Regional limited electric quantity rapid distribution method based on emergency load control plan
Through the combination of emergency load control plan and grid topology data, power supply path tracking technology is used to achieve refined distribution of grid load, solve the problem of rapid control during grid load peaks, and ensure the satisfaction of people's electricity needs and power restriction strategies. optimization.
Patent Information
- Application Number
- CN202410736672.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-10-08
AI Technical Summary
It is difficult for the power grid to quickly and effectively implement emergency load control during load peaks, resulting in the inability to reduce the scope of power outages, and the provincial and prefecture-level regulatory scopes lead to overlapping loads, making it impossible to accurately measure controllable resources in each region, resulting in irrational allocation of control plans.
Through the rapid allocation method of regional power curtailment based on emergency load control plan, using the control cloud resources and power supply path tracking and power supply range search technology to conduct reasonable assessment of regional power curtailment capabilities and resource cleaning and aggregation, combined with power grid topology and real-time data, Classify, monitor and distribute loads to achieve refined cleaning and optimal distribution of loads.
It achieves rapid distribution of power rationing during grid load peaks, reduces the scope of power outages, and ensures people's electricity needs. Through load classification and multi-objective function optimization, the optimal solution to the power rationing strategy is achieved and supports regulatory operations under emergencies.
Smart Images

Figure CN118748408A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power system dispatching and control, and in particular relates to a method for quickly distributing regional power restrictions based on an emergency load control plan. Background Art
[0002] In recent years, affected by the high temperature weather in summer, the power grid has faced the largest load peak in history, and has gradually transformed from "supply exceeds demand" to "supply exceeds demand and blocked water abandonment coexistence". The safe operation of the power grid faces unprecedented challenges. The demand-side response plan can no longer meet the safe and stable operation of the power grid under the peak load. In order to ensure the electricity demand for people's livelihood as much as possible and minimize the scope of power outage, a fast and effective emergency load control plan is needed. However, since the operation of the power grid is a dynamic process, this control plan cannot guarantee that the control target can be achieved in the shortest time, and it cannot guarantee rapid and reasonable distribution. On the one hand, the emergency load control ranking table changes every year due to different demands in various places, and it is impossible to track all emergency loads in time with the change of operation mode; on the other hand, due to the different regulation scopes at the provincial and local levels, there are many load overlaps in the emergency load control plans formulated by the provincial and local levels, and it is impossible to finely measure the controllable resources in various regions, resulting in unreasonable distribution of control plans. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the existing technology and propose a method for rapid allocation of regional power restrictions based on emergency load control plan. The present invention makes full use of the control cloud resources, combines the power supply path tracking and power supply range search technology, realizes the cleaning and aggregation of regional accident power restrictions resources, makes a reasonable assessment of the power restriction capacity in the region, provides strong support for the control operation under emergency accidents, and meets the electricity demand of people's livelihood.
[0004] The embodiment of the present invention provides a method for quickly allocating regional power restrictions based on an emergency load control plan, including:
[0005] Obtain the limit switch information from the emergency load control sequence table of each regional power grid;
[0006] For each regional power grid, based on the limit switch information, the limit switches are grouped according to the load properties of each limit switch, wherein the limit switches with industrial load properties are classified into Class I load switches, the limit switches with mixed load properties are classified into Class II load switches, and the limit switches with civilian load properties are classified into Class III load switches;
[0007] Based on the grouping result of the limit switch and in combination with the current topology of the power grid, obtaining the vertex switch in each limit switch group;
[0008] Through the power supply path search, the vertex switches of the first type of load switch group and the vertex switches of the third type of load switch group are classified respectively, wherein the vertex switches that overlap with the second type of load switch are recorded as the overlapping switches of the group, and the remaining vertex switches that do not overlap are recorded as the calculation switches of the group;
[0009] Based on the classification results of the vertex switches, classify and count all loads of the power grid;
[0010] Based on the load classification statistics of each regional power grid, the loads that need power rationing are regionally allocated.
