of the positioning block is consistent with the axial direction of the first circular plate. The clamping assembly includes a base and a rotating member, the base is fixedly mounted on the upper end surface of the first circular plate, and the rotating member is rotatably mounted on the side of the base, and the rotation center of the rotating member is consistent with the axial direction of the first circular plate. The clamp is mounted on the base through the rotating member, and the rotating member is provided with a positioning slot corresponding to the positioning block.
[0008] Furthermore, it includes a positioning device, which is distributed along the rotation direction of the first circular plate. The positioning device includes a first cylinder and an insertion rod. The first cylinder can drive the insertion rod to extend and retract up and down. The number of the rotating parts is two. The base is provided with a seat groove. The two rotating parts are respectively located on both sides of the seat groove. The insertion rod can be inserted into the positioning slot of the rotating part away from the center of the first circular plate.
[0009] Furthermore, the clamp includes a first clamp block, a second clamp block, a first transmission rod, and a second transmission rod. The first clamp block and the second clamp block can approach or move away from each other, and the pipe joint can be clamped between the first clamp block and the second clamp block. The first transmission rod is connected to the first clamp block, and the second transmission rod is connected to the second clamp block. The first transmission rod can transmit the second transmission rod to move in the opposite direction while moving. The second circular plate is installed with a push-open cylinder, and the push-open cylinder is provided with a push rod, and the push rod can be extended and retracted toward the direction of the first transmission rod.
[0010] Furthermore, the plastic ring assembly mechanism includes a second loading device, a first pushing device, and a first vibration plate. The plastic ring is arranged in the first vibration plate. The first vibration plate transports the plastic ring to the upper end surface of the first pushing device. The second loading device is located above the first pushing device. The second loading device includes a second transverse movement device, a second lifting device, and a second clamp. The second lifting device can move along the second transverse movement device. The second clamp can be lifted and lowered along the second lifting device. The second clamp can clamp the plastic ring from the first pushing device and clamp the plastic ring to the fixture.
[0011] Furthermore, the rubber ring assembly mechanism includes a third loading device, a discharging rack, and a second vibration disk. The rubber ring is arranged in the second vibration disk. The discharging rack includes a material receiving seat and a spreading seat. The second vibration disk sends the rubber ring to the material receiving seat. The third loading device is located above the discharging rack. The third loading device includes a third transverse movement device and a third lifting device. The third lifting device includes a first material picking device and a second material picking device. The third lifting device can move along the third transverse movement device. The first material picking device and the second material picking device can be lifted up and down. The rubber ring at the material receiving seat is sent to the spreading seat for spreading through the first material picking device, and the rubber ring spread at the spreading seat is sent to the clamp through the second material picking device.
[0012] Furthermore, two rubber rings are installed at the connecting pipe end, and the two rubber rings are distributed along the length direction of the connecting pipe end. The number of rubber ring assembly mechanisms is correspondingly two, and the rotation directions of the two clamps corresponding to the two rubber ring assembly mechanisms are opposite.
[0013] Furthermore, the steel ring assembly mechanism includes a fourth loading device, a second pushing device, and a third vibration plate. The steel ring is arranged in the third vibration plate. The third vibration plate transports the steel ring to the upper end surface of the second pushing device. The fourth loading device is located above the second pushing device. The fourth loading device includes a fourth transverse movement device, a fourth lifting device, and a third clamp. The fourth lifting device can move along the fourth transverse movement device. The third clamp can be lifted and lowered along the fourth lifting device. The third clamp can clamp the steel ring from the second pushing device and clamp the steel ring to the clamp.
[0014] Furthermore, the material picking mechanism includes a material discharge device and a material discharge hopper. The material discharge device includes a fifth transverse movement device, a fifth lifting device, and a fourth clamp. The fifth lifting device can move along the fifth transverse movement device, and the fourth clamp can be lifted and lowered along the fifth lifting device. The fourth clamp can take the assembled pipe fitting from the fixture and send it to the material discharge hopper.
[0015] The beneficial effects of the present invention are:
[0016] The present invention realizes automatic assembly by installing parts on each pipe end at the same working position through the cooperation between multiple assembly mechanisms and rotatable clamps, thereby improving the assembly efficiency of the product, improving the product qualification rate and having strong practicality. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic diagram of this embodiment.
[0018] Figure 2 It is a partial schematic diagram of the feeding mechanism and the turntable in this embodiment.
