Liquefied natural gas inlet and outlet terminal of gravity type foundation structure and installation method
By designing a gravity-based infrastructure LNG import and export terminal, using steel skirts, layered structures and prefabricated concrete boxes, combined with airbag floating and big data to control seawater density, the problems of high LNG terminal construction costs and safety risks have been solved. Achieved the construction of a stable, fast and environmentally friendly LNG import and export terminal.
Patent Information
- Application Number
- CN202410992133.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2044-07-23
AI Technical Summary
The existing reclamation or long-distance trestle layout of LNG terminals has problems such as high investment costs, difficult construction and large environmental impact, and it is impossible to effectively avoid safety risks in LNG storage and transportation.
The LNG import and export terminal adopts a gravity-based basic structure, including steel skirt, layered structure, box design divided by partition walls, thermal insulation insulation materials between LNG storage tanks and concrete, as well as pre-embedded heating cables and temperature control systems. Combining prefabricated reinforced concrete boxes and on-site settlement installation methods, an air bag system is used for structural floating and installation, and seawater density is controlled through big data and graph neural networks to ensure structural stability.
It reduces the risks in the LNG storage and transportation process, reduces construction costs and construction time, improves the stability and durability of the structure, avoids high requirements for the foundation, and provides a safe and convenient loading, unloading and storage environment for LNG import and export. .
Smart Images

Figure CN118746104A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of infrastructure, and in particular to a gravity-type infrastructure liquefied natural gas import and export terminal and an installation method thereof. Background Art
[0002] Liquefied natural gas (LNG), whose main component is methane, is recognized as the cleanest fossil energy on earth.
[0003] Since LNG has certain safety risks in the storage and transportation process, in order to avoid safety risks, LNG terminals generally use land reclamation or long-distance piers to keep berths away from densely populated areas. Both of these arrangements have high investment costs, difficult construction, and adverse effects on environmental protection. With the increase in domestic LNG demand, the saturation of terminal shoreline resources, and the difficulty of approving land reclamation projects due to environmental protection requirements, offshore LNG import and export terminals will play a greater role in energy import and export.
[0004] The concrete gravity-based structure (GBS) has high bearing capacity, good durability and fire resistance, and is particularly suitable for the foundation structure of large offshore engineering platforms. The structure can be produced by factory prefabrication and placed offshore, which can avoid the problems of traditional LNG terminals, such as high investment costs, difficult construction, and proximity to densely populated areas. The structure has space for storing LNG and can carry various equipment with large footprints and complex structures on the upper part, which can provide a good operating environment for LNG imports and exports, carry out LNG loading and unloading and storage operations away from densely populated areas, and expand the use functions of LNG import and export terminals. Based on the existing engineering technology reserves, the research and development of concrete gravity-based structures can be completed. Summary of the invention
[0005] The present invention overcomes the shortcomings of the prior art and provides a gravity-based structure liquefied natural gas import and export terminal and an installation method.
[0006] To achieve the above object, the technical solution adopted by the present invention is:
[0007] The first aspect of the present invention provides a gravity-based liquefied natural gas import and export terminal, comprising:
[0008] The bottom of the inlet and outlet terminals is provided with a steel skirt along the periphery and in the horizontal direction, and a bottom plate, a tank plate and a top plate are provided in the horizontal direction;
[0009] The import and export terminal is divided into two layers, and a partition wall is set between the bottom plate and the tank plate to divide it into several cabins. The middle space between the tank plate and the top plate is used to install the LNG storage tank, which is divided into several ballast tanks and equipment cabins by partition walls around the LNG storage tank, finally forming a box structure.
[0010] Furthermore, in the gravity-based liquefied natural gas import and export terminal, the top plate on the upper part of the import and export terminal carries at least the berthing equipment, loading and unloading equipment and personnel activity building of the LNG receiving station.
[0011] Furthermore, in the gravity-based liquefied natural gas import and export terminal, an opening is provided on the top plate of the import and export terminal to allow the upper equipment to be connected to the LNG storage tank and the equipment cabin.
