Special gas transmission control method and system
Through the combination of a double closed-loop control structure and a machine learning model, the problem of slow response speed and insufficient control accuracy of the special gas transmission control system is solved, and the special gas flow rate is quickly and accurately adjusted, improving the stability and adaptability of the system and ensuring product quality and performance.
Patent Information
- Application Number
- CN202411025118.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing special gas transmission control system responds slowly when faced with rapidly changing flow demands, making it difficult to quickly reach the target flow rate. It also has insufficient control accuracy, poor stability, and weak adaptability, which affects product quality and performance.
Using a double closed-loop control structure combined with a machine learning model, the PID controller is used to adjust the control signal of the special gas delivery component, and the preset first PID and second PID controllers are used to quickly adjust the special gas flow rate, and when the actual flow rate does not reach the target , updating PID parameters through machine learning models to improve response speed and control accuracy.
It significantly improves the response speed, control accuracy and stability of the special gas transmission control system, enhances the anti-interference ability, ensures that the special gas flow reaches the target value quickly and accurately, and improves product quality and system performance.
Smart Images

Figure CN118856232A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of special gas transmission, and in particular to a special gas transmission control method and system. Background Art
[0002] Specialty gases (specialty gases) refer to high-purity gases used in semiconductor manufacturing, laboratory research, and other high-tech industries. These gases usually have special physical and chemical properties and are used in various precision processes, such as etching, deposition, cleaning, etc. The quality of specialty gases directly affects the performance and reliability of the product, so precise control of their transmission and use is essential.
[0003] In the special gas transmission control system, controlling the gas flow is a very critical step. In order to ensure that the required flow value is achieved, the special gas transmission control system usually uses a controller to adjust the valve opening. However, the existing control technology has a slow response to the rapidly changing flow demand, resulting in the system being unable to quickly reach the target flow. Summary of the invention
[0004] The technical problem to be solved by this application is to provide a method and system for controlling the transmission of special gases, which can effectively improve the response speed of the transmission control of special gases. The specific scheme is as follows:
[0005] According to a first aspect of an embodiment of the present application, a special gas transmission control method is provided, which is applied to 1. A special gas transmission control method, characterized in that it is applied to a control device in a special gas transmission control system, the special gas transmission control system also includes a special gas supply source and a special gas delivery component, the special gas delivery component is used to deliver the special gas in the special gas supply source to the special gas use point, and the method includes:
[0006] In response to a special gas transmission instruction, a target special gas flow rate, an actual special gas flow rate in the special gas transmission control system, and a rate of change of the actual special gas flow rate are obtained;
[0007] According to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller, a target special gas flow rate change rate is obtained;
[0008] According to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller, a control signal of the special gas delivery component in the special gas transmission control system is obtained;
[0009] The operation of the special gas delivery component is controlled according to the control signal to adjust the flow rate of the special gas delivered by the special gas delivery component.
[0010] The above method, optionally, after controlling the operation of the special gas delivery component according to the control signal, further comprises:
[0011] If the actual special gas flow rate of the special gas delivery component does not reach the target special gas flow rate within the preset duration, the current environmental parameters of the special gas transmission control system are obtained;
[0012] Inputting the current environmental parameters of the special gas transmission control system into a pre-trained machine learning model to obtain a PID parameter prediction result; the PID parameter prediction result includes a first target PID parameter and a second target PID parameter;
[0013] The first target PID parameter is used to update the first PID controller, and the second target PID parameter is used to update the second PID controller, and the step of returning to execute the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and the preset first PID controller is obtained.
[0014] In the above method, optionally, the process of training the machine learning model includes:
[0015] Obtain a training data set and an initial machine learning model; the training data set includes a plurality of training samples, each of the training samples includes at least a special gas pressure value, a special gas temperature value, a first PID controller parameter and a second PID controller parameter;
[0016] Training the initial machine learning model using training samples in the training data set;
[0017] When the initial machine learning model meets the preset training completion conditions, the initial machine learning model that meets the training completion conditions will be used as the trained machine learning model.