[0019] Figure 3 Schematic diagram of a pipe joint in this embodiment.
[0020] Figure 4 It is a partial schematic diagram of the turntable in this embodiment.
[0021] Figure 5 It is a partial top view of the turntable in this embodiment.
[0022] Figure 6 Schematic diagram of the clamping assembly in this embodiment.
[0023] Figure 7 for Figure 6 Schematic diagram of another direction of the clamping assembly.
[0024] Figure 8 A cross-sectional view of the clamping assembly in this embodiment.
[0025] Fig. 9 Schematic diagram of the plastic ring assembly mechanism in this embodiment.
[0026] Fig.10 Schematic diagram of the rubber ring assembly mechanism in this embodiment.
[0027] Fig.11 for Fig.10 Enlarged view of point A in the middle.
[0028] Fig.12 It is a cross-sectional view of the first material taking device and the propping seat in this embodiment.
[0029] Fig.13 It is a cross-sectional view of the second material taking device and the propping seat in this embodiment.
[0030] Fig.14 Schematic diagram of the steel ring assembly mechanism in this embodiment.
[0031] Fig.15 It is a schematic diagram of the material taking mechanism in this embodiment.
[0032] Figure numerals: 1, turntable; 11, first circular plate; 12, second circular plate; 101, positioning device; 102, first cylinder; 103, insertion rod; 1001, table; 2, feeding mechanism; 21, supporting device; 211, translation track; 212, tray; 22, first feeding device; 221, first transverse device; 222, first lifting device; 223, first clamping claw; 201, pipe joint; 2011, pipe end; 3, plastic ring assembly mechanism; 31, second feeding device; 311, second transverse device; 312, second lifting device; 313, second clamping claw; 32, first Pushing device; 321, first unloading plate; 3211, first discharging trough; 3212, blocking block; 322, first pushing block; 33, first vibrating plate; 331, first discharging port; 301, plastic ring; 4, rubber ring assembly mechanism; 41, third loading device; 411, third transverse moving device; 412, third lifting device; 4121, first picking device; 41211, insert plate; 4122, second picking device; 41221, sleeve; 41222, pushing plate; 41223, second cylinder; 42, discharging rack; 421, receiving seat; 4211, first slot; 422, Open seat; 4221, guide sleeve; 4222, socket; 42221, second slot; 4223, first spring; 43, second vibration plate; 431, second discharge port; 401, rubber ring; 5, steel ring assembly mechanism; 51, fourth loading device; 511, fourth lateral movement device; 512, fourth lifting device; 513, third clamping claw; 52, second pushing device; 521, second discharge plate; 5211, second discharge trough; 522, second pushing block; 53, third vibration plate; 531, third discharge port; 501, steel ring; 6, material taking mechanism; 61, unloading device; 611, The fifth transverse movement device; 612, the fifth lifting device; 613, the fourth clamp; 62, the lower hopper; 7, the clamping assembly; 71, the base; 711, the seat groove; 72, the clamp; 721, the clamp seat; 7211, the guide groove; 722, the first clamp block; 723, the second clamp block; 724, the back cover; 725, the first transmission rod; 726, the second transmission rod; 727, the gear; 728, the second spring; 73, the rotating part; 731, the positioning slot; 74, the spring latch; 8, the push cylinder; 81, the push rod; 9, the driving assembly; 91, the feed cylinder; 92, the rotating cylinder; 93, the positioning plug. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in this embodiment to clearly and completely describe the technical solution in this embodiment. Obviously, the described embodiment is only a part of the embodiment of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0034] like Figure 1 , Figure 3 As shown, this embodiment discloses an automatic assembly device for pipe joints, which is used to install a plastic ring 301, a rubber ring 401, and a steel ring 501 on pipe ends 2011 of pipe joints 201 in different directions, and can be applicable to three types of joints: straight-line, L-shaped, and T-shaped. An automatic assembly device for pipe joints includes a table 1001 and a turntable 1. The turntable 1 includes a first circular plate 11 rotatably connected to the table 1001, a second circular plate 12 fixedly installed on the table 1001, and a motor (not shown in the figure) driving the first circular plate 11 to rotate. The second circular plate 12 is located at the center of the upper end surface of the first circular plate 11, and the second circular plate 12 is connected to the first circular plate 11. The second circular plate 12 is concentrically arranged and has a diameter smaller than that of the first circular plate 11. A plurality of clamping assemblies 7 are arranged on the circumference of the first circular plate 11. The plurality of clamping assemblies 7 are annularly distributed on the upper end surface of the first circular plate 11. A plurality of driving assemblies 9 and two top-opening cylinders 8 are arranged on the circumference of the second circular plate 12. A feeding mechanism 2, a plastic ring assembly mechanism 3, a rubber ring assembly mechanism 4, a steel ring assembly mechanism 5, and a picking mechanism 6 are arranged along the rotation direction of the first circular plate 11. The positions of the two top-opening cylinders 8 correspond to the feeding mechanism 2 and the picking mechanism 6 respectively, and the positions of the plurality of driving assemblies 9 correspond to the plastic ring assembly mechanism 3, the rubber ring assembly mechanism 4, and the steel ring assembly mechanism 5 respectively.