[0011] In a specific embodiment of the present invention, the method further comprises:
[0012] By acquiring the power flow of the limit switch and the grid-connected power plant corresponding to the limit switch, the limit switch can be monitored;
[0013] The power flow acquisition method of the pull-limit switch is as follows:
[0014] 1) In the power grid topology results, start from the head end node of any pull-limit switch to conduct a deep search of the power grid. If a switch or switch device appears in the search direction, skip the device and continue to search the next node in the search direction until the measurement and acquisition device is found, and enter step 3);
[0015] If a busbar appears in the search direction, stop searching in that direction and go to step 2);
[0016] If the measurement acquisition device is still not found after searching in the search direction, proceed to step 2);
[0017] 2) In the power grid topology result, a deep search is performed on the power grid starting from the end node of the pull-limit switch. If a knife switch or switch device appears in the search direction, the device is skipped and the search continues to the next node in the search direction until the measurement and acquisition device is found, and then step 3 is entered;
[0018] If a busbar appears in the search direction, stop searching in that direction and go to step 4);
[0019] If the measurement acquisition device is still not found after searching in the search direction, proceed to step 4);
[0020] 3) Obtaining real-time data collected from the measurement and collection equipment as the power flow data of the pull-limit switch;
[0021] 4) Modify the limit switch model in the power grid topology. After the modification is completed, return to step 1) to re-acquire the power flow data of the limit switch;
[0022] The grid-connected power plant station corresponding to the pull-limit switch is obtained in the following manner:
[0023] Based on the current topology of the power grid, all plant and station buses are traversed, and a deep topological search is performed downward from the 220kv bus as the starting point until all calculation buses within the power supply range of the 220kv bus are searched; during the search process, the relationship between the upper-level calculation buses corresponding to all lower-level calculation buses is recorded; the branches connecting each level of the calculation bus are recorded, and the relationship between the lower-level branches and the upper-level branches is recorded; based on the switches connected to the branches, the relationship between the lower-level switches and the upper-level switches is recorded; after the recording is completed, the power supply relationship based on the calculation bus is obtained;
[0024] Obtain the calculated bus corresponding to each limiting switch in the emergency load control table, and based on the upper and lower relationships between the calculated buses in the power supply relationship, search for the power supply path upward with the calculated bus as the starting point until a 220kV plant on the path is found, and use the 220kV plant as the grid-connected power plant corresponding to the limiting switch.
[0025] In a specific embodiment of the present invention, the method further comprises:
[0026] Based on the relationship between the lower switch and the upper switch in the power supply relationship, the upper and lower relationships between all the pull-limit switches are obtained.
[0027] In a specific embodiment of the present invention, obtaining the vertex switch in each pull-limit switch group includes:
[0028] If there is a superior-subordinate relationship between two limit switches in any group, the superior switch is used as the representative switch of the subordinate switch, and the superior switch is added as a vertex switch to the initially empty vertex switch set; if the superior switch is the subordinate switch of other switches in the same group, the superior switch is deleted from the vertex switch set; the isolated limit switch in any group is added as a vertex switch to the vertex switch set; after traversing all the limit switches in each group, all vertex switches retained in the vertex switch set are recorded.
[0029] In a specific embodiment of the present invention, the method further comprises:
[0030] Taking each vertex switch in the first type of load switch group and each vertex switch in the third type of load switch group as a starting point, the power supply path is traced upwards;
[0031] If any Class II load switch appears on any power supply path during the tracing process, the tracing stops. If different loads overlap on the path, the limit switch at the starting point of the path is recorded as the overlapping switch of its group.
[0032] If any Class II load switch appears on the power supply path tracing process with the Class I load vertex switch as the starting point, then all Class I load switches contained in the lower level of the Class II load switch are recorded; if any Class II load switch appears on the power supply path tracing process with the Class III load vertex switch as the starting point, then the upper Class II load switch corresponding to the Class III vertex load switch is recorded;
[0033] If no Class II load switch appears on any power supply path during the tracing process, there is no load overlap on the path, and the vertex switch at the starting point of the path is recorded as the calculation switch of the group to which it belongs.