[0018] The above method, optionally, after obtaining the current environmental parameters of the special gas transmission control system, further comprises:
[0019] If the temperature of the special gas in the environmental parameters exceeds a preset temperature threshold, or the pressure of the special gas in the environmental parameters exceeds a preset pressure threshold, an alarm message is output.
[0020] In the above method, optionally, obtaining the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller includes:
[0021] Determining a difference between the actual special gas flow rate and the target special gas flow rate;
[0022] The difference between the actual special gas flow rate and the target special gas flow rate is input into the first PID controller to obtain the target special gas flow rate change rate. The target special gas flow rate change rate is the expected special gas flow rate change rate.
[0023] The above method, optionally, obtaining a control signal of a special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller, comprises:
[0024] Determine the difference between the target characteristic gas flow rate change rate and the actual characteristic gas flow rate change rate;
[0025] The difference between the target special gas flow rate change rate and the actual special gas flow rate change rate is input into the second PID controller to obtain the control signal of the special gas delivery component in the special gas transmission control system.
[0026] In the above method, optionally, obtaining the target characteristic gas flow rate includes:
[0027] Obtaining a target flow rate of a reactant associated with the characteristic gas;
[0028] The target characteristic gas flow rate is calculated based on the target flow rate of the reactants and the preset mixing ratio value.
[0029] According to a second aspect of an embodiment of the present application, a special gas transmission control system is provided, comprising:
[0030] Special gas supply sources, special gas delivery components, detection components and control equipment;
[0031] The special gas supply source is used to store special gas;
[0032] The special gas delivery component is used to deliver the special gas in the special gas supply source to the special gas use point;
[0033] The detection component is used to detect the actual special gas flow rate and the actual special gas flow rate change rate in the special gas transmission control system in real time;
[0034] The control device is used to obtain a target special gas flow rate and an actual special gas flow rate and an actual special gas flow rate change rate detected by the detection component in response to a special gas transmission instruction; obtain a target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller; obtain a control signal of a special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller; and control the operation of the special gas delivery component according to the control signal to adjust the special gas flow rate delivered by the special gas delivery component.
[0035] In the above system, optionally, the special gas delivery component comprises:
[0036] at least one of a valve and an air pump;
[0037] Correspondingly, the control device is used to adjust the opening of the valve and / or the rotation speed of the air pump according to the control signal.
[0038] In the above system, optionally, the special gas supply source comprises:
[0039] Gas cylinder cabinets, purge panels, and purifiers;
[0040] The gas cylinder cabinet is used to store special gases;
[0041] The purge panel is used to purge the special gas delivery pipeline with inert gas;
[0042] The purifier is used to purify the special gas in the gas cylinder cabinet.
[0043] Based on the above-mentioned implementation of the present application, a special gas transmission control method and system are provided, the special gas transmission control system includes a control device, a special gas supply source and a special gas delivery component, the special gas delivery component is used to deliver the special gas in the special gas supply source to the special gas use point, and the method includes: in response to the special gas transmission instruction, obtaining the target special gas flow, the actual special gas flow in the special gas transmission control system and the actual special gas flow change rate; according to the actual special gas flow, the target special gas flow and the preset first PID controller, obtaining the target special gas flow change rate; according to the target special gas flow change rate, the actual special gas flow change rate and the preset second PID controller, obtaining the control signal of the special gas delivery component in the special gas transmission control system; according to the control signal, the operation of the special gas delivery component is controlled to adjust the special gas flow delivered by the special gas delivery component. It can effectively improve the response speed of special gas transmission control. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.
