A virtual power plant energy storage parallel system power control method, system and medium

By monitoring the total power demand of the power grid and the state of the energy storage unit of the virtual power plant, calculating the battery health status and maximum charging and discharge power capability coefficient, and distributing power weights, the problem of unbalanced SOC of the energy storage unit is solved, and the energy storage of the virtual power plant is improved. energy efficiency and adaptability of the machine system.

CN118763711BActive Publication Date: 2024-11-19SHENZHEN EN-JOY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411253477.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-19
Estimated Expiration
2044-09-09

AI Technical Summary

Technical Problem

In the existing virtual power plant energy storage system, the power equal distribution method between energy storage cabinets is unbalanced due to different battery manufacturing processes, different usage environments and inconsistent self-discharge rates, which reduces the system energy efficiency and increases maintenance costs.

Method used

By monitoring the total power demand of the power grid and the state parameters of the energy storage unit, calculate the battery health status coefficient and the maximum charging and discharge power capability coefficient, perform power weight allocation, and adjust the command power data of the energy storage unit to realize the power control of the system.

Benefits of technology

The power distribution between energy storage units is achieved more reasonable, the energy efficiency and available capacity of the system are improved, and maintenance costs and complexity are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118763711B_ABST
    Figure CN118763711B_ABST
Patent Text Reader

Abstract

The present application provides a method, system and medium for controlling the power of a virtual power plant energy storage parallel system. The method includes: collecting the total power demand data of the power grid and the state parameters of each energy storage unit, obtaining the corresponding battery state parameters, and processing to obtain the battery health state coefficient, obtaining the corresponding battery performance data, and processing in combination with the state parameters to obtain the maximum charge and discharge power capacity coefficient, according to the total power demand data and the state parameters, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed to obtain the corresponding command power data, the actual total power data of the power grid corresponding to m time points within a preset time period and the corresponding total power demand data are collected, and the energy storage supply deviation index is obtained by processing, and compared with the preset energy storage supply deviation threshold, to determine whether the allocation scheme is reasonable, and to make corresponding adjustments, so as to realize the technology of power control of the virtual power plant energy storage parallel system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of power control technology, and in particular to a power control method, system and medium for a virtual power plant energy storage parallel system. Background Art

[0002] With the rise of the concept of virtual power plants, energy storage parallel systems play an important role in them. However, in existing virtual power plant energy storage parallel systems, the more commonly used power control method is to evenly distribute power between energy storage cabinets. However, due to differences in battery manufacturing processes, different usage environments, inconsistent self-discharge rates, and actual charge and discharge power deviations, the SOC of different battery groups in each energy storage cabinet will gradually deviate from the equilibrium state during the charge and discharge process. This imbalance will reduce the available capacity and energy efficiency of the entire battery system and increase the maintenance cost and complexity of the system.

[0003] Therefore, in order to improve the performance and adaptability of the virtual power plant energy storage parallel system and meet the increasingly complex needs of the power system, it is of great practical significance and application value to develop an innovative, precise and efficient energy storage parallel system power control method.

[0004] In view of the above problems, effective technical solutions are urgently needed. Summary of the invention

[0005] The purpose of the present application is to provide a power control method, system and medium for a virtual power plant energy storage parallel system, which can allocate power weights to each energy storage unit based on the total power demand data of the power grid and the status parameters of each energy storage unit, combined with the battery health status coefficient and the maximum charge and discharge power capacity coefficient, obtain the command power data corresponding to each energy storage unit, and adjust it according to the specific operating conditions, thereby realizing the technology of power control of the virtual power plant energy storage parallel system.

[0006] The present application also provides a virtual power plant energy storage parallel system power control method, comprising the following steps:

[0007] Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0008] Obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit;

[0009] Acquire battery performance data corresponding to each energy storage unit, and process the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit;

[0010] According to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is allocated power and operated according to the command power data;

[0011] Collecting actual total power data of the power grid and corresponding total power demand data corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data, and processing to obtain an energy storage supply deviation index;

[0012] A threshold comparison is performed based on the energy storage supply deviation index and a preset energy storage supply deviation threshold, and whether the allocation plan is reasonable is determined based on the comparison result, and corresponding adjustments are made.

[0013] Optionally, in the virtual power plant energy storage parallel system power control method described in the present application, the monitoring of the operation of the virtual power plant and the collection of total power demand data of the power grid and status parameters of each energy storage unit include:

[0014] Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0015] The state parameters of each energy storage unit include charge state data, voltage data, current data and temperature data.

[0016] Optionally, in the power control method for the virtual power plant energy storage parallel system described in the present application, the obtaining of the battery status parameters corresponding to each energy storage unit and the processing to obtain the battery health status coefficient corresponding to each energy storage unit include:

[0017] Obtaining battery status parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle number data;

[0018] Processing the battery capacity data, the battery internal resistance data, the battery charge and discharge efficiency data, and the battery cycle number data to obtain a battery health status coefficient corresponding to each energy storage unit;

[0019] The calculation formula of the battery health status coefficient is:

[0020] ;

[0021] in, is the battery health status coefficient corresponding to the i-th energy storage unit, , , , They are the battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data corresponding to the i-th energy storage unit. , , , , is the preset characteristic coefficient.

[0022] Optionally, in the power control method of the virtual power plant energy storage parallel system described in the present application, the acquiring of battery performance data corresponding to each energy storage unit and processing in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit includes:

[0023] Obtaining battery performance data corresponding to each energy storage unit, including battery maximum current data, battery thermal management performance data, and battery voltage data;

[0024] The battery thermal management performance data includes battery heat dissipation efficiency data and operating temperature range data;

[0025] The battery voltage data includes battery rated voltage data and battery actual voltage data;

[0026] According to the battery performance data corresponding to each energy storage unit, combined with the charge state data corresponding to each energy storage unit, the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit is obtained;

[0027] The calculation formula of the maximum charge and discharge power capacity coefficient is:

[0028] ;

[0029] in, is the maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit, , , , , They are the maximum current data of the battery corresponding to the i-th energy storage unit, the battery heat dissipation efficiency data, the operating temperature range data, the battery rated voltage data, and the battery actual voltage data. is the state of charge data corresponding to the i-th energy storage unit, , , , , , is the preset characteristic coefficient.