[0034] In a specific embodiment of the present invention, the classification result based on the vertex switch is used to classify and count all loads of the power grid, including:
[0035] If any vertex switch is a calculation switch, the load of the vertex switch is taken as the load superposition of the vertex switch and all its subordinate switches at the corresponding load type of the vertex switch;
[0036] When calculating the statistics of a class of load, the load quantities of all the switches calculating the class of load are superimposed to obtain the statistical value of the class of load;
[0037] When the second-class load is counted, firstly, the load of the second-class load vertex switch that does not overlap with the first-class load switch is superimposed to obtain the second-class load superposition value 1; then the load of the remaining second-class load vertex switches is superimposed. When superimposing, if the second-class load vertex switch contains the first-class load switch, the load of the first-class load switch included is deducted from the load of the second-class load vertex switch, and the second-class load superposition value 2 is obtained after the superposition is completed; the second-class load superposition value 1 and the second-class load superposition value 2 are summed to obtain the second-class load statistical value;
[0038] When counting the three types of loads, firstly, the load amounts of the three types of load calculation switches are superimposed to obtain the three types of load superposition value 1; then, the load amounts of the remaining three types of load vertex switches are superimposed. When superimposing, if the second type of load switch includes the third type of load vertex switch, then when counting the three types of loads, it is necessary to deduct the load amount of the second type of load switch included from the load amount of the third type of load vertex switch, and after superposition, the three types of load superposition value 2 is obtained; the three types of load superposition value 1 and the three types of load superposition value 2 are summed to obtain the three types of load statistical value.
[0039] In a specific embodiment of the present invention, the regional allocation of loads requiring power restriction based on load classification statistics of each regional power grid includes:
[0040] The load that needs to be limited is P Cut, N is the number of the power grid in the current control area, N = 1, 2, ..., M, M is the total number of control areas; P 1N is the load statistic of the Nth regional power grid, P 2N is the second-class load statistics of the Nth regional power grid, P 3N are the three types of load statistics of the Nth regional power grid;
[0041] determination:
[0042] If the load P that needs to be limited Cut If the load is less than or equal to the sum of the load statistics of all control areas, the power limit allocated by the Nth regional power grid is:
[0043]
[0044] If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics of all regions and less than or equal to the sum of the Class I load statistics and Class II load statistics of all regions, the power limit allocated to the Nth regional power grid is:
[0045]
[0046] If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics and Class II load statistics of all regions and less than the sum of the Class I load statistics, Class II load statistics, and Class III load statistics of all regions, then the power limit allocated to the Nth regional power grid is:
[0047]
[0048] If the load P that needs to be limited Cut It is equal to the sum of the first-class load statistics, second-class load statistics, and third-class load statistics of all regions. Then the power limit allocated to the Nth regional power grid is:
[0049] P 1N +P 2N +P 3N
[0050] Where, N = 1, 2, ..., M;
[0051] If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics, Class II load statistics, and Class III load statistics in all areas, the power limit exceeds the controllable capacity of the entire network and the power grid shortage allocation cannot be completed through the current control area.
[0052] The characteristics and beneficial effects of the present invention are:
[0053] The present invention is based on the emergency load control plan, and is mainly aimed at the peak period of power grid load. The demand-side response scheme can no longer meet the people's livelihood needs. Emergency load control needs to be taken for the power grid. In order to reduce the scope of power outage as much as possible, the load nature, control round, and importance are comprehensively considered to classify and monitor the load limit load, and the multi-objective function is integrated to realize the rapid allocation of regional power limit. The method takes the emergency load control ranking table limit switch as the object, combines the power grid topology, obtains the grid-connected power supply and real-time acquisition data corresponding to the limit switch for monitoring, and classifies them horizontally and vertically according to the load nature and power supply relationship of the limit switch, intelligently identifies the inclusion relationship between loads, and finally realizes the load refinement cleaning, and completes the controllable resource capacity analysis of the three types of industrial, mixed, and civil loads; and takes this as the object, supports the allocation of power limit from multiple dimensions such as load priority, region, sensitivity, etc., integrates and optimizes multi-objective functions, implements multi-strategy parallel power limit, and strives to seek a dynamic balance point under the three principles of protecting people's livelihood, fairness, and effectiveness, and realize the optimal solution of the power limit strategy.
