Output power test system

By using humidity, sunlight and wind simulation systems in the output power test system, the problem of vehicle low-voltage load detection requiring a large test site is solved, and low-voltage load output power detection in a small test chamber is simple and easy to implement.

CN118858748AActive Publication Date: 2024-10-29CHERY AUTOMOBILE CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410901529.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-10-29
Estimated Expiration
2044-07-05

AI Technical Summary

Technical Problem

In the existing technology, the output power detection of vehicle low-voltage loads requires standardized testing at large test sites. The test conditions are harsh and implementation is difficult.

Method used

An output power test system is designed, including a test chamber, a rotating hub test bench, a data collector and a controller. It simulates various environmental conditions through a humidity simulation system, a sunlight simulation system and a wind simulation system, and calculates the low-voltage load output of the vehicle under test. power.

Benefits of technology

Low-voltage load output power testing can be carried out without the need for a large testing site. The testing process is simple and easy, the floor space is small, and the equipment is simple to set up.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118858748A_ABST
    Figure CN118858748A_ABST
Patent Text Reader

Abstract

The invention provides an output power test system, and belongs to the technical field of automobiles. According to the invention, the output power test system is used for testing the low-voltage load output power of the tested vehicle, a large test site is not needed, the output power test system only needs to occupy the site size of one test bin, the occupied area of the test bin is much larger than that of one vehicle, and the test efficiency is greatly improved. The rotating hub test bed, the data collector and the controller are not complex equipment, so that the construction of the power test system is much simpler than that of a large test site, and the test process is simpler and more feasible when the power test system is used for testing the low-voltage load output power of the vehicle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the field of automobile technology, and in particular to an output power testing system. Background Art

[0002] As cars become smarter, there are more and more types of low-voltage loads in cars, such as fans, speakers, etc. In the vehicle production process, there are often problems with improper installation of low-voltage loads or the low-voltage load equipment itself not meeting the requirements. Generally, such problems can be identified by testing the output power of the low-voltage load.

[0003] In the related art, when the output power of a vehicle's low-voltage load is detected, the vehicle under test needs to undergo standardized testing (simulating various specified road conditions for a specified duration) in a large test site (including a straight or circular test road), and collect data on the vehicle under test during its driving in the standardized test site, and calculate the low-voltage load output power of the vehicle under test based on the collected data.

[0004] However, the above method requires the vehicle under test to undergo standardized testing in a large test site, the test conditions are relatively harsh, and the test process is difficult to implement. Summary of the invention

[0005] The present disclosure provides an output power testing system, comprising a testing chamber (1), a rotating hub test bench (2), a data collector (3) and a controller (4);

[0006] The rotating hub test bench (2) is located at the bottom of the test chamber (1), and the rotating hub test bench (2) is used to carry the vehicle to be tested;

[0007] The data collector (3) is used to collect the voltage and current of each low-voltage load of the tested vehicle;

[0008] The controller (4) is used to calculate the low-voltage load output power of the tested vehicle based on the voltage and current of the low-voltage load.

[0009] In a possible implementation, the output power test system further includes a humidity simulation system (5), wherein the humidity simulation system (5) includes a drying component (51), a humidifying component (52), and a humidity sensor (53);

[0010] The drying component (51) is in communication with the test chamber (1) and is electrically connected to the controller (4);

[0011] The humidifying component (52) and the humidity sensor (53) are respectively placed in the test chamber (1) and are electrically connected to the controller (4);

[0012] The controller (4) is used to receive a humidity setting instruction, obtain a target humidity corresponding to the humidity setting instruction, and obtain a current humidity detected by the humidity sensor (53); when the current humidity is higher than the target humidity, based on the difference between the current humidity and the target humidity, the drying component (51) is controlled to operate; when the target humidity is higher than the current humidity, based on the difference between the target humidity and the current humidity, the humidifying component (52) is controlled to operate.

