Signal intersection straight-going waiting area traffic signal control method
By predicting the queue length of through vehicles and the green light release relationship at signalized intersections, dynamically adjusting the signal light turn-on time in the through waiting area solves the problems of traffic delays and carbon emissions in traditional methods, and improves the intersection's traffic capacity and usage efficiency.
Patent Information
- Application Number
- CN202410910898.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2024-10-15
AI Technical Summary
The traditional traffic signal control method of the straight-way waiting area at signalized intersections cannot effectively adjust the signal activation time of the straight-going waiting area under different traffic flow conditions, resulting in traffic delays and increased carbon emissions, and has a negative impact on the driver's psychology.
By obtaining the signal timing plan and real-time traffic data of the signalized intersection, a straight lane queuing model is constructed to predict the relationship between the vehicle queue length and the green light release vehicle queue length, dynamically determine the turn-on time of the traffic signal in the straight waiting area, and improve the straight waiting area. usage efficiency.
It effectively improves the use efficiency of the straight waiting area, reduces traffic delays and carbon emissions, reduces the number of secondary starts and stops of vehicles, and improves the traffic capacity of the intersection.
Smart Images

Figure CN118781833A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of traffic information and control, and in particular to a traffic signal control method in a straight-ahead waiting area of a signalized intersection. Background Art
[0002] Urban road signal intersections are the key to urban traffic. They have complex traffic characteristics and are prone to traffic congestion. By setting up a straight-through waiting area, we can make full use of time and space resources to improve the traffic capacity and traffic efficiency of the intersection. The traditional straight-through waiting area traffic signal control method is to activate the straight-through waiting area signal when the left-turning vehicle in the previous phase is released, so that the vehicle enters the straight-through waiting area in advance to increase the traffic capacity of the intersection. However, the traffic flow arriving at the intersection at different time periods is different. According to the characteristics of the straight-through traffic flow on the entrance road, it can be divided into two situations: saturated traffic and unsaturated traffic.
[0003] Under saturated traffic conditions, the through-traffic volume arriving at the entrance is large, the vehicle density is high, and traffic jams are prone to occur. The traditional through-traffic waiting area traffic signal control method can improve the traffic capacity of the intersection and shorten the length of the vehicle queue. However, there is also the phenomenon of unreasonable activation time of the traffic signal entering the through-traffic waiting area, which causes the through-traffic vehicles to start and stop twice, increasing traffic delays at the intersection and increasing vehicle carbon emissions.
[0004] Under unsaturated traffic conditions, there are not enough straight-moving vehicles arriving at the entrance, and conventional release methods can satisfy vehicles to pass through the intersection smoothly. At this time, setting up a straight-moving waiting area will not only cause space loss at the intersection and have a certain impact on the operation of other traffic, but also cause vehicles to enter the straight-moving waiting area and cause secondary start-stop phenomena, increasing intersection delays and increasing carbon emissions at the intersection. At the same time, the number of starts and stops of straight-moving vehicles increases after the waiting area is set, which will also have a negative impact on the driver's psychology. Summary of the invention
[0005] The purpose of the present invention is to provide a traffic signal control method for a straight-through waiting area at a signalized intersection. According to the traffic flow characteristics of different signal periods at the intersection, by predicting the length of the straight-through vehicle queue, analyzing the relationship between the vehicle queue length and the green light vehicle queue length and the straight-through waiting area length, a traffic signal control method for straight-through vehicles under different situations is given.
[0006] To achieve the above object, the technical solution of the present invention is:
[0007] The present invention provides a traffic signal control method for a straight-through waiting area at a signalized intersection, which specifically comprises the following steps:
[0008] S1. Obtain a signal timing plan for a signalized intersection, the signal timing plan including: signal cycle time, green light time of each phase of the intersection within the signal cycle time, green-to-signal ratio, and effective green light time;
[0009] S2. Real-time traffic data of the signalized intersection during each signal cycle is collected and stored in the original database of intersection traffic. Based on the traffic data, the through traffic flow rate, through lane saturation and through lane green light saturation flow rate during each signal cycle are calculated;
[0010] S3, constructing a queuing model for the number of vehicles queuing in the through lane, and calculating the maximum number of vehicles queuing in the through lane within the current signal cycle time according to the through traffic flow rate and the saturation of the through lane within the current signal cycle time;
[0011] S4. Calculate the maximum queue length of the through lane in the current signal cycle and the queue length of the vehicles passing through the through lane within the effective green light time of the current signal cycle according to the maximum number of vehicles queuing in the through lane and the green light saturation flow rate of the through lane in the current signal cycle;
[0012] S5. Obtain the length of the through waiting area, calculate the sum of the length of the through waiting area and the length of the queue of vehicles passing through the through lane within the effective green light time, and obtain the waiting length;
[0013] S6. Compare the maximum queue length of through vehicles with the waiting length, determine the traffic light opening time of the through waiting area according to the comparison result, and control the traffic light of the through waiting area to open when the opening time is reached within the current signal cycle.