[0054] The present invention makes full use of the topological model of the power grid, real-time measurement data, emergency load control ranking table and other control cloud resources, and realizes the cleaning and aggregation of the province's accident power-limiting resources by combining power supply path tracking and power supply range search technology, and makes a reasonable assessment of the power-limiting capacity in the region, providing strong support for the control operation under emergency accidents and meeting the electricity demand of the people's livelihood. The method of the present invention includes but is not limited to the cleaning statistics and auxiliary decision-making of emergency loads, and can also be extended to other applications such as program formulation, plan execution, and execution evaluation. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] Figure 1 The present invention is an overall flow chart of a method for rapid distribution of regional power restrictions based on an emergency load control plan according to an embodiment of the method of the present invention.
[0056] Figure 2 It is a schematic diagram of searching for vertex switches in each pull-limit switch group in a specific embodiment of the method of the present invention. DETAILED DESCRIPTION
[0057] The present invention proposes a method for rapid distribution of regional power restrictions based on an emergency load control plan. The technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0058] The embodiment of the present invention proposes a method for rapidly allocating regional power restrictions based on an emergency load control plan. The overall process is as follows: Figure 1As shown, including:
[0059] Obtain the limit switch information from the emergency load control sequence table of each regional power grid;
[0060] For each regional power grid, based on the limit switch information, the limit switches are grouped according to the load properties of each limit switch, wherein the limit switches with industrial load properties are classified into Class I load switches, the limit switches with mixed load properties are classified into Class II load switches, and the limit switches with civilian load properties are classified into Class III load switches;
[0061] Based on the grouping result of the limit switch and in combination with the current topology of the power grid, obtaining the vertex switch in each limit switch group;
[0062] Through the power supply path search, the vertex switches of the first type of load switch group and the vertex switches of the third type of load switch group are classified respectively, wherein the vertex switches that overlap with the second type of load switch are recorded as the overlapping switches of the group, and the remaining vertex switches that do not overlap are recorded as the calculation switches of the group;
[0063] Based on the classification results of the vertex switches, classify and count all loads of the power grid;
[0064] Based on the load classification statistics of each regional power grid, the loads that need power rationing are regionally allocated.
[0065] In a specific implementation of the present invention, the method for rapidly allocating regional power restrictions based on an emergency load control plan comprises the following steps:
[0066] 1) Obtain all equipment and operating status of the current power grid from the control cloud platform, determine the real-time operating mode of the current power grid, and obtain the current topology results of the power grid.
[0067] 2) Read the limit switches involved in the emergency load control sequence table from the control cloud platform as monitoring objects, and obtain the information of each limit switch, including: switch ID, switch name, load nature, control round, whether there is reverse transmission, and whether it is valid;
[0068] 3) Based on the topological result of step 1), obtain the power flow of each pull-limit switch; the specific steps are as follows:
[0069] 3-1) In the power grid topology results, start from the head end node of any pull-limit switch to conduct a deep search of the power grid. If a switch or switch device appears in the search direction, skip the device and continue to search the next node in the search direction until the measurement and acquisition device is found, and enter step 3-3);
[0070] If a busbar appears in the search direction, stop searching in that direction and go to step 3-2);
[0071] If the measurement acquisition device is still not found after searching in the search direction, go to step 3-2).
[0072] 3-2) In the power grid topology result, a deep search is performed on the power grid starting from the end node of the pull-limit switch. If a knife switch or switch device appears in the search direction, the device is skipped and the search continues to the next node in the search direction until the measurement and acquisition device is found, and step 3-3) is entered;
[0073] If a busbar appears in the search direction, stop searching in that direction and go to step 3-4);
[0074] If the measurement acquisition device is still not found after searching in the search direction, go to step 3-4).
[0075] 3-3) Acquire the real-time data collected on the measurement and collection equipment as the power flow data of the pull-limit switch.
[0076] 3-4) If no measurement equipment is found in the search in both directions of the first and last nodes of the limit switch, the switch is marked and the user is prompted that there is a problem with the switch model in the topology result and the switch model needs to be corrected in the power grid topology. After the correction is completed, return to step 3-1) to re-acquire the power flow data of the limit switch.