[0035] like Figure 4 , Figure 6As shown, the clamping assembly 7 includes a base 71, a fixture 72, and a rotating member 73. The base 71 is fixedly installed on the upper end surface of the first circular plate 11. The base 71 is provided with a seat groove 711. Two rotating members 73 are respectively rotatably installed on the two side surfaces of the seat groove 711 of the base 71. The rotation center of the two rotating members 73 is consistent with the axial direction of the first circular plate 11. The fixture 72 is installed on the base 71 through the rotating member 73. The fixture 72 can rotate in the seat groove 711. The driving assembly 9 includes a feed cylinder 91 and a rotating cylinder 92. The feed cylinder 91 drives the rotating cylinder 92 to approach or move away from the clamping assembly 7. The rotating cylinder 92 is provided with a rotatable positioning plug 93. The rotation axis of the positioning plug 93 is consistent with the axial direction of the first circular plate 11. The rotating member 73 is provided with a rotating block 93. The positioning block 93 corresponds to the positioning slot 731, and the positioning block 93 and the positioning slot 731 are plugged into each other to form a limit in the rotation direction. When the clamp 72 needs to be rotated, the feed cylinder 91 is started to push the rotating cylinder 92 out, so that the positioning block 93 is inserted into the corresponding positioning slot 731. The rotation of the rotating cylinder 92 can drive the clamp 72 to rotate, and then the pipe joint 201 clamped in the clamp 72 can be rotated to adjust the pipe end 2011 that needs to be installed, and all the pipe ends 2011 of the pipe joint 201 can be installed with the required components in the same installation position. After the installation is completed, the feed cylinder 91 is retracted to disengage the positioning block 93 from the positioning slot 731, and the first circular plate 11 can be rotated to move the clamping assembly 7 to the next working position.
[0036] More preferably, a spring latch 74 is installed on the base 71. After the rotating member 73 rotates, the spring latch 74 can be inserted into the corresponding recessed hole of the rotating member 73 to position the rotating member 73. When rotating, the spring latch 74 can be disengaged from the recessed hole due to the force of rotation.
[0037] like Figure 2 , Figure 4 As shown, more preferably, this embodiment also includes a positioning device 101, and the positioning device 101 is distributed along the rotation direction of the first circular plate 11. The position of the positioning device 101 corresponds to the position of the plastic ring assembly mechanism 3, the rubber ring assembly mechanism 4, and the steel ring assembly mechanism 5. The positioning device 101 is fixedly installed on the upper end surface of the table 1001. The positioning device 101 includes a first cylinder 102 and an insertion rod 103. The first cylinder 102 can drive the insertion rod 103 to extend and retract up and down. The insertion rod 103 can be inserted into a positioning slot 731 of the rotating member 73 away from the center side of the first circular plate 11. The positioning slot 731 is in the shape of a cross, and the positioning slot 731 passes through the circumferential side wall of the rotating member 73. When the pipe joint 201 on the clamp 72 is assembled, the first cylinder 102 drives the insertion rod 103 to rise and insert it into the positioning slot 731 to lock the rotation direction of the rotating member 73, further ensuring that the clamp 72 will not rotate and deviate when the pipe joint 201 is assembled, and the assembly process is more stable.