[0045] Figure 1 A method flow chart of a special gas transmission control method provided in this application;
[0046] Figure 2 A schematic diagram of a double closed-loop control structure provided for this application;
[0047] Figure 3 A flowchart of a process for training a machine learning model provided for this application;
[0048] Figure 4 A structural schematic diagram of a special gas transmission control system provided in this application;
[0049] Figure 5 A schematic diagram of the structure of another special gas transmission control system provided in this application. DETAILED DESCRIPTION
[0050] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0051] In this application, the terms "comprises", "comprising" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprising a ..." does not exclude the presence of other identical elements in the process, method, article or device comprising the element.
[0052] In the special gas transmission control system, controlling the gas flow is a very critical step. In order to ensure that the required flow value is achieved, the special gas transmission control system usually uses a controller to adjust the valve opening. However, in the special gas transmission control system, controlling the gas flow is a very critical step. In order to ensure that the required flow value is achieved, the special gas transmission control system usually uses a controller to adjust the valve opening. However, the existing control technology has the following limitations in the special gas transmission control system:
[0053] Insufficient control accuracy: Traditional controllers have difficulty maintaining high control accuracy when facing external disturbances (such as temperature changes and pressure fluctuations). This may cause the special gas flow to deviate from the target value, thereby affecting the quality and performance of the final product.
[0054] Slow response: When faced with rapidly changing flow requirements, the controller responds slowly, causing the system to be unable to quickly reach the target flow. This is particularly important in application scenarios where rapid flow adjustments are required, such as in semiconductor manufacturing, where rapidly changing process conditions require that the specialty gas flow be able to respond quickly.
[0055] Poor stability: The controller has poor stability when dealing with changes in system parameters and is prone to oscillation. This may cause fluctuations in the flow of special gases and affect product quality.
[0056] Weak adaptability: The controller has poor adaptability to load changes and system parameter changes, and the controller parameters need to be adjusted frequently to adapt to different working conditions. This increases the complexity and maintenance cost of the system.
[0057] Based on this, an embodiment of the present invention provides a special gas transmission control method, which is applied to a control device in a special gas transmission control system. The special gas transmission control system also includes a special gas supply source and a special gas delivery component. The special gas delivery component is used to deliver the special gas in the special gas supply source to the special gas use point. The method flow chart of the method is as follows Figure 1 As shown, specifically including:
[0058] S101: In response to a special gas transmission instruction, a target special gas flow rate, an actual special gas flow rate in the special gas transmission control system, and a rate of change of the actual special gas flow rate are obtained.
[0059] In this embodiment, the target special gas flow rate is the special gas flow rate that is expected to be achieved.
[0060] Optionally, the special gas in this embodiment may include one or more of various special gases such as argon, helium, neon, arsine, diborane, ammonia, silane, phosphine, nitric oxide, nitrogen trifluoride, hydrogen chloride, hydrogen bromide, boron trichloride, boron trifluoride, silicon tetrachloride, etc.
[0061] Optionally, the actual special gas flow in the special gas transmission control system can be detected by a detection component, and the detection component may include a flow meter, which may be at least one of a vortex flowmeter, a turbine flowmeter, a mass flowmeter (such as a thermal mass flowmeter) and an ultrasonic flowmeter; the actual special gas flow rate change rate can be calculated based on the actual special gas flow detected by the detection component within a preset time.
[0062] In this embodiment, the special gas transmission instruction can be parsed to obtain instruction information, and the target special gas flow rate can be obtained from the instruction information.
[0063] In some embodiments, the process of obtaining the target special gas flow rate may include: obtaining the target flow rate of the reactant associated with the special gas; and calculating the target special gas flow rate based on the target flow rate of the reactant and a preset mixing ratio value.
[0064] Optionally, the reactant associated with the special gas may be a target special gas, that is, another special gas different from the special gas; the mixing ratio value may be a mixing ratio of the special gas to the target special gas. The target special gas flow rate may be obtained by multiplying the target flow rate of the target special gas by the mixing ratio value.