[0030] Optionally, in the power control method of the virtual power plant energy storage parallel system described in the present application, the power weight allocation is performed on each energy storage unit according to the total power demand data of the power grid and the state parameters of each energy storage unit, in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the command power data corresponding to each energy storage unit is obtained, and the power allocation and operation of the virtual power plant are performed according to the command power data, including:

[0031] According to the total power demand data of the power grid and the charge state data of each energy storage unit, the power weight allocation is performed on each energy storage unit through a preset energy storage power allocation model in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, so as to obtain the command power data corresponding to each energy storage unit;

[0032] Allocating power and operating the virtual power plant according to the command power data;

[0033] The calculation formula of the command power data is:

[0034] ;

[0035] in, is the command power data corresponding to the i-th energy storage unit among the n energy storage units, is the total power demand data, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient.

[0036] Optionally, in the power control method for the virtual power plant energy storage parallel system described in the present application, the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data are collected, and the energy storage supply deviation index is obtained by processing, including:

[0037] Collect the actual total power data of the power grid and the corresponding total power demand data corresponding to the m time points within the preset time period when the virtual power plant runs according to the command power data, and process them through a preset power grid power control model to obtain an energy storage supply deviation index;

[0038] The calculation formula of the energy storage supply deviation index is:

[0039] ;

[0040] in, is the energy storage supply deviation index, , are the actual total power data and total power demand data corresponding to the jth time point among m time points, is the preset characteristic coefficient.

[0041] Optionally, the virtual power plant energy storage parallel system power control method described in the present application further includes:

[0042] Perform fault identification evaluation according to the state parameters of each energy storage unit in combination with the battery health status coefficient corresponding to each energy storage unit to obtain a fault identification index corresponding to each energy storage unit;

[0043] Performing a threshold comparison between the fault identification index and a preset fault identification threshold, and judging whether a fault occurs in the corresponding energy storage unit according to the threshold comparison result;

[0044] If the threshold comparison result falls within the preset threshold range, it indicates that the corresponding energy storage unit has a fault;

[0045] Removing the failed energy storage unit and reallocating the corresponding command power data to the remaining energy storage units according to the power allocation scheme;

[0046] The calculation formula of the fault identification index is:

[0047] ;

[0048] in, is the fault identification index corresponding to the i-th energy storage unit among the n energy storage units, , , , , They are respectively the state of charge data, voltage data, current data, temperature data, and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , , , , is the preset characteristic coefficient.

[0049] Optionally, the virtual power plant energy storage parallel system power control method described in the present application further includes:

[0050] Acquire real-time electricity price data, and perform a threshold comparison with a first preset electricity price threshold to obtain a threshold comparison result;

[0051] If the threshold comparison result is less than the first preset electricity price threshold, the corresponding time node belongs to the electricity consumption valley;

[0052] Processing the state of charge data corresponding to each energy storage unit in combination with the battery health state coefficient to obtain a charging demand index corresponding to each energy storage unit;

[0053] Comparing the charging demand index corresponding to each energy storage unit with the preset charging demand threshold, and determining the charging priority of the corresponding energy storage unit according to the comparison result;

[0054] The calculation formula of the charging demand index is:

[0055] ;

[0056] in, is the charging demand index corresponding to the i-th energy storage unit among the n energy storage units, , They are the state of charge data and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , is the preset characteristic coefficient.

[0057] In a second aspect, the present application provides a power control system for a virtual power plant energy storage parallel system, the system comprising: a memory and a processor, the memory comprising a program of a power control method for a virtual power plant energy storage parallel system, and the program of the power control method for a virtual power plant energy storage parallel system is executed by the processor to implement the following steps:

[0058] Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0059] Obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit;

[0060] Acquire battery performance data corresponding to each energy storage unit, and process the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit;

[0061] According to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is allocated power and operated according to the command power data;

[0062] Collecting actual total power data of the power grid and corresponding total power demand data corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data, and processing to obtain an energy storage supply deviation index;

[0063] A threshold comparison is performed based on the energy storage supply deviation index and a preset energy storage supply deviation threshold, and whether the allocation plan is reasonable is determined based on the comparison result, and corresponding adjustments are made.

[0064] In a third aspect, the present application also provides a computer-readable storage medium, which stores a virtual power plant energy storage parallel system power control method program. When the virtual power plant energy storage parallel system power control method program is executed by a processor, the steps of the virtual power plant energy storage parallel system power control method as described in any one of the above items are implemented.

[0065] As can be seen from the above, the power control method, system and medium of the virtual power plant energy storage parallel system provided by the present application monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit, obtain the battery status parameters corresponding to each energy storage unit, and process to obtain the corresponding battery health status coefficient, obtain the corresponding battery performance data, and process in combination with the status parameters of each energy storage unit to obtain the corresponding maximum charge and discharge power capacity coefficient, and distribute power weights according to the total power demand data and status parameters of the power grid in combination with the battery health status coefficient and the maximum charge and discharge power capacity coefficient, obtain the command power data corresponding to each energy storage unit, and distribute power and operate the virtual power plant according to the command power data, collect the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and process to obtain the energy storage supply deviation index, perform a threshold comparison between the energy storage supply deviation index and the preset energy storage supply deviation threshold, judge whether the allocation scheme is reasonable according to the comparison result, and make corresponding adjustments, thereby realizing the technology of power control of the virtual power plant energy storage parallel system.

[0066] Other features and advantages of the present application will be described in the following description, and partly become apparent from the description, or understood by practicing the embodiments of the present application. The purpose and other advantages of the present application can be realized and obtained by the structures specifically pointed out in the written description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0068] Figure 1 A flow chart of a power control method for a virtual power plant energy storage parallel system provided in an embodiment of the present application;

[0069] Figure 2 A flow chart of obtaining a battery health status coefficient for a power control method for a virtual power plant energy storage parallel system provided in an embodiment of the present application;

[0070] Figure 3 A flow chart of obtaining the maximum charge and discharge power capability coefficient of the power control method of the virtual power plant energy storage parallel system provided in the embodiment of the present application;

[0071] Figure 4 A flow chart of obtaining command power data for a power control method for a virtual power plant energy storage parallel system provided in an embodiment of the present application. DETAILED DESCRIPTION

[0072] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all of the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present application provided in the drawings is not intended to limit the scope of the application claimed for protection, but merely represents the selected embodiments of the present application. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without making creative work belong to the scope of protection of the present application.