[0038] like Figure 4 , Figure 5 , Figure 6 , Figure 7 , Figure 8 As shown, the clamp 72 includes a clamp seat 721, a first clamp block 722, a second clamp block 723, a rear cover 724, a first transmission rod 725, a second transmission rod 726, a gear 727, and a second spring 728. The clamp seat 721 is provided with a guide groove 7211, along which the first clamp block 722 and the second clamp block 723 can slide. The rear cover 724 is installed on the clamp seat 721, and the first transmission rod 725, the second transmission rod 726, the gear 727, and the second spring 728 are installed between the rear cover 724 and the clamp seat 721. Transmission rod 726, gear 727, second spring 728, gear 727 is rotatably connected to the inside of rear cover 724, first transmission rod 725 and second transmission rod 726 are respectively located at the upper and lower sides of gear 727 and are arranged in parallel, first transmission rod 725 and second transmission rod 726 are both provided with racks corresponding to gear 727, both ends of first transmission rod 725 can penetrate the side wall of rear cover 724, first transmission rod 725 is provided with gear 727, and gear 727 is provided with gear 727. A second spring 728 is sleeved on one end of the transmission rod 725, and the second spring 728 resists the rack of the first transmission rod 725 and a side wall of the rear cover 724. The second transmission rod 726 has the same structure as the first transmission rod 725. The second spring 728 located at the first transmission rod 725 and the second transmission rod 726 provides the first clamping block 722 and the second clamping block 723 with a force to clamp the pipe joint 201 close to each other. When the first transmission rod 725 moves, the rack of the first transmission rod 725 drives the gear 727 to rotate and then drives the second transmission rod 726 to move. The first transmission rod 725 is connected to the first clamping block 722, and the second transmission rod 726 is connected to the second clamping block 723. When the first transmission rod 725 moves, it can drive the second transmission rod 726 to move in the opposite direction, so that the first clamping block 722 and the second clamping block 723 can approach or move away from each other, and the first clamping block 722 and the second clamping block 723 can clamp the pipe joint 201. Figure 5 The push-opening cylinder 8 shown in the figure is provided with a push rod 81, which can be extended and retracted toward the first transmission rod 725. When the push-opening cylinder 8 is started, the push rod 81 can be extended to press against the first transmission rod 725 and push the first transmission rod 725 to move away from the push-opening cylinder 8, and at the same time, the second transmission rod 726 moves toward the direction close to the push-opening cylinder 8. At this time, the first clamping block 722 and the second clamping block 723 are away from each other, and the pipe joint 201 can be placed in or taken out of the clamp 72.
[0039] like Figure 2As shown, the pipe joint 201 is moved to the fixture 72 by the feeding mechanism 2. The feeding mechanism 2 includes a supporting device 21 and a first feeding device 22. The supporting device 21 includes a translation rail 211 and a tray 212 moving along the translation rail 211. The structure of the translation rail 211 moving the tray 212 is the prior art and is not repeated here. The first feeding device 22 is located above the tray 212. The first feeding device 22 includes a first transverse device 221, a first lifting device 222, and a first clamp 223. The first lifting device 222 can move along the first transverse device 221. The first clamping jaw 223 can be lifted and lowered along the first lifting device 222. The first clamping jaw 223 can clamp the pipe joint 201 from the tray 212 and clamp the pipe joint 201 to the clamp 72. The pipe joint 201 is placed in the tray 212. The upper end surface of the tray 212 is provided with a plurality of strip grooves, which are arranged along the length direction of the first transverse movement device 221. When clamping the pipe joint 201, the first clamping jaw 223 first clamps the pipe joint 201 along the length direction of the first transverse movement device 221, and then moves the tray 212 through the translation track 211 to clamp another row of pipe joints 201.
