Project cost prediction method and device

By obtaining and analyzing multiple cost collision factors of the target project, and using the preset neural network model to predict the project cost, the problem of insufficient element analysis in the existing technology is solved, and the accuracy of the project cost prediction and decision support capabilities are improved.

CN118798947APending Publication Date: 2024-10-18CHINA MOBILE GROUP DESIGN INST +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410485701.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-04-22
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

Existing project cost prediction methods lack systematic analysis of multiple factors, resulting in low prediction accuracy.

Method used

By obtaining multiple target project cost collision factors of the target project and inputting them into the pre-built project cost prediction model, the model trains the preset neural network model through training samples and comprehensively considers multiple factors that affect the target project. In order to obtain more accurate project cost prediction results.

Benefits of technology

It improves the accuracy and comprehensiveness of project cost forecasts, provides more effective decision-making support for engineering project teams, and enhances the efficiency and control capabilities of managers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798947A_ABST
    Figure CN118798947A_ABST
Patent Text Reader

Abstract

The invention relates to a project cost prediction method and device. The method comprises the following steps: acquiring a plurality of target project cost collision factors of a target project; inputting the plurality of target project cost collision factors into a pre-constructed project cost prediction model to obtain a project cost prediction result of the target project; wherein the project cost prediction model is obtained by training a preset neural network model through a training sample, and the training sample comprises a historical project cost collision factor in a historical project and an actual cost of the historical project. The project cost prediction model is obtained by training the preset neural network model through the training sample comprising the historical project cost collision factors in the historical project and the actual cost of the historical project, and the multiple target project cost collision factors influencing the target project are comprehensively considered. Therefore, a more accurate project cost prediction result is obtained.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of engineering construction, and in particular to an engineering cost prediction method and device. Background Art

[0002] As competition in the construction market intensifies, cost management becomes increasingly important. Project cost forecasting, as the initial link in cost management, can provide support for project planning and optimization decisions.

[0003] In the related technologies, when predicting the construction cost, there is often a lack of systematic analysis of multiple factors, which makes the accuracy of the construction cost prediction low. Summary of the invention

[0004] The present invention provides a method and device for predicting construction cost.

[0005] According to a first aspect of the present disclosure, a method for predicting construction cost is provided, the method comprising:

[0006] Obtain multiple target project cost collision factors of the target project;

[0007] The multiple target project cost collision factors are input into a pre-constructed project cost prediction model to obtain a project cost prediction result for the target project; wherein the project cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical project cost collision factors in historical projects and the actual costs of the historical projects.

[0008] According to a second aspect of the present disclosure, a construction cost prediction device is provided, the device comprising:

[0009] A collision factor acquisition module is used to obtain multiple target project cost collision factors of a target project;

[0010] The project cost prediction module is used to input the multiple target project cost collision factors into a pre-built project cost prediction model to obtain a project cost prediction result for the target project; wherein the project cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical project cost collision factors in historical projects and the actual costs of the historical projects.

[0011] According to a third aspect of the present disclosure, an electronic device is provided, which includes a memory and a processor, wherein a computer program is stored in the memory, and when the processor executes the program, the method described above is implemented.

[0012] According to a fourth aspect of the present disclosure, a computer-readable storage medium is provided, on which a computer program is stored, and when the program is executed by a processor, the above method of the present disclosure is implemented.

[0013] According to a fifth aspect of the present disclosure, a computer program product is provided, including a computer program, and when the computer program is executed by a processor, the method described above is implemented.

[0014] The project cost prediction method and device provided by the embodiment of the present disclosure can obtain a project cost prediction result for the target project by obtaining multiple target project cost collision factors of the target project and inputting the multiple target project cost collision factors into a pre-built project cost prediction model. Since the project cost prediction model is obtained by training a preset neural network model using training samples including historical project cost collision factors in historical projects and actual costs of historical projects, and by comprehensively considering multiple target project cost collision factors affecting the target project, a more accurate project cost prediction result is obtained. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Further details, features and advantages of the present disclosure are disclosed in the following description of exemplary embodiments in conjunction with the accompanying drawings, in which:

[0016] Figure 1 A schematic diagram of a construction cost prediction system provided for an exemplary embodiment of the present disclosure;

[0017] Figure 2 A flowchart of a method for predicting construction cost provided by an exemplary embodiment of the present disclosure;

[0018] Figure 3 A schematic block diagram of functional modules of a construction cost prediction device provided for an exemplary embodiment of the present disclosure;

[0019] Figure 4 A structural block diagram of an electronic device provided for an exemplary embodiment of the present disclosure;

[0020] Figure 5 A structural block diagram of a computer system provided for an exemplary embodiment of the present disclosure. DETAILED DESCRIPTION

[0021] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments described herein, which are instead provided for a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.