[0013] In a possible implementation, the drying component (51) comprises a drying chamber (511), a fan (512) and a drying medium (513); the drying chamber (511), the fan (512) and the test chamber (1) are connected in sequence to form a circulation loop; the fan (512) is electrically connected to the controller (4); and the drying medium (513) is placed in the drying chamber (511);

[0014] The controller (4) is used to control the fan (512) to operate based on the difference between the current humidity and the target humidity when the current humidity is higher than the target humidity, and to control the humidification component (52) to operate based on the difference between the target humidity and the current humidity when the target humidity is higher than the current humidity.

[0015] In a possible implementation, the output power test system further includes a sunlight simulation system (6), wherein the sunlight simulation system (6) includes a first moving component (61) and a high-energy radiation lamp (62);

[0016] The first moving component (61) is located in the testing chamber (1), connected to the testing chamber (1), and electrically connected to the controller (4);

[0017] The high-energy radiation lamp (62) is located in the test chamber (1), connected to the first moving component (61), and electrically connected to the controller (4), and the high-energy radiation lamp (62) is directed toward the position of the vehicle under test;

[0018] The controller (4) is used to receive a lighting setting instruction, obtain a target lighting angle corresponding to the lighting setting instruction, and control the first moving component (61) to drive the high-energy radiation lamp (62) to move based on the target lighting angle, and control the high-energy radiation lamp (62) to emit light.

[0019] In a possible implementation, the first moving assembly (61) includes a first annular moving track (611), an arc-shaped moving track (612) and a displacement member (613);

[0020] The first annular movable track (611) is located above the rotating hub test bench (2) in the testing chamber (1), surrounds the rotating hub test bench (2), and is connected to the testing chamber (1);

[0021] The arc-shaped movable track (612) is perpendicular to the first circular movable track (611), the arc center of the arc-shaped movable track (612) is located at the position of the vehicle to be tested, the arc-shaped movable track (612) is connected to the first circular movable track (611), and can move along the first circular movable track (611) under the control of the controller (4);

[0022] The displacement member (613) is connected to the arc-shaped moving track (612) and can move along the arc-shaped moving track (612) under the control of the controller (4). The displacement member (613) is connected to the high-energy radiation lamp (62).

[0023] In a possible implementation, the controller (4) is used to obtain the light intensity corresponding to the light setting instruction, and control the high-energy radiation lamp (62) to emit light based on the light intensity.

[0024] In a possible implementation, the output power test system further comprises a wind simulation system (7), and the wind simulation system (7) comprises a second moving component (71) and a wind turbine module (72);

[0025] The second moving component (71) is located in the test chamber (1), connected to the test chamber (1), and electrically connected to the controller (4);

[0026] The fan module (72) is located in the test chamber (1), connected to the second moving component (71), and electrically connected to the controller (4), and the fan module (72) is oriented toward the position of the vehicle under test;

[0027] The controller (4) is used to receive an airflow setting instruction, obtain a target airflow direction corresponding to the airflow setting instruction, and control the second moving component (71) to drive the fan module (72) to move based on the target airflow direction, maintain the position of the fan module (72) facing the vehicle under test, and control the fan module (72) to blow air.

[0028] In a possible implementation, the second moving component (71) includes a second annular moving track (711) and a multi-joint mechanical arm (712);

[0029] The second annular movable track (711) is located at the bottom of the test chamber (1), surrounds the rotating hub test bench (2), and is connected to the test chamber (1);

[0030] The first end (712a) of the multi-joint robotic arm (712) is connected to the second circular movable track (711), and the second end (712b) of the multi-joint robotic arm (712) is connected to the fan module (72). The multi-joint robotic arm (712) can move along the second circular movable track (711) under the control of the controller (4), and can adjust the direction of the fan module (72) under the control of the controller (4).

[0031] In a possible implementation, the fan module (72) includes a fan bracket (721) and a plurality of fan units (722);

[0032] The fan support (721) is connected to the second moving component (71);

[0033] The fan unit (722) is located on the fan bracket (721) and is connected to the fan bracket (721); the fan unit (722) can adjust its posture relative to the fan bracket (721) under the control of the controller (4).

