5WMh liquid cooling external maintenance battery energy storage system cabin

By using liquid cooling and heat management systems and advanced fire protection systems in energy storage power stations, the problems of long construction cycles, poor cell temperature uniformity and operation and maintenance risks of traditional energy storage power stations have been solved, and efficient energy storage density and system stability have been achieved. , improving economic performance and safety.

CN118801016APending Publication Date: 2024-10-18BEIJING SOJO ELECTRIC CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202410775500.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

Existing energy storage power stations have long construction periods, high civil construction costs, low single battery capacity, poor cell temperature uniformity in the air-cooled thermal management system, lack of effective fire re-ignition response mechanisms, and high operation and maintenance risks, resulting in power grid frequency fluctuations. and system stability issues.

Method used

Design a 5WMh liquid-cooled external maintenance battery energy storage system cabin, using a liquid-cooled thermal management system, advanced fire protection system and fire early warning system, including multi-functional fire detection sensors, gas and water fire protection components, liquid-cooled main engine room and battery room Partitioned, modular design, the electrical control room is isolated from the converging room, using liquid cooling and thermal management systems and Pack-level fire protection hardware.

Benefits of technology

It increases the storage energy of a single container, reduces the floor space and construction costs, extends the battery life, enhances the reliability, stability and safety of the system, reduces operation and maintenance risks, and achieves higher economic performance and safety. sex.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118801016A_ABST
    Figure CN118801016A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of battery energy storage, in particular to a 5WMh liquid cooling external maintenance battery energy storage system cabin. Comprising a battery chamber, an electrical chamber and a liquid cooling host chamber, a plurality of battery cluster frames are arranged in the battery chamber; a fire detection sensor, an execution assembly and a combustible gas exhaust assembly are arranged at the top of the battery chamber; a liquid cooling pipeline of a liquid cooling heat management system is arranged in the battery chamber, the upper part of the battery rack is a water return pipeline, and the bottom of the battery rack is a water supply pipeline; a liquid cooling host is mounted in the liquid cooling host chamber, the liquid cooling host is mounted on a corresponding base through a bottom bolt, and the liquid cooling host is connected with the side part of the battery cabin by using a mounting plate at the side part of the liquid cooling host chamber; the electrical room is divided into an upper layer and a lower layer, the lower layer is a DC confluence room, and the upper layer is an electrical control room; converging copper bars and a cable box are arranged in the DC confluence chamber, the batteries are connected in series with the high-voltage box and then connected to the copper bars for current collection, and the other ends of the copper bars are connected to the PCS direct current side through cables. The device is reasonable in layout and safe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of battery energy storage, and in particular to a 5WMh liquid-cooled externally maintained battery energy storage system cabin. Background Art

[0002] The description of the background technology in the present invention belongs to the related technology related to the present invention and is only used to illustrate and facilitate the understanding of the content of the present invention. It should not be understood that the applicant explicitly believes or presumes that the applicant believes that it is the prior art of the present invention on the filing date of the first application.

[0003] The current energy structure will undergo major changes, and the proportion of renewable energy represented by solar energy and wind energy in the energy structure will increase significantly. However, compared with traditional thermal power and hydropower, new energy generation represented by solar energy and wind energy is random and volatile, which has frequency problems for the power grid. Power disturbances cause increased frequency fluctuations, weak system voltage support capabilities, weak anti-disturbance capabilities, and resonance between power generation equipment and the system. To solve the above problems, adding energy storage systems on the new energy power generation side can effectively solve the above problems caused by new energy power generation on the power grid.

[0004] Traditional energy storage power stations have disadvantages such as long construction period, high civil engineering cost and many construction restrictions. The traditional 1000V low-voltage solution requires more equipment and the battery capacity of a single cabin is low, resulting in high single-cell cost and low energy density per unit area. The air-cooled thermal management system has poor temperature uniformity of the battery cells in the cabin, which is not conducive to the cycle life of the battery cells. Only gas fire extinguishing devices are configured, and there is no fire re-ignition response mechanism. The cabin operation and maintenance has certain risks. Summary of the invention

[0005] The purpose of the embodiment of the present invention is to provide a 5WMh liquid-cooled external maintenance battery energy storage system cabin.