[0022] It should be understood that the various steps described in the method embodiments of the present disclosure may be performed in different orders and / or in parallel. In addition, the method embodiments may include additional steps and / or omit the steps shown. The scope of the present disclosure is not limited in this respect.

[0023] The term "including" and its variations used in this document are open inclusions, that is, "including but not limited to". The term "based on" means "based at least in part on". The term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one other embodiment"; the term "some embodiments" means "at least some embodiments". Relevant definitions of other terms will be given in the description below. It should be noted that the concepts of "first", "second", etc. mentioned in this disclosure are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.

[0024] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".

[0025] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.

[0026] It is understandable that before using the technical solutions disclosed in the embodiments of the present disclosure, the types, scope of use, usage scenarios, etc. of the personal information involved in the present disclosure should be informed to the user and the user's authorization should be obtained in an appropriate manner in accordance with relevant laws and regulations.

[0027] For example, in response to receiving an active request from a user, a prompt message is sent to the user to clearly prompt the user that the operation requested to be performed will require obtaining and using the user's personal information. Thus, the user can autonomously choose whether to provide personal information to software or hardware such as an electronic device, application, server, or storage medium that performs the operation of the technical solution of the present disclosure according to the prompt message.

[0028] As an optional but non-limiting implementation, in response to receiving an active request from the user, the method of sending a prompt message to the user may be, for example, a pop-up window, in which the prompt message may be presented in text. In addition, the pop-up window may also carry a selection control for the user to choose "agree" or "disagree" to provide personal information to the electronic device. It is understandable that the above notification and the process of obtaining user authorization are only illustrative and do not constitute a limitation on the implementation of the present disclosure. Other methods that meet relevant laws and regulations may also be applied to the implementation of the present disclosure.

[0029] In the embodiments provided by the present disclosure, by combining the multi-factor collision model with the engineering BIM (Building Information Modeling) model, an accurate prediction of the project cost can be achieved. In the project cost prediction model, a neural network and a BIM model are used for spatial linkage, and the deviation analysis between the actual value and the predicted value of the project cost is completed through BIM technology to form a highly reliable project deviation analysis report. In this way, digital tools can be provided for project cost prediction and project cost deviation analysis, ultimately improving the efficiency of managers in project management.

[0030] Among them, BIM technology is a production operation tool to solve the construction field. It can be used to collect, manage and present the physical characteristics and functional attributes of buildings, promote the multi-party collaboration of project team members in management, design, construction and operation, and efficiently share information in engineering construction. BIM technology changes the operation mode in the traditional engineering field and improves the design quality, construction efficiency and operational energy efficiency of engineering projects. It presents building information in a three-dimensional visual way, and can add elements such as time, cost and prediction. It can simulate and predict engineering conditions more intuitively and accurately, and can discover and solve problems in advance, reducing engineering rework and resource waste. The application scope of BIM technology is not limited to the construction industry, but is also widely used in urban planning, infrastructure, industrial design and other fields. It provides a new perspective and method to manage various engineering projects, bringing great changes to the industry.

[0031] In the embodiment, by adopting the multi-factor collision prediction, the fluctuation of the project cost is predicted by analyzing the relationship between various factors, the weight relationship between various factors in the project can be solved, and the factors affecting the project cost can be sorted by collision, which can simplify the complex relationship of the project cost. In this way, the fluctuation of the project cost can be predicted more accurately, which has a good effect on project budget and decision analysis. The multi-factor collision prediction of the project cost can comprehensively consider the interaction between multiple factors, which helps to improve the accuracy and comprehensiveness of the prediction and provide more effective decision support for the project team.

[0032] In the embodiments provided in the present disclosure, Figure 1As shown, the engineering cost prediction system provided by the embodiment may include an acquisition layer, a capability layer, an application layer and a display layer. Among them, the acquisition layer is mainly used for the collection of cost prediction elements and the collection of construction engineering data, and the acquisition layer provides data support for the capability layer. The capability layer mainly includes multi-factor capability analysis, engineering cost prediction model, engineering cost deviation analysis capability and BIM capability, and the capability layer mainly provides capability building for the application layer. The application layer may include engineering cost prediction, engineering cost deviation analysis and three-dimensional visualization presentation, and the application layer mainly provides digital applications for the display layer. The display layer may include four-dimensional engineering cost presentation, engineering cost prediction report, engineering deviation analysis report and historical data precipitation.