[0034] In a possible implementation, the rotary hub test bench (2) comprises a support plate (21), a support frame (22) and a plurality of rotary hubs (23);

[0035] The support plate (21) is located at the bottom of the test chamber (1), and the support plate (21) has a plurality of through holes (21a);

[0036] The support frame (22) is located below the support plate (21) and is connected to the support plate (21);

[0037] The multiple rotating hubs (22) are parallel to each other and to the support plate (21), and every two rotating hubs (22) correspond to a through hole (21a). The upper edge of the rotating hub (22) is located at the corresponding through hole (21a), and each rotating hub (22) is rotatably connected to the support frame (22). The two rotating hubs (22) corresponding to the same through hole (21a) are used to support at least one tire of the vehicle under test, and one rotating hub (22) of the two rotating hubs (22) is used to support the bottom front side of the at least one tire, and the other rotating hub (22) is used to support the bottom rear side of the at least one tire.

[0038] In a possible implementation, the hub test bench (2) further includes a plurality of pressure sensors (24);

[0039] The plurality of pressure sensors (24) are evenly distributed on the cylindrical surface of each rotating hub (22) along the circumferential direction, and are electrically connected to the controller (4) respectively;

[0040] The controller (4) is used to continuously determine, for each rotating hub (22), a total pressure value obtained by summing up the pressure values ​​detected by all pressure sensors (24) corresponding to the rotating hub (22), and obtain time-varying data of the total pressure value. When the tire of the vehicle under test contacts the rotating hub (22) and drives the rotating hub (22) to rotate, if N consecutive peak values ​​of the total pressure value are all less than a pressure threshold value, where N is a preset positive integer, an alarm signal is issued, wherein the alarm signal is used to indicate that the test vehicle is driving too fast.

[0041] In a possible implementation, the controller (4) is used to:

[0042] Calculating the low-voltage load output power of each low-voltage load based on the voltage and current of the low-voltage load;

[0043] The sum of the low-voltage load output powers of each low-voltage load is calculated as the low-voltage load output power of the tested vehicle.

[0044] In a possible implementation, the output power test system further includes a bus signal collector

[0046] The bus signal collector (5) is used to collect bus signals;

[0047] The controller (4) is also used to determine whether the low-voltage load of the tested vehicle meets the processing requirements based on the bus signal, the low-voltage load output power of the tested vehicle and the target low-voltage load output power of the tested vehicle.

[0048] By adopting this method, the output power test system is used to test the low-voltage load output power of the vehicle under test. No large test site is required. The output power test system only needs to occupy the size of a test chamber. The floor area of ​​the test chamber is not much larger than that of a car. Moreover, the hub test bench, data acquisition device and controller are not very complicated equipment. It can be seen that the construction of the power test system is much simpler than that of a large test site. The power test system is used to test the low-voltage load output power of the vehicle, and the test process is simpler and easier. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0050] Figure 1is a structural schematic diagram of an output power test system provided by an embodiment of the present disclosure;

[0051] Figure 2 is a structural schematic diagram of a controller 4 provided in an embodiment of the present disclosure;

[0052] Figure 3 is a structural schematic diagram of an output power test system provided by an embodiment of the present disclosure;

[0053] Figure 4 is a structural schematic diagram of an output power test system provided by an embodiment of the present disclosure;

[0054] Figure 5 is a structural schematic diagram of an output power test system provided by an embodiment of the present disclosure;

[0055] Figure 6 is a structural schematic diagram of an output power test system provided by an embodiment of the present disclosure;

[0056] Figure 7 It is a structural schematic diagram of a rotary hub test bench 2 provided in an embodiment of the present disclosure;

[0057] Figure 8 It is a schematic diagram of a processing flow for calculating the output power of a low-voltage load provided by an embodiment of the present disclosure;

[0058] Fig. 9 It is a schematic diagram of a processing flow for determining whether a low-voltage load meets processing requirements provided by an embodiment of the present disclosure. DETAILED DESCRIPTION

[0059] In order to make the objectives, technical solutions and advantages of the present disclosure more clear, the embodiments of the present disclosure will be further described in detail below with reference to the accompanying drawings.

[0060] Reference Figure 1 As shown, the present disclosure provides an output power testing system, which includes a testing chamber 1, a rotating hub test bench 2, a data collector 3 and a controller 4.