[0006] A 5WMh liquid-cooled external maintenance battery energy storage system cabin, comprising: a battery room, an electrical room and a liquid-cooled main engine room;

[0007] The battery room is provided with a plurality of battery cluster racks, which are fixed to the bottom of the battery room by threads. A single battery cluster rack can hold 24 liquid-cooled battery packs and 3 high-voltage boxes. The top of the battery room is provided with a fire detection sensor, an actuator, and a combustible gas exhaust assembly. The actuator includes a gas fire extinguishing assembly and a water fire fighting assembly. The fire detection sensor is signal-connected to the actuator and the combustible gas exhaust assembly respectively. The battery room is provided with liquid cooling pipelines of the liquid cooling thermal management system. The upper part of the battery rack is the return pipeline, and the bottom of the battery rack is the water supply pipeline. Together with the cooling plate and the liquid cooling host in the battery pack, they form a liquid cooling thermal management system.

[0008] The liquid-cooled host is installed in the liquid-cooled host room. The liquid-cooled host is installed on the corresponding base through the bottom bolts. The side of the liquid-cooled host room uses a mounting plate to connect the liquid-cooled host with the side of the battery compartment;

[0009] The electrical room is divided into two floors, the lower floor is the DC bus room, and the upper floor is the electrical control room;

[0010] The DC busbar and cable box are installed in the DC busbar room. Each battery cluster in the battery room is connected in series with a high-voltage box, which is then connected to the busbar via a cable for current collection. The other end of the busbar is connected to the PCS DC side by a cable.

[0011] The electrical control room consists of an integrated control cabinet, fire gas storage tanks, fire host and fire control box.

[0012] Furthermore, the number of battery cluster racks in the battery room is 4, and the fire detection sensor includes hydrogen, carbon monoxide, VOC (volatile organic compound), temperature, and smoke detection functions. The detection sensors and actuators constitute the fire protection system and fire warning system of the prefabricated cabin of the energy storage system. The fire protection system contains a secondary fire suppression system. The first suppression function is performed by the gas fire extinguishing component. When the execution is completed, the water fire fighting component performs secondary suppression when the system detection shows that the fire is re-ignited; the combustible gas exhaust component monitors the relevant data in real time through the relevant fire detection sensors. When the concentration reaches the relevant threshold, the combustible gas exhaust device is started to replace the fresh air outside the cabin with the gas in the cabin to ensure that the combustible gas concentration in the cabin is below the threshold; the battery room is equipped with temperature and humidity sensors, water immersion sensors and temperature and humidity sensors; the battery room is equipped with 4 explosion-proof LED lights, each of which is combined with its corresponding travel switch.

[0013] Furthermore, the battery room is equipped with 4 explosion-proof LED lights, each light is combined with its corresponding travel switch;

[0014] The liquid-cooled host door adopts a frame plus wire mesh structure, with removable shutters on the sides;

[0015] The first-level pipeline of the liquid cooling pipeline is connected to the liquid cooling host through the middle opening of the partition, the second-level pipeline passes through the control valve, the tertiary pipeline is connected to the second-level pipeline through a tee, and the tertiary pipeline is connected to the liquid cooling pack14 through a quick-plug interface to form a liquid cooling water cooling loop system; the partition through-hole adopts sealing plates installed on both sides, and the middle of the sealing plate is filled with fireproof mud. The bottom line communication line of the liquid cooling host enters the control room and the grounding bar through the control room partition.

[0016] Furthermore, the electrical control room is composed of an integrated control cabinet, a fire gas storage tank, a fire control host and a fire control box;

[0017] The integrated control cabinet is composed of a distribution box, a backup power box, a control cabinet, and an environmental detection function integration;

[0018] The electrical control room has smoke detection sensors and temperature detection sensors connected to the fire control host. A dehumidification air conditioner is hung on the outer door of the electrical control room to cool the electrical room and the junction room.

