Port single ship operation cost control evaluation management method and system thereof

Through big data processing and multi-dimensional data modeling, combined with life cycle and earned value perspective evaluation models, the problem of port single-vessel operation cost control relying on manual management has been solved, automated and intelligent management has been achieved, and cost control and operational efficiency have been improved.

CN118798740AInactive Publication Date: 2024-10-18YANTAI PORT GRP CO LTD +1

Patent Information

Application Number
CN202411273061.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Single-vessel operation cost control in ports relies on manual management and lacks informatization and intelligence, resulting in low data processing efficiency and insufficient decision-making support, making it difficult to achieve a balance between cost control and efficiency improvement.

Method used

Big data processing technology is used to integrate, standardize, multi-dimensional data modeling and governance of single ship operation cost data, establish a life cycle assessment model and an earned value perspective assessment model, and realize automated and intelligent cost control management.

Benefits of technology

It improves the cost control efficiency and management level of single ship operations in the port, improves operational efficiency and competitiveness, provides fast processing and real-time visual analysis capabilities, and adapts to the flexible needs of enterprises.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798740A_ABST
    Figure CN118798740A_ABST
Patent Text Reader

Abstract

The invention discloses a port single-ship operation cost control evaluation management method and system, and relates to the field of port single-ship operation management. In order to solve the defects that the existing port single-ship operation cost management and control depends on manpower, the real-time performance is poor, the efficiency is low and the interactivity is poor, data integration is carried out on cost data related to single-ship operation dispersed in each transactional business system; carrying out data standardization on the integrated single-ship operation cost income data; building a multi-dimensional data plate type and building a data mining data model; performing comprehensive data management on the standardized single-ship operation cost income data; system construction display is carried out on the single-ship operation process after comprehensive data treatment; performing multi-dimensional single-ship operation benefit data model establishment and management mode construction according to the displayed single-ship operation process; a single ship work promotion indicator is generated using the life cycle evaluation model and the win value perspective evaluation model. The method is mainly used for evaluating and controlling the single-ship operation cost of the port.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of port single ship operation management, and in particular to a port single ship operation cost control evaluation management method and system thereof. Background Art

[0002] Single-ship port operations involve multiple links and departments, including ship scheduling, loading and unloading operations, cargo storage, equipment maintenance, etc. These links are interrelated, and delays or mistakes in any link may affect the efficiency of the entire operation process, thereby increasing costs. At the same time, port operations are also faced with dynamic factors such as changes in market demand and uncertain ship arrival times. These factors make the operation process difficult to predict and control, increasing the difficulty of cost control.

[0003] Port operations require a large amount of equipment support, such as yard bridges, trailers, cranes, etc. How to efficiently utilize these equipment resources and reduce idleness and waste is an important aspect of cost control. However, in actual operations, due to factors such as equipment failure, maintenance requirements, and operator skill levels, it is often difficult to achieve optimal equipment utilization. In addition, different ship types and cargo types have different requirements for equipment, which further increases the complexity of equipment resource management.

[0004] In port single-ship operations, there is often a contradiction between cost control and efficiency improvement. In order to reduce costs, it may be necessary to reduce manpower and equipment input, but this may reduce operating efficiency; in order to improve efficiency, it may be necessary to increase manpower and equipment input, thereby increasing costs. How to find a balance between cost control and efficiency improvement is an important issue that port enterprises need to solve.

[0005] The current manual statistical analysis of single ship cost control has the following problems: 1. The current business system lacks the function of single-ship cost control and the ability to convert data into information and knowledge. The process and decision-making of single-ship cost control can only rely on personal experience; 2. The income and costs related to single-vessel operations are calculated manually. There is no unified management platform for the data that needs to be calculated, resulting in low processing efficiency. 3. There is no benefit evaluation model for revenue and cost, and decisions are made based on personal management experience; Although information and intelligent technologies have been widely used in the port industry, some port enterprises still have deficiencies in information and intelligent construction. This leads to problems such as poor information transmission, untimely data processing, and insufficient decision support during the operation process, which increases the difficulty of cost control. Therefore, the current management of single-ship operations in ports is basically based on manual management models to handle various business processes in terms of operation efficiency and cost control.