[0040] like Figure 1 , Fig. 9As shown, after the pipe joint 201 is placed on the fixture 72 through the feeding mechanism 2, the fixture 72 holding the pipe joint 201 is moved to the corresponding position of the plastic ring assembly mechanism 3 by rotating the first circular plate 11. The plastic ring assembly mechanism 3 includes a second feeding device 31, a first pushing device 32, and a first vibration plate 33. A plastic ring 301 is arranged in the plastic ring assembly mechanism 3. The plastic ring 301 is located in the first vibration plate 33. The first vibration plate 33 transports the plastic ring 301 to the upper end surface of the first pushing device 32. The first pushing device 32 The upper end of the first discharge plate 321 is provided with a first discharge groove 3211, and the upper end surface of the first discharge plate 321 is provided with a first discharge groove 3211. The first vibration plate 33 delivers the plastic ring 301 to the first discharge groove 3211 through the first discharge port 331. The side of the first discharge plate 321 is provided with a first push block 322. The first push block 322 is pushed by the cylinder to push one plastic ring 301 out of the first discharge groove 3211 each time. The end of the first discharge plate 321 away from the first push block 322 is provided with a stop block 3212. The stop block 3212 can The second feeding device 31 is located above the first pushing device 32, and the second feeding device 31 includes a second transverse moving device 311, a second lifting device 312, and a second clamping jaw 313. The second lifting device 312 can move along the second transverse moving device 311, and the second clamping jaw 313 can be lifted and lowered along the second lifting device 312. The second clamping jaw 313 can clamp the plastic ring 301 from the first pushing device 32 and clamp the plastic ring 301 to the fixture 72. The second clamping jaw 313 clamps the plastic ring 301 and moves it to the top of the pipe joint 201, and the plastic ring 301 is pressed down by the second lifting device 312 to be sleeved on the pipe end 2011. The pipe end 2011 facing the second lifting device 312 is changed by rotating the clamp 72, and then the plastic ring 301 is sleeved on each pipe end 2011. A supporting cylinder is installed under the first circular plate 11 corresponding to the position of the clamping component 7 of the plastic ring assembly mechanism 3, which can support the first circular plate 11 when the second clamping jaw 313 presses down to install the plastic ring 301.
[0041] like Figure 1 , Fig.10 , Fig.11 , Fig.12 , Fig.13As shown, the rubber ring assembly mechanism 4 includes a third loading device 41, a discharging rack 42, and a second vibration plate 43. The rubber ring 401 is located in the second vibration plate 43. The second vibration plate 43 delivers the rubber ring 401 to the discharging rack 42 through the second discharging port 431. The third loading device 41 is located above the discharging rack 42. The third lifting device 412 includes a first picking device 4121 and a second picking device 4122. The third lifting device 412 can move along the third transverse moving device 411. The first picking device 4121 and the second picking device 4122 can be lifted up and down. The discharging rack 42 includes a receiving seat 42 1 and a spreading seat 422, the receiving seat 421 is provided with a cross-shaped first slot 4211, and the upper end surface of the receiving seat 421 is provided with a slot capable of accommodating a rubber ring 401, and the lower end of the first material taking device 4121 is provided with a cross-shaped plug plate 41211 corresponding to the first slot 4211, and the plug plate 41211 can be inserted into the first slot 4211 by the lifting of the third lifting device 412, so that the rubber ring 401 is spread open by the plug plate 41211 and fixed on the plug plate 41211, and the lower end edge of the plug plate 41211 is provided with a chamfer to facilitate the spread of the rubber ring 401 when it contacts the plug plate 41211.
[0042] The first material taking device 4121 sends the rubber ring 401 at the material receiving seat 421 to the top of the expansion seat 422. The expansion seat 422 includes a guide sleeve 4221, a socket 4222, and a first spring 4223. The socket 4222 is a cone with a diameter gradually decreasing upward. The socket 4222 is provided with a second slot 42221 opening toward the top. The second slot 42221 corresponds to the plug plate 41211 for the plug plate 41211 to be inserted. When the plug plate 41211 with the rubber ring 401 is inserted downward into the second slot 42221, the rubber ring 401 is blocked by the step limit at the upper end of the plug plate 41211, and then the rubber ring 401 is expanded by the socket 4222 and detached from the plug plate 41211 to fix the maximum diameter of the socket 4222.
[0043] The second material taking device 4122 includes a sleeve 41221, a push plate 41222, and a second cylinder 41223. The sleeve 41221 is located at the lower end of the second material taking device 4122. The second cylinder 41223 is located above the sleeve 41221. The push plate 41222 is driven by the second cylinder 41223. The sleeve 41221 passes through the push plate 41222. When the second cylinder 41223 is extended, the push plate 41222 is located in the sleeve 41221. When the second cylinder 41223 is retracted, the push plate 41222 is located at the lower end of the sleeve 41221, the first spring 4223 is installed on the guide sleeve 4221, at least a part of the socket 4222 is located in the guide sleeve 4221, the upper end of the first spring 4223 abuts against the lower end of the socket 4222, and the socket 4222 can slide up and down along the guide sleeve 4221. When the second material taking device 4122 is located above the support seat 422, The second material taking device 4122 descends to make the sleeve 41221 cover and press the socket 4222 downwards. As the socket 4222 retracts the guide sleeve 4221, the rubber ring 401 on the socket 4222 is covered on the sleeve 41221. The second material taking device 4122 completes the material taking work. The rubber ring 401 opened at the opening seat 422 is sent to the top of the clamp 72 by the second material taking device 4122. The second material taking device 4122 descends to make the sleeve 41221 cover and press the socket 4222 downwards. The tube 41221 is sleeved at the corresponding height position of the connecting pipe end 2011, and the second cylinder 41223 is retracted to make the push plate 41222 push the rubber ring 401 on the sleeve 41221 downward, so that the rubber ring 401 is pushed downward out of the range of the sleeve 41221 and then sleeved on the connecting pipe end 2011, and the connecting pipe end 2011 facing the second material taking device 4122 is changed by rotating the clamp 72, so that the rubber ring 401 is sleeved on each connecting pipe end 2011.