[0019] Furthermore, the end is equipped with a fire-fighting warning light and an audible and visual alarm. When the alarm is triggered, the alarm bell, audible and visual alarm, and the warning light will light up, and the gas fire extinguishing device will start to spray gas inhibitors after 20 seconds. A KN65 internal buckle external water interface is installed, which can be directly connected to a fire hose or an external pipeline.

[0020] By means of the above scheme, the present invention has at least the following beneficial effects:

[0021] The storage capacity of a single container has been greatly increased, the floor space of the prefabricated cabin has been saved by more than 20%, the construction workload has been reduced by 15%, the commissioning and operation and maintenance costs have been reduced by 10%, and the container usage of the project has been reduced by more than 10%, which has greatly improved the economic performance. At the same time, the selection of Pack-level fire protection has been increased, which has higher reliability, stability and safety.

[0022] Using liquid cooling as a thermal management solution is much better than air cooling. The average temperature in the cabin is 5°C lower than that of the air cooling solution, effectively extending the battery life by 20%.

[0023] Adopt advanced fire protection system and fire warning system.

[0024] The overall integration is high and the internal space utilization rate is high.

[0025] Using external maintenance solutions effectively reduces the possibility of personnel danger compared to internal maintenance solutions.

[0026] The battery room, electrical control room and junction room are isolated to effectively protect the safety of electrical control and fire control systems.

[0027] The modular design can meet the needs of different users by reducing the number of battery clusters and high-voltage boxes and being backward compatible with 1000V (low-voltage solution). The modular design can meet the needs of different users by reducing the number of battery clusters and high-voltage boxes in the cabin and being backward compatible with 1000V (d low-voltage solution). BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the technical solution of the present invention, the following is a brief introduction to the drawings required for describing the embodiments:

[0029] Figure 1 This is a structural schematic diagram of a 5WMh liquid-cooled external maintenance battery energy storage system cabin of the present invention;

[0030] Figure 2This is another structural schematic diagram of a 5WMh liquid-cooled external maintenance battery energy storage system cabin of the present invention. DETAILED DESCRIPTION

[0031] The present invention is further described in detail below in conjunction with the embodiments. It should be understood that the embodiments are for those skilled in the art to more easily understand the technical solutions of the present invention and cannot be used as a limitation on the protection scope of the present invention.

[0032] In the following description, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance. The following description provides multiple embodiments of the present invention, and different embodiments can be replaced or combined, so the present invention can also be considered to include all possible combinations of the same and / or different embodiments described. Therefore, if one embodiment includes features A, B, and C, and another embodiment includes features B and D, then the present invention should also be considered to include embodiments containing one or more of all other possible combinations of A, B, C, and D, even though the embodiment may not be clearly described in the following text.

[0033] The traditional 1000V low-voltage solution requires more equipment, and the battery capacity of a single cabin is low, resulting in higher monomer costs and lower energy density per unit area;

[0034] The air-cooled thermal management system has poor temperature uniformity in the battery cells, which is not conducive to the cycle life of the battery cells;

[0035] Only equipped with gas fire extinguishing device, no fire re-ignition response mechanism;

[0036] In-cabin operation and maintenance has certain risks;

[0037] Combined with Figure 1 and 2 , a 5WMh liquid-cooled external maintenance battery energy storage system cabin, including: a battery room, an electrical room and a liquid-cooled main engine room;

[0038] The battery room is provided with a plurality of battery cluster racks, which are fixed to the bottom of the battery room by threads. A single battery cluster rack can hold 24 liquid-cooled battery packs and 3 high-voltage boxes. The top of the battery room is provided with a fire detection sensor, an actuator, and a combustible gas exhaust assembly. The actuator includes a gas fire extinguishing assembly and a water fire fighting assembly. The fire detection sensor is signal-connected to the actuator and the combustible gas exhaust assembly respectively. The battery room is provided with liquid cooling pipelines of the liquid cooling thermal management system. The upper part of the battery rack is the return pipeline, and the bottom of the battery rack is the water supply pipeline. Together with the cooling plate and the liquid cooling host in the battery pack, they form a liquid cooling thermal management system.