[0065] In some embodiments, after obtaining the target special gas flow rate and the actual special gas flow rate in the special gas transmission control system, if the difference between the target special gas flow rate and the actual special gas flow rate is greater than a preset difference threshold, it is also possible to first look up a table based on the target special gas flow rate to obtain an initial control signal of the special gas delivery component, control the operation of the special gas delivery component based on the initial control signal, and then perform double closed-loop control through the preset first PID controller and the second PID controller, which can enable the actual flow rate of the special gas to quickly change to the target special gas flow rate, thereby improving the response speed.
[0066] S102: Obtain a target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller.
[0067] In one embodiment provided in the present application, the process of obtaining the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and the preset first PID controller includes:
[0068] Determining a difference between the actual special gas flow rate and the target special gas flow rate;
[0069] The difference between the actual special gas flow rate and the target special gas flow rate is input into the first PID controller to obtain the target special gas flow rate change rate. The target special gas flow rate change rate is the expected special gas flow rate change rate.
[0070] S103: obtaining a control signal of a special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller;
[0071] In one embodiment provided in the present application, the process of obtaining the control signal of the special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and the preset second PID controller includes:
[0072] Determine the difference between the target characteristic gas flow rate change rate and the actual characteristic gas flow rate change rate;
[0073] The difference between the target special gas flow rate change rate and the actual special gas flow rate change rate is input into the second PID controller to obtain the control signal of the special gas delivery component in the special gas transmission control system.
[0074] S104: Controlling the operation of the special gas delivery component according to the control signal to adjust the flow rate of the special gas delivered by the special gas delivery component.
[0075] In this embodiment, the control signal can be used to instruct the valve assembly and / or the air pump in the special gas delivery assembly to operate, so that the special gas flow delivered by the special gas delivery assembly changes toward the target special gas flow.
[0076] By applying the method provided in the embodiment of the present application and controlling through a double closed-loop control PID controller, the control accuracy, operating stability and dynamic performance of the special gas transmission control system can be effectively improved, the anti-interference ability of the special gas transmission control system can be enhanced, and the response speed of the special gas transmission control can be improved.
[0077] See also Figure 2 , which is a schematic diagram of a dual closed-loop control structure provided in an embodiment of the present application, the difference between the actual special gas flow rate and the target special gas flow rate can be input into the first PID controller to obtain the target special gas flow rate change rate; the difference between the target special gas flow rate change rate and the actual special gas flow rate change rate can be input into the second PID controller to obtain the control signal of the special gas delivery component in the special gas transmission control system.
[0078] In some embodiments provided in the present application, based on the above solution, optionally, after controlling the operation of the special gas delivery component according to the control signal, the method further includes:
[0079] If the actual special gas flow rate of the special gas delivery component does not reach the target special gas flow rate within the preset duration, the current environmental parameters of the special gas transmission control system are obtained;
[0080] Inputting the current environmental parameters of the special gas transmission control system into a pre-trained machine learning model to obtain a PID parameter prediction result; the PID parameter prediction result includes a first target PID parameter and a second target PID parameter;
[0081] The first target PID parameter is used to update the first PID controller, and the second target PID parameter is used to update the second PID controller, and the step of returning to execute the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and the preset first PID controller is obtained.
[0082] In this embodiment, the environmental parameters may include one or more parameters such as special gas pressure, special gas temperature, etc.
[0083] In some embodiments, at least one variable including the valve opening in the special gas delivery component, the air pump operating rate, the target special gas flow rate, the current actual special gas flow rate of the special gas transmission control system, and environmental parameters can be input into the machine learning model to obtain PID parameter prediction results.
[0084] Optionally, the first target PID parameters may include a first proportional coefficient Kp_outer, a first integral coefficient ki_outer, and a differential coefficient kd_outer of the first PID controller.
[0085] Optionally, the second target PID parameters may include a first proportional coefficient Kp_inner, a first integral coefficient ki_inner and a differential coefficient kd_inner of the second PID controller.
[0086] In this embodiment, the machine learning module may include: a combination of one or more of a neural network model, a Gaussian regression GPR, a decision tree, and a support vector machine; optionally, the machine learning model may include a CNN convolutional neural network model.