[0033] Among them, the project cost prediction model can include: multi-factor selection and preliminary determination of the scope of multi-factors affecting the project cost; multi-factor collision factor collection, which can determine the collection method according to the characteristics of different factors, collect data on the project cost, fill in missing data and eliminate duplicate data to ensure data quality; multi-factor collision model, the multi-factor collision model is to associate the factors affecting the project cost, analyze the collision factors according to the degree of influence on the project cost, and determine the main influencing factors of the project cost; project cost prediction, establish a multi-factor collision project cost prediction model, improve its prediction accuracy through standard engineering data set training model, and finally calculate the project cost deviation based on the actual project cost.

[0034] Therefore, the project cost prediction method provided by the embodiment of the present disclosure may include the following steps:

[0035] 1) Preliminarily select the project cost collision factors and establish a data system for project cost.

[0036] In the embodiment, the building area, personnel input and construction period of the target project can be preliminarily determined according to the basic rules of project cost, and the above contents can be used as multi-factor collision factors. The multi-factor collision factors in the embodiment can also include land prices, building material prices and personnel input costs, etc., and the embodiment is not limited thereto. The multi-factor collision factor can be used as the target project cost collision factor.

[0037] 2) Construct a multi-factor collision factor collection plan.

[0038] In the embodiment, a structured data and unstructured data collection scheme can be established according to the characteristics of various factors of the project cost. Specifically, the following steps can be included:

[0039] 2.1) Collect various types of engineering construction information, such as construction drawings, construction pictures, and construction site information, classify and archive such information, and separate structured data from unstructured data.

[0040] 2.2) Directly extract structured data and archive the extracted data. Use image recognition and other methods to extract features from unstructured data.

[0041] 2.3) Integrate the extracted data into the engineering cost collision element set, remove duplicate data, and fill in missing data.

[0042] 2.4) Integrate the final data set to form a standard engineering cost data set.

[0043] 3) Establish a multi-factor collision model, sort the main factors affecting the project cost, and select the main factors.

[0044] In the embodiment, a multi-factor collision model may be established to rank the main factors affecting the project cost and select the main factors.

[0045] For example, the original and unadjusted multi-factor data can be obtained from the multi-factor data set, and the incomplete data can be determined. If there is incomplete data, the incomplete data can be supplemented. The multi-factor collision algorithm is used to complete the multi-factor collision and form a data set after the multi-factor collision. For example, the relationship between the elements can be obtained to exclude irrelevant elements, and then a data set containing multiple collision factors can be obtained.

[0046] By sorting the collision factors in the multi-factor data set, the factors with large influencing factors are selected. For example, multiple collision factors can be sorted according to the degree of impact on the project cost, and the obtained multi-factor data can be saved to form the underlying data capability to support the multi-factor collision prediction model and BIM modeling.

[0047] 4) Establish a project cost prediction model and output the project cost prediction results.

[0048] In an embodiment, the project cost prediction result can be used as the underlying data to provide a data source for BIM modeling and deviation analysis. A project cost prediction model can be established through multi-factor collision factors to predict the project cost, and the prediction result can be mapped with the BIM model.

[0049] Specifically, the multi-factor data can be normalized to obtain a data set with the same range, and a multi-factor engineering cost prediction model can be established, and the engineering cost prediction model can be trained and the error result can be returned. By judging whether the error result is within the controllable range, if the error accuracy is within the controllable range, the engineering cost prediction model is saved, otherwise the model is continued to be trained until the error result is within the controllable range, thereby completing the training of the engineering cost prediction model.

[0050] In the embodiment, the three-dimensional visualization presentation module can also be used to present the project cost prediction results and the degree of deviation between the project cost prediction results and the actual cost in three dimensions. The three-dimensional visualization presentation module can use BIM technology to model the project site data, decouple the spatial components during the modeling process, map the real data with the spatial components, and map the predicted data with the BIM model to form a visualization presentation of the project cost based on the BIM model. It also supports component attribute viewing. By clicking on the component, its cost attributes can be displayed. The attributes record in detail the engineering material codes and information used by the component. And when there is a large deviation between the predicted value and the actual value in the component, the degree of deviation can be distinguished by different colors.