[0014] In some optional implementations, the length of the straight waiting area includes the length of the straight waiting area corresponding to each straight lane, and the length of each straight waiting area is stored in the waiting area length sequence. Then, the length to be passed in step S5 includes:
[0015] S51, summing the minimum straight waiting area length in the waiting area length sequence and the length of the queue of vehicles passing through the straight lane within the effective green light time to obtain a first waiting length;
[0016] S52: sum the maximum straight-through waiting area length in the waiting area length sequence and the length of the queue of vehicles passing through the straight lane within the effective green light time to obtain a second waiting length.
[0017] In some optional implementations, the specific process of step S6 is:
[0018] S61, when the maximum queue length of through vehicles is greater than the queue length of vehicles passing through the through lane within the effective green light time and is less than or equal to the first waiting length, determining the traffic signal light opening time of the through waiting area according to the minimum through waiting area length in the waiting area length sequence;
[0019] S62, when the maximum queue length of straight vehicles is greater than the first waiting length to be passed and less than or equal to the second waiting length to be passed, determining the traffic signal light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence;
[0020] S63: When the maximum queue length of straight vehicles is greater than the second waiting length, determining the traffic signal light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence.
[0021] In some optional implementations, according to the length sequence of the waiting area (L1, L2.....L N ), N represents the number of through lanes, and the calculation method for determining the opening time Δt of the traffic signal lights in the through waiting area within the time signal cycle is:
[0022]
[0023] Among them, a is the preset acceleration of the vehicle entering the straight waiting area, max(L1,L2.....L N ) represents the maximum length of the waiting area in the waiting area length sequence, min(L1,L2.....L N ) represents the minimum straight waiting area length in the waiting area length sequence.
[0024] In some optional implementations, the process of determining the traffic light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence in step S63 further includes:
[0025] Determine whether the traffic signal light activation time in the straight waiting area is greater than the left turn green light release time in the opposite phase. If so, the left turn green light release time in the opposite phase is determined as the traffic signal light activation time in the straight waiting area.
[0026] In some optional implementations, the method for calculating the green light saturation flow rate of the through lane is:
[0027] Real-time statistics of the number of vehicles passing through the green light time of each signal cycle based on traffic data;
[0028] The maximum value of the ratio of the number of vehicles passing through the green light time to the green light time in each signal cycle time is calculated to obtain the green light saturation flow rate of the through lane.
[0029] In some optional implementations, the method for obtaining the through traffic flow rate and the through lane saturation within the current signal cycle time in step S3 is:
[0030] The through traffic flow rate sequence of the import in the n-1 signal cycles before the current nth signal cycle is calculated to obtain the through traffic flow rate sequence {q1,q2,q3......q n-1};
[0031] According to the through traffic flow rate sequence, the through traffic flow rate q of the current nth signal cycle time is predicted using the exponential smoothing method. n ;
[0032] Combined with the green-light ratio λ of the through lane phase and the green light saturation flow rate p of the through lane n , calculate the capacity c of the through lane at the signalized intersection L , according to the traffic capacity c L Calculate the saturation x of the straight lane at the current nth signal cycle time. The calculation formula is:
[0033] c L =3600p n λ
[0034] x=3600q n λ / c L .
[0036] In some optional implementations, the queuing model is:
[0037]
[0038] K b =0.12I(q n g E ) 0.7
[0039] Where T is the signal cycle time, in seconds; λ is the green-to-signal ratio of the phase of the import through lane; g is the green light time, in seconds; K b is the correction coefficient, I is the upstream intersection arrival rate correlation coefficient; g E is the effective green light time of the through lane phase, Q bL It is the initial queue length of the import through lane phase at the beginning of the nth signal cycle time.