[0087] In some embodiments, after obtaining the PID parameter prediction result, the first PID controller may be updated only by using the first target PID parameter, or the second PID controller may be updated only by using the second target PID parameter, and then the process returns to execute S102.
[0088] By applying the method provided in this embodiment, if the actual special gas flow rate of the special gas delivery component does not reach the target special gas flow rate within the preset duration, it indicates that the current first PID controller and the second PID controller cannot adapt well to the current working conditions of the special gas transmission control system. In this case, the PID parameter prediction results can be obtained based on the current environmental parameters of the special gas transmission control system through a machine learning model, and then the first PID controller and the second PID controller are updated according to the PID parameter prediction results, so that the first PID controller and the second PID controller can adapt to the current working conditions of the special gas transmission control system, thereby further improving the response speed, control accuracy and operation stability of the special gas transmission control system.
[0089] In some embodiments, after obtaining the target special gas flow, the actual special gas flow in the special gas transmission control system and the actual special gas flow change rate in response to the special gas transmission instruction in S101, the current environmental parameters of the special gas transmission control system can also be obtained first; then the valve opening, the air pump operation rate, the target special gas flow, at least one variable of the current actual special gas flow of the special gas transmission control system, and the environmental parameters in the special gas delivery component are input into the machine learning model to obtain a PID parameter prediction result; then the first target PID parameter in the PID parameter prediction result is used to update the first PID controller, and the second target PID parameter in the PID parameter prediction result is used to update the second PID controller, and steps S102 to S104 are executed.
[0090] In one embodiment provided in the present application, based on the above solution, optionally, the process of training the machine learning model is as follows: Figure 3 As shown, including:
[0091] S301: Obtain a training data set and an initial machine learning model; the training data set includes multiple training samples, each of which includes at least a special gas pressure value, a special gas temperature value, a first PID controller parameter and a second PID controller parameter.
[0092] In some embodiments, the training samples may also include valve openings, air pump operating rates, etc. in the specialty gas delivery components.
[0093] In some embodiments, as shown in Table 1, the training sample may include valve opening, special gas pressure value, special gas temperature value, first PID controller parameter and second PID controller parameter.
[0094] Table 1
[0095]
[0096] In this embodiment, the model parameters of the initial machine learning model are optimized based on a preset genetic algorithm.
[0097] S302: Train the initial machine learning model using training samples in the training data set.
[0098] In this embodiment, the process of training the initial machine learning model using the training samples in the training data set includes: selecting the target training sample currently used for training in the training data set, and then inputting the valve opening, target special gas flow, current actual special gas flow of the special gas transmission control system and environmental parameters in the target training sample into the machine learning model to obtain PID parameter prediction results; calculating the loss function value based on the PID parameter prediction results and the first PID controller parameters and the second PID controller parameters in the target training sample, and updating the model parameters of the initial machine learning model according to the loss function value.
[0099] S303: When the initial machine learning model satisfies a preset training completion condition, the initial machine learning model that satisfies the training completion condition is used as a trained machine learning model.
[0100] In this embodiment, the training completion condition may be that the number of training times of the initial machine learning model reaches a preset training times threshold, the loss function converges, or the prediction accuracy of the initial machine learning model meets a preset accuracy threshold, etc.
[0101] If the initial machine learning model does not meet the training completion condition, return to execute S302 until the initial machine learning model meets the preset training completion condition.
[0102] In an embodiment provided in the present application, based on the above solution, optionally, after obtaining the current environmental parameters of the special gas transmission control system, the method further includes:
[0103] If the temperature of the special gas in the environmental parameters exceeds a preset temperature threshold, or the pressure of the special gas in the environmental parameters exceeds a preset pressure threshold, an alarm message is output.
[0104] In this embodiment, the alarm information may be output and displayed in a preset display interface, or the alarm information may be sent to a preset terminal.