[0006] Therefore, there is a need for a port single ship operation cost control evaluation management method and system that can improve the port's information and intelligence level and realize the automation, intelligence and refined management of the operation process. Summary of the invention

[0007] The present invention aims to solve the defects of the existing port single ship operation cost control that relies on manpower, has poor real-time performance, low efficiency and poor interactivity, and provides a port single ship operation cost control evaluation management method and system that can improve the port information and intelligence level and realize the automation, intelligence and refined management of the operation process.

[0008] The method for controlling, evaluating and managing the cost of single-ship operation in a port according to the present invention comprises the following steps: S1. Integrate the cost data related to single ship operations scattered in various transactional business systems; S2. Standardize the integrated single-vessel operation cost and income data; S3. Construct multi-dimensional data templates and data mining data models based on the standardized single-ship operation cost and income data; S4. Conduct comprehensive data management on the standardized single-vessel operation cost and income data; S5. System construction and display of the single-vessel operation process after comprehensive data management; S6. Establish a multi-dimensional single-ship operation benefit data model and management model based on the displayed single-ship operation process; S7. Generate single-vessel operation improvement indicators using the life cycle assessment model and earned value perspective assessment model.

[0009] Further: in S1, the data integration is to obtain the single ship operation data of each business system and external platform, and perform corresponding data type conversion according to the data type of the single ship operation.

[0010] Further: in S2, the data standardization is to standardize the integrated single-ship operation data according to preset business management requirements and specifications, establish a unified standard system for single-ship operation cost data, and formulate single-ship operation cost data standards at the same time. The single-ship operation cost data standards include data classification standards, metadata management standards, data exchange standards and / or data quality management standards.

[0011] Further: in S3, the multi-dimensional data template construction is designed based on indicators of organizational structure, position, ship, single ship operation and operation steps.

[0012] Further: In S3, the data mining data model refers to a data application model that obtains the cost value and income value of a single ship operation through a data mining algorithm for the managed data and is used for direct call by the application system.

[0013] Further: in S4, the comprehensive data governance includes data quality governance, data security management and metadata management, and the data quality governance, data security management and metadata management respectively perform data governance according to corresponding data standards.

[0014] Further: in S6, the multi-dimensional single-ship operation benefit data model includes an operation data layer, a public dimension data layer and a data application layer. The operation data layer is located between the business system and the data warehouse, and is used for data integration, preliminary data cleaning, data storage and real-time data query of the single-ship operation cost data of the business system; the public dimension data layer is the core layer in the data warehouse, and is used to define the common data structure and business rules used in the data warehouse, and map different data sources and data formats into a common model; the data application layer is the top layer of the data warehouse architecture, and is used to query the data of the common model according to actual preset requirements, thereby generating statistical reports.

[0015] Further: in S7, the life cycle assessment model includes an ex ante operation plan assessment unit, an in-process operation resource management unit and an ex post single ship benefit analysis unit, the ex ante operation plan assessment unit is used to generate an optimal operation plan assessment result based on the assessment history; the in-process operation resource management unit is used to adjust the operation content and resource allocation of the target work shift according to the optimal operation plan assessment result, and during the operation process of the work shift, the cost-to-income ratio corresponding to the adjusted operation plan is evaluated in advance and the evaluation results are compared; the ex post single ship benefit analysis unit is used to display the detailed information that needs to be improved according to the evaluation report.

[0016] Further: in S7, the earned value perspective evaluation model includes an indicator evaluation unit, an earned value evaluation unit, a performance deviation evaluation unit and a completion prediction unit, wherein the indicator evaluation unit is used to generate earned value indicators and calculation formulas according to the current operation status; the earned value evaluation unit monitors the changes in the earned value of ship operations at a preset period according to the granularity of a single ship, and forms a complete single-ship earned value based on the work shift operation plan and the work shift operation progress; the performance deviation evaluation unit evaluates the current progress performance and progress deviation according to the preset period, and presents the meaning of the current progress performance deviation in a differentiated manner; the completion prediction unit predicts the deviation between the actual operation and the plan for the work shift operation plan that has been issued.