[0061] The rotary hub test bench 2 is located at the bottom of the test chamber 1, and the rotary hub test bench 2 is used to carry the vehicle under test. The data collector 3 is used to collect the voltage and current of the low-voltage load of the vehicle under test. The data collector 3 can be an ammeter and a voltmeter. The controller 4 is used to calculate the low-voltage load output power of the vehicle under test based on the voltage and current of the low-voltage load.

[0062] The controller 4 can perform various calculations, receive and store collected data, and so on.

[0063] The controller 4 may include a processor 210, a memory 220, a display component 230, and a communication component 240. Figure 2 shown.

[0064] The processor 210 may be a central processing unit (CPU) or a system on chip (SoC), etc. The processor 210 may be used to process various operation instructions, for example, calculating the output power of a low-voltage load, etc.

[0065] The memory 220 may include various volatile memories or non-volatile memories, such as a solid state disk (SSD), a dynamic random access memory (DRAM), etc. The memory 220 may be used to store initial data, intermediate data, and result data used in the relevant processing, for example, to store pressure thresholds, etc.

[0066] The display component 230 can be an independent screen, or a screen integrated with the user device body, a projector, etc. The screen can be a touch screen or a non-touch screen (which can be displayed remotely), etc. The display component 230 is used to display the system interface, application interface, etc., for example, display the test temperature, test humidity, etc.

[0067] The communication component 240 may be a wired network connector, ultra wide band (UWB), wireless fidelity (WiFi) module, Bluetooth module, cellular network communication module, etc. The communication component 240 may be used to receive and send various instructions and data, for example, to send the output power of a low voltage load to other devices, etc.

[0068] In one possible implementation, for example Figure 3 As shown, the output power test system further includes a humidity simulation system 5 , and the humidity simulation system 5 includes a drying component 51 , a humidifying component 52 and a humidity sensor 53 .

[0069] The drying component 51 is connected to the test chamber 1 and is electrically connected to the controller 4. The humidifying component 52 and the humidity sensor 53 are respectively placed in the test chamber 1 and are electrically connected to the controller 4. Figure 4As shown, the drying component 51 includes a drying chamber 511, a fan 512 and a drying medium 513. The drying chamber 511, the fan 512 and the test chamber 1 are connected in sequence to form a circulation loop. The fan 512 is electrically connected to the controller 4. The drying medium 513 is placed in the drying chamber 511, and the drying medium 513 can be evenly distributed in the drying chamber 511. The fan 512 includes a housing 5121, a motor 5122 and a plurality of blades 5123. The housing 5121 is electrically connected to the motor 5122, and the plurality of blades 5123 are connected to each other at one point and fixed inside the housing 5121. The motor 5122 is electrically connected to the controller 4, and the controller 4 can control the motor 5122 to work.

[0070] The controller 4 is used to receive a humidity setting instruction, obtain the target humidity corresponding to the humidity setting instruction, and obtain the current humidity detected by the humidity sensor 53. When the current humidity is higher than the target humidity, the drying component 51 is controlled to work based on the difference between the current humidity and the target humidity. When the target humidity is higher than the current humidity, the humidification component 52 is controlled to work based on the difference between the target humidity and the current humidity. The controller 4 is used to control the fan 512 to work based on the difference between the current humidity and the target humidity when the current humidity is higher than the target humidity. When the target humidity is higher than the current humidity, the humidification component 52 is controlled to work based on the difference between the target humidity and the current humidity. For example, when the controller 4 receives a humidity setting instruction with a target humidity of 60%, if the current humidity is 70%, the current humidity is higher than the target humidity. At this time, the controller 4 controls the drying component 51 to work, and the controller 4 can also determine the working gear of the drying component 51 according to the difference between the current humidity and the target humidity.

[0071] When the drying component 51 is in operation, open Figure 4 The two channels A and B shown are connected to the test chamber 1 respectively, and the fan 512 is controlled to start working. The air in the test chamber 1 is blown to the drying chamber 511 from the fan 512 side. The drying medium 513 in the drying chamber 511 absorbs moisture in the air. After that, the air flows out of the drying chamber 511 through the channel and flows to the test chamber 1. In this way, the air humidity out of the test chamber 1 is reduced.