[0012] Furthermore, in the gravity-based liquefied natural gas import and export terminal, several layers of materials having functions of isolating water vapor and maintaining heat are arranged between the LNG storage tank and the concrete.
[0013] Furthermore, in the gravity-based liquefied natural gas import and export terminal, a heating cable and a temperature control system are pre-buried in the concrete, and the temperature of the concrete is controlled within a preset range by the temperature control system.
[0014] Furthermore, in the gravity-based liquefied natural gas import and export terminal, before the base plate is constructed, an air bag and its inflation pipe are embedded at the bottom of the base plate, and an interface is reserved at the top of the air bag, which is connected to the inflation pipe inside the base plate. The air bag is used to inflate during shipment, fill the space between the base plate and the steel skirt, and then lift the GBS.
[0015] Furthermore, a second aspect of the present invention provides a method for installing a gravity-based liquefied natural gas import / export terminal, which is applied to any of the gravity-based liquefied natural gas import / export terminals described above, and comprises the following steps:
[0016] Step 1: Build a dry land prefabrication site near the sea, calculate the buoyancy required for GBS floating to determine the bottom elevation of the prefabrication site, and build a dock gate at the prefabrication site that is connected to the sea and allows tugboats to tow the GBS structure; the GBS is a gravity-based liquefied natural gas import and export terminal;
[0017] Step 2: Level the site and lay the steel bottom formwork. The steel bottom formwork reserves space for the GBS steel skirt to be embedded so that the GBS concrete is in direct contact with the steel formwork;
[0018] Step 3: Install the steel skirt, build the GBS bottom plate, ballast tank and tank plate, and arrange the airbag inflation system and ballast water system in the bottom plate;
[0019] Step 4: Construct the ballast tank, equipment tank, water tank, tank tank and top plate on three sides of the GBS, and reserve one side as the installation channel for the LNG tank;
[0020] Step 5: Install the LNG storage tank horizontally into the GBS through the installation channel reserved on the side;
[0021] Step 6: Construct water storage tanks, fire fighting compartments, equipment compartments and top plates with reserved passages, complete the structural construction, and install the superstructure.
[0022] Furthermore, in the installation method of the gravity-based liquefied natural gas import and export terminal, the following steps are also included:
[0023] Step 7: Inject ballast water into the structural ballast tanks to keep the structure at a certain deadweight and prevent the structure from floating in the prefabrication yard during the dock filling period;
[0024] Step 8: Open the dock door and inject seawater into the prefabricated dock until the water level in the dock is consistent with the sea level;
[0025] Step 9: Empty the ballast water, activate the air bag system at the bottom of the structure, and slowly lift the structure up;
[0026] Step 10: Start the winch to tow the structure from the dock to the sea surface and connect it to the tugboat;
[0027] Step 11: Re-inject ballast water into the structure to balance it and maintain balance during towing at sea;
[0028] Step 11: After the GBS is towed to the installation site, it is positioned by GPS and other means to maintain the designed installation accuracy and tilt limit. After the ballast water is injected and it sinks to the seabed, other ballast materials are quickly injected to enable the structure to resist wind and waves. At the same time, the air in the airbag is completely pumped out to form negative pressure under the bottom plate, which accelerates the foundation consolidation speed and completes the installation construction.
[0029] Furthermore, in the installation method of the gravity-based liquefied natural gas import and export terminal, the following steps are also included:
[0030] Obtain seawater density data information under different environmental characteristics through big data, introduce a graph neural network, input the seawater density data information under different environmental characteristics into the graph neural network, and use the environmental characteristics as the first graph node;
[0031] Using the seawater density data as a second graph node, constructing an undirected edge description relationship, connecting the first graph node and the second graph node according to the undirected edge description relationship, and generating a related topological structure graph;
[0032] Acquiring a relevant adjacency matrix according to the relevant topological structure diagram, constructing a seawater density knowledge graph, and inputting the relevant adjacency matrix into the seawater density knowledge graph for storage;
[0033] The environmental characteristics of the tugboat in the target sea area are obtained, the environmental characteristics of the target sea area are input into the seawater density knowledge graph for data matching, the seawater density data in the target sea area is obtained, and the input amount of ballast water is regulated based on the seawater density data in the target sea area.