[0044] The spacing between the receiving seat 421 and the spreading seat 422 is the same as the spacing between the first material picking device 4121 and the second material picking device 4122. While the first material picking device 4121 sends the rubber ring 401 at the receiving seat 421 to the spreading seat 422, the second material picking device 4122 sends the rubber ring 401 at the spreading seat 422 to the clamp 72. Spreading the rubber ring 401 and assembling the rubber ring 401 are performed simultaneously. The rubber ring assembling mechanism 4 has higher working efficiency and more reasonable assembly.
[0045] like Figure 1 , Figure 3As described, two rubber rings 401 are installed on the pipe end 2011, and the two rubber rings 401 are distributed along the length direction of the pipe end 2011. The number of rubber ring assembly mechanisms 4 is correspondingly provided with two, and the height positions of the two rubber rings 401 installed on the pipe end 2011 are different, so the height positions of the third loading devices 41 and the discharging racks 42 of the two rubber ring assembly mechanisms 4 are also correspondingly different. The rotation directions of the two clamps 72 corresponding to the two rubber ring assembly mechanisms 4 are opposite. For example, the pipe joint 201 in this embodiment is provided with three pipe ends 2011. When the first rubber ring 401 is installed, the clamp 72 needs to be rotated clockwise twice to install the rubber rings 401 at the same height of the three pipe ends 2011. When the second rubber ring 401 is installed, the clamp 72 needs to be rotated counterclockwise twice.
[0046] like Figure 1 , Fig.14 As shown, the structure of the steel ring assembly mechanism 5 is similar to that of the plastic ring assembly mechanism 3. The steel ring assembly mechanism 5 includes a fourth feeding device 51, a second pushing device 52, and a third vibration plate 53. The steel ring 501 is located in the third vibration plate 53. The third vibration plate 53 transports the steel ring 501 to the upper end surface of the second pushing device 52. The upper end of the second pushing device 52 is provided with a second discharge plate 521. The upper end surface of the second discharge plate 521 is provided with a second discharge trough 5211. The third vibration plate 53 is provided with a second discharge plate 521. The plate 53 delivers the steel ring 501 to the second discharge trough 5211 through the third discharge port 531. A second push block 522 is provided on the side of the second discharge plate 521. The second push block 522 is pushed by a cylinder to push one steel ring 501 out of the second discharge trough 5211 each time. A stopper is provided at one end of the second discharge plate 521 away from the second push block 522. The stopper can limit the steel ring 501 pushed out by the second push block 522. The fourth feeding device 51 is located at Above the second pushing device 52, the fourth loading device 51 includes a fourth transverse moving device 511, a fourth lifting device 512, and a third clamping jaw 513. The fourth lifting device 512 can move along the fourth transverse moving device 511, and the third clamping jaw 513 can be lifted and lowered along the fourth lifting device 512. The third clamping jaw 513 can clamp the steel ring 501 from the second pushing device 52 and clamp the steel ring 501 to the clamp 72. The third clamping jaw 513 clamps the steel ring 501 and moves it to the top of the pipe joint 201, and the steel ring 501 is pressed down by the fourth lifting device 512 to be sleeved on the pipe end 2011. The clamp 72 is rotated to change the pipe end 2011 facing the fourth lifting device 512, and then the steel ring 501 is sleeved on each pipe end 2011. A supporting cylinder is installed under the first circular plate 11 corresponding to the position of the clamping assembly 7 of the steel ring assembly mechanism 5, which can support the first circular plate 11 when the second clamping jaw 313 presses down to install the steel ring 501.