[0040] In some optional implementations, the maximum queue length L of straight-going vehicles in the current signal cycle is calculated in step S4. m The calculation method is:
[0041]
[0042] Where N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.
[0043] In some optional implementations, the length L of the queue of vehicles passing through the through lane within the effective green light time of the current signal cycle is calculated. f The calculation method is:
[0044]
[0045] Where β is the delay adjustment coefficient; p n is the green light saturation flow rate of the straight lane, in veh / s; g E is the effective green light time in seconds, N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.
[0046] The present invention has the beneficial effects:
[0047] Compared with the traditional signal intersection straight waiting area traffic signal control scheme, the present invention predicts the queue of straight vehicles arriving at the intersection, and judges its relationship with the maximum queue length of vehicles passing through the intersection during the effective green light time and the straight waiting area, and dynamically determines whether to enable the signal to enter the straight waiting area and the signal time to enter the straight waiting area in advance, thereby improving the use efficiency of the straight waiting area. The present invention can effectively improve the adaptability of the straight waiting area, reduce traffic delays at intersections, reduce the number of secondary vehicle starts and stops, and reduce carbon emissions from intersection traffic, thereby maximizing the traffic capacity of the intersection. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 A flow chart of a traffic signal control method provided by an embodiment of the present invention;
[0049] Figure 2 A schematic diagram of signal control in a straight-ahead waiting area at a signal light intersection provided by an embodiment of the present invention;
[0050] Figure 3 A schematic diagram of a setting scheme for a straight-ahead waiting area at a signal light intersection provided by an embodiment of the present invention;
[0051] Figure 4 A schematic diagram of the phase scheme setting of a signal light intersection provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means intended to limit the present invention and its application or use. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] The relative arrangement of components and steps, the numerical expressions and numerical values set forth in these embodiments do not limit the scope of the present invention unless specifically stated otherwise.
[0054] At the same time, it should be understood that for the convenience of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship.
[0055] Additionally, descriptions of well-known structures, functions, and configurations may be omitted for clarity and conciseness.One of ordinary skill in the art will recognize that various changes and modifications may be made to the examples described herein without departing from the spirit and scope of the present disclosure.
[0056] Technologies, methods, and apparatus known to ordinary technicians in the relevant field may not be discussed in detail, but where appropriate, such technologies, methods, and apparatus should be considered part of the authorization specification.
[0057] In all examples shown and discussed herein, any specific values should be interpreted as merely exemplary and not as limiting. Therefore, other examples of the exemplary embodiments may have different values.
[0058] Example 1
[0059] like Figure 3 As shown in the figure, in order to improve the traffic capacity of the intersection, a straight-ahead waiting area is set at the intersection with conditions and the straight-ahead waiting vehicles are guided into the center of the intersection to wait through traffic signal control. At this time, the waiting vehicles start to drive from the first stop line to the second stop line and stop and wait, as shown in the figure. Figure 3 On the other hand, in order to better direct vehicles to enter the straight waiting area, a signal display screen for entering the straight waiting area in advance is set on the intersection signal light pole for signal prompts, such as Figure 4 In the fixed cycle mode, the intersection adopts four-phase release. The first phase releases east-west straight vehicles, the second phase releases east-west left-turning vehicles, the third phase releases north-south straight vehicles, and the fourth phase releases north-south left-turning vehicles. Each phase is set with green light signal G, green flashing signal H, yellow light signal Y, and red light signal R in sequence. The time for entering the straight waiting area in advance is set to Δt, as shown in the attached figure. Figure 2 The present invention dynamically adjusts the traffic signal for entering the straight waiting area and advances the time to enter the straight waiting area according to the queue length of the straight vehicles, thereby improving the traffic capacity of the signal intersection, reducing traffic delays at the intersection, reducing the number of secondary starts and stops of vehicles, and reducing carbon emissions from intersection traffic.