[0034] The input amount of ballast water is regulated based on the seawater density data in the target sea area, specifically including:
[0035] Calculating the buoyancy information of the gravity-based liquefied natural gas import and export terminal in the sea area according to the seawater density data in the target sea area, and obtaining the ballast water volume information currently injected into the gravity-based liquefied natural gas import and export terminal;
[0036] Calculating the quality information of the ballast water according to the amount of ballast water injected into the current gravity-based liquefied natural gas import and export terminal, and obtaining the quality information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected;
[0037] Calculate the total mass information according to the mass information of the ballast water and the mass information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected, and calculate the deviation rate between the total mass information and the buoyancy information;
[0038] When the deviation rate is greater than a preset deviation rate threshold, the information on the amount of ballast water injected into the gravity-based liquefied natural gas import and export terminal is adjusted until the deviation rate is no greater than the preset deviation rate threshold.
[0039] The present invention solves the defects existing in the background technology and has the following beneficial effects:
[0040] The installation location of the present invention is far away from densely populated areas, reducing the risks in the LNG storage and transportation process; the present invention designs a double-layer concrete structure and fills it with ballast to reduce the risk of damage to the LNG storage tank when a ship collides with the structure, and by arranging the LNG storage tank inside the structure, the weight of the LNG storage tank is used to increase the stability of the structure. On the one hand, the installation location of the present invention is located in the offshore area with good water depth conditions, which is convenient for large LNG ships to operate, and the structure adopts a prefabricated reinforced concrete box form and an on-site settlement installation construction method, with low construction cost, fast construction speed, good durability and good fire resistance. Finally, the structure has a large projected area and is provided with an anti-slip steel skirt, which reduces the structure's requirements on the foundation and provides sufficient space for ship berthing, LNG loading and unloading operations, and production and life of personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.
[0042] Figure 1 A schematic diagram of the structural layering is shown;
[0043] Figure 2 The bottom steel skirt arrangement diagram is shown;
[0044] Figure 3 shows a first schematic diagram during installation;
[0045] Figure 4 shows a second schematic diagram during installation;
[0046] Figure 5 shows a third schematic diagram during installation;
[0047] Figure 6 A fourth schematic diagram showing the installation process;
[0048] Figure 7 A fifth schematic diagram showing the installation process;
[0049] Figure 8 shows a sixth schematic diagram during installation;
[0050] Fig. 9 A seventh schematic diagram showing the installation process;
[0051] Fig.10 An eighth schematic diagram showing the installation process;
[0052] Fig.11 A ninth schematic diagram showing the installation process;
[0053] Fig.12 A tenth schematic diagram showing the installation process;
[0054] Fig.13 An eleventh schematic diagram showing the installation process;
[0055] Fig.14 A twelfth schematic diagram is shown during installation.
[0056] In the figure:
[0057] 1. Bottom plate, 2. Tank plate, 3. Top plate, 4. Ballast tank, 5. Steel skirt, 6. Fire compartment, 7. Equipment compartment, 8. LNG tank compartment. DETAILED DESCRIPTION
[0058] In order to more clearly understand the above-mentioned purposes, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. These drawings are all simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the structures related to the present invention. It should be noted that the embodiments in this application and the features in the embodiments can be combined with each other without conflict.
[0059] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the scope of protection of the present application. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, features defined as "first", "second", etc. may explicitly or implicitly include one or more of the features. In the description of the invention, unless otherwise specified, "multiple" means two or more.
[0060] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood by specific circumstances.
[0061] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. The preferred embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly understood.