[0047] like Figure 1 , Fig.15As shown, the material picking mechanism 6 includes a material discharge device 61 and a material discharge hopper 62. The material discharge device 61 includes a fifth transverse moving device 611, a fifth lifting device 612, and a fourth clamping jaw 613. The fifth lifting device 612 can move along the fifth transverse moving device 611, and the fourth clamping jaw 613 can be lifted and lowered along the fifth lifting device 612. When the fourth clamping jaw 613 clamps the pipe joint 201 on the fixture 72, the top opening cylinder 8 located in the material picking mechanism 6 extends to loosen the fixture 72 so that the pipe joint 201 can be removed from the fixture 72. The material discharge device 61 can take the assembled pipe joint 201 from the fixture 72 and send it to the material discharge hopper 62. The assembled pipe joint 201 is removed from the fixture 72 by the material discharge device 61 and placed in the material discharge hopper 62 to complete the material discharge.
[0048] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. An automatic assembly device for pipe joints, characterized in that: The invention comprises a rotating disk (1), wherein the rotating disk (1) comprises a first rotatable circular plate (11), wherein a plurality of clamping assemblies (7) are arranged in the circumferential direction of the first circular plate (11), wherein the clamping assemblies (7) comprise a rotatable clamp (72), wherein the clamp (72) can clamp a pipe joint (201), wherein the pipe joint (201) comprises a plurality of pipe ends (2011) facing in different directions, wherein a feeding mechanism (2), a plastic ring assembly mechanism (3), a rubber ring assembly mechanism (4), a steel ring assembly mechanism (5), and a material taking mechanism (6) are arranged along the rotation direction of the first circular plate (11), wherein the pipe joint (201) is fed into the rotating disk through the feeding mechanism (2) and the plastic ring assembly mechanism (3), a rubber ring assembly mechanism (4), a steel ring assembly mechanism (5), and a material taking mechanism (6) 01) is moved to the clamp (72), the plastic ring assembly mechanism (3) and the clamp (72) are rotated to sleeve the plastic ring (301) on each of the pipe ends (2011), the rubber ring assembly mechanism (4) and the clamp (72) are rotated to sleeve the rubber ring (401) on each of the pipe ends (2011), the steel ring assembly mechanism (5) and the clamp (72) are rotated to sleeve the steel ring (501) on each of the pipe ends (2011), and the assembled pipe joint (201) can be removed from the clamp (72) by the material removal mechanism (6).
2. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The feeding mechanism (2) comprises a supporting device (21) and a first feeding device (22); the supporting device (21) comprises a translation track (211) and a tray (212) that moves along the translation track (211); the pipe joint (201) is placed in the tray (212); the first feeding device (22) is located above the tray (212); the first feeding device (22) comprises a first transverse device (221), a first lifting device (222), and a first clamp (223); the first lifting device (222) can move along the first transverse device (221); the first clamp (223) can be lifted and lowered along the first lifting device (222); the first clamp (223) can clamp the pipe joint (201) from the tray (212) and clamp the pipe joint (201) to the fixture (72).
3. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The turntable (1) comprises a second circular plate (12), the second circular plate (12) is in a fixed state relative to the first circular plate (11), the second circular plate (12) is located at the center of the upper end surface of the first circular plate (11), a plurality of driving components (9) are arranged in the circumferential direction of the second circular plate (12), the driving components (9) comprise a feeding cylinder (91) and a rotating cylinder (92), the feeding cylinder (91) drives the rotating cylinder (92) to approach or move away from the clamping component (7), the rotating cylinder (92) is provided with a rotatable positioning plug (93), the positioning plug (93) ) is consistent with the axial direction of the first circular plate (11), the clamping assembly (7) comprises a base (71) and a rotating member (73), the base (71) is fixedly mounted on the upper end surface of the first circular plate (11), the rotating member (73) is rotatably mounted on the side of the base (71), the rotation center of the rotating member (73) is consistent with the axial direction of the first circular plate (11), the clamp (72) is mounted on the base (71) through the rotating member (73), and the rotating member (73) is provided with a positioning slot (731) corresponding to the positioning plug (93).
4. The automatic pipe joint assembly equipment according to claim 3, characterized in that: The invention comprises a positioning device (101), wherein the positioning device (101) is distributed along the rotation direction of the first circular plate (11), the positioning device (101) comprises a first cylinder (102) and an insertion rod (103), the first cylinder (102) can drive the insertion rod (103) to extend and retract up and down, the number of the rotating members (73) is two, the base (71) is provided with a seat groove (711), the two rotating members (73) are respectively located on both sides of the seat groove (711), and the insertion rod (103) can be inserted into the positioning slot (731) away from the center of the first circular plate (11).