[0105] See also Figure 4 , is a structural diagram of a special gas transmission control system provided in an embodiment of the present application, the special gas transmission control system comprises:
[0106] Special gas supply source 401, special gas delivery component 402, detection component 403 and control device 404;
[0107] The special gas supply source 401 is used to store special gas;
[0108] The special gas delivery component 402 is used to deliver the special gas in the special gas supply source to the special gas use point;
[0109] The detection component 403 is used to detect the actual special gas flow rate and the actual special gas flow rate change rate in the special gas transmission control system in real time;
[0110] The control device 404 is used to obtain the target special gas flow rate and the actual special gas flow rate and the actual special gas flow rate change rate detected by the detection component in response to the special gas transmission instruction; obtain the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and the preset first PID controller; obtain the control signal of the special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and the preset second PID controller; control the operation of the special gas delivery component according to the control signal to adjust the special gas flow rate delivered by the special gas delivery component. In this embodiment, the control device may include a mass flow controller.
[0111] In an embodiment provided in the present application, based on the above solution, optionally, the special gas delivery assembly includes:
[0112] at least one of a valve and an air pump;
[0113] Correspondingly, the control device is used to adjust the opening of the valve and / or the rotation speed of the air pump according to the control signal.
[0114] In an embodiment provided in the present application, based on the above solution, optionally, the special gas supply source includes:
[0115] Gas cylinder cabinets, purge panels, and purifiers;
[0116] The gas cylinder cabinet is used to store special gases;
[0117] The purge panel is used to purge the special gas delivery pipeline with inert gas;
[0118] The purifier is used to purify the special gas in the gas cylinder cabinet.
[0119] See also Figure 5 , is a structural diagram of another special gas transmission control system provided by an embodiment of the present application, wherein a steel cylinder storing special gas is placed in a gas cylinder cabinet, and then the gas is supplied to a valve manifold box (VMB) near the site through a pipeline, and then enters the special gas use point (POU:) of the process machine. Before entering the machine cavity, there will be an independent gas control panel (Gas Box, GB) connected to the process control module, and the mass flow controller (Mass Flow Controller, MFC) is used to control the flow rate and the mixing ratio of the intake gas. General inert gas is supplied by an open gas cylinder rack (Gas Rack, GR) and a valve manifold panel (VMP).
[0120] It should be noted that the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0121] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are merely used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations.
[0122] For the convenience of description, the above device is described in various units according to their functions. Of course, when implementing the present application, the functions of each unit can be implemented in the same or multiple software and / or hardware.
[0123] It can be known from the description of the above implementation methods that those skilled in the art can clearly understand that the present application can be implemented by means of software plus a necessary general hardware platform. Based on such an understanding, the technical solution of the present application can be essentially or partly contributed to the prior art in the form of a software product, which can be stored in a storage medium such as ROM / RAM, a magnetic disk, an optical disk, etc., and includes several instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in the various embodiments of the present application or certain parts of the embodiments.
[0124] The above is a detailed introduction to a special gas transmission control method provided by the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea; at the same time, for general technical personnel in this field, according to the idea of the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.
Claims
1. A method for controlling the transmission of special gases, characterized in that: A control device applied to a special gas transmission control system, wherein the special gas transmission control system further comprises a special gas supply source and a special gas delivery component, wherein the special gas delivery component is used to deliver the special gas in the special gas supply source to a special gas use point, and the method comprises: In response to the special gas transmission instruction, obtaining a target special gas flow rate, an actual special gas flow rate in the special gas transmission control system, and a rate of change of the actual special gas flow rate; According to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller, a target special gas flow rate change rate is obtained; According to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller, a control signal of the special gas delivery component in the special gas transmission control system is obtained; The operation of the special gas delivery component is controlled according to the control signal to adjust the flow rate of the special gas delivered by the special gas delivery component.