[0017] A port single-ship operation cost control evaluation management system described in the present invention includes a data middle platform and a single-ship cost control evaluation management module; the data middle platform includes a basic platform and a data governance platform, and the data governance platform includes a metadata management module, a big data processing module, a data integration module, a multi-dimensional single-ship operation benefit data model and a data security management module; The basic platform is used to obtain the historical cost data of single ship operations of the transactional business system; The metadata management module is used to define and manage various elements of data governance and create metadata standardization rules; The data integration module is used to process, handle, convert and / or integrate the historical cost data according to the metadata standardization rules to generate standardized data; The multi-dimensional single-vessel operation benefit data model is used to retrieve and calculate corresponding data according to the user's customized requirements, thereby generating analysis results; The data security management module is used for data encryption and data authority configuration.

[0018] The beneficial effects of the present invention are: The present invention uses big data processing technology to control the operating cost of a single ship in a port, establishes a method and system for fast and effective analysis and business management of single ship operations, strengthens cost control and management, and improves operational efficiency and competitiveness. The system interface is good, which solves the defect of lacking a single ship cost control process in the original business management. The present invention uses big data processing technology to process and manage the relevant data of single ship operation cost control, and then designs a model and builds a system for single ship operation cost control; the life cycle assessment model and the earned value perspective assessment model are used to achieve the purpose of improving the efficiency of single ship operations.

[0019] The present invention has the following advantages: 1. Fast processing speed: The system architecture adopts big data technology to reasonably schedule data calculations and adopts effective data analysis technology to quickly process corresponding statistical forecasting and other businesses; 2. Good user experience: The system supports multiple terminals, supports real-time visualization at all levels, and provides effective and intuitive interaction methods; 3. High flexibility: The analysis model can be flexibly created and configured according to the actual situation of the enterprise. The system adopts a layered design, which is easy to deploy, implement, upgrade and maintain. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a flow chart of the cost control evaluation management method of a single ship operation in a port; Figure 2 It is a schematic diagram of real-time evaluation of cost-income ratio; Figure 3 It is a schematic diagram of the evaluation results of the pre-operation plan evaluation unit; Figure 4 It is a schematic diagram of the control results of the in-process operation resource control unit; Figure 5 It is a schematic diagram of the analysis results of the ex post single ship benefit analysis unit; Figure 6 It is a schematic diagram of real-time evaluation of earned value. DETAILED DESCRIPTION

[0021] The following are only preferred specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a technician familiar with the technical field within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. The embodiments described below are only used to explain the present invention and cannot be interpreted as limitations on the present invention. The protection scope of the present invention should be based on the protection scope of the claims. The embodiments of the present invention are described in detail below. In order to facilitate the description of the present invention and simplify the description, the technical terms used in the specification of the present invention should be interpreted in a broad sense, including but not limited to conventional replacement schemes not mentioned in this application, and also including direct implementation methods and indirect implementation methods.

[0022] Example 1 Combination Figure 1-Figure 6 This embodiment describes a method for controlling and evaluating the cost of single-ship operation in a port, which specifically includes the following steps: S1. Integrate the cost data related to single-ship operations scattered in various transactional business systems; the transactional business systems mainly include existing systems such as production integration system, business and financial management system, equipment management system, etc. The cost data includes data related to calculated costs and actual operation benefits, such as various single-ship operation plan data, various single-ship operation actual cost related steps, time, equipment used, and other data related to calculated benefits.

[0023] S2. Standardize the integrated single-vessel operation cost and income data; S3. Constructing a multidimensional data template and a data mining data model based on the standardized single-vessel operation cost income data; the data mining data model is an application data model obtained by configuring a data mining algorithm; the multidimensional data template is a data storage model for the data design process; S4. Conduct comprehensive data management on the standardized single-vessel operation cost and income data; S5. System construction and display of the single-vessel operation process after comprehensive data management; S6. Establish a multi-dimensional single-ship operation benefit data model and a management model according to the displayed single-ship operation process; the multi-dimensional single-ship operation benefit data model is an application model based on multi-dimensional analysis used by the application end; S7. Generate single-vessel operation improvement indicators using the life cycle assessment model and earned value perspective assessment model.