[0077] 4) Based on the topological results of step 1), traverse all plant and station buses, and perform a deep topological search downward from the 220kv bus as the starting point until all calculation buses within the power supply range of the 220kv bus are searched; during the search process, record the relationship between the upper-level calculation bus corresponding to all lower-level calculation buses; record the branches connecting each level of the calculation bus, and record the relationship between the lower-level branches and the upper-level branches; based on the switches connected to the branches, record the relationship between the lower-level switches and the upper-level switches; after recording, obtain the power supply relationship based on the calculation bus.
[0078] In a specific embodiment of the present invention, the power supply relationship includes: calculating a bus tree, a branch tree, and a switch tree.
[0079] 5) Obtain the calculated bus corresponding to each limiting switch in the emergency load control table, and based on the calculated bus tree obtained in step 4), search the power supply path upward with the calculated bus as the starting point until the 220kV plant on the path is found, and use the 220kV plant as the grid-connected power plant corresponding to the limiting switch.
[0080] In this embodiment, the grid-connected power plant corresponding to each limit switch obtained in this step and the power flow of each limit switch obtained in step 3) can realize the monitoring of all limit switches.
[0081] 6) Based on the information of the limiting switch in step 2), the power supply path is searched upward according to the switch tree obtained in step 4) to obtain the superior-subordinate relationship between all the limiting switches.
[0082] 7) Based on the information of the pull-limit switches in step 2), the pull-limit switches are grouped according to the load properties of each pull-limit switch.
[0083] In this embodiment, the pull-limit switch with the load nature of industrial load is classified as a type of load switch, the pull-limit switch with the load nature of mixed load is classified as a type of load switch, and the pull-limit switch with the load nature of civil load is classified as a type of load switch.
[0084] 8) Based on the pull-limit switch grouping result obtained in step 7), the vertex switches in the grouping of the first type of load switch, the second type of load switch and the third type of load switch are obtained respectively.
[0085] A schematic diagram of searching for a vertex switch in each pull-limit switch group in a specific embodiment of the present invention is shown in FIG. Figure 2 As shown. The three elliptical dashed boxes represent the first type of load switch group, the second type of load switch group, and the third type of load switch group, respectively. In each elliptical dashed box, the black dots represent the pull-limit switches in the group, and the connecting lines between the black dots represent the power supply relationship between the pull-limit switches. In this implementation, a power supply relationship tree within the same group is drawn according to the power supply relationship of the pull-limit switches in the same group, in which the pull-limit switches that do not have a power supply relationship in the same group exist in isolation, and finally a schematic diagram of the power supply relationship of the three groups is obtained.
[0086] Among them, if there is a superior-subordinate relationship between two limit switches in any group, the superior switch is used as the representative switch of the subordinate switch, and the superior switch is added as a vertex switch to the initially empty vertex switch set of the group; if the superior switch is the subordinate switch of other switches in the same group, the superior switch is deleted from the vertex switch set; the isolated limit switch in any group is added as a vertex switch to the vertex switch set; after traversing all the limit switches in each group, all vertex switches retained in the vertex switch set are recorded.
[0087] 9) Based on the result of step 8), each vertex switch in the first category load switch group and each vertex switch in the third category load switch group are used as starting points to trace the power supply path upward, and load cleaning is achieved according to the load priority level corresponding to the limit switch.
[0088] In this embodiment, the load priority levels corresponding to the pull-limit switch are: the priority of the first-class load is higher than that of the second-class load, and the priority of the second-class load is higher than that of the third-class load.
[0089] Among them, if any Class II load switch appears on any power supply path during the tracing process, the tracing stops. Different loads overlap on the path, and the pull-limit switch at the starting point of the path is recorded as the overlapping switch of its group.
[0090] Furthermore, if any Class II load switch appears on the power supply path tracing process with the Class I load vertex switch as the starting point, all Class I load switches contained in the lower level of the Class II load switch are recorded; if any Class II load switch appears on the power supply path tracing process with the Class III load vertex switch as the starting point, the upper Class II load switch corresponding to the Class III vertex load switch is recorded;
[0091] If no Class II load switch appears on any power supply path during the tracing process, it means that there is no load overlap on the path, and the vertex switch at the starting point of the path is recorded as the calculation switch of the group to which it belongs.