2. The method according to claim 1, characterized in that After controlling the operation of the special gas delivery component according to the control signal, the method further includes: If the actual special gas flow rate of the special gas delivery component does not reach the target special gas flow rate within the preset duration, the current environmental parameters of the special gas transmission control system are obtained; Inputting the current environmental parameters of the special gas transmission control system into a pre-trained machine learning model to obtain a PID parameter prediction result; the PID parameter prediction result includes a first target PID parameter and a second target PID parameter; The first target PID parameter is used to update the first PID controller, and the second target PID parameter is used to update the second PID controller, and the step of returning to execute the target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and the preset first PID controller is obtained.
3. The method according to claim 2, characterized in that The process of training the machine learning model includes: Obtain a training data set and an initial machine learning model; the training data set includes a plurality of training samples, each of the training samples includes at least a special gas pressure value, a special gas temperature value, a first PID controller parameter and a second PID controller parameter; Training the initial machine learning model using training samples in the training data set; When the initial machine learning model meets the preset training completion conditions, the initial machine learning model that meets the training completion conditions will be used as the trained machine learning model.
4. The method according to claim 2, characterized in that: After obtaining the current environmental parameters of the special gas transmission control system, the method further includes: If the temperature of the special gas in the environmental parameters exceeds a preset temperature threshold, or the pressure of the special gas in the environmental parameters exceeds a preset pressure threshold, an alarm message is output.
5. The method according to claim 1, characterized in that The step of obtaining a target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller includes: Determining a difference between the actual special gas flow rate and the target special gas flow rate; The difference between the actual special gas flow rate and the target special gas flow rate is input into the first PID controller to obtain the target special gas flow rate change rate. The target special gas flow rate change rate is the expected special gas flow rate change rate.
6. The method according to claim 1, characterized in that The step of obtaining a control signal of a special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller includes: Determine the difference between the target characteristic gas flow rate change rate and the actual characteristic gas flow rate change rate; The difference between the target special gas flow rate change rate and the actual special gas flow rate change rate is input into the second PID controller to obtain the control signal of the special gas delivery component in the special gas transmission control system.
7. The method according to claim 1, characterized in that The step of obtaining the target characteristic gas flow rate comprises: Obtaining a target flow rate of a reactant associated with the characteristic gas; The target characteristic gas flow rate is calculated based on the target flow rate of the reactants and the preset mixing ratio value.
8. A special gas transmission control system, characterized in that: include: Special gas supply sources, special gas delivery components, detection components and control equipment; The special gas supply source is used to store special gas; The special gas delivery component is used to deliver the special gas in the special gas supply source to the special gas use point; The detection component is used to detect the actual special gas flow rate and the actual special gas flow rate change rate in the special gas transmission control system in real time; The control device is used to obtain a target special gas flow rate and an actual special gas flow rate and an actual special gas flow rate change rate detected by the detection component in response to a special gas transmission instruction; obtain a target special gas flow rate change rate according to the actual special gas flow rate, the target special gas flow rate and a preset first PID controller; obtain a control signal of a special gas delivery component in the special gas transmission control system according to the target special gas flow rate change rate, the actual special gas flow rate change rate and a preset second PID controller; and control the operation of the special gas delivery component according to the control signal to adjust the special gas flow rate delivered by the special gas delivery component.
9. The system according to claim 8, characterized in that The special gas delivery component comprises: at least one of a valve and an air pump; Correspondingly, the control device is used to adjust the opening of the valve and / or the rotation speed of the air pump according to the control signal.
10. The system according to claim 8, characterized in that The special gas supply source comprises: Gas cylinder cabinets, purge panels, and purifiers; The gas cylinder cabinet is used to store special gases; The purge panel is used to purge the special gas delivery pipeline with inert gas; The purifier is used to purify the special gas in the gas cylinder cabinet.
Citation Information
Patent Citations
System and method for autonomous operation of pipeline and midstream facility systems
CA3119550A1
Compound control system and method for piezoelectric precision gas flow valve
CN113359421A
Pneumatic clutch control method and device
CN114857183A
Pressure control method, breathing ventilation device, and storage medium
CN118304528A
Control method and system of micro proportional valve
CN118348774A