[0051] Specifically, the process of predicting the project cost can include the following steps:

[0052] 1) Extract feature data from construction drawings and project site data to form the basic data of the BIM model.

[0053] 2) Expand the properties of spatial components in the BIM model.

[0054] The attributes of the spatial component can include cost information generated in actual projects such as construction materials and labor input, and various cost data in the BIM component can also be improved through manual supplementation.

[0055] Specifically, various spatial components can be generated through BIM technology, and data on the actual process of engineering cost can be filled in through Internet of Things technology, image recognition technology or manual reporting. The prediction model and BIM model are associated to form a BIM-based engineering cost prediction model. By mapping and associating spatial components according to the actual construction process, the engineering cost can be displayed according to the actual situation in the simulation.

[0056] 3) Display the three-dimensional space model and focus on presenting the dynamic data of project cost.

[0057] This three-dimensional space model can support clicking on component properties to view various types of engineering information.

[0058] 4) Establish a deviation analysis model and use the color difference model to distinguish the comparison between the actual project cost and the predicted project cost.

[0059] In the embodiment, the actual value of the project cost can be calculated and a project cost deviation model can be established to perform deviation analysis on the predicted value, and the deviation result can be saved in the space component.

[0060] The actual construction cost of the project can be obtained, which can include labor costs, equipment costs, and project material costs, and the cost deviation can be analyzed, that is, the difference between the actual value and the predicted value. In this way, when the cost deviation is within the predicted range, it can be displayed by setting the component to green or other colors; when the cost deviation is not within the controllable range, the cause of the deviation is recorded and the component is set to red or other colors for display. In this way, different colors can be used to quickly locate the part with large cost deviation, which is convenient for cost analysis.

[0061] In an embodiment, the deviation analysis model can dynamically simulate the generation of project costs at each stage and display the predicted value of the project cost at the next stage.

[0062] Specifically, in the embodiment, the mapped components can be connected to form a construction cost simulation animation. A construction cost display window is established to display the construction costs that have occurred, are occurring, and will occur in the future according to the construction process. In the embodiment, the deviation model analysis results can also be displayed in two colors, red and green.

[0063] In the embodiments provided by the present disclosure, the main influencing weights of the project cost are determined by multi-factor collision, and the weights are sorted. In this way, the results of the multi-factor collision can be used as a data source and input into the neural network prediction model, so that the prediction accuracy and convergence speed of the model are significantly improved. In the embodiments, the visualization of the project cost and the deviation analysis of the project cost are realized according to the BIM technology, and the degree of deviation between the predicted value of the project cost and the actual value is displayed by color difference analysis. And by simulating the actual cost of the project through BIM technology and displaying the project cost of the construction process, the management personnel's ability to control the project cost can be improved.

[0064] Based on the above embodiments, the present disclosure first provides a method for predicting construction cost. Figure 2 As shown, the method may include the following steps:

[0065] In step S210, a plurality of target project cost collision factors of the target project are obtained.

[0066] In the embodiment, multiple target project cost collision factors that affect the target project cost can be obtained, such as labor cost, building material cost and land cost, as well as construction period, etc., which can all be used as collision factors that affect the work cost. The specific factors can be determined based on historical data and can also be adjusted according to specific circumstances, and the embodiment is not limited thereto.

[0067] In step S220, the target project cost collision factor is input into a pre-built project cost prediction model to obtain a project cost prediction result for the target project.

[0068] Among them, the engineering cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical engineering cost collision factors in historical projects and the actual costs of historical projects.

[0069] In an embodiment, relevant data of historical projects completed recently or within a preset period of time, such as the actual cost of the historical projects and various historical project cost collision factors that affect the actual cost, can be obtained, and a preset neural network model can be trained using the historical project cost collision factors and the actual cost of the historical projects. After the model training is completed, a constructed project cost prediction model can be obtained.

[0070] For example, the actual cost of historical projects, as well as the construction period, number of construction workers, labor costs, material costs of various categories, project scale, etc. are used as training samples to train the preset neural network model to obtain a project cost prediction model. In this way, before planning to construct the target project, multiple target project cost collision factors that affect the target project cost can be input into the project cost prediction model to obtain the target project's work cost prediction results.