[0092] 10) Based on the result of step 9), classify and count the loads of the vertex switches in each pull-limit switch group.
[0093] Specifically, if any vertex switch is a calculation switch, the load amount of the vertex switch is used as the load superposition amount of the vertex switch and all its subordinate switches of the load type corresponding to the vertex switch.
[0094] When performing statistics on a type of load, based on the result of step 8), the load amounts of all type-one load calculation switches are superimposed to obtain a type-one load statistical value, that is, the power limit statistics for the type-one load are completed.
[0095] When counting the Class II load, firstly, the load amounts of the Class II load vertex switches that do not overlap with the Class I load switches are superimposed to obtain the Class II load superposition value 1; then, based on the result of step 9), the load amounts of the remaining Class II load vertex switches are superimposed. When superimposing, if the Class II load vertex switch contains a Class I load switch, the load amount of the contained Class I load switch is deducted from the load amount of the Class II load vertex switch, and after the superposition is completed, the Class II load superposition value 2 is obtained; Class I load has a higher priority than Class II load and is included in the calculation of Class I load first; finally, the Class II load superposition value 1 and the Class II load superposition value 2 are summed to obtain the Class II load statistical value, that is, the power limit statistics for Class II load are completed.
[0096] When counting the three types of loads, firstly, the loads of the three types of load calculation switches that do not overlap with the two types of load switches are superimposed to obtain the three types of load superposition value 1; then, based on the result in step 9), the loads of the remaining three types of load vertex switches are superimposed. When superimposing, if the two types of load switches include the three types of load vertex switches, then when counting the three types of loads, it is necessary to deduct the loads of the two types of load switches included from the loads of the three types of load vertex switches, and after superposition, the three types of load superposition value 2 is obtained. The two types of loads have a higher priority than the three types of loads and are included in the calculation of the two types of loads first. Finally, the three types of load superposition value 1 and the three types of load superposition value 2 are summed to obtain the three types of load statistics, that is, the power limit statistics for the three types of loads are completed.
[0097] This embodiment superimposes the calculated switch loads of the three load categories, thereby ultimately realizing controllable resource capacity analysis for the three load categories of industrial, mixed, and civil.
[0098] 11) Based on the result of step 10), load control is allocated according to the power grid shortage and regional controllable resources, and load restriction is quickly implemented.
[0099] Among them, the load that needs to be limited is P Cut , N is the number of the power grid in the current control area, N = 1, 2, ..., M, M is the total number of control areas; P 1N is the load statistic of the Nth regional power grid, P 2N is the second-class load statistics of the Nth regional power grid, P 3N are the three types of load statistics of the Nth regional power grid; P of a single regional power grid 1N , P 2N and P 3N Obtained by executing the above steps 1)-11) on the power grid.
[0100] determination:
[0101] If the load P that needs to be limited Cut If the load is less than or equal to the sum of the load statistics of all control areas, the power limit allocated by the Nth regional power grid is:
[0102]
[0103] If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics of all regions and less than or equal to the sum of the Class I load statistics and Class II load statistics of all regions, the power limit allocated to the Nth regional power grid is:
[0104]
[0105] If the load P that needs to be limited CutIf it is greater than the sum of the Class I load statistics and Class II load statistics of all regions and less than the sum of the Class I load statistics, Class II load statistics, and Class III load statistics of all regions, then the power limit allocated to the Nth regional power grid is:
[0106]
[0107] If the load P that needs to be limited Cut It is equal to the sum of the statistical values of Class I, Class II and Class III loads in all regions. Then the power limit allocated to the Nth regional power grid is:
[0108] P 1N +P 2N +P 3N
[0109] Among them, N=1,2,…,M.
[0110] If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics, Class II load statistics, and Class III load statistics of all areas, the system will give an alarm prompt that the power limit exceeds the controllable capacity of the entire network, and inform the user that the power grid shortage allocation cannot be completed through the current control area.