[0062] The present invention is a reinforced concrete gravity foundation structure used in offshore LNG import and export terminals. The overall structure is a box-shaped structure with rounded rectangles in top view. A steel skirt 5 with a height of 1m and a thickness of 6cm is set along the perimeter and horizontal direction of the bottom, and is embedded in the soil after installation to increase the anti-slip ability of the structure; the box body is composed of a bottom plate 1, a tank plate 2 and a top plate 3 in the horizontal direction, and the box body space is divided into two layers; longitudinal and transverse partition walls are set between the bottom plate and the tank plate for the ballast layer, which is divided into a plurality of compartments with different functions, such as ballast tanks 4, fresh water tanks, fire fighting compartments 6, etc., to enhance the rigidity of the structure; the middle space of the LNG storage tank compartment 8 between the tank plate and the top plate is used to install LNG storage tanks, and is divided into a plurality of equipment compartments 7 by a plurality of longitudinal and transverse partition walls around the LNG storage tanks; the top plate on the upper part of the box body carries the berthing equipment, loading and unloading equipment, personnel activity buildings and other facilities of the LNG receiving station, and an opening is set on the top plate for the upper equipment to connect with the LNG storage tanks and the equipment compartment. The structural layering schematic diagram and the steel skirt layout diagram are shown in the figure Figure 1 as well as Figure 2 shown.
[0063] Among them, further, the second aspect of the present invention provides a method for installing a gravity-based liquefied natural gas import and export terminal, which is applied to any of the gravity-based liquefied natural gas import and export terminals described above, and comprises the following steps:
[0064] Step 1: Build a dry land prefabrication site near the sea, calculate the buoyancy required for GBS floating to determine the bottom elevation of the prefabrication site, and build a dock gate at the prefabrication site that is connected to the sea and allows tugboats to tow the GBS structure; the GBS is a gravity-based liquefied natural gas import and export terminal;
[0065] Step 2: Level the site and lay the steel bottom formwork. The steel bottom formwork reserves space for the GBS steel skirt to be embedded so that the GBS concrete is in direct contact with the steel formwork;
[0066] It should be noted that the present invention designs a double-layer concrete structure and fills it with ballast to reduce the risk of damage to the LNG storage tank when a ship collides with the structure. By arranging the LNG storage tank inside the structure, the weight of the LNG storage tank is used to increase the stability of the structure.
[0067] Step 3: Install the steel skirt, build the GBS bottom plate, ballast tank and tank plate, and arrange the airbag inflation system and ballast water system in the bottom plate;
[0068] Step 4: Construct the ballast tank, equipment tank, water tank, tank tank and top plate on three sides of the GBS, and reserve one side as the installation channel for the LNG tank;
[0069] In steps 1 to 4, the construction process is as follows Figures 3 to 4As shown, before the base plate is constructed, an air bag and its inflation pipe are embedded at the bottom of the base plate. An interface is reserved at the top of the air bag to connect with the inflation pipe inside the base plate. The air bag is used to inflate during shipment, fill the space between the base plate and the steel skirt, and then lift the GBS.
[0070] Step 5: Install the LNG storage tank horizontally into the GBS through the installation channel reserved on the side;
[0071] During the construction process, Figure 5 to Figure 6 It should be noted that, on the one hand, the installation location of the present invention is located in the offshore area, the water depth condition is good, which is convenient for large LNG ship operations, and the structure adopts the prefabricated reinforced concrete box form and the on-site settlement installation construction method, which has low construction cost, fast construction speed, good durability and fire resistance, and finally the structure has a large projected area, and an anti-slip steel skirt is set, which reduces the requirements of the structure on the foundation, and provides sufficient space for ship berthing, LNG loading and unloading operations, and production and life of personnel.
[0072] Step 6: Build the water storage tank, fire fighting tank, equipment compartment and top plate with reserved passages, complete the structural construction, and install the superstructure. Step 6 construction process, such as Figure 7 by Figure 8 shown.