[0071] The project cost prediction method provided by the embodiment of the present disclosure can obtain a project cost prediction result for the target project by obtaining multiple target project cost collision factors of the target project and inputting the multiple target project cost collision factors into a pre-built project cost prediction model. Since the project cost prediction model is obtained by training a preset neural network model using training samples including historical project cost collision factors in historical projects and actual costs of historical projects, and by comprehensively considering multiple target project cost collision factors affecting the target project, a more accurate project cost prediction result is obtained.

[0072] Based on the above embodiment, in another embodiment provided by the present disclosure, the above step S210 may further include the following steps:

[0073] In step S211, a plurality of project cost collision factors of the target project are obtained.

[0074] In step S212, multiple project cost collision factors are input into the multi-factor collision model, and the weights corresponding to the multiple project cost collision factors are determined by the multi-factor collision model, wherein the weights are positively correlated with the degree of influence of the project cost.

[0075] In step S213, the construction cost collision factor with a weight greater than a threshold is used as a target construction cost collision factor.

[0076] In an embodiment, multiple engineering cost collision factors of a target project can be input into a multi-factor collision model, and the influence of each engineering cost collision factor on the total cost of the target project can be obtained through the multi-factor collision model, and the weights corresponding to each engineering cost collision factor can be set. For example, the land cost has the highest impact on the total cost of the target project among all engineering cost collision factors, so the weight of the land cost can be set to the highest among all engineering cost collision factors, so that the weights corresponding to each engineering cost collision factor can be sorted, for example, the first N engineering cost collision factors in the sorting can be used as multiple engineering cost collision factors of the target project, where N is a positive integer. Of course, the weights corresponding to each engineering cost collision factor can also be compared with a threshold value, and the engineering cost collision factor with a weight greater than the threshold value can be used as the target engineering cost collision factor. The threshold value can be set as needed, and the embodiment is not limited to this.

[0077] Based on the above embodiment, in another embodiment provided by the present disclosure, the method may further include the following steps:

[0078] In step S230, the actual cost of the target project is obtained.

[0079] In step S240, the actual cost and the project cost prediction results are input into the project cost prediction building information model, and the project cost deviation is output. The project cost prediction building information model is obtained by spatially mapping the project cost prediction model with the building information model.

[0080] In an embodiment, the engineering cost prediction building information model can be used to obtain the engineering cost deviation between the actual cost of the target project and the engineering cost prediction result. The engineering cost deviation can include deviations in various dimensions, such as deviations corresponding to multiple target engineering cost collision factors, including the deviation between the actual cost and the predicted cost of labor costs, the deviation between the actual cost and the predicted cost of a certain building material, etc., so that deviations in various dimensions can be obtained.

[0081] In the embodiment, when the deviation of the project cost is greater than a threshold, the deviation between the project cost prediction result and the actual cost can be displayed by color difference. For example, different colors are used to display the project cost prediction result and the actual cost respectively, which is convenient for analysis.

[0082] Based on the above embodiment, in another embodiment provided by the present disclosure, the method may further include the following steps:

[0083] In step S250, a plurality of initial project cost collision factors of the target project are obtained.

[0084] In step S260, data of the target project is obtained based on a plurality of initial project cost collision factors.

[0085] In step S270, data extraction is performed on the document data, and the extracted data is added to the project template to obtain a multi-factor data set of the project cost, and a target project cost collision factor is determined from the multi-factor data set.

[0086] In the embodiment, it is also possible to obtain multiple initial project cost collision factors of the target project, and obtain data of the target project based on the multiple initial project cost collision factors. The initial project cost collision factors may include various types of construction data, etc. For example, various types of data on engineering construction may be collected, such as construction drawings, construction pictures, and construction site information, etc. By classifying and archiving such data, structured data and unstructured data are separated, and feature extraction is performed by image recognition and other methods. By adding the extracted data to the project template, a multi-factor data set of the project cost is obtained, so that the target project cost collision factor can be determined from the multi-factor data set. Specifically, the target project cost collision factor can be determined from the multi-factor data set by manual screening, and can also be determined by the weight method in the above-mentioned embodiment, and the embodiment is not limited to this.

[0087] Specifically, the engineering cost collision factors in the multi-factor data set can be sorted, and the target engineering cost collision factor can be determined from the sorted engineering cost collision factors. The basis for sorting can be the importance of each engineering cost collision factor or the degree of influence on the engineering cost.