[0072] In one possible implementation, for example Figure 5 As shown, the output power test system further includes a sunlight simulation system 6 , and the sunlight simulation system 6 includes a first moving component 61 and a high-energy radiation lamp 62 .

[0073] The first moving assembly 61 is located in the test chamber 1, connected to the test chamber 1, and electrically connected to the controller 4. The first moving assembly 61 includes a first annular moving track 611, an arcuate moving track 612, and a displacement member 613. The first annular moving track 611 is located above the hub test bench 2 in the test chamber 1, surrounds the hub test bench 2, and is connected to the test chamber 1. The arcuate moving track 612 is perpendicular to the first annular moving track 611, and the arc center of the arcuate moving track 612 is located at the position of the vehicle under test. The arcuate moving track 612 is connected to the first annular moving track 611 and can move along the first annular moving track 611 under the control of the controller 4. The displacement member 613 is connected to the arcuate moving track 612 and can move along the arcuate moving track 612 under the control of the controller 4. The displacement member 613 is connected to the high-energy radiation lamp 62.

[0074] The high-energy radiation lamp 62 is located in the test chamber 1, connected to the first moving assembly 61, and electrically connected to the controller 4. The high-energy radiation lamp 62 faces the position of the tested vehicle, and the high-energy radiation lamp 62 moves along the arc-shaped moving track 612 to adjust the height relationship between the high-energy radiation lamp 62 and the position of the tested vehicle. The high-energy radiation lamp 62 is installed at a specified height above the rotary hub test bench 2, and the specified height can be pre-set by the tester.

[0075] The controller 4 is used to receive the illumination setting instruction, obtain the target illumination angle corresponding to the illumination setting instruction, control the first moving component 61 to drive the high-energy radiation lamp 62 to move based on the target illumination angle, and control the high-energy radiation lamp 62 to emit light. The controller 4 is used to obtain the illumination intensity corresponding to the illumination setting instruction, and control the high-energy radiation lamp 62 to emit light based on the illumination intensity.

[0076] In one possible implementation, for example Figure 6 As shown, the output power test system also includes a wind simulation system 7, and the wind simulation system 7 includes a second moving component 71 and a fan module 72. The wind simulation system 7 may include one or more multi-joint mechanical arms 712 and one or more fan modules 72, and the number of the multi-joint mechanical arms 712 and the number of the fan modules 72 are the same.

[0077] The second moving assembly 71 is located in the test chamber 1, connected to the test chamber 1, and electrically connected to the controller 4. The second moving assembly 71 includes a second annular moving track 711 and a multi-joint mechanical arm 712. The second annular moving track 711 is located at the bottom of the test chamber 1, surrounds the hub test bench 2, and is connected to the test chamber 1. The first end 712a of the multi-joint mechanical arm 712 is connected to the second annular moving track 711, and the second end 712b of the multi-joint mechanical arm 712 is connected to the fan module 72. The multi-joint mechanical arm 712 can move along the second annular moving track 711 under the control of the controller 4, and can adjust the direction of the fan module 72 under the control of the controller 4. The multi-joint mechanical arm 712 may include a plurality of joints and a plurality of connecting components, and the connecting components are used to connect two joints, and one end of each connecting component is connected to one joint, and the other end is connected to another joint, so that the connection of the two joints is achieved.

[0078] The fan module 72 is located in the test chamber 1, connected to the second moving assembly 71, and electrically connected to the controller 4. The fan module 72 faces the position of the tested vehicle. The fan module 72 includes a fan bracket 721 and a plurality of fan units 722. The fan bracket 721 is connected to the second moving assembly 71. The fan unit 722 is located on the fan bracket 721 and connected to the fan bracket 721. The fan unit 722 can adjust its posture relative to the fan bracket 721 under the control of the controller 4.

[0079] The controller 4 is used to receive airflow setting instructions, obtain the target airflow direction corresponding to the airflow setting instructions, control the second moving component 71 to drive the fan module 72 to move based on the target airflow direction, keep the fan module 72 facing the position of the vehicle under test, and control the fan module 72 to blow air.