[0024] like Figure 1 As shown in the figure, the specific processing process of a port single ship operation cost control evaluation management method is as follows: First, we will build a single-vessel operation cost control and evaluation management system to realize the application system of unified standards, unified management, and unified services for single-vessel operation cost data. This system is a computer application system that is implemented through design and programming. The following are the technical capabilities of such data application systems, among which data charts and visualization capabilities provide multi-dimensional and multi-view indicator information presentation. You can select different dimensions of indicators to view indicator data and the corresponding year-on-year and month-on-month values. Users can view indicator cards in layers and grades, and can achieve single-cargo analysis scenario collaboration and complementarity in interactive scenarios.

[0025] The single-ship cost control evaluation model adopted in this embodiment takes the loading and unloading operation of a ship as a project, constructs a full life cycle evaluation management capability throughout the pre-, mid- and post-operation, and solves the problem of single-ship operation management efficiency. The following data application processes are business elements of the single-ship cost control evaluation model, and the implementation method is designed and developed according to business function requirements. Conduct a collaborative evaluation of the benefits of planned resources to evaluate the rationality of the plan in advance and continuously improve the planning management capabilities; conduct a dynamic resource scheduling benefit evaluation for in-process control, which can make timely adjustments to single-ship operations and select recommended strategies; conduct a single-ship benefit evaluation and post-analysis to continuously improve the efficiency of single-ship operation management.

[0026] Based on the concept of "business and finance integration", the "cost-to-income ratio index" is introduced from the perspective of cost-to-income. For single-ship loading and unloading operations, cost control is incorporated into the production process, and comprehensive deviation assessment and control capabilities based on cost, income, and progress are established, as well as the ability to coordinate the full life cycle benefit assessment management capabilities before, during, and after the event, to assist the management to carry out refined operations and continuously improve benefits. The specific full life cycle benefit assessment management includes the following three parts: 1. Calculation formula of indicator evaluation unit; Cost-to-income ratio = operating cost / operating income*100%; Operating costs include resource costs (operation labor costs, equipment energy consumption costs, and shoreline resource costs), equipment depreciation allocations, management expense allocations, and other allocated costs, which are specifically defined in the benefit basic data.

[0027] Resource cost = ∑ (resource input * resource unit time cost * operation duration).

[0028] Activity cost = resource cost + equipment depreciation allocation, management expense allocation, and other allocated costs.

[0029] Income: Calculate the cost of ship loading and unloading operations.

[0030] Revenue = ∑ (loading and unloading fee income); loading and unloading fee income is calculated based on the estimated cost income of a single ship plan / operation (calculated based on plan / operation data and loading and unloading fee pricing data). Cost items include loading and unloading costs (specific cost items are subject to on-site investigation), but do not include yard usage fees, port-related costs, customs inspection-related costs, etc., which are specifically defined in the benefit basic data.

[0031] 2. Real-time evaluation of cost-to-income ratio; like Figure 2 As shown, the cost-to-income ratio is evaluated in real time, and the changes in the cost-to-income ratio of ship operations are monitored on an hourly basis according to the granularity of the work shift. Planners, duty managers, terminal / group managers and marketing personnel can view them in time. Monitoring cycle: From tying the first cable to untying the last cable, the cumulative cost-to-income ratio of the work shift is monitored on an hourly basis, and the hourly cost-to-income ratio of the historical work shift can be viewed.

[0032] Cost-to-income ratio curve: Standard value: A defined cost-to-income ratio benefit baseline taken from the underlying data.

[0033] Planned value: the cost-to-income ratio calculated based on the work plan of the work shift.

[0034] Actual value: The cumulative cost-to-income ratio of actual work shift operations during the current monitoring period.

[0035] The data application system displays a real-time evaluation example of cost-to-income ratio based on the above content. Figure 2 .

[0036] 3. Life cycle assessment model; Pre-operation plan evaluation unit: When the operation plan is issued, the evaluation results based on the issued operation plan are presented. When the operation plan has not been issued, the optimal result of a single ship in the ship operation plan evaluation history is presented.

[0037] In-process operation resource control unit: presents the cumulative data of a single ship up to the current time (on the hour) based on actual loading and unloading operations and resource input during the operation. After tying the first cable, you can view the details.

[0038] Post-event single ship benefit analysis unit: presents the final cost and income of a single ship. After untying the last cable, you can view the details.