[0039] A liquid-cooled host 6 is installed in the liquid-cooled host room, and the liquid-cooled host 6 is installed on the corresponding base through bottom bolts. The side of the liquid-cooled host room uses a mounting plate to connect the liquid-cooled host 6 with the side of the battery compartment;

[0040] The electrical room is divided into two floors, the lower floor is the DC bus room, and the upper floor is the electrical control room;

[0041] The DC busbar and cable box are installed in the DC busbar room. Each battery cluster in the battery room is connected in series with a high-voltage box, which is then connected to the busbar via a cable for current collection. The other end of the busbar is connected to the PCS DC side by a cable.

[0042] The electrical control room is composed of an integrated control cabinet 5, a fire gas storage tank, a fire host and a fire control box.

[0043] Combined with Figure 1 and 2 The energy storage battery compartment 1 is divided into four parts: battery room, electrical control room, liquid cooling main engine room, and junction cabinet room 15. The four chambers are made of metal partitions filled with heat-insulating and fire-proof materials. The battery room is arranged with 4 battery cluster racks 3. A single battery cluster rack 3 can hold 24 liquid cooling battery packs and 3 high-voltage boxes 4. The battery cluster rack 3 is directly installed with the bottom plate of the energy storage compartment using threads, without the need for battery mounting frame conversion. The non-welded installation maximizes the use of height space, facilitates the replacement and installation of the entire cluster in the later maintenance, and is conducive to the later maintenance. With such a battery cluster and high-voltage box layout, combined with the currently used liquid cooling pack, the rated voltage of a single cluster can reach (single battery cell 3.2V) 1331.2V, and the charging stop voltage (single battery cell 3.65v) 1518.4V, reaching the 1500V level (high voltage solution), and the overall energy density has increased significantly compared to the 1000V level (low voltage solution). A removable fixing plate is installed on the front end of the battery rack for installing pack-level fire protection.

[0044] A fire detection sensor is installed on the top of the battery room, which includes hydrogen, carbon monoxide, VOC (volatile organic compound), temperature, and smoke detection functions on one side. There are 2 sets of fire detection sensors on the top of the battery room. At the same time, a gas fire extinguishing component, a water fire fighting component, and a combustible gas exhaust component are also installed on the top. The above detection sensors and actuators constitute the fire protection system 9 and fire warning system of the energy storage system prefabricated cabin. The fire protection system contains a secondary fire suppression system. The first suppression function is performed by the gas fire extinguishing component. When the execution is completed, the system detection shows that the fire has re-ignited. The water fire fighting component performs the secondary suppression. The combustible gas exhaust component is used to cause slight combustible gas leakage (hydrogen, carbon monoxide, VOC) to accumulate in the battery cabin when the energy storage system is working normally. When it reaches a certain concentration, it will cause the risk of explosion. The combustible gas exhaust component can monitor the relevant data in real time through the relevant detection sensor. When the concentration reaches the relevant threshold, the combustible gas exhaust device is started to replace the fresh air outside the cabin with the gas inside the cabin to ensure that the concentration of combustible gas in the cabin is below the threshold. At the same time, the battery compartment is equipped with temperature and humidity sensors, water immersion sensors, and temperature and humidity sensors to ensure that the temperature and humidity in the compartment are within the proper range. The water immersion sensor and supporting equipment can detect in real time whether there is any coolant leakage and rain leakage in the box. At the same time, the bottom plate of the battery compartment is divided into 12 areas. Each area adopts a design with a high middle and low sides, and the lower areas are provided with leakage holes to ensure that when liquid appears inside the container, the liquid can be discharged from the container in time to prevent liquid accumulation and ensure safety in the warehouse.