[0080] In one possible implementation, for example Figure 7 As shown, the hub test bench 2 includes a support plate 21, a support frame 22 and a plurality of hubs 23. The support plate 21 is located at the bottom of the test chamber 1, and the support plate 21 has a plurality of through holes 21a. The number of through holes in a support plate 21 can be determined by a technician, and can be 2, 4, Figure 6 The support frame 22 is located below the support plate 21 and is connected to the support plate 21 . Figure 6 The black strip in the figure represents a hub 22. The multiple hubs 22 are parallel to each other and to the support plate 21. Every two hubs 22 correspond to a through hole 21a. The upper edge of the hub 22 is located at the corresponding through hole 21a. Each hub 22 is rotatably connected to the support frame 22. The two hubs 22 corresponding to the same through hole 21a are used to support at least one tire of the vehicle under test. One of the two hubs 22 is used to support the bottom front side of at least one tire, and the other hub 22 is used to support the bottom rear side of at least one tire.

[0081] In a possible implementation, the rotary hub test bench 2 further includes a plurality of pressure sensors 24. The plurality of pressure sensors 24 are evenly distributed along the circumferential direction on the cylindrical surface of each rotary hub 22, and are electrically connected to the controller 4 respectively. A protective cover may also be put on the surface of the rotary hub 22. The controller 4 is used to continuously determine the total pressure value after summing the pressure values ​​detected by all the pressure sensors 24 corresponding to the rotary hub 22 for each rotary hub 22, and obtain the time-varying data of the total pressure value. When the tire of the tested vehicle contacts the rotary hub 22 and drives the rotary hub 22 to rotate, the detection method may be a manual input start test instruction, or the controller 4 may detect that M consecutive peak values ​​are greater than a pressure threshold (a first pressure threshold, which is preset by the tester). If N consecutive peak values ​​of the total pressure value are less than the pressure threshold (a second pressure threshold, which is preset by the tester, and the second pressure threshold is less than the first pressure threshold), N is a preset positive integer, then an alarm signal is issued, wherein the alarm signal is used to indicate that the test vehicle is too fast. For example, the pressure threshold is 500 Newtons. When the peak values ​​of three consecutive pressure sensors 24 are all less than 500 Newtons, the controller 4 controls the speaker to emit an alarm tone. There can be multiple alarm tones, which can be set arbitrarily by the user.

[0082] In a possible implementation, the processing flow of the controller 4 calculating the output power of the low-voltage load can be as follows: Figure 8 As shown, the following steps are included:

[0083] 801, calculating the low-voltage load output power of each low-voltage load based on the voltage and current of the low-voltage load.

[0084] The controller 4 receives the voltage and current of each low-voltage load collected by the data collector 3 , and calculates the output power of the low-voltage load based on the voltage and current of each low-voltage load.

[0085] 802 , calculating the sum of the low-voltage load output power of each low-voltage load as the low-voltage load output power of the tested vehicle.

[0086] After calculating the output power of each low-voltage load, the controller 4 calculates the sum of the low-voltage load output powers of all low-voltage loads as the low-voltage load output power of the tested vehicle.

[0087] In a possible implementation, the output power test system further includes a bus signal collector 5, and the processing flow for determining whether the low-voltage load meets the processing requirements can be as follows: Fig. 9 As shown, the following steps are included.

[0088] 901, the bus signal collector 5 collects the bus signal.

[0089] 902 , the controller 4 determines whether the low-voltage load of the tested vehicle meets the processing requirement based on the bus signal, the low-voltage load output power of the tested vehicle and the target low-voltage load output power of the tested vehicle.

[0090] Based on the bus signal, the low-voltage load output power and the target low-voltage load output power, if the low-voltage load output power is greater than the target low-voltage load output power, it is necessary to check whether the design of the low-voltage load meets the processing requirements. If the difference between the low-voltage load output power and the target low-voltage load output power is less than the difference threshold, it means that the design of the low-voltage load meets the processing requirements.