[0073] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings. At the same time, in the description of this application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0074] Please refer to Figure 1 , Figure 1 The flowchart of the power control method of the virtual power plant energy storage parallel system in some embodiments of the present application. The power control method of the virtual power plant energy storage parallel system is used in terminal equipment, such as computers, mobile terminals, etc. The power control method of the virtual power plant energy storage parallel system includes the following steps:

[0075] S11, monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0076] S12, obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit;

[0077] S13, obtaining battery performance data corresponding to each energy storage unit, and processing the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit;

[0078] S14, according to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, and the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is power allocated and operated according to the command power data;

[0079] S15, collecting the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and processing to obtain the energy storage supply deviation index;

[0080] S16. Perform a threshold comparison between the energy storage supply deviation index and a preset energy storage supply deviation threshold, determine whether the allocation plan is reasonable based on the comparison result, and make corresponding adjustments.

[0081] It should be noted that with the rise of the concept of virtual power plants, energy storage parallel systems play an important role in them. In order to improve the performance and adaptability of virtual power plant energy storage parallel systems and meet the increasingly complex needs of power systems, it is of great practical significance and application value to develop an innovative, precise and efficient energy storage parallel system power control method. Therefore, in order to formulate a reasonable power allocation strategy based on the total power demand of the system and the status of each energy storage unit, a technology for weight allocation based on factors such as the remaining power of the energy storage unit, the maximum charge and discharge power capacity, and the health status can be used. First, by monitoring the operation of the virtual power plant and collecting the total power demand data of the power grid and the status parameters of each energy storage unit, the battery status parameters corresponding to each energy storage unit are obtained, and the corresponding battery health status coefficient is obtained by processing. The corresponding battery performance coefficient is obtained. According to the data, and combined with the state parameters of each energy storage unit for processing, the corresponding maximum charge and discharge power capacity coefficient is obtained, and the power weight is allocated according to the total power demand data and state parameters of the power grid in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, and the command power data corresponding to each energy storage unit is obtained. The virtual power plant is allocated and operated according to the command power data, and the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data are collected, and the energy storage supply deviation index is obtained by processing. The energy storage supply deviation index is compared with the preset energy storage supply deviation threshold, and whether the allocation plan is reasonable is judged according to the comparison result, and corresponding adjustments are made, thereby realizing the technology of power control of the virtual power plant energy storage parallel system.

[0082] According to an embodiment of the present invention, the monitoring of the operation of the virtual power plant and the collection of total power demand data of the power grid and status parameters of each energy storage unit include:

[0083] Monitor the operation of the virtual power plant and collect total power demand data of the power grid and status parameters of each energy storage unit;

[0084] The state parameters of each energy storage unit include charge state data, voltage data, current data and temperature data.

[0085] It should be noted that before allocating power to each energy storage unit in the power grid, it is necessary to monitor the operation of the virtual power plant and collect the total power demand data of the power grid, while also collecting the status parameters of each energy storage unit, including data on charge status, voltage, current and temperature.

[0086] Please refer to Figure 2 , Figure 2 The present invention is a flowchart of obtaining a battery health status coefficient of a virtual power plant energy storage parallel system power control method in some embodiments of the present application. According to an embodiment of the present invention, the obtaining of the battery status parameters corresponding to each energy storage unit and the processing to obtain the battery health status coefficient corresponding to each energy storage unit include:

[0087] S21, obtaining battery status parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle number data;

[0088] S22, processing the battery capacity data, the battery internal resistance data, the battery charge and discharge efficiency data, and the battery cycle number data to obtain a battery health status coefficient corresponding to each energy storage unit;

[0089] The calculation formula of the battery health status coefficient is:

[0090] ;

[0091] in, is the battery health status coefficient corresponding to the i-th energy storage unit, , , , They are the battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data corresponding to the i-th energy storage unit. , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0092] It should be noted that the state of each energy storage unit has an important impact on the subsequent power weight distribution. Therefore, it is necessary to obtain the battery state parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data. Among them, battery charge and discharge efficiency data refers to data reflecting the effective conversion degree of energy during the charging and discharging process of the battery, and battery cycle data refers to the number of complete charge and discharge cycles experienced by the battery. Then, the above data is processed to obtain the battery health status coefficient corresponding to each energy storage unit.

[0093] Please refer to Figure 3 , Figure 3 It is a flow chart of obtaining the maximum charge and discharge power capacity coefficient of the power control method of the virtual power plant energy storage parallel system in some embodiments of the present application. According to an embodiment of the present invention, the battery performance data corresponding to each energy storage unit is obtained, and the state parameters of each energy storage unit are combined for processing to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit, including:

[0094] S31, obtaining battery performance data corresponding to each energy storage unit, including battery maximum current data, battery thermal management performance data, and battery voltage data;

[0095] S32, the battery thermal management performance data includes battery heat dissipation efficiency data and operating temperature range data;

[0096] S33, the battery voltage data includes battery rated voltage data and battery actual voltage data;

[0097] S34, processing the battery performance data corresponding to each energy storage unit in combination with the state of charge data corresponding to each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit;

[0098] The calculation formula of the maximum charge and discharge power capacity coefficient is:

[0099] ;

[0100] in, is the maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit, , , , , They are the maximum current data of the battery corresponding to the i-th energy storage unit, the battery heat dissipation efficiency data, the operating temperature range data, the battery rated voltage data, and the battery actual voltage data. is the state of charge data corresponding to the i-th energy storage unit, , , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0101] It should be noted that the battery performance data corresponding to each energy storage unit is further obtained, including the data of the maximum battery current, the battery thermal management performance and the battery voltage, wherein the battery thermal management performance data includes the battery heat dissipation efficiency data and the operating temperature range data, and the battery voltage data includes the battery rated voltage data and the battery actual voltage data, and then the above data are processed to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit.