[0073] Among them, the LNG temperature is about -162℃, and multiple layers of insulation materials need to be installed between the storage tank and the concrete to prevent the low temperature from being transmitted to the concrete to form temperature stress and cause concrete cracking. During the design process of the GBS structure, a detailed heat conduction analysis is required to consider the steady-state and transient temperature distribution conditions and evaluate the impact of the low temperature of the LNG storage tank on the concrete structure. If necessary, heating cables and temperature control systems can be embedded in the concrete to keep the concrete temperature between +2℃ and +8℃, while maintaining an appropriate temperature gradient in the structure, avoiding freeze-thaw cycles and temperature stress from having adverse effects on the concrete structure.
[0074] Furthermore, in the installation method of the gravity-based liquefied natural gas import and export terminal, the following steps are also included:
[0075] Step 7: Fig. 9 As shown, ballast water is injected into the structural ballast tank to keep the structure at a certain deadweight and prevent the structure from floating in the prefabrication yard during the dock filling period;
[0076] Step 8: Fig.10 As shown, the dock door is opened and seawater is injected into the prefabricated dock until the water level in the dock is consistent with the sea level;
[0077] Step 9: Fig.11 As shown, the ballast water is emptied, the air bag system at the bottom of the structure is activated, and the structure is slowly lifted up;
[0078] Step 10: Fig.12 As shown, the winch is started to tow the structure from the dock to the sea surface and connect it to the tugboat;
[0079] Step 11: Fig.13 As shown, ballast water is re-injected into the structure for counterweighting to maintain the balance of marine towing transportation; the buoyancy information can be calculated according to the seawater density characteristics in different sea areas, so as to calculate the weight of the water to be injected, and the structure can be automatically adjusted according to the seawater density characteristics in different sea areas to achieve the balance of marine towing transportation. The seawater density change characteristics in the sea area can also be estimated through different temperature environments and salinity environments, so as to further determine the density of the seawater in the sea area.
[0080] Step 11: Fig.14 As shown in the figure, after the GBS is towed to the installation site, it is positioned by GPS and other means to maintain the designed installation accuracy and tilt limit. After it is injected with ballast water and sinks to the seabed, other ballast is quickly injected to enable the structure to resist wind and waves. At the same time, the air in the airbag is completely pumped out to form negative pressure under the bottom plate, which speeds up the foundation consolidation and completes the installation construction.
[0081] Furthermore, in the installation method of the gravity-based liquefied natural gas import and export terminal, the following steps are also included:
[0082] Obtain seawater density data information under different environmental characteristics through big data, introduce a graph neural network, input the seawater density data information under different environmental characteristics into the graph neural network, and use the environmental characteristics as the first graph node;
[0083] Using the seawater density data as a second graph node, constructing an undirected edge description relationship, connecting the first graph node and the second graph node according to the undirected edge description relationship, and generating a related topological structure graph;
[0084] Acquiring a relevant adjacency matrix according to the relevant topological structure diagram, constructing a seawater density knowledge graph, and inputting the relevant adjacency matrix into the seawater density knowledge graph for storage;
[0085] The environmental characteristics of the tugboat in the target sea area are obtained, the environmental characteristics of the target sea area are input into the seawater density knowledge graph for data matching, the seawater density data in the target sea area is obtained, and the input amount of ballast water is regulated based on the seawater density data in the target sea area.
[0086] It should be noted that environmental characteristics include data such as seawater temperature and salinity. This method can be used to estimate the density of seawater under different environmental characteristics, thereby improving the stability of the tugboat when towing the import and export terminals and maintaining the balance of transportation.