[0060] S2. Real-time traffic data of the signalized intersection during each signal cycle is collected and stored in the original database of intersection traffic. Based on the traffic data, the through traffic flow rate, through lane saturation and through lane green light saturation flow rate during each signal cycle are calculated;
[0061] like Figure 1 As shown, this embodiment provides a method for controlling a traffic signal in a straight-through waiting area at a signalized intersection, taking the execution of a waiting area signal light control in an east-west straight-through phase as an example, specifically comprising the following steps:
[0062] S1. Obtain a signal timing plan for a signalized intersection, the signal timing plan including: signal cycle time, green light time of each phase of the intersection within the signal cycle time, green-to-signal ratio, and effective green light time;
[0063] The signal light timing scheme is generally pre-configured and in this application, the signal light timing scheme is preset, wherein the green-to-signal ratio is the ratio of the green light time to the signal cycle of the phase, and the effective green light time is the sum of the green flash time and the yellow light time;
[0064] S2. Real-time traffic data of the signalized intersection during each signal cycle is collected and stored in the original database of intersection traffic. Based on the traffic data, the through traffic flow rate, through lane saturation and through lane green light saturation flow rate of the through phase during each signal cycle are calculated;
[0065] For each intersection, a video detection device is generally installed. Traffic data of the signalized intersection can be collected by using the device to establish an original database of intersection traffic. Traffic data includes: the initial queue of the through lane at the beginning of each signal cycle time, and the number of vehicles passing through each signal cycle time;
[0066] Using the original database data, calculate the intersection traffic related data. The traffic related data includes the straight traffic flow rate of the straight phase within the signal cycle time, the green light saturation flow rate of the straight lane, and the saturation of the straight lane;
[0067] If we want to calculate the through traffic flow rate in the current nth signal cycle, we need to obtain the through lane traffic flow rate sequence of the entrance road in the previous n-1 cycles, and obtain the through lane traffic flow rate sequence {q1,q2,q3...q n-1}, and the exponential smoothing method is used to predict the straight traffic flow rate q of the current nth signal cycle time n ;
[0068] For the through lane, the green light saturation flow rate is the maximum value of the ratio of the number of vehicles passing through the green light time to the green light time in each signal cycle time;
[0069] Then, combined with the green-light ratio λ of the through lane phase and the green light saturation flow rate p of the through lane n , calculate the capacity c of the through lane at the signalized intersection L , according to the traffic capacity c L Calculate the saturation x of the straight lane at the current nth signal cycle time. The calculation formula is:
[0070] c L =3600p n λ
[0071] x=3600q n λ / c L .
[0073] S3, constructing a queuing model for the number of vehicles queuing in the through lane, and calculating the maximum number of vehicles queuing in the through lane within the current signal cycle time according to the through traffic flow rate and the saturation of the through lane within the current signal cycle time;
[0074] The queue model is:
[0075]
[0076] K b =0.12I(q n g E ) 0.7
[0077] Among them, q n is the traffic flow rate of the through lane in the nth cycle, veh / s; T is the signal cycle time, in seconds; λ is the green signal ratio of the import lane; g is the green light time, in seconds; c L is the through lane capacity, veh / h; x is the through lane saturation, x=3600q n λ / c L ; K b is the correction factor, K b =0.12I(q n g E ) 0.7 , I is the upstream arrival rate correlation coefficient; g E is the effective green light time, in seconds; Q bL is the initial queue of the through lane at the beginning of the nth cycle, obtained through the intersection video detector.
[0078] S4. Calculate the maximum queue length of the through lane in the current signal cycle and the queue length of the vehicles passing through the through lane within the effective green light time of the current signal cycle according to the maximum number of vehicles queuing in the through lane and the green light saturation flow rate of the through lane in the current signal cycle;
[0079] Specifically, if the straight-moving vehicles are evenly distributed after arriving at the entrance, the vehicles at the end of different lanes are in the same queue position. At this time, the maximum queue length L of straight-moving vehicles in the east-west straight-moving phase in the current signal cycle is calculated: m The calculation method is:
[0080]
[0081] Where N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.
[0082] Specifically, calculate the queue length L of vehicles passing through the through lane within the effective green light time of the current signal cycle. f The calculation method is:
[0083]
[0084] Where β is the delay adjustment coefficient; p n is the green light saturation flow rate of the straight lane, in veh / s; g E is the effective green light time in seconds, N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.