[0102] Please refer to Figure 4 , Figure 4 It is a flowchart of obtaining command power data of a power control method for a virtual power plant energy storage parallel system in some embodiments of the present application. According to an embodiment of the present invention, according to the total power demand data of the power grid and the state parameters of each energy storage unit, the power weight of each energy storage unit is allocated in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the command power data corresponding to each energy storage unit is obtained, and the power of the virtual power plant is allocated and operated according to the command power data, including:

[0103] S41, according to the total power demand data of the power grid and the charge state data of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the power weight allocation is performed on each energy storage unit through a preset energy storage power allocation model to obtain the command power data corresponding to each energy storage unit;

[0104] S42, allocating power and operating the virtual power plant according to the command power data;

[0105] The calculation formula of the command power data is:

[0106] ;

[0107] in, is the command power data corresponding to the i-th energy storage unit among the n energy storage units, is the total power demand data, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0108] It should be noted that, based on the total power demand data of the power grid and the charge state data of each energy storage unit, combined with the battery health status coefficient and the maximum charge and discharge power capacity coefficient, the power weight of each energy storage unit is allocated through the calculation formula of the preset energy storage power allocation model, and the command power data corresponding to each energy storage unit is obtained. Then, according to the obtained command power data, it is allocated to the corresponding energy storage units of the virtual power plant and operated, and the operating status is monitored.

[0109] According to an embodiment of the present invention, the collecting of actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and processing to obtain the energy storage supply deviation index, includes:

[0110] Collect the actual total power data of the power grid and the corresponding total power demand data corresponding to the m time points within the preset time period when the virtual power plant runs according to the command power data, and process them through a preset power grid power control model to obtain an energy storage supply deviation index;

[0111] The calculation formula of the energy storage supply deviation index is:

[0112] ;

[0113] in, is the energy storage supply deviation index, , are the actual total power data and total power demand data corresponding to the jth time point among m time points, is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0114] It should be noted that in order to evaluate whether the power allocation plan is reasonable, it is necessary to determine whether there is a deviation between the actual situation of energy storage supply and demand. Therefore, it is necessary to collect the actual total power data of the power grid corresponding to the m time points within the preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and process them through the calculation formula of the preset power grid power control model to obtain the energy storage supply deviation index.

[0115] According to an embodiment of the present invention, it also includes:

[0116] Perform fault identification evaluation according to the state parameters of each energy storage unit in combination with the battery health status coefficient corresponding to each energy storage unit to obtain a fault identification index corresponding to each energy storage unit;

[0117] Performing a threshold comparison between the fault identification index and a preset fault identification threshold, and judging whether a fault occurs in the corresponding energy storage unit according to the threshold comparison result;

[0118] If the threshold comparison result falls within the preset threshold range, it indicates that the corresponding energy storage unit has a fault;

[0119] Removing the failed energy storage unit and reallocating the corresponding command power data to the remaining energy storage units according to the power allocation scheme;

[0120] The calculation formula of the fault identification index is:

[0121] ;

[0122] in, is the fault identification index corresponding to the i-th energy storage unit among the n energy storage units, , , , , They are respectively the state of charge data, voltage data, current data, temperature data, and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0123] It should be noted that in order to make the power allocation scheme more reasonable and flexible, the situation where some energy storage units fail during the actual operation process is fully considered, and the failed energy storage units are removed from the power allocation queue, and then reallocated according to the remaining energy storage units. Therefore, fault identification and evaluation are performed based on the state parameters of each energy storage unit combined with the battery health status coefficient corresponding to each energy storage unit, and the fault identification index corresponding to each energy storage unit is obtained. The threshold is compared with the preset fault identification threshold, and whether the corresponding energy storage unit fails is determined according to the threshold comparison result. If the corresponding energy storage unit fails, the failed energy storage unit is removed, and the remaining energy storage units are reallocated with the corresponding instruction power data according to the power allocation scheme.

[0124] According to an embodiment of the present invention, it also includes:

[0125] Acquire real-time electricity price data, and perform a threshold comparison with a first preset electricity price threshold to obtain a threshold comparison result;

[0126] If the threshold comparison result is less than the first preset electricity price threshold, the corresponding time node belongs to the electricity consumption valley;

[0127] Processing the state of charge data corresponding to each energy storage unit in combination with the battery health state coefficient to obtain a charging demand index corresponding to each energy storage unit;

[0128] Comparing the charging demand index corresponding to each energy storage unit with the preset charging demand threshold, and determining the charging priority of the corresponding energy storage unit according to the comparison result;

[0129] The calculation formula of the charging demand index is:

[0130] ;

[0131] in, is the charging demand index corresponding to the i-th energy storage unit among the n energy storage units, , They are the state of charge data and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0132] It should be noted that in order to make the entire virtual power plant more economical in electricity consumption and fully consider energy-saving and environmental protection factors, the power grid needs to charge as much electricity as possible during the low electricity consumption period, that is, when the electricity price is low. First, obtain real-time electricity price data and compare it with the first preset electricity price threshold. If the electricity price is less than the first preset electricity price threshold, it indicates that this is the low electricity consumption period. The next step is to process the battery health status coefficient according to the corresponding charge state data of each energy storage unit to obtain the charging demand index corresponding to each energy storage unit. The charging demand index corresponding to each energy storage unit is compared with the preset charging demand threshold. The charging priority of the corresponding energy storage unit is determined according to the comparison result, that is, the energy storage units with low remaining battery power and good condition are charged first.

[0133] According to an embodiment of the present invention, it also includes:

[0134] Performing a threshold comparison between the real-time electricity price data and a second preset electricity price threshold to obtain a threshold comparison result;

[0135] If the threshold comparison result is greater than the second preset electricity price threshold, the corresponding time node belongs to the peak electricity consumption;

[0136] According to the corresponding state of charge data of each energy storage unit and the battery health state coefficient, combined with the maximum charge and discharge power capacity coefficient, a discharge intensity index corresponding to each energy storage unit is obtained;

[0137] Comparing the discharge intensity index corresponding to each energy storage unit with the preset discharge intensity threshold, determining the discharge priority of the corresponding energy storage unit and increasing the corresponding discharge rate according to the comparison result;

[0138] The calculation formula of the discharge intensity index is:

[0139] ;

[0140] in, is the discharge intensity index corresponding to the i-th energy storage unit among the n energy storage units, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0141] It should be noted that in order to make the entire virtual power plant more economical in electricity consumption and fully consider energy-saving and environmental protection factors, the power grid needs to be discharged during peak electricity consumption periods, that is, as much as possible when the electricity price is high. First, a threshold comparison is made between the real-time electricity price and the second preset electricity price threshold. If the electricity price is greater than the second preset electricity price threshold, it indicates that this is the peak electricity consumption period and the electricity price is high. Furthermore, according to the corresponding state of charge data and the battery health status coefficient of each energy storage unit, combined with the maximum charge and discharge power capacity coefficient, the discharge intensity index corresponding to each energy storage unit is obtained. The discharge intensity index corresponding to each energy storage unit is compared with the preset discharge intensity threshold respectively. According to the comparison result, the discharge priority of the corresponding energy storage unit is determined and the corresponding discharge rate is increased, that is, the energy storage unit with sufficient remaining battery power, good condition and strong maximum charge and discharge power capacity is selected for rapid discharge first.