[0087] The input amount of ballast water is regulated based on the seawater density data in the target sea area, specifically including:
[0088] Calculating the buoyancy information of the gravity-based liquefied natural gas import and export terminal in the sea area according to the seawater density data in the target sea area, and obtaining the ballast water volume information currently injected into the gravity-based liquefied natural gas import and export terminal;
[0089] Calculating the quality information of the ballast water according to the amount information of the ballast water injected into the current gravity-based liquefied natural gas import and export terminal, and obtaining the quality information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected;
[0090] Calculate the total mass information according to the mass information of the ballast water and the mass information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected, and calculate the deviation rate between the total mass information and the buoyancy information;
[0091] When the deviation rate is greater than a preset deviation rate threshold, the ballast water volume information injected into the gravity-based liquefied natural gas import and export terminal is adjusted until the deviation rate is no greater than the preset deviation rate threshold.
[0092] It should be noted that this method can improve the stability of the tugboat when towing the import and export terminals, maintain the balance of transportation, and control the input or output ballast water volume.
[0093] To sum up, the installation location of the present invention is far away from the population gathering area, which reduces the risk of LNG storage and transportation process; the present invention designs a double-layer concrete structure and fills it with ballast to reduce the risk of LNG storage tanks being damaged when a ship collides with the structure, and by arranging the LNG storage tanks inside the structure, the weight of the LNG storage tanks is used to increase the stability of the structure. On the one hand, the installation location of the present invention is located in the offshore area with good water depth conditions, which is convenient for large LNG ships to operate, and the structure adopts a prefabricated reinforced concrete box form and an on-site settlement installation construction method, with low construction cost, fast construction speed, good durability and good fire resistance. Finally, the structure has a large projected area and is provided with an anti-slip steel skirt, which reduces the structure's requirements on the foundation and provides sufficient space for ship berthing, LNG loading and unloading operations, and production and life of personnel.
[0094] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
[0095] The above is based on the ideal embodiment of the present invention. Through the above description, relevant personnel can make various changes and modifications without departing from the technical concept of the present invention. The technical scope of the present invention is not limited to the content in the specification, and the technology must be determined according to the scope of the claims.
Claims
1. A gravity-based liquefied natural gas import and export terminal, characterized in that: include: The bottom of the inlet and outlet terminals is provided with a steel skirt along the periphery and in the horizontal direction, and a bottom plate, a tank plate and a top plate are provided in the horizontal direction; The import and export terminal is divided into two layers, and a partition wall is set between the bottom plate and the tank plate to divide it into several cabins. The middle space between the tank plate and the top plate is used to install the LNG storage tank, which is divided into several ballast tanks and equipment cabins by partition walls around the LNG storage tank, finally forming a box structure.
2. A gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: The top plate above the import and export terminal carries at least the berthing equipment, loading and unloading equipment and personnel activity buildings of the LNG receiving station.
3. A gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: An opening is provided on the top plate of the import / export terminal to allow the upper equipment to be connected to the LNG storage tank and the equipment cabin.
4. A gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: Several layers of water vapor isolation and heat insulation materials are arranged between the LNG storage tank and the concrete.
5. The gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: A heating cable and a temperature control system are pre-buried in the concrete, and the temperature of the concrete is controlled within a preset range by the temperature control system.
6. A gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: Before the base plate is built, the airbag and its inflation pipe are embedded at the bottom of the base plate, and the airbag has a reserved interface on the top to connect with the inflation pipe inside the base plate. The airbag is used to inflate during shipment, fill the space between the base plate and the steel skirt, and then lift the GBS.
7. The method for installing a gravity-based liquefied natural gas import and export terminal according to claim 1, characterized in that: The gravity-based liquefied natural gas import and export terminal according to any one of claims 1 to 6 comprises the following steps: Step 1: Build a dry land prefabrication site near the sea, calculate the buoyancy required for GBS floating to determine the bottom elevation of the prefabrication site, and build a dock gate at the prefabrication site that is connected to the sea and allows tugboats to tow the GBS structure; the GBS is a gravity-based liquefied natural gas import and export terminal; Step 2: Level the site and lay the steel bottom formwork. The steel bottom formwork reserves space for the GBS steel skirt to be embedded so that the GBS concrete is in direct contact with the steel formwork; Step 3: Install the steel skirt, build the GBS bottom plate, ballast tank and tank plate, and arrange the airbag inflation system and ballast water system in the bottom plate; Step 4: Construct the ballast tank, equipment tank, water tank, tank tank and top plate on three sides of the GBS, and reserve one side as the installation channel for the LNG tank; Step 5: Install the LNG storage tank horizontally into the GBS through the installation channel reserved on the side; Step 6: Construct water storage tanks, fire fighting compartments, equipment compartments and top plates with reserved passages, complete the structural construction, and install the superstructure.