[0045] The battery room of the energy storage system prefabricated cabin is equipped with 4 explosion-proof LED lights 7. Each light is combined with its corresponding travel switch 8 to realize the function of automatically lighting up the door opening light. At the same time, the travel switch 8 can display the state of the door opening in the background through the line. The battery room is equipped with a liquid cooling pipeline 2 of the liquid cooling thermal management system. The upper part of the battery rack is the return pipeline, and the bottom of the battery rack is the water supply pipeline. They form a liquid cooling thermal management system with the cooling plate and liquid cooling host in the battery pack. Through this efficient thermal management system, the average difference of the battery cells in the entire cabin can be maintained at 3°C, which can effectively increase the life of the battery cells by 20%.

[0046] The liquid-cooled host room is mainly used to install the liquid-cooled host. The liquid-cooled host is installed on the corresponding base through the bottom bolts. At the same time, the mounting plate is used on the side to connect the liquid-cooled host to the side of the battery compartment. The liquid-cooled host door adopts a frame plus wire mesh structure to ensure the exhaust efficiency of the liquid-cooled host. At the same time, the side is a removable shutter. The ventilation rate of the liquid-cooled window design can reach 85% to ensure the return air efficiency of the liquid-cooled host and easy installation. The first-level pipeline of the liquid-cooled pipeline is connected to the liquid-cooled host through the middle opening of the partition, the second-level pipeline is connected to the second-level pipeline through a tee through the control valve, and the third-level pipeline is connected to the liquid-cooled pack through a quick-plug interface. The above forms a liquid-cooled water-cooled circuit system. At the same time, the entire liquid-cooled pipeline system also includes 2 stop valves, 2 exhaust valves, and 2 drain valves. At the same time, the partition through-hole adopts the installation of sealing plates on both sides, and the middle of the sealing plate is filled with fireproof mud to ensure the protection level of the battery room. The bottom line of the power line of the liquid-cooled host and the communication line enter the control room and the grounding bar through the control room partition.

[0047] The electrical room is divided into two floors, the lower floor is the DC bus room and the upper floor is the electrical control room.

[0048] The DC busbar is mainly composed of a busbar and a cable box. Each battery cluster in the battery compartment is connected in series with a high-voltage box, which is then connected to the copper busbar via a cable for current collection. The other end of the copper busbar is connected to the PCS DC side by a cable.

[0049] The electrical control room is composed of an integrated control cabinet 5, a fire gas storage tank, a fire host and a fire control box. The integrated control cabinet 5 is fixed to the container with bolts, and its important functions include a distribution box, a backup power box (UPS), a control cabinet, and environmental detection. The electrical control room has 1 smoke detection sensor and 1 temperature detection sensor connected to the fire control host, 1 explosion-proof single switch, and the lighting system can be manually turned off during the day. 1 temperature and humidity sensor, 1 water immersion sensor related functions refer to the battery compartment function, 1 five-hole explosion-proof socket, which is convenient for future maintenance. A dehumidification and cooling air conditioner 12 is hung on the outer door of the electrical room to cool the electrical room and the confluence room.

[0050] The electrical room is equipped with fire protection system gas storage device and gas fire protection delivery device, emergency stop system, fire protection manual start device, fire protection host, module box, alarm and other fire protection system equipment. The fire protection control host is the core control device of the entire fire protection system and fire warning system. All fire protection related detection sensors and solenoid valves, and warning devices are connected to the control host. The fire protection manual start device can manually start the release of gas suppressants when the fire protection automatic system fails or the manual judgment is earlier than the fire warning. The combustible gas exhaust manual start device can manually start the combustible system exhaust system 10. The alarm can emit a harsh bell when the first-level fire alarm is triggered to warn relevant personnel to stay away from the energy storage system prefabricated cabin. The fire protection module box 11 is installed with relevant relay data collection module control module, etc. The emergency stop system is used to press the emergency stop button, and the relevant switches involving DC in the entire cabin are tripped, and the entire cabin DC system exits the system.