[0142] In a second aspect, the present invention further discloses a power control system for a virtual power plant energy storage parallel system, comprising a memory and a processor, wherein the memory comprises a power control method program for a virtual power plant energy storage parallel system, and when the power control method program for a virtual power plant energy storage parallel system is executed by the processor, the following steps are implemented:

[0143] Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0144] Obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit;

[0145] Acquire battery performance data corresponding to each energy storage unit, and process the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit;

[0146] According to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is allocated power and operated according to the command power data;

[0147] Collecting actual total power data of the power grid and corresponding total power demand data corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data, and processing to obtain an energy storage supply deviation index;

[0148] A threshold comparison is performed based on the energy storage supply deviation index and a preset energy storage supply deviation threshold, and whether the allocation plan is reasonable is determined based on the comparison result, and corresponding adjustments are made.

[0149] It should be noted that with the rise of the concept of virtual power plants, energy storage parallel systems play an important role in them. In order to improve the performance and adaptability of virtual power plant energy storage parallel systems and meet the increasingly complex needs of power systems, it is of great practical significance and application value to develop an innovative, precise and efficient energy storage parallel system power control method. Therefore, in order to formulate a reasonable power allocation strategy based on the total power demand of the system and the status of each energy storage unit, a technology for weight allocation based on factors such as the remaining power of the energy storage unit, the maximum charge and discharge power capacity, and the health status can be used. First, by monitoring the operation of the virtual power plant and collecting the total power demand data of the power grid and the status parameters of each energy storage unit, the battery status parameters corresponding to each energy storage unit are obtained, and the corresponding battery health status coefficient is obtained by processing. The corresponding battery performance coefficient is obtained. According to the data, and combined with the state parameters of each energy storage unit for processing, the corresponding maximum charge and discharge power capacity coefficient is obtained, and the power weight is allocated according to the total power demand data and state parameters of the power grid in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, and the command power data corresponding to each energy storage unit is obtained. The virtual power plant is allocated and operated according to the command power data, and the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data are collected, and the energy storage supply deviation index is obtained by processing. The energy storage supply deviation index is compared with the preset energy storage supply deviation threshold, and whether the allocation plan is reasonable is judged according to the comparison result, and corresponding adjustments are made, thereby realizing the technology of power control of the virtual power plant energy storage parallel system.

[0150] According to an embodiment of the present invention, the monitoring of the operation of the virtual power plant and the collection of total power demand data of the power grid and status parameters of each energy storage unit include:

[0151] Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit;

[0152] The state parameters of each energy storage unit include charge state data, voltage data, current data and temperature data.

[0153] It should be noted that before allocating power to each energy storage unit in the power grid, it is necessary to monitor the operation of the virtual power plant and collect the total power demand data of the power grid, while also collecting the status parameters of each energy storage unit, including data on charge status, voltage, current and temperature.

[0154] According to an embodiment of the present invention, the acquiring of the battery status parameters corresponding to each energy storage unit and the processing to obtain the battery health status coefficient corresponding to each energy storage unit include:

[0155] Obtaining battery status parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle number data;

[0156] Processing the battery capacity data, the battery internal resistance data, the battery charge and discharge efficiency data, and the battery cycle number data to obtain a battery health status coefficient corresponding to each energy storage unit;

[0157] The calculation formula of the battery health status coefficient is:

[0158] ;

[0159] in, is the battery health status coefficient corresponding to the i-th energy storage unit, , , , They are the battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data corresponding to the i-th energy storage unit. , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0160] It should be noted that the state of each energy storage unit has an important impact on the subsequent power weight distribution. Therefore, it is necessary to obtain the battery state parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data. Among them, battery charge and discharge efficiency data refers to data reflecting the effective conversion degree of energy during the charging and discharging process of the battery, and battery cycle data refers to the number of complete charge and discharge cycles experienced by the battery. Then, the above data is processed to obtain the battery health status coefficient corresponding to each energy storage unit.

[0161] According to an embodiment of the present invention, the acquiring of battery performance data corresponding to each energy storage unit and processing in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit includes:

[0162] Obtaining battery performance data corresponding to each energy storage unit, including battery maximum current data, battery thermal management performance data, and battery voltage data;

[0163] The battery thermal management performance data includes battery heat dissipation efficiency data and operating temperature range data;

[0164] The battery voltage data includes battery rated voltage data and battery actual voltage data;

[0165] According to the battery performance data corresponding to each energy storage unit, combined with the charge state data corresponding to each energy storage unit, the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit is obtained;

[0166] The calculation formula of the maximum charge and discharge power capacity coefficient is:

[0167] ;

[0168] in, is the maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit, , , , , They are the maximum current data of the battery corresponding to the i-th energy storage unit, the battery heat dissipation efficiency data, the operating temperature range data, the battery rated voltage data, and the battery actual voltage data. is the state of charge data corresponding to the i-th energy storage unit, , , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0169] It should be noted that the battery performance data corresponding to each energy storage unit is further obtained, including the data of the maximum battery current, the battery thermal management performance and the battery voltage, wherein the battery thermal management performance data includes the battery heat dissipation efficiency data and the operating temperature range data, and the battery voltage data includes the battery rated voltage data and the battery actual voltage data, and then the above data are processed to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit.