[0088] In the embodiments provided by the present disclosure, the data can also be mapped to the spatial components in the building information model, and the project cost prediction results can be mapped to the building information model. In this way, the project cost of the target project can be displayed in three dimensions based on the mapping results. Among them, in the three-dimensional visualization display, different colors represent different construction progress in the target project. In this way, during the implementation of the target project, the construction degree of the target project can be dynamically displayed by different colors, which is convenient for quickly understanding the construction progress of the target project as a whole. In particular, when there are multiple projects under construction at the same time, by displaying the construction of each project in three dimensions and dynamically displaying the construction degree of each project by different colors, the progress of all projects under construction can be intuitively and quickly understood.

[0089] In the case of dividing each functional module according to each function, an embodiment of the present disclosure provides a construction cost prediction device, which can be a server, a terminal, or a chip applied to a server. Figure 3 This is a schematic block diagram of the functional modules of a construction cost prediction device provided by an exemplary embodiment of the present disclosure. Figure 3 As shown, the project cost prediction device includes:

[0090] A collision factor acquisition module 10 is used to acquire multiple target project cost collision factors of a target project;

[0091] The project cost prediction module 20 is used to input the multiple target project cost collision factors into a pre-constructed project cost prediction model to obtain a project cost prediction result for the target project; wherein the project cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical project cost collision factors in historical projects and the actual costs of the historical projects.

[0092] In another embodiment provided by the present disclosure, the collision factor acquisition module is specifically used to:

[0093] Obtaining multiple project cost collision factors of the target project;

[0094] Inputting the plurality of project cost collision factors into a multi-factor collision model, and determining weights corresponding to the plurality of project cost collision factors respectively through the multi-factor collision model; wherein the weights are positively correlated with the degree of influence of the project cost;

[0095] The project cost collision factor with a weight greater than a threshold is used as the target project cost collision factor.

[0096] In another embodiment provided by the present disclosure, the device further includes:

[0097] An actual cost acquisition module, used to acquire the actual cost of the target project;

[0098] The project cost deviation acquisition module is used to input the actual cost and the project cost prediction result into the project cost prediction building information model, and output the project cost deviation; wherein the project cost prediction building information model is obtained by spatially mapping the project cost prediction model with the building information model.

[0099] In another embodiment provided by the present disclosure, the device further includes:

[0100] The deviation degree display module is used to display the deviation degree between the project cost prediction result and the actual cost by means of color difference when the project cost deviation is greater than a threshold value.

[0101] In another embodiment provided by the present disclosure, the device further includes:

[0102] An initial project cost collision factor acquisition module is used to acquire multiple initial project cost collision factors of the target project;

[0103] A data acquisition module, used for acquiring information data of the target project based on the multiple initial project cost collision factors;

[0104] The data extraction module is used to extract data from the information data, add the extracted data to the engineering template, obtain a multi-factor data set of the engineering cost, and determine the target engineering cost collision factor from the multi-factor data set.

[0105] In another embodiment provided by the present disclosure, the data extraction module is further configured to:

[0106] Sorting the project cost collision factors in the multi-factor data set;

[0107] The target project cost collision factor is determined from the sorted project cost collision factors.

[0108] In another embodiment provided by the present disclosure, the device further includes:

[0109] A mapping module, used to map the data with the spatial components in the building information model, and to map the project cost prediction result with the building information model;

[0110] The display module is used to perform a three-dimensional visualization of the project cost of the target project based on the mapping result; wherein, in the three-dimensional visualization, different colors represent different construction progresses in the target project.

[0111] The relevant device part corresponds to the above method. Please refer to the description of the corresponding embodiment of the method for details, which will not be repeated here.

[0112] The project cost prediction device provided by the embodiment of the present disclosure can obtain a project cost prediction result for the target project by obtaining multiple target project cost collision factors of the target project and inputting the multiple target project cost collision factors into a pre-built project cost prediction model. Since the project cost prediction model is obtained by training a preset neural network model using training samples including historical project cost collision factors in historical projects and actual costs of historical projects, and by comprehensively considering multiple target project cost collision factors affecting the target project, a more accurate project cost prediction result is obtained.

[0113] An embodiment of the present disclosure also provides an electronic device, comprising: at least one processor; and a memory for storing instructions executable by the at least one processor; wherein the at least one processor is configured to execute the instructions to implement the above method disclosed in the embodiment of the present disclosure.