[0091] In the disclosed embodiment, an output power test system is used to test the low-voltage load output power of the vehicle under test. No large test site is required. The output power test system only needs to occupy the size of a test chamber. The floor area of ​​the test chamber is not much larger than that of a car. Moreover, the hub test bench, data acquisition device and controller are not very complex equipment. It can be seen that the construction of the power test system is much simpler than that of a large test site. The power test system is used to test the low-voltage load output power of the vehicle, and the test process is simpler and easier.

[0092] The present disclosure does not specifically limit the type of vehicle, for example, a sedan, a bus, a truck, a sport utility vehicle (SUV), etc.

[0093] In the description of this specification, the description with reference to the terms "certain embodiments", "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiments or examples are included in at least one embodiment or example of the present disclosure. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0094] It is to be understood that in the present disclosure, "plurality" refers to two or more than two, and other quantifiers are similar. "And / or" describes the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the associated objects before and after are in an "or" relationship. The singular forms "a", "the" and "the" are also intended to include plural forms, unless the context clearly indicates other meanings.

[0095] It is further understood that the terms "first", "second", etc. are used to describe various information, but such information should not be limited to these terms. These terms are only used to distinguish the same type of information from each other, and do not indicate a specific order or degree of importance. In fact, the expressions "first", "second", etc. can be used interchangeably. For example, without departing from the scope of the present disclosure, the first information can also be referred to as the second information, and similarly, the second information can also be referred to as the first information.

[0096] It can be further understood that the orientation or position relationship indicated by terms such as "center", "longitudinal", "lateral", "front", "rear", "up", "down", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", and "circumferential" are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present embodiment and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation.

[0097] It is further understood that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral molding; it can be a mechanical connection, an electrical connection, or can communicate with each other; it can be a direct connection without other components between the two, or it can be an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this disclosure can be understood according to specific circumstances.

[0098] It is further understood that, although the operations are described in a specific order in the drawings in the embodiments of the present disclosure, it should not be understood as requiring the operations to be performed in the specific order shown or in a serial order, or requiring the execution of all the operations shown to obtain the desired results. In certain environments, multitasking and parallel processing may be advantageous.

[0099] Those skilled in the art will readily appreciate other embodiments of the present disclosure after considering the specification and practicing the scheme disclosed herein. The present disclosure is intended to cover any variation, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the art that are not disclosed in the present disclosure. The specification and examples are considered to be exemplary only, and the true scope and spirit of the present disclosure are indicated by the scope of rights.

[0100] It should be understood that the present disclosure is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the scope of the appended claims.

Claims

1. An output power test system, characterized in that: The output power test system comprises a test chamber (1), a rotating hub test bench (2), a data acquisition device (3) and a controller (4); The rotating hub test bench (2) is located at the bottom of the test chamber (1), and the rotating hub test bench (2) is used to carry the vehicle to be tested; The data collector (3) is used to collect the voltage and current of each low-voltage load of the tested vehicle; The controller (4) is used to calculate the low-voltage load output power of the tested vehicle based on the voltage and current of the low-voltage load.

2. The output power test system according to claim 1, characterized in that: The output power test system also includes a humidity simulation system (5), wherein the humidity simulation system (5) includes a drying component (51), a humidifying component (52) and a humidity sensor (53); The drying component (51) is in communication with the test chamber (1) and is electrically connected to the controller (4); The humidifying component (52) and the humidity sensor (53) are respectively placed in the test chamber (1) and are electrically connected to the controller (4); The controller (4) is used to receive a humidity setting instruction, obtain a target humidity corresponding to the humidity setting instruction, and obtain a current humidity detected by the humidity sensor (53); when the current humidity is higher than the target humidity, based on the difference between the current humidity and the target humidity, the drying component (51) is controlled to operate; when the target humidity is higher than the current humidity, based on the difference between the target humidity and the current humidity, the humidifying component (52) is controlled to operate.