[0170] According to an embodiment of the present invention, the power weight allocation is performed on each energy storage unit according to the total power demand data of the power grid and the state parameters of each energy storage unit, in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the command power data corresponding to each energy storage unit is obtained, and the power allocation and operation of the virtual power plant according to the command power data are performed, including:

[0171] According to the total power demand data of the power grid and the charge state data of each energy storage unit, the power weight allocation is performed on each energy storage unit through a preset energy storage power allocation model in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, so as to obtain the command power data corresponding to each energy storage unit;

[0172] Allocating power and operating the virtual power plant according to the command power data;

[0173] The calculation formula of the command power data is:

[0174] ;

[0175] in, is the command power data corresponding to the i-th energy storage unit among the n energy storage units, is the total power demand data, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0176] It should be noted that, based on the total power demand data of the power grid and the charge state data of each energy storage unit, combined with the battery health status coefficient and the maximum charge and discharge power capacity coefficient, the power weight of each energy storage unit is allocated through the calculation formula of the preset energy storage power allocation model, and the command power data corresponding to each energy storage unit is obtained. Then, according to the obtained command power data, it is allocated to the corresponding energy storage units of the virtual power plant and operated, and the operating status is monitored.

[0177] According to an embodiment of the present invention, the collecting of actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and processing to obtain the energy storage supply deviation index, includes:

[0178] Collect the actual total power data of the power grid and the corresponding total power demand data corresponding to the m time points within the preset time period when the virtual power plant runs according to the command power data, and process them through a preset power grid power control model to obtain an energy storage supply deviation index;

[0179] The calculation formula of the energy storage supply deviation index is:

[0180] ;

[0181] in, is the energy storage supply deviation index, , are the actual total power data and total power demand data corresponding to the jth time point among m time points, is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0182] It should be noted that in order to evaluate whether the power allocation plan is reasonable, it is necessary to determine whether there is a deviation between the actual situation of energy storage supply and demand. Therefore, it is necessary to collect the actual total power data of the power grid corresponding to the m time points within the preset time period when the virtual power plant operates according to the command power data and the corresponding total power demand data, and process them through the calculation formula of the preset power grid power control model to obtain the energy storage supply deviation index.

[0183] According to an embodiment of the present invention, it also includes:

[0184] Perform fault identification evaluation according to the state parameters of each energy storage unit in combination with the battery health status coefficient corresponding to each energy storage unit to obtain a fault identification index corresponding to each energy storage unit;

[0185] Performing a threshold comparison between the fault identification index and a preset fault identification threshold, and judging whether a fault occurs in the corresponding energy storage unit according to the threshold comparison result;

[0186] If the threshold comparison result falls within the preset threshold range, it indicates that the corresponding energy storage unit has a fault;

[0187] Removing the failed energy storage unit and reallocating the corresponding command power data to the remaining energy storage units according to the power allocation scheme;

[0188] The calculation formula of the fault identification index is:

[0189] ;

[0190] in, is the fault identification index corresponding to the i-th energy storage unit among the n energy storage units, , , , , They are respectively the state of charge data, voltage data, current data, temperature data, and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , , , , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0191] It should be noted that in order to make the power allocation scheme more reasonable and flexible, the situation where some energy storage units fail during the actual operation process is fully considered, and the failed energy storage units are removed from the power allocation queue, and then reallocated according to the remaining energy storage units. Therefore, fault identification and evaluation are performed based on the state parameters of each energy storage unit combined with the battery health status coefficient corresponding to each energy storage unit, and the fault identification index corresponding to each energy storage unit is obtained. The threshold is compared with the preset fault identification threshold, and whether the corresponding energy storage unit fails is determined according to the threshold comparison result. If the corresponding energy storage unit fails, the failed energy storage unit is removed, and the remaining energy storage units are reallocated with the corresponding instruction power data according to the power allocation scheme.

[0192] According to an embodiment of the present invention, it also includes:

[0193] Acquire real-time electricity price data, and perform a threshold comparison with a first preset electricity price threshold to obtain a threshold comparison result;

[0194] If the threshold comparison result is less than the first preset electricity price threshold, the corresponding time node belongs to the electricity consumption valley;

[0195] Processing the state of charge data corresponding to each energy storage unit in combination with the battery health state coefficient to obtain a charging demand index corresponding to each energy storage unit;

[0196] Comparing the charging demand index corresponding to each energy storage unit with the preset charging demand threshold, and determining the charging priority of the corresponding energy storage unit according to the comparison result;

[0197] The calculation formula of the charging demand index is:

[0198] ;

[0199] in, is the charging demand index corresponding to the i-th energy storage unit among the n energy storage units, , They are the state of charge data and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0200] It should be noted that in order to make the entire virtual power plant more economical in electricity consumption and fully consider energy-saving and environmental protection factors, the power grid needs to charge as much electricity as possible during the low electricity consumption period, that is, when the electricity price is low. First, obtain real-time electricity price data and compare it with the first preset electricity price threshold. If the electricity price is less than the first preset electricity price threshold, it indicates that this is the low electricity consumption period. The next step is to process the battery health status coefficient according to the corresponding charge state data of each energy storage unit to obtain the charging demand index corresponding to each energy storage unit. The charging demand index corresponding to each energy storage unit is compared with the preset charging demand threshold. The charging priority of the corresponding energy storage unit is determined according to the comparison result, that is, the energy storage units with low remaining battery power and good condition are charged first.

[0201] According to an embodiment of the present invention, it also includes:

[0202] Performing a threshold comparison between the real-time electricity price data and a second preset electricity price threshold to obtain a threshold comparison result;

[0203] If the threshold comparison result is greater than the second preset electricity price threshold, the corresponding time node belongs to the peak electricity consumption;

[0204] According to the corresponding state of charge data of each energy storage unit and the battery health state coefficient, combined with the maximum charge and discharge power capacity coefficient, a discharge intensity index corresponding to each energy storage unit is obtained;

[0205] Comparing the discharge intensity index corresponding to each energy storage unit with the preset discharge intensity threshold, determining the discharge priority of the corresponding energy storage unit and increasing the corresponding discharge rate according to the comparison result;

[0206] The calculation formula of the discharge intensity index is:

[0207] ;

[0208] in, is the discharge intensity index corresponding to the i-th energy storage unit among the n energy storage units, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient (the characteristic coefficient is obtained by querying the preset energy storage power control monitoring platform database).