[0111] The above is a preferred embodiment of the present disclosure, which can be understood and implemented by ordinary technicians in the field without creative work. It should be pointed out that ordinary technicians in this technical field can make several improvements and modifications without departing from the principles of the present invention, and these improvements and modifications are also considered to be within the scope of protection of the present invention.
Claims
1. A method for rapidly allocating regional power restrictions based on an emergency load control plan, characterized in that: include: Obtain the limit switch information from the emergency load control sequence table of each regional power grid; For each regional power grid, based on the load limit switch information, the load limit switches are grouped according to the load nature of each load limit switch, wherein the load limit switches with industrial load nature are classified as Class I load switches, the load limit switches with mixed load nature are classified as Class II load switches, and the load limit switches with civilian load nature are classified as Class III load switches; Based on the grouping result of the limit switches and in combination with the current topology of the power grid, obtaining the vertex switch in each limit switch group; Through power supply path search, the vertex switches of the first-class load switch group and the vertex switches of the third-class load switch group are classified respectively. The vertex switches that have an overlapping relationship with the second-class load switch are recorded as the overlapping switches of the group, and the remaining vertex switches that do not have an overlapping relationship are recorded as the calculation switches of the group. Based on the classification results of the vertex switches, classify and count all loads of the power grid; Based on the load classification statistics of each regional power grid, the loads that need power rationing are regionally allocated.
2. The method according to claim 1, characterized in that The method further comprises: By acquiring the power flow of the limit switch and the grid-connected power plant corresponding to the limit switch, the limit switch can be monitored; The power flow of the limit switch is obtained as follows: 1) In the grid topology results, start from the head end node of any pull-limit switch and conduct a deep search of the grid. If a switch or switch device appears in the search direction, skip the device and continue searching to the next node in the search direction until the measurement and acquisition device is found, and then proceed to step 3); If a busbar appears in the search direction, stop searching in that direction and go to step 2); If the measurement acquisition device is still not found after searching in the search direction, proceed to step 2); 2) In the grid topology results, a deep search of the grid is performed starting from the end node of the pull-limit switch. If a switch or switch device appears in the search direction, the device is skipped and the search continues to the next node in the search direction until the measurement acquisition device is found, and then the process goes to step 3); If a busbar appears in the search direction, stop searching in that direction and go to step 4); If the measurement acquisition device is not found after searching in the search direction, proceed to step 4); 3) Obtaining real-time data collected from the measurement and collection equipment as the power flow data of the pull-limit switch; 4) Modifying the limiting switch model in the power grid topology. After the modification is completed, return to step 1) to reacquire the power flow data of the limiting switch; The grid-connected power plant station corresponding to the pull-limit switch is obtained as follows: Based on the current topology of the power grid, all plant and station buses are traversed, and a deep topology search is performed downward from the 220kV bus as the starting point until all calculation buses within the power supply range of the 220kV bus are searched. During the search, the relationship between all lower-level calculation buses and the upper-level calculation buses is recorded; the branches connecting each level of the calculation bus are recorded, and the relationship between the lower-level branches and the upper-level branches is recorded; based on the switches connected to the branches, the relationship between the lower-level switches and the upper-level switches is recorded; after the recording is completed, the power supply relationship based on the calculation bus is obtained; Obtain the calculated bus corresponding to each limiting switch in the emergency load control table. Based on the hierarchical relationship between the calculated buses in the power supply relationship, search for the power supply path upward from the calculated bus until a 220kV plant station on the path is found. Use the 220kV plant station as the grid-connected power supply plant station corresponding to the limiting switch.
3. The method according to claim 2, characterized in that The method further comprises: Based on the relationship between the lower-level switches and the upper-level switches in the power supply relationship, the upper-lower-level relationship between all the pull-limit switches is obtained.
4. The method according to claim 3, characterized in that The step of obtaining the vertex switches in each pull-limit switch group includes: If there is a superior-subordinate relationship between two limit switches in any group, the superior switch is used as the representative switch of the subordinate switch and is added as a vertex switch to the initially empty vertex switch set; if the superior switch is the subordinate switch of other switches in the same group, the superior switch is deleted from the vertex switch set; an isolated limit switch in any group is added as a vertex switch to the vertex switch set; after traversing all limit switches in each group, all vertex switches retained in the vertex switch set are recorded.