[0051] The end is equipped with a fire-fighting do not enter warning light and sound and light alarm, which have similar functions to alarm bells. When the first alarm is triggered, the sound and light alarm emits a harsh sound and the red warning light is on. When the third alarm is triggered, the alarm bell, sound and light alarm, and do not enter warning light are on, and the gas fire extinguishing device is activated to spray gas inhibitors after 20 seconds. A KN65 inner buckle external water interface 13 is installed, which can be directly connected to a fire hose or an external pipeline to provide water spray suppression to prevent the gas fire from being completely extinguished.

[0052] The overall layout plan of this application is reasonable, such as the installation of a fixed Pack battery rack and a pack-level fire protection design and installation plan; the junction room and the electrical room are separated, which is more conducive to safety; the overall layout and structural features include the fire protection structure layout and the internal structure and layout of the liquid-cooled host and liquid-cooling pipes.

[0053] 1. This solution uses a 1500V high-voltage solution. Compared with the 1000V low-voltage solution, it requires fewer integrated bus devices and requires the use of higher-power PCS devices.

[0054] 2. This solution uses a liquid cooling unit and a liquid cooling pipeline system. The thermal management system using a glycol mixed liquid coolant has a better cooling effect than the mainstream air cooling solution. The temperature difference of the battery cells in the air cooling cabin reaches 8°C, while the temperature difference in the liquid cooling cabin is 3°C, which is beneficial to the charge and discharge life of the battery cells, and the theoretical life can be increased by 20%. At the same time, compared with air cooling, it has better economic benefits. When the battery cells reach the same average temperature, the energy consumption of air cooling is 2-3 times higher than that of liquid cooling.

[0055] 3. Compared with traditional solutions, this solution has a higher degree of integration. The integrated control cabinet integrates other solutions such as the combiner cabinet, distribution box, backup power box, control cabinet, environmental detection and other functions.

[0056] 4. Fire protection scheme is similar to other schemes. One side is equipped with five detectors of hydrogen, carbon monoxide, VOC, temperature and smoke. It has a 3-level alarm mode and can perform corresponding actions according to the set single alarm or compound fire alarm to protect the installation of the entire cabin. It also has two fire extinguishing mechanisms, gas fire and water fire, which effectively prevent the secondary reignition of the fire and provide double insurance for the battery system. It also has pack-level fire protection hardware configuration, which can be upgraded according to different user needs.

[0057] 5. Use extravehicular maintenance design to avoid personal injury caused by related accidents

[0058] 6. All relevant modules of this solution are connected by thread, which is convenient for maintenance and replacement of relevant modules

[0059] 7. Equipped with a dehumidification device to ensure that the entire cabin operates in a suitable environment

[0060] 8. This solution uses fireproof and heat-insulating partitions to divide the cabin into the electrical cabin and the battery cabin, ensuring that the relevant control systems and fire protection systems have enough time to execute corresponding strategies in the event of a dangerous situation

[0061] 9. Configure temperature, humidity and water immersion sensors to monitor the cabin environment in real time, and issue an alarm immediately when a problem occurs.

[0062] Compared with the maximum storage capacity of 3.8WMh of the previous generation standard 20-foot container, the storage capacity of a single container has been greatly increased, the floor space of the prefabricated cabin has been saved by more than 20%, the construction workload has been reduced by 15%, the commissioning and operation and maintenance costs have been reduced by 10%, and the container usage of the project has been reduced by more than 10%, which has greatly improved the economic performance. At the same time, the selection of Pack-level fire protection has been increased, which has higher reliability, stability and safety.