5. The automatic pipe joint assembly equipment according to claim 3, characterized in that: The clamp (72) comprises a first clamp block (722), a second clamp block (723), a first transmission rod (725), and a second transmission rod (726); the first clamp block (722) and the second clamp block (723) can move closer to or farther from each other; the first clamp block (722) and the second clamp block (723) can clamp the pipe joint (201); the first transmission rod (725) is connected to the first clamp block (722); the second transmission rod (726) is connected to the second clamp block (723); the first transmission rod (725) can simultaneously drive the second transmission rod (726) to move in the opposite direction; the second circular plate (12) is installed with a push-opening cylinder (8); the push-opening cylinder (8) is provided with a push rod (81); the push rod (81) can be extended and retracted toward the first transmission rod (725).
6. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The invention comprises a second feeding device (31), a first pushing device (32), and a first vibration plate (33); the plastic ring (301) is arranged in the first vibration plate (33); the first vibration plate (33) conveys the plastic ring (301) to the upper end surface of the first pushing device (32); the second feeding device (31) is located above the first pushing device (32); the second feeding device (31) comprises a second transverse moving device (311), a second lifting device (312), and a second clamping jaw (313); the second lifting device (312) can move along the second transverse moving device (311); the second clamping jaw (313) can be lifted and lowered along the second lifting device (312); the second clamping jaw (313) can clamp the plastic ring (301) from the first pushing device (32) and clamp the plastic ring (301) to the clamp (72).
7. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The rubber ring assembly mechanism (4) comprises a third feeding device (41), a discharging frame (42), and a second vibration plate (43); the rubber ring (401) is arranged in the second vibration plate (43); the discharging frame (42) comprises a receiving seat (421) and a support seat (422); the second vibration plate (43) delivers the rubber ring (401) to the receiving seat (421); the third feeding device (41) is located above the discharging frame (42); the third feeding device (41) comprises a third transverse moving device (411) and a third lifting device (412); the third lifting device (411) is arranged on the upper side of the discharging frame (42); 12) includes a first material picking device (4121) and a second material picking device (4122), the third lifting device (412) can move along the third transverse moving device (411), the first material picking device (4121) and the second material picking device (4122) can be lifted up and down, the rubber ring (401) at the material receiving seat (421) is sent to the opening seat (422) for opening through the first material picking device (4121), and the rubber ring (401) opened at the opening seat (422) is sent to the clamp (72) through the second material picking device (4122).
8. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The pipe end (2011) is provided with two rubber rings (401), and the two rubber rings (401) are distributed along the length direction of the pipe end (2011). The number of rubber ring assembly mechanisms (4) is correspondingly two, and the rotation directions of the two clamps (72) corresponding to the two rubber ring assembly mechanisms (4) are opposite.
9. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The steel ring assembly mechanism (5) includes a fourth loading device (51), a second pushing device (52), and a third vibration disk (53). The steel ring (501) is arranged in the third vibration disk (53). The third vibration disk (53) transports the steel ring (501) to the upper end surface of the second pushing device (52). The fourth loading device (51) is located above the second pushing device (52). The fourth loading device (51) includes a fourth transverse movement device (511), a fourth lifting device (512), and a third clamp (513). The fourth lifting device (512) can move along the fourth transverse movement device (511). The third clamp (513) can be lifted and lowered along the fourth lifting device (512). The third clamp (513) can clamp the steel ring (501) from the second pushing device (52) and clamp the steel ring (501) to the clamp (72).
10. The automatic pipe joint assembly equipment according to claim 1, characterized in that: The material taking mechanism (6) includes a material discharge device (61) and a material discharge hopper (62); the material discharge device (61) includes a fifth transverse moving device (611), a fifth lifting device (612), and a fourth clamp (613); the fifth lifting device (612) can move along the fifth transverse moving device (611); the fourth clamp (613) can be lifted and lowered along the fifth lifting device (612); the fourth clamp (613) can take the assembled pipe joint (201) from the fixture (72) and send it to the material discharge hopper (62).
Citation Information
Cited By
Joint assembling equipment
CN120244567A
A joint assembly apparatus
CN120244567B