5. The method according to claim 4, characterized in that The method further comprises: Each vertex switch in the first-class load switch group and each vertex switch in the third-class load switch group are used as starting points to trace the power supply path upwards; If any Class II load switch appears on any power supply path during the tracing process, the tracing stops. If different loads overlap on the path, the limit switch at the starting point of the path is recorded as the overlapping switch of its group. If any Class II load switch appears on the power supply path tracing process with the Class I load vertex switch as the starting point, all Class I load switches contained in the lower level of the Class II load switch will be recorded; if any Class II load switch appears on the power supply path tracing process with the Class III load vertex switch as the starting point, the Class II load switch corresponding to the upper level of the Class III vertex load switch will be recorded; If no Class II load switch appears on any power supply path during the tracing process, there is no load overlap on the path, and the vertex switch at the starting point of the path is recorded as the calculation switch of the group to which it belongs.
6. The method according to claim 5, characterized in that The classification result based on the vertex switch is used to classify and count all loads of the power grid, including: If any vertex switch is a calculation switch, the load of the vertex switch is taken as the load superposition of the vertex switch and all its lower-level switches for the load type corresponding to the vertex switch; Among them, when calculating the statistics of a class of load, the load amounts of all the switches calculating the class of load are added together to obtain the statistical value of the class of load; When calculating the second-class load, first, the load amounts of the second-class load vertex switches that do not overlap with the first-class load switches are superimposed to obtain the second-class load superposition value 1; then, the load amounts of the remaining second-class load vertex switches are superimposed. During superposition, if the second-class load vertex switch contains a first-class load switch, the load amount of the included first-class load switch is deducted from the load amount of the second-class load vertex switch. After superposition, the second-class load superposition value 2 is obtained; the second-class load superposition value 1 and the second-class load superposition value 2 are summed to obtain the second-class load statistical value; When counting the three types of loads, first superimpose the load amounts of the three types of load calculation switches to obtain the three types of load superposition value 1; then superimpose the load amounts of the remaining three types of load vertex switches. When superimposing, if the second type of load switch includes the third type of load vertex switch, then when counting the three types of loads, it is necessary to deduct the load amount of the second type of load switch included from the load amount of the third type of load vertex switch. After superposition is completed, the three types of load superposition value 2 is obtained; the three types of load superposition value 1 and the three types of load superposition value 2 are summed to obtain the three types of load statistical value.
7. The method according to claim 6, characterized in that The load classification statistics of each regional power grid are used to allocate loads that require power rationing to different regions, including: The load that needs to be limited is P Cut , N is the number of the current control area grid, N = 1, 2, ..., M, M is the total number of control areas; P 1N is the load statistic of the Nth regional power grid, P 2N is the second-class load statistics of the Nth regional power grid, P 3N are the three types of load statistics of the Nth regional power grid; determination: If the load P that needs to be limited Cut If the load limit is less than or equal to the sum of the load statistics of all control areas, the power limit allocated to the Nth area power grid is: If the load P that needs to be limited Cut If the load limit is greater than the sum of the first-class load statistics of all regions and less than or equal to the sum of the first-class load statistics and the second-class load statistics of all regions, the power limit allocated to the Nth regional power grid is: If the load P that needs to be limited Cut If the value is greater than the sum of the Class 1 and Class 2 load statistics of all regions and less than the sum of the Class 1, Class 2, and Class 3 load statistics of all regions, the power limit allocated to the Nth regional power grid is: If the load P that needs to be limited Cut is equal to the sum of the Class I, Class II, and Class III load statistics of all regions. The power limit allocated to the Nth regional power grid is: P 1N +P 2N +P 3N Where N = 1, 2, ..., M; If the load P that needs to be limited Cut If it is greater than the sum of the Class I load statistics, Class II load statistics, and Class III load statistics of all areas, the power limit exceeds the controllable capacity of the entire network and the power grid shortage allocation cannot be completed through the current control area.