[0063] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A 5WMh liquid-cooled external maintenance battery energy storage system cabin, characterized in that: include: Battery room, electrical room and liquid-cooled main engine room; The battery room is provided with a plurality of battery cluster racks, which are threadedly fixed to the bottom of the battery room. A single battery cluster rack can hold 24 liquid-cooled battery packs and 3 high-voltage boxes; the top of the battery room is provided with a fire detection sensor, an actuator and a combustible gas exhaust assembly, and the actuator includes a gas fire extinguishing assembly and a water fire fighting assembly; the fire detection sensor is signal-connected to the actuator and the combustible gas exhaust assembly respectively; the battery room is provided with a liquid cooling pipeline of a liquid cooling thermal management system, the upper part of the battery rack is a return water pipeline, and the bottom of the battery rack is a water supply pipeline, which together with the cooling plate in the battery pack and the liquid cooling host constitute a liquid cooling thermal management system; The liquid-cooled host is installed in the liquid-cooled host room. The liquid-cooled host is installed on the corresponding base through the bottom bolts. The side of the liquid-cooled host room uses a mounting plate to connect the liquid-cooled host with the side of the battery compartment; The electrical room is divided into two floors, the lower floor is the DC bus room, and the upper floor is the electrical control room; The DC busbar and cable box are installed in the DC busbar room. Each battery cluster in the battery room is connected in series with a high-voltage box, which is then connected to the busbar via a cable for current collection. The other end of the busbar is connected to the PCS DC side by a cable. The electrical control room consists of an integrated control cabinet, fire gas storage tanks, fire host and fire control box.

2. The 5WMh liquid-cooled external maintenance battery energy storage system cabin according to claim 1 is characterized in that: The number of battery cluster racks in the battery room is 4. The fire detection sensor includes hydrogen, carbon monoxide, VOC (volatile organic compound), temperature, and smoke detection functions. The detection sensor and the execution component constitute the fire protection system and fire warning system of the prefabricated cabin of the energy storage system. The fire protection system contains a secondary fire suppression system. The first suppression function is performed by the gas fire extinguishing component 17. When the execution is completed, when the system detection shows that the fire is re-ignited, the water fire fighting component performs the secondary suppression; the combustible gas exhaust component monitors the relevant data in real time through the relevant fire detection sensor. When the concentration reaches the relevant threshold, the combustible gas exhaust device is started to replace the fresh air outside the cabin with the gas in the cabin to ensure that the combustible gas concentration in the cabin is below the threshold; the battery room is equipped with a temperature and humidity sensor, a water immersion sensor and a temperature and humidity sensor; the battery room is equipped with 4 explosion-proof LED lights, each of which is combined with its corresponding travel switch.

3. The 5WMh liquid-cooled external maintenance battery energy storage system cabin according to claim 2 is characterized in that: The battery room is equipped with 4 explosion-proof LED lights, each light is combined with its corresponding travel switch; The liquid-cooled host door adopts a frame plus wire mesh structure, with removable shutters on the sides; The first-level pipeline of the liquid cooling pipeline is connected to the liquid cooling host through the middle opening of the partition, the second-level pipeline passes through the control valve, the tertiary pipeline is connected to the second-level pipeline through a tee, and the tertiary pipeline is connected to the liquid cooling pack through a quick-plug interface to form a liquid cooling water cooling loop system; the partition through-hole adopts sealing plates installed on both sides, and the middle of the sealing plate is filled with fireproof mud. The bottom line communication line of the liquid cooling host enters the control room and the grounding bar through the control room partition.

4. The 5WMh liquid-cooled external maintenance battery energy storage system cabin according to claim 3 is characterized in that: The electrical control room is composed of an integrated control cabinet, a fire gas storage tank, a fire control host and a fire control box; The integrated control cabinet is composed of a distribution box, a backup power box, a control cabinet, and an environmental detection function integration; The electrical control room has smoke detection sensors and temperature detection sensors connected to the fire control host. A dehumidification air conditioner is hung on the outer door of the electrical control room to cool the electrical room and the junction room.

5. The 5WMh liquid-cooled external maintenance battery energy storage system cabin according to claim 4 is characterized in that: The end is equipped with a fire-fighting "Do Not Deflate" warning light and an audible and visual alarm. When the alarm is triggered, the alarm bell, audible and visual alarm, and "Do Not Deflate" warning light will light up, and the gas fire extinguishing device will start to spray gas inhibitors after 20 seconds. A KN65 inner buckle external water interface is installed, which can be directly connected to a fire hose or an external pipeline.

Citation Information

Cited By

  • Box-type power supply control cabinet

    CN119726445A

  • A box-type power control cabinet

    CN119726445B

  • Energy storage container with liquid cooling system

    CN120073148A