[0114] Figure 4 The structure diagram of an electronic device provided by an exemplary embodiment of the present disclosure is shown in FIG. Figure 4As shown, the electronic device 1800 includes at least one processor 1801 and a memory 1802 coupled to the processor 1801 , and the processor 1801 can execute corresponding steps in the above method disclosed in the embodiment of the present disclosure.

[0115] The processor 1801 may also be referred to as a central processing unit (CPU), which may be an integrated circuit chip having signal processing capabilities. Each step in the method disclosed in the embodiment of the present disclosure may be completed by an integrated logic circuit of hardware in the processor 1801 or by instructions in the form of software. The processor 1801 may be a general-purpose processor, a digital signal processor (DSP), an ASIC (Application Specific Integrated Circuit), a field-programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. A general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc. The steps of the method disclosed in the embodiment of the present disclosure may be directly embodied as being executed by a hardware decoding processor, or may be executed by a combination of hardware and software modules in a decoding processor. The software module may be located in a memory 1802, such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory or an electrically erasable programmable memory, a register, or other mature storage media in the art. The processor 1801 reads the information in the memory 1802 and completes the steps of the method in combination with its hardware.

[0116] In addition, when various operations / processes according to the present disclosure are implemented by software and / or firmware, they can be transmitted from a storage medium or a network to a computer system having a dedicated hardware structure, such as Figure 5 The computer system 1900 shown is installed with the programs constituting the software. When the various programs are installed, the computer system can perform various functions, including the functions described above. Figure 5 A structural block diagram of a computer system provided for an exemplary embodiment of the present disclosure.

[0117] Computer system 1900 is intended to represent various forms of digital electronic computer devices, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. Electronic devices can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present disclosure described and / or claimed herein.

[0118] like Figure 5 As shown, the computer system 1900 includes a computing unit 1901, which can perform various appropriate actions and processes according to a computer program stored in a read-only memory (ROM) 1902 or a computer program loaded from a storage unit 1908 to a random access memory (RAM) 1903. In the RAM 1903, various programs and data required for the operation of the computer system 1900 can also be stored. The computing unit 1901, the ROM 1902, and the RAM 1903 are connected to each other via a bus 1904. An input / output (I / O) interface 1905 is also connected to the bus 1904.

[0119] A plurality of components in the computer system 1900 are connected to the I / O interface 1905, including: an input unit 1906, an output unit 1907, a storage unit 1908, and a communication unit 1909. The input unit 1906 may be any type of device capable of inputting information to the computer system 1900, and the input unit 1906 may receive input digital or character information, and generate key signal inputs related to user settings and / or function control of the electronic device. The output unit 1907 may be any type of device capable of presenting information, and may include, but is not limited to, a display, a speaker, a video / audio output terminal, a vibrator, and / or a printer. The storage unit 1908 may include, but is not limited to, a disk, an optical disk. The communication unit 1909 allows the computer system 1900 to exchange information / data with other devices over a network such as the Internet, and may include, but is not limited to, a modem, a network card, an infrared communication device, a wireless communication transceiver, and / or a chipset, such as a Bluetooth™ device, a WiFi device, a WiMax device, a cellular communication device, and / or the like.

[0120] The computing unit 1901 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 1901 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various computing units running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The computing unit 1901 performs the various methods and processes described above. For example, in some embodiments, the above methods disclosed in the embodiments of the present disclosure may be implemented as a computer software program, which is tangibly included in a machine-readable medium, such as a storage unit 1908. In some embodiments, part or all of the computer program may be loaded and / or installed on an electronic device via ROM 1902 and / or communication unit 1909. In some embodiments, the computing unit 1901 may be configured to perform the above methods disclosed in the embodiments of the present disclosure in any other appropriate manner (e.g., by means of firmware).

[0121] The embodiment of the present disclosure further provides a computer-readable storage medium, wherein when instructions in the computer-readable storage medium are executed by a processor of an electronic device, the electronic device is enabled to execute the above method disclosed in the embodiment of the present disclosure.

[0122] The computer-readable storage medium in the disclosed embodiments may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. The computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or equipment, or any suitable combination of the foregoing. More specifically, the computer-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0123] The computer-readable medium may be included in the electronic device, or may exist independently without being incorporated into the electronic device.

[0124] The embodiments of the present disclosure further provide a computer program product, including a computer program, wherein when the computer program is executed by a processor, the above method disclosed in the embodiments of the present disclosure is implemented.