[0039] The pre-operation plan evaluation unit is mainly used to guide planners to allocate resources reasonably. Planners evaluate the cost-to-income ratio of the work shift operation plan (multiple work shift operation plans for one ship) and compare the evaluation results of multiple evaluations. The duty manager views the cost-to-income ratio evaluation history, and the operation department supervisor views the evaluation history as needed. The data application system displays an example of the operation plan evaluation based on the above content, such as Figure 3 .

[0040] The in-process operation resource control unit is mainly used to guide the dispatcher to adjust the operation resources in a timely manner (calculating and improving while working). When the duty manager adjusts the operation resources / operation volume of a certain work shift during the work shift, he / she shall evaluate the cost-to-income ratio after the resource adjustment in advance and compare the evaluation results. The evaluation object is the work shift plan, and the resource adjustment of a work shift operation plan (data in the plan table) can be evaluated multiple times. Based on the above content, the data application system displays an example of operation resource control, such as Figure 4 .

[0041] The post-event single-ship benefit analysis unit mainly guides the continuous improvement of single-ship operations through single-ship benefit reports.

[0042] After the single-vessel operation is completed, a single-vessel benefit report is generated for timely review by the operation department's statisticians, market analysts, and other personnel, including the following information: Basic information of the vessel: import and export voyages, import and export container volume, operation start time, operation end time, cost, income and profit.

[0043] Cost-to-income ratio: includes standard value, planned value and actual value.

[0044] Income structure: income structure calculated based on charging items.

[0045] Cost structure: the cost structure calculated based on the proportion coefficient of loading and unloading operation costs.

[0046] Resource cost breakdown: resource cost breakdown calculated based on the resource dimension in the resource cost definition of loading and unloading operations.

[0047] The data application system shows an example of single ship benefit analysis based on the above content. Figure 5 .

[0048] The business process of the earned value perspective evaluation model for single ship cost control is as follows: The earned value perspective assessment model introduces an internationally mature project monitoring method (earned value evaluation technology) to construct a quantitative assessment system and correction tools, enabling the terminal to manage single-ship operations as projects during single-ship operations, conduct a comprehensive assessment of costs, schedules, and shift efficiency based on the work shift plan, and guide duty managers and planners to timely evaluate performance deviations (cost performance, schedule performance), conduct completion forecasts (completion time and completion cost), and achieve "calculating and improving while doing" in production operations. Operational deviations are corrected in a timely manner to provide guarantees for the effective achievement of single-ship operation plans.

[0049] The earned value perspective evaluation model includes an indicator evaluation unit, an earned value evaluation unit, a performance deviation evaluation unit and a completion prediction unit: 1. Index evaluation unit; The standard earned value evaluation technology in project management is combined with the characteristics of terminal loading and unloading operations to form earned value indicators and calculation formulas suitable for terminals, including the following indicators: Planned Value: BCWS, also known as PV: The cost of the work that should be completed by a certain point in time based on the approved schedule and budget resources. It is the benchmark for measuring work progress and cost.

[0050] Planned value = planned unit cost * planned workload (the planned workload at a certain point in time) Among them: planned unit cost = ∑ planned cost of work shift / planned workload.

[0051] Earned Value: BCWP, also known as EV: The cost of budgeted resources consumed to complete the work volume at a certain point in time, used to measure the progress of the work.

[0052] Earned value = planned unit cost * actual workload (actual workload at a certain point in time).

[0053] Actual value: ACWP, also known as AC: the actual resource cost consumed by the amount of work completed at a certain point in time, used to measure the actual operating cost.

[0054] Actual value = actual unit cost * actual workload (actual workload at a certain point in time), that is, the actual cost incurred at a certain point in time.

[0055] 2. Earned value assessment unit; The earned value assessment unit monitors the changes in the earned value of ship operations at the hourly cycle according to the granularity of a single ship. Planners, duty managers, terminal / group managers and marketing personnel can view the displayed earned value indicators in a timely manner. The monitoring cycle starts from tying the first cable to untying the last cable, and the cumulative cost-to-income ratio of a single ship is monitored on an hourly basis.

[0056] The earned value assessment is based on the work plan and progress of the work shift. The plan is adjusted and issued on a rolling basis, so the graph will also be rolled over and superimposed according to the work plan to eventually form a complete earned value for a single ship.

[0057] Planned value: Multiple work shifts are added up according to their planned values, and the planned values ​​within a work shift are broken down linearly.