8. The method for installing a gravity-based liquefied natural gas import and export terminal according to claim 7, characterized in that: The following steps are also included: Step 7: Inject ballast water into the structural ballast tanks to keep the structure at a certain deadweight and prevent the structure from floating in the prefabrication yard during the dock filling period; Step 8: Open the dock door and inject seawater into the prefabricated dock until the water level in the dock is consistent with the sea level; Step 9: Empty the ballast water, activate the air bag system at the bottom of the structure, and slowly lift the structure up; Step 10: Start the winch to tow the structure from the dock to the sea surface and connect it to the tugboat; Step 11: Re-inject ballast water into the structure to balance it and maintain balance during towing at sea; Step 11: After the GBS is towed to the installation site, it is positioned by GPS and other means to maintain the designed installation accuracy and tilt limit. After the ballast water is injected and it sinks to the seabed, other ballast materials are quickly injected to enable the structure to resist wind and waves. At the same time, the air in the airbag is completely pumped out to form negative pressure under the bottom plate, which accelerates the foundation consolidation speed and completes the installation construction.
9. The method for installing a gravity-based liquefied natural gas import and export terminal according to claim 7, characterized in that: The following steps are also included: Obtain seawater density data information under different environmental characteristics through big data, introduce a graph neural network, input the seawater density data information under different environmental characteristics into the graph neural network, and use the environmental characteristics as the first graph node; Using the seawater density data as a second graph node, constructing an undirected edge description relationship, connecting the first graph node and the second graph node according to the undirected edge description relationship, and generating a related topological structure graph; Acquire a relevant adjacency matrix according to the relevant topological structure diagram, construct a seawater density knowledge graph, and input the relevant adjacency matrix into the seawater density knowledge graph for storage; The environmental characteristics of the tugboat in the target sea area are obtained, the environmental characteristics of the target sea area are input into the seawater density knowledge graph for data matching, the seawater density data in the target sea area is obtained, and the input amount of ballast water is regulated based on the seawater density data in the target sea area.
10. The method for installing a gravity-based liquefied natural gas import and export terminal according to claim 9, characterized in that: The input amount of ballast water is regulated based on the seawater density data in the target sea area, specifically including: Calculating the buoyancy information of the gravity-based liquefied natural gas import and export terminal in the sea area according to the seawater density data in the target sea area, and obtaining the ballast water volume information currently injected into the gravity-based liquefied natural gas import and export terminal; Calculating the quality information of the ballast water according to the amount information of the ballast water injected into the current gravity-based liquefied natural gas import and export terminal, and obtaining the quality information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected; Calculate the total mass information according to the mass information of the ballast water and the mass information of the current gravity-based liquefied natural gas import and export terminal when no ballast water is injected, and calculate the deviation rate between the total mass information and the buoyancy information; When the deviation rate is greater than a preset deviation rate threshold, the information on the amount of ballast water injected into the gravity-based liquefied natural gas import and export terminal is adjusted until the deviation rate is no greater than the preset deviation rate threshold.
Citation Information
Patent Citations
Gravity type foundation structure and construction method thereof
CN102877482A
Maneuvering bottom resting offshore platform and installation method thereof
CN105178273A
Bottomless air bag method underwater dry operation construction system and method
CN111335177A
Buoy capable of self-ballasting by using seawater and control method of buoy
CN112874698A
Installation method of small starfish type tension leg platform
CN116513404A