[0209] It should be noted that in order to make the entire virtual power plant more economical in electricity consumption and fully consider energy-saving and environmental protection factors, the power grid needs to be discharged during peak electricity consumption periods, that is, as much as possible when the electricity price is high. First, a threshold comparison is made between the real-time electricity price and the second preset electricity price threshold. If the electricity price is greater than the second preset electricity price threshold, it indicates that this is the peak electricity consumption period and the electricity price is high. Furthermore, according to the corresponding state of charge data and the battery health status coefficient of each energy storage unit, combined with the maximum charge and discharge power capacity coefficient, the discharge intensity index corresponding to each energy storage unit is obtained. The discharge intensity index corresponding to each energy storage unit is compared with the preset discharge intensity threshold respectively. According to the comparison result, the discharge priority of the corresponding energy storage unit is determined and the corresponding discharge rate is increased, that is, the energy storage unit with sufficient remaining battery power, good condition and strong maximum charge and discharge power capacity is selected for rapid discharge first.

[0210] A third aspect of the present invention provides a readable storage medium, which stores a virtual power plant energy storage parallel system power control method program. When the virtual power plant energy storage parallel system power control method program is executed by a processor, the steps of the virtual power plant energy storage parallel system power control method as described in any one of the above items are implemented.

[0211] The power control method, system and medium of the virtual power plant energy storage parallel system disclosed in the present invention monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the state parameters of each energy storage unit, obtain the battery state parameters corresponding to each energy storage unit, and process to obtain the corresponding battery health state coefficient, obtain the corresponding battery performance data, and process in combination with the state parameters of each energy storage unit to obtain the corresponding maximum charge and discharge power capacity coefficient, perform power weight allocation according to the total power demand data and state parameters of the power grid, in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, obtain the command power data corresponding to each energy storage unit, and perform power allocation and operation of the virtual power plant according to the command power data, collect the actual total power data of the power grid corresponding to m time points within a preset time period when the virtual power plant runs according to the command power data and the corresponding total power demand data, and process to obtain the energy storage supply deviation index, perform threshold comparison between the energy storage supply deviation index and the preset energy storage supply deviation threshold, judge whether the allocation scheme is reasonable according to the comparison result, and make corresponding adjustments, thereby realizing the technology of power control of the virtual power plant energy storage parallel system.

[0212] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as: multiple units or components can be combined, or can be integrated into another system, or some features can be ignored or not executed. In addition, the coupling, direct coupling, or communication connection between the components shown or discussed can be through some interfaces, and the indirect coupling or communication connection of the devices or units can be electrical, mechanical or other forms.

[0213] The units described above as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units; they may be located in one place or distributed on multiple network units; some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0214] In addition, all functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may be separately used as a unit, or two or more units may be integrated into one unit; the above-mentioned integrated units may be implemented in the form of hardware or in the form of hardware plus software functional units.

[0215] Those skilled in the art can understand that: all or part of the steps of implementing the above method embodiments can be completed by hardware related to program instructions, the aforementioned program can be stored in a readable storage medium, and when the program is executed, it executes the steps of the above method embodiments; and the aforementioned storage medium includes: mobile storage devices, read-only memories (ROM, Read-Only Memory), random access memories (RAM, Random Access Memory), disks or optical disks, and other media that can store program codes.

[0216] Alternatively, if the above-mentioned integrated unit of the present invention is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a readable storage medium. Based on this understanding, the technical solution of the embodiment of the present invention can be essentially or partly reflected in the form of a software product that contributes to the prior art. The software product is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as mobile storage devices, ROM, RAM, magnetic disks or optical disks.

Claims

1. A power control method for a virtual power plant energy storage parallel system. It is characterized in that The following steps are involved: Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit; Obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit; Acquire battery performance data corresponding to each energy storage unit, and process the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit; According to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is allocated power and operated according to the command power data; Collecting actual total power data of the power grid and corresponding total power demand data corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data, and processing to obtain an energy storage supply deviation index; Comparing the energy storage supply deviation index with a preset energy storage supply deviation threshold, judging whether the allocation scheme is reasonable based on the comparison result, and making corresponding adjustments; The obtaining of the battery status parameters corresponding to each energy storage unit and processing to obtain the battery health status coefficient corresponding to each energy storage unit includes: Obtaining battery status parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle number data; Processing the battery capacity data, the battery internal resistance data, the battery charge and discharge efficiency data, and the battery cycle number data to obtain a battery health status coefficient corresponding to each energy storage unit; The calculation formula of the battery health status coefficient is: ; in, is the battery health status coefficient corresponding to the i-th energy storage unit, , , , They are the battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data corresponding to the i-th energy storage unit. , , , , is the preset characteristic coefficient; The acquiring of battery performance data corresponding to each energy storage unit and processing in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit includes: Obtaining battery performance data corresponding to each energy storage unit, including battery maximum current data, battery thermal management performance data, and battery voltage data; The battery thermal management performance data includes battery heat dissipation efficiency data and operating temperature range data; The battery voltage data includes battery rated voltage data and battery actual voltage data; According to the battery performance data corresponding to each energy storage unit, combined with the charge state data corresponding to each energy storage unit, the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit is obtained; The calculation formula of the maximum charge and discharge power capacity coefficient is: ; in, is the maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit, , , , , They are the maximum current data of the battery corresponding to the i-th energy storage unit, the battery heat dissipation efficiency data, the operating temperature range data, the battery rated voltage data, and the battery actual voltage data. is the state of charge data corresponding to the i-th energy storage unit, , , , , , is the preset characteristic coefficient; The power weight allocation is performed on each energy storage unit according to the total power demand data of the power grid and the state parameters of each energy storage unit in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the command power data corresponding to each energy storage unit is obtained, and the power allocation and operation of the virtual power plant are performed according to the command power data, including: According to the total power demand data of the power grid and the state of charge data of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the power weight allocation is performed on each energy storage unit through a preset energy storage power allocation model to obtain the command power data corresponding to each energy storage unit; Allocating power and operating the virtual power plant according to the command power data; The calculation formula of the command power data is: ; in, is the command power data corresponding to the i-th energy storage unit among the n energy storage units, is the total power demand data, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient.

2. The power control method of the virtual power plant energy storage parallel system according to claim 1, It is characterized in that The monitoring of the operation of the virtual power plant and the collection of the total power demand data of the power grid and the status parameters of each energy storage unit include: Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit; The state parameters of each energy storage unit include charge state data, voltage data, current data and temperature data.