[0058] Earned Value: Starting from the actual start time of the work, the horizontal axis is calculated by monitoring and accumulating every hour and across work shifts.

[0059] Actual value: starting from the actual start time of work, the value is accumulated according to hourly monitoring and across shifts.

[0060] The data application system conducts model system construction analysis based on the above content. Examples are as follows: Figure 6 .

[0061] 3. Performance deviation assessment unit; The performance deviation assessment unit evaluates and presents the current progress performance and progress deviation on an hourly basis, and presents the meaning of the current progress performance deviation through differentiated font colors.

[0062] When you hover the mouse to view a historical time node, the data of the historical time node is presented.

[0063] The algorithm is as follows: Cost performance = earned value / actual value, which reflects the ratio of budget input to actual input to complete the same work, and reflects the cost efficiency of the completed work. A ratio <1 represents cost overrun, and a ratio >1 represents cost savings.

[0064] Cost variance = earned value – actual value.

[0065] Schedule performance = earned value / planned value, which is the ratio of actual progress to planned progress, reflecting the efficiency of the team's use of time. A ratio <1 means that the progress is lagging behind, and a ratio >1 means that the progress is ahead of schedule.

[0066] Schedule deviation = ∑ planned working hours of the work shift (up to the current moment) / schedule performance - ∑ planned working hours of the work shift (up to the current moment). The data application system builds the performance deviation model system based on the above content.

[0067] 4. Completion prediction unit The completion prediction unit is to predict the deviation between the actual work and the plan for the work shift work plan that has been issued. The completion prediction unit is to estimate the deviation between the expected completion cost and the expected completion time according to the algorithm.

[0068] The algorithm is as follows: Budget at completion = planned value.

[0069] Estimate at completion = Planned value / cost performance.

[0070] Cost Variance = Completion Estimate – Completion Budget. Cost Variance > 0 indicates overspending, while Cost Variance < 0 indicates cost savings.

[0071] Completion deviation = ∑ planned working time of the work shift / progress performance - ∑ planned working time of the work shift. Completion deviation > 0 indicates delayed completion, and completion deviation < 0 indicates early completion. The data application system analyzes the construction of the completion prediction model system based on the above content and displays it.

[0072] Example 2 This embodiment is described in conjunction with Example 1. This embodiment discloses a port single-ship operation cost control evaluation management system, including a data middle platform and a single-ship cost control evaluation management module; the data middle platform includes a basic platform and a data governance platform, and the data governance platform includes a metadata management module, a big data processing module, a data integration module, a multi-dimensional single-ship operation benefit data model and a data security management module; The basic platform is used to obtain historical cost data of single-vessel operations of production integration systems, business and financial management systems, equipment management systems, etc. The metadata management module is used to create metadata standardization rules based on the historical data; The data integration module is used to process, handle, convert and / or integrate the historical cost data according to the metadata standardization rules to generate standardized data; The multi-dimensional single-vessel operation benefit data model is used to retrieve and calculate corresponding data according to the user's customized requirements, thereby generating analysis results; The data security management module is used to generate visual charts based on calculation results and user customized requirements.

[0073] First, a data middle platform is provided, which provides a unified data base for the horizontal data interaction and collaboration of various business systems of the port, through the basic platform and the data governance platform. The data governance platform includes a metadata management module, a big data processing module, a data integration module, a multi-dimensional single-ship operation efficiency data model and a data security management module. Among them, data collection is realized through the basic platform, data governance and data storage are realized through the metadata management module and the big data processing module, data sharing and exchange are realized through the data integration module, data management, data services and other data services are realized through the multi-dimensional single-ship operation efficiency data model and the data security management module, and unified management of data tools is realized.

[0074] Generally speaking, the basic platform actually refers to the system tools of the data middle platform, which is the data middle platform software installed on the computer. The software functions also include a series of data governance functions.