[0085] S5. Obtain the length of the through waiting area, calculate the sum of the length of the through waiting area and the length of the queue of vehicles passing through the through lane within the effective green light time, and obtain the waiting length;
[0086] The length of the straight waiting area includes the length of the straight waiting area corresponding to each straight lane. The length of each straight waiting area is stored in the waiting area length sequence (L1, L2.....L N ), N represents the number of through lanes, and the length to be passed in step S5 includes:
[0087] S51, sum the minimum straight waiting area length in the waiting area length sequence and the length of the vehicle queue passing through the straight lane within the effective green light time to obtain the first waiting length: min(L1, L2.....L N )+L f ;
[0088] S52, summing the maximum straight-through waiting area length in the waiting area length sequence and the length of the vehicle queue passing through the straight lane within the effective green light time, to obtain the second waiting length: max(L1,L2.....L N )+L f .
[0089] S6. Compare the maximum queue length of through vehicles with the waiting length, determine the traffic light opening time of the through waiting area according to the comparison result, and control the traffic light of the through waiting area to open when the opening time is reached within the current signal cycle.
[0090] Specifically, the comparison process is:
[0091] S61, if L m ≤L f , indicating that the traffic saturation rate is not high at this time, so the traffic signal for entering the straight-ahead waiting area is not activated;
[0092] S62, if L f <L m ≤min(L1,L2.....L N )+L f , indicating that when the maximum queue length of through vehicles is greater than the queue length of vehicles passing through the through lane within the effective green light time and is less than or equal to the first waiting length, the traffic signal of the through waiting area needs to be turned on. Figure 4 As shown, the traffic light opening time is Δt before the start of the next signal cycle time, that is, the traffic signal of the straight waiting area is turned on at Δt before the end of the red light time of the current signal cycle time (Δt in this application represents a time period, for example, if the total length of the red light time is 30s, the traffic signal of the waiting area needs to be turned on at (30-Δt)th time):
[0093] a is the acceleration when entering the straight-ahead waiting area;
[0094] S63, min (L1, L2.....L N )+L f <L m ≤max(L1,L2.....L N )+L f , when the maximum queue length of through vehicles is greater than the first waiting length and less than or equal to the second waiting length, the traffic signal light opening time of the through waiting area is determined according to the maximum through waiting area length in the waiting area length sequence:
[0095] If △t is greater than the left turn green light release time of the opposite phase (in this embodiment, the east-west straight phase is taken as an example, and the opposite phase is the north-south left turn phase), the advance time is the left turn green light release time of the opposite phase;
[0096] S64, if L m ≥max(L1,L2......L N )+L f When the maximum queue length of straight vehicles is greater than the second waiting length, the traffic signal light opening time of the straight waiting area is determined according to the maximum straight waiting area length in the waiting area length sequence:
[0097] If the traffic signal light activation time in the straight waiting area is greater than the left turn green light release time in the opposite phase, the left turn green light release time in the opposite phase is determined as the traffic signal light activation time in the straight waiting area.
[0098] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. According to the technical essence of the present invention, within the spirit and principles of the present invention, any simple modification, equivalent replacement and improvement made to the above embodiment still falls within the protection scope of the technical solution of the present invention.
Claims
1. A traffic signal control method for a straight-through waiting area at a signalized intersection, characterized in that: The specific steps include: S1. Obtain a signal timing plan for a signalized intersection, the signal timing plan including: signal cycle time, green light time of each phase of the intersection within the signal cycle time, green-to-signal ratio, and effective green light time; S2. Real-time traffic data of the signalized intersection during each signal cycle is collected and stored in the original database of intersection traffic. Based on the traffic data, the through traffic flow rate, through lane saturation and through lane green light saturation flow rate during each signal cycle are calculated; S3, constructing a queuing model for the number of vehicles queuing in the through lane, and calculating the maximum number of vehicles queuing in the through lane within the current signal cycle time according to the through traffic flow rate and the saturation of the through lane within the current signal cycle time; S4. Calculate the maximum queue length of the through lane in the current signal cycle and the queue length of the vehicles passing through the through lane within the effective green light time of the current signal cycle according to the maximum number of vehicles queuing in the through lane and the green light saturation flow rate of the through lane in the current signal cycle; S5. Obtain the length of the through waiting area, calculate the sum of the length of the through waiting area and the length of the queue of vehicles passing through the through lane within the effective green light time, and obtain the waiting length; S6. Compare the maximum queue length of through vehicles with the waiting length, determine the traffic light opening time of the through waiting area according to the comparison result, and control the traffic light of the through waiting area to open when the opening time is reached within the current signal cycle.
2. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 1, characterized in that: The length of the straight waiting area includes the length of the straight waiting area corresponding to each straight lane. The length of each straight waiting area is stored in the waiting area length sequence. Then, the length to be passed in step S5 includes: S51, summing the minimum straight waiting area length in the waiting area length sequence and the length of the queue of vehicles passing through the straight lane within the effective green light time to obtain a first waiting length; S52: sum the maximum straight-through waiting area length in the waiting area length sequence and the length of the queue of vehicles passing through the straight lane within the effective green light time to obtain a second waiting length.
3. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 2, characterized in that: The specific process of step S6 is: S61, when the maximum queue length of through vehicles is greater than the queue length of vehicles passing through the through lane within the effective green light time and is less than or equal to the first waiting length, determining the traffic signal light opening time of the through waiting area according to the minimum through waiting area length in the waiting area length sequence; S62, when the maximum queue length of straight vehicles is greater than the first waiting length to be passed and less than or equal to the second waiting length to be passed, determining the traffic signal light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence; S63: When the maximum queue length of straight vehicles is greater than the second waiting length, determining the traffic signal light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence.
4. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 3, characterized in that: According to the length sequence of the waiting area (L1, L2.....L N ), N represents the number of through lanes, and the calculation method for determining the opening time Δt of the traffic signal lights in the through waiting area within the time signal cycle is: or Among them, a is the preset acceleration of the vehicle entering the straight waiting area, max(L1,L2.....L N ) represents the maximum length of the waiting area in the waiting area length sequence, min(L1,L2.....L N ) represents the minimum straight waiting area length in the waiting area length sequence.
5. The method for controlling a traffic signal in a straight-ahead waiting area at a signalized intersection according to claim 3, characterized in that: The process of determining the traffic signal light opening time of the straight waiting area according to the maximum straight waiting area length in the waiting area length sequence in step S63 further includes: Determine whether the traffic signal light activation time in the straight waiting area is greater than the left turn green light release time in the opposite phase. If so, the left turn green light release time in the opposite phase is determined as the traffic signal light activation time in the straight waiting area.
6. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 1, characterized in that: The method for calculating the green light saturation flow rate of the through lane is: Real-time statistics of the number of vehicles passing through the green light time of each signal cycle based on traffic data; The maximum value of the ratio of the number of vehicles passing through the green light time to the green light time in each signal cycle time is calculated to obtain the green light saturation flow rate of the through lane.
7. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 6, characterized in that: The method for obtaining the through traffic flow rate and through lane saturation within the current signal cycle time in step S3 is: The through traffic flow rate sequence of the import in the n-1 signal cycles before the current nth signal cycle is calculated to obtain the through traffic flow rate sequence {q1,q2,q3......q n-1 }; According to the through traffic flow rate sequence, the through traffic flow rate q of the current nth signal cycle time is predicted using the exponential smoothing method. n ; Combined with the green-light ratio λ of the through lane phase and the green light saturation flow rate p of the through lane n , calculate the capacity c of the through lane at the signalized intersection L , according to the traffic capacity c L Calculate the saturation x of the straight lane at the current nth signal cycle time. The calculation formula is: c L =3600p n l x=3600q n λ / c L 。 8. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 7, characterized in that: The queue model is: K b =0.12I(q n g E ) 0.7 Where T is the signal cycle time, in seconds; λ is the green-to-signal ratio of the phase of the import through lane; g is the green light time, in seconds; K b is the correction coefficient, I is the upstream intersection arrival rate correlation coefficient; g E is the effective green light time of the through lane phase, Q bL It is the initial queue length of the import through lane phase at the beginning of the nth signal cycle time.
9. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 8, characterized in that: In step S4, the maximum queue length L of straight-going vehicles in the current signal cycle is calculated. m The calculation method is: Where N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.
10. A traffic signal control method for a straight-through waiting area at a signalized intersection according to claim 6, characterized in that: Calculate the length L of the queue of vehicles passing through the through lane within the effective green light time of the current signal cycle f The calculation method is: Where β is the delay adjustment coefficient; p n is the green light saturation flow rate of the straight lane, in veh / s; g E is the effective green light time in seconds, N is the number of through lanes, l c The default length of the vehicle, in m, l s It is the safe distance for queue parking, in meters.