3. The power control method of the virtual power plant energy storage parallel system according to claim 2, It is characterized in that The collecting the actual total power data of the power grid and the corresponding total power demand data corresponding to the m time points within the preset time period when the virtual power plant runs according to the command power data, and processing to obtain the energy storage supply deviation index, includes: Collect the actual total power data of the power grid and the corresponding total power demand data corresponding to the m time points within the preset time period when the virtual power plant runs according to the command power data, and process them through a preset power grid power control model to obtain an energy storage supply deviation index; The calculation formula of the energy storage supply deviation index is: ; in, is the energy storage supply deviation index, , are the actual total power data and total power demand data corresponding to the jth time point among m time points, is the preset characteristic coefficient.

4. The power control method of the virtual power plant energy storage parallel system according to claim 3, It is characterized in that Also includes: Perform fault identification evaluation according to the state parameters of each energy storage unit in combination with the battery health status coefficient corresponding to each energy storage unit to obtain a fault identification index corresponding to each energy storage unit; Performing a threshold comparison between the fault identification index and a preset fault identification threshold, and judging whether a fault occurs in the corresponding energy storage unit according to the threshold comparison result; If the threshold comparison result falls within the preset threshold range, it indicates that the corresponding energy storage unit has a fault; Removing the failed energy storage unit and reallocating the corresponding command power data to the remaining energy storage units according to the power allocation scheme; The calculation formula of the fault identification index is: ; in, is the fault identification index corresponding to the i-th energy storage unit among the n energy storage units, , , , , They are respectively the state of charge data, voltage data, current data, temperature data, and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , , , , is the preset characteristic coefficient.

5. The power control method of the virtual power plant energy storage parallel system according to claim 3, It is characterized in that Also includes: Acquire real-time electricity price data, and perform a threshold comparison with a first preset electricity price threshold to obtain a threshold comparison result; If the threshold comparison result is less than the first preset electricity price threshold, the corresponding time node belongs to the electricity consumption valley; Processing the state of charge data corresponding to each energy storage unit in combination with the battery health state coefficient to obtain a charging demand index corresponding to each energy storage unit; Comparing the charging demand index corresponding to each energy storage unit with the preset charging demand threshold, and determining the charging priority of the corresponding energy storage unit according to the comparison result; The calculation formula of the charging demand index is: ; in, is the charging demand index corresponding to the i-th energy storage unit among the n energy storage units, , They are the state of charge data and battery health status coefficient corresponding to the i-th energy storage unit among the n energy storage units, , is the preset characteristic coefficient.

6. A power control system for a virtual power plant energy storage parallel system. It is characterized in that The system includes: a memory and a processor, wherein the memory includes a program of a power control method for a virtual power plant energy storage parallel system, and when the program of the power control method for a virtual power plant energy storage parallel system is executed by the processor, the following steps are implemented: Monitor the operation of the virtual power plant and collect the total power demand data of the power grid and the status parameters of each energy storage unit; Obtaining battery status parameters corresponding to each energy storage unit, and processing to obtain battery health status coefficients corresponding to each energy storage unit; Acquire battery performance data corresponding to each energy storage unit, and process the data in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit; According to the total power demand data of the power grid and the state parameters of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, power weight allocation is performed on each energy storage unit, the command power data corresponding to each energy storage unit is obtained, and the virtual power plant is allocated power and operated according to the command power data; Collecting actual total power data of the power grid and corresponding total power demand data corresponding to m time points within a preset time period when the virtual power plant operates according to the command power data, and processing to obtain an energy storage supply deviation index; Comparing the energy storage supply deviation index with a preset energy storage supply deviation threshold, judging whether the allocation scheme is reasonable based on the comparison result, and making corresponding adjustments; The obtaining of the battery status parameters corresponding to each energy storage unit and processing to obtain the battery health status coefficient corresponding to each energy storage unit includes: Obtaining battery status parameters corresponding to each energy storage unit, including battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle number data; Processing the battery capacity data, the battery internal resistance data, the battery charge and discharge efficiency data, and the battery cycle number data to obtain a battery health status coefficient corresponding to each energy storage unit; The calculation formula of the battery health status coefficient is: ; in, is the battery health status coefficient corresponding to the i-th energy storage unit, , , , They are the battery capacity data, battery internal resistance data, battery charge and discharge efficiency data, and battery cycle data corresponding to the i-th energy storage unit. , , , , is the preset characteristic coefficient; The acquiring of battery performance data corresponding to each energy storage unit and processing in combination with the state parameters of each energy storage unit to obtain the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit includes: Obtaining battery performance data corresponding to each energy storage unit, including battery maximum current data, battery thermal management performance data, and battery voltage data; The battery thermal management performance data includes battery heat dissipation efficiency data and operating temperature range data; The battery voltage data includes battery rated voltage data and battery actual voltage data; According to the battery performance data corresponding to each energy storage unit, combined with the charge state data corresponding to each energy storage unit, the maximum charge and discharge power capacity coefficient corresponding to each energy storage unit is obtained; The calculation formula of the maximum charge and discharge power capacity coefficient is: ; in, is the maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit, , , , , They are the maximum current data of the battery corresponding to the i-th energy storage unit, the battery heat dissipation efficiency data, the operating temperature range data, the battery rated voltage data, and the battery actual voltage data. is the state of charge data corresponding to the i-th energy storage unit, , , , , , is the preset characteristic coefficient; The power weight allocation is performed on each energy storage unit according to the total power demand data of the power grid and the state parameters of each energy storage unit in combination with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the command power data corresponding to each energy storage unit is obtained, and the power allocation and operation of the virtual power plant are performed according to the command power data, including: According to the total power demand data of the power grid and the state of charge data of each energy storage unit, combined with the battery health state coefficient and the maximum charge and discharge power capacity coefficient, the power weight allocation is performed on each energy storage unit through a preset energy storage power allocation model to obtain the command power data corresponding to each energy storage unit; Allocating power and operating the virtual power plant according to the command power data; The calculation formula of the command power data is: ; in, is the command power data corresponding to the i-th energy storage unit among the n energy storage units, is the total power demand data, , , They are the state of charge data, battery health status coefficient, and maximum charge and discharge power capacity coefficient corresponding to the i-th energy storage unit among the n energy storage units. is the preset characteristic coefficient.

7. A computer-readable storage medium, It is characterized in that The computer-readable storage medium includes a virtual power plant energy storage parallel system power control method program. When the virtual power plant energy storage parallel system power control method program is executed by a processor, the steps of the virtual power plant energy storage parallel system power control method as described in any one of claims 1 to 5 are implemented.