[0125] In embodiments of the present disclosure, computer program codes for performing the operations of the present disclosure may be written in one or more programming languages ​​or combinations thereof, including but not limited to object-oriented programming languages, such as Java, Smalltalk, C++, and conventional procedural programming languages, such as "C" language or similar programming languages. The program code may be executed entirely on a user's computer, partially on a user's computer, as an independent software package, partially on a user's computer, partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer via any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer.

[0126] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present disclosure. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some implementations as replacements, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0127] The modules, components or units involved in the embodiments described in the present disclosure may be implemented by software or hardware, wherein the names of the modules, components or units do not, in some cases, limit the modules, components or units themselves.

[0128] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chip (SOCs), complex programmable logic devices (CPLDs), and the like.

[0129] The above descriptions are only some embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of disclosure involved in the present disclosure is not limited to the technical solutions formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the above disclosed concept. For example, a technical solution formed by replacing the above features with the technical features with similar functions disclosed in the present disclosure (but not limited to).

[0130] Although some specific embodiments of the present disclosure have been described in detail by way of example, it should be understood by those skilled in the art that the above examples are for illustration only and are not intended to limit the scope of the present disclosure. It should be understood by those skilled in the art that the above embodiments may be modified without departing from the scope and spirit of the present disclosure. The scope of the present disclosure is defined by the appended claims.

Claims

1. A method for predicting construction cost. It is characterized in that The method comprises: Obtain multiple target project cost collision factors of the target project; The multiple target project cost collision factors are input into a pre-constructed project cost prediction model to obtain a project cost prediction result for the target project; wherein the project cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical project cost collision factors in historical projects and the actual costs of the historical projects.

2. The method according to claim 1, It is characterized in that The step of obtaining target project cost collision factors of multiple target projects includes: Obtaining multiple project cost collision factors of the target project; Inputting the plurality of project cost collision factors into a multi-factor collision model, and determining weights corresponding to the plurality of project cost collision factors respectively through the multi-factor collision model; wherein the weights are positively correlated with the degree of influence of the project cost; The project cost collision factor with a weight greater than a threshold is used as the target project cost collision factor.

3. The method according to claim 1, It is characterized in that The method further comprises: Obtaining the actual cost of the target project; The actual cost and the project cost prediction result are input into a project cost prediction building information model, and a project cost deviation is output; wherein the project cost prediction building information model is obtained by spatially mapping the project cost prediction model with a building information model.

4. The method according to claim 3, It is characterized in that The method further comprises: When the engineering cost deviation is greater than a threshold value, the degree of deviation between the engineering cost prediction result and the actual cost is displayed by means of color difference.

5. The method according to claim 1, It is characterized in that The method further comprises: Obtaining a plurality of initial project cost collision factors of the target project; Acquiring data of the target project based on the multiple initial project cost collision factors; The information data is extracted, the extracted data is added to the engineering template to obtain a multi-factor data set of the engineering cost, and the target engineering cost collision factor is determined from the multi-factor data set.

6. The method according to claim 5, It is characterized in that Determining the target project cost collision factor from the multi-factor data set includes: Sorting the project cost collision factors in the multi-factor data set; The target project cost collision factor is determined from the sorted project cost collision factors.

7. The method according to claim 5, It is characterized in that The method further comprises: Mapping the data with the spatial components in the building information model, and mapping the project cost prediction result with the building information model; Based on the mapping result, the project cost of the target project is displayed in three dimensions in a visualized manner; wherein, in the three-dimensional visualized display, different colors represent different construction progresses in the target project.

8. A device for predicting construction cost, It is characterized in that The device comprises: A collision factor acquisition module is used to obtain multiple target project cost collision factors of a target project; The project cost prediction module is used to input the multiple target project cost collision factors into a pre-built project cost prediction model to obtain a project cost prediction result for the target project; wherein the project cost prediction model is obtained by training a preset neural network model through training samples, and the training samples include historical project cost collision factors in historical projects and the actual costs of the historical projects.

9. An electronic device, It is characterized in that include: at least one processor; a memory for storing the at least one processor-executable instruction; The at least one processor is configured to execute the instructions to implement the method according to any one of claims 1 to 7.

10. A computer-readable storage medium, It is characterized in that When the instructions in the computer-readable storage medium are executed by a processor of an electronic device, the electronic device is enabled to perform the method as claimed in any one of claims 1 to 7.

11. A computer program product, It is characterized in that The invention comprises a computer program, which implements the method according to any one of claims 1 to 7 when being executed by a processor.