[0075] Among them, the data governance platform processes the historical cost data in the process of single ship operation according to the preset metadata standardization rules through the big data processing module. In the process of metadata standardization, the historical cost data entering the data governance platform is standardized and constrained, and metadata is used as a driver to connect the various stages of standard management, data quality management and data security management of the data integration module to form a unified and complete data governance system, so as to carry out data governance in various dimensions such as material cost control (such as procurement cost and material usage control), labor cost control (such as direct labor cost control and outsourcing labor cost control), special cost control (such as design fees, testing fees, inspection fees, insurance premiums, patent fees and other costs related to ship construction, or energy conservation and emission reduction costs), quality cost control (such as quality training, quality inspection, quality improvement and loss costs), management cost control (such as office expenses, travel expenses, conference expenses, etc.) and other cost control (such as risk costs and opportunity costs, etc.) for single ship operations, so as to solve actual business problems and enhance the data governance platform's support for business development.

[0076] The metadata management module includes a data collection unit, a metadata management creation unit, a metadata description unit, a metadata display unit and a metadata integration unit. The metadata management module is an important source of data knowledge. Metadata management must run through the entire process of data collection, processing, storage and governance, and manage a complete set of processes for metadata creation, description, display, integration and control, providing basic capabilities for data processing, data governance and data sharing based on metadata.

[0077] The metadata management module is a function of the data governance system, which is to define and manage the various elements of data governance. Data processing generally refers to the business historical data directly entering the data warehouse according to the data standards and then processing it into multidimensional data.

[0078] The data integration module is based on the data governance platform. It collects and synchronizes data from business systems and external platforms, collects single-ship operation benefit data scattered in business systems and files into the basic data base of the data center, and performs necessary conversions on data types to prepare for subsequent data processing, mining, and application. The integration platform can provide visual orchestration, and integrated business development uses interface orchestration to reduce code development. It supports real-time monitoring capabilities of integrated tasks, supports reporting or alarming of the execution process and results of integrated tasks, and provides data integrity check reports. It can support the access of multiple third-party data sources such as MySQL, Oracle and other databases, and file data collection in CSV / XM / JSON and other formats.

[0079] The data standardization and data planning process is to sort out the integrated single-ship operation benefit data according to the business management requirements and corresponding data specifications, establish a unified single-ship operation benefit data standard system, and formulate single-ship operation benefit cost data standards, including data classification standards, metadata management standards, data exchange standards and / or data quality management standards, etc., to effectively ensure data quality. Data standards and planning capabilities support data planning, custom data models, unified data standards, visual data modeling, data labeling and other functions, open up the data governance link from the data source to the standard layer and application layer, and implement data standards and data assets. Data standardization is achieved through relational modeling and dimensional modeling; the indicator system is standardized through indicator construction, ambiguity is eliminated, the caliber is unified, and the calculation logic is unified, and thematic data query and mining services are provided to the outside world.

[0080] Provide a multi-dimensional single-ship operation benefit data model that meets the general data governance process hierarchy. The layers include the operation data layer (ODS layer), the common dimension data layer (CDM layer), and the data application layer (ADS layer). According to the data application requirements of the single-ship cost control indicators, the query delay, concurrency and other factors of data access are comprehensively considered to complete the design of the data model, including the data model (conceptual, logical, physical), mapping relationship, and output the corresponding single-ship cost control data model.

[0081] After the single-ship operation benefit data included in the business is cleaned, integrated and confirmed through the data governance platform, the single-ship operation benefit-related data assets are formed, unified data asset management is provided, and visualization of single-ship operation benefit data assets is provided to the outside world, providing data consumers with quick retrieval, viewing, subscription and other operations of various data assets, and supporting cataloging of different types of metadata and data. Provide rich data openness capabilities to realize open sharing of internal data of the data service platform.

[0082] Data security management provides a complete data security strategy to carry out data permission control, sensitive data desensitization and data classification management, etc., to ensure the storage security and access security of data during its life cycle.

Claims

1. A method for controlling and evaluating the cost of single-ship operation in a port, characterized in that: The steps include: S1. Integrate the cost data related to single ship operations scattered in various transactional business systems; S2. Standardize the integrated single-vessel operation cost and income data; S3. Construct multi-dimensional data templates and data mining data models based on the standardized single-ship operation cost and income data; S4. Conduct comprehensive data management on the standardized single-vessel operation cost and income data; S5. System construction and display of the single-vessel operation process after comprehensive data management; S6. Establish a multi-dimensional single-ship operation benefit data model and management model based on the displayed single-ship operation process; S7. Generate single-vessel operation improvement indicators using the life cycle assessment model and earned value perspective assessment model.

2. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S1, the data integration is to obtain the single ship operation data of each business system and external platform, and perform corresponding data type conversion according to the data type of the single ship operation.

3. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S2, the data standardization is to standardize the integrated single-ship operation data according to the preset business management requirements and specifications, establish a unified standard system for single-ship operation cost data, and formulate single-ship operation cost data standards. The single-ship operation cost data standards include data classification standards, metadata management standards, data exchange standards and / or data quality management standards.

4. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S3, the multi-dimensional data template construction is designed based on indicators of organizational structure, position, ship, single ship operation and operation steps.

5. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S3, the data mining data model refers to a data application model that obtains the cost value and income value of a single ship operation through a data mining algorithm for the managed data and is used for direct call by the application system.

6. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S4, the comprehensive data governance includes data quality governance, data security management and metadata management, and the data quality governance, data security management and metadata management respectively perform data governance according to corresponding data standards.

7. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S6, the multi-dimensional single-ship operation benefit data model includes an operation data layer, a public dimension data layer and a data application layer. The operation data layer is located between the business system and the data warehouse and is used for data integration, preliminary data cleaning, data storage and real-time data query of the single-ship operation cost data of the business system; The public dimension data layer is the core layer in the data warehouse, which is used to define the common data structure and business rules used in the data warehouse, and map different data sources and data formats into a common model; the data application layer is the top layer of the data warehouse architecture, which is used to query the data of the common model according to actual preset requirements, thereby generating statistical reports.

8. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S7, the life cycle assessment model includes an ex ante operation plan assessment unit, an in-process operation resource management unit and an ex post single ship benefit analysis unit. The ex ante operation plan assessment unit is used to generate an optimal operation plan assessment result based on the assessment history; the in-process operation resource management unit is used to adjust the operation content and resource allocation of the target work shift according to the optimal operation plan assessment result, and during the operation process of the work shift, the cost-to-income ratio corresponding to the adjusted operation plan is evaluated in advance and the evaluation results are compared; the ex post single ship benefit analysis unit is used to display detailed information that needs to be improved according to the assessment report.

9. A method for controlling, evaluating and managing port single-ship operation costs according to claim 1, characterized in that: In S7, the earned value perspective evaluation model includes an indicator evaluation unit, an earned value evaluation unit, a performance deviation evaluation unit and a completion prediction unit. The indicator evaluation unit is used to generate earned value indicators and calculation formulas according to the current operation status; the earned value evaluation unit monitors the changes in the earned value of ship operations at a preset period according to the granularity of a single ship, and forms a complete earned value of a single ship based on the work shift operation plan and the work shift operation progress; the performance deviation evaluation unit evaluates the current progress performance and progress deviation according to the preset period, and presents the meaning of the current progress performance deviation in a differentiated manner; the completion prediction unit predicts the deviation between the actual operation and the plan for the work shift operation plan that has been issued.

10. A port single ship operation cost control evaluation management system, characterized in that: It includes a data middle platform and a single-ship cost control evaluation management module; the data middle platform includes a basic platform and a data governance platform, and the data governance platform includes a metadata management module, a big data processing module, a data integration module, a multi-dimensional single-ship operation benefit data model and a data security management module; The basic platform is used to obtain the historical cost data of single ship operations of the transactional business system; The metadata management module is used to define and manage various elements of data governance and create metadata standardization rules; The data integration module is used to process, handle, convert and / or integrate the historical cost data according to the metadata standardization rules to generate standardized data; The multi-dimensional single-vessel operation benefit data model is used to retrieve and calculate corresponding data according to the user's customized requirements, thereby generating analysis results; The data security management module is used for data encryption and data authority configuration.

Citation Information

Patent Citations

  • Container terminal operation cost control and customer value analysis method

    CN108090599A

  • Port ship management system based on cloud technology

    CN109919486A

  • Port data comprehensive application method and system based on big data platform

    CN115328983A

  • Engineering project comprehensive control and evaluation method based on information system

    CN117436755A

  • Framework system and method for evaluating performance measures of container terminal operations

    KR1020140107004A

Cited By

  • Safety boundary early warning method and system for pontoon operation

    CN120725470A

  • A safety boundary early warning method and system for floating vessel operations

    CN120725470B