3. The output power test system according to claim 2, characterized in that: The drying component (51) comprises a drying chamber (511), a fan (512) and a drying medium (513); the drying chamber (511), the fan (512) and the testing chamber (1) are connected in sequence to form a circulation loop; the fan (512) is electrically connected to the controller (4); and the drying medium (513) is placed in the drying chamber (511); The controller (4) is used to control the fan (512) to operate based on the difference between the current humidity and the target humidity when the current humidity is higher than the target humidity, and to control the humidification component (52) to operate based on the difference between the target humidity and the current humidity when the target humidity is higher than the current humidity.

4. The output power test system according to claim 1, characterized in that: The output power test system also includes a sunlight simulation system (6), wherein the sunlight simulation system (6) includes a first moving component (61) and a high-energy radiation lamp (62); The first moving component (61) is located in the testing chamber (1), connected to the testing chamber (1), and electrically connected to the controller (4); The high-energy radiation lamp (62) is located in the test chamber (1), connected to the first moving component (61), and electrically connected to the controller (4), and the high-energy radiation lamp (62) is directed toward the position of the vehicle under test; The controller (4) is used to receive a lighting setting instruction, obtain a target lighting angle corresponding to the lighting setting instruction, and control the first moving component (61) to drive the high-energy radiation lamp (62) to move based on the target lighting angle, and control the high-energy radiation lamp (62) to emit light.

5. The output power test system according to claim 4, characterized in that: The first moving assembly (61) comprises a first annular moving track (611), an arc-shaped moving track (612) and a displacement member (613); The first annular movable track (611) is located above the rotating hub test bench (2) in the testing chamber (1), surrounds the rotating hub test bench (2), and is connected to the testing chamber (1); The arc-shaped movable track (612) is perpendicular to the first circular movable track (611), the arc center of the arc-shaped movable track (612) is located at the position of the vehicle to be tested, the arc-shaped movable track (612) is connected to the first circular movable track (611), and can move along the first circular movable track (611) under the control of the controller (4); The displacement member (613) is connected to the arc-shaped moving track (612) and can move along the arc-shaped moving track (612) under the control of the controller (4). The displacement member (613) is connected to the high-energy radiation lamp (62).

6. The output power test system according to claim 4, characterized in that: The controller (4) is used to obtain the light intensity corresponding to the light setting instruction, and control the high-energy radiation lamp (62) to emit light based on the light intensity.

7. The output power test system according to claim 1, characterized in that: The output power test system further comprises a wind simulation system (7), wherein the wind simulation system (7) comprises a second moving component (71) and a wind turbine module (72); The second moving component (71) is located in the test chamber (1), connected to the test chamber (1), and electrically connected to the controller (4); The fan module (72) is located in the test chamber (1), connected to the second moving component (71), and electrically connected to the controller (4), and the fan module (72) is oriented toward the position of the vehicle under test; The controller (4) is used to receive an airflow setting instruction, obtain a target airflow direction corresponding to the airflow setting instruction, and control the second moving component (71) to drive the fan module (72) to move based on the target airflow direction, maintain the position of the fan module (72) facing the vehicle under test, and control the fan module (72) to blow air.

8. The output power test system according to claim 7, characterized in that: The second moving assembly (71) comprises a second annular moving track (711) and a multi-joint mechanical arm (712); The second annular movable track (711) is located at the bottom of the test chamber (1), surrounds the rotating hub test bench (2), and is connected to the test chamber (1); The first end (712a) of the multi-joint robotic arm (712) is connected to the second circular movable track (711), and the second end (712b) of the multi-joint robotic arm (712) is connected to the fan module (72). The multi-joint robotic arm (712) can move along the second circular movable track (711) under the control of the controller (4), and can adjust the direction of the fan module (72) under the control of the controller (4).

9. The output power test system according to claim 1, characterized in that: The controller (4) is used for: Calculating the low-voltage load output power of each low-voltage load based on the voltage and current of the low-voltage load; The sum of the low-voltage load output power of each low-voltage load is calculated to obtain the total low-voltage load output power of the tested vehicle.

10. The output power test system according to claim 1, characterized in that: The output power test system also includes a bus signal collector (5); The bus signal collector (5) is used to collect bus signals; The controller (4) is also used to determine whether the low-voltage load of the tested vehicle meets the processing requirements based on the bus signal, the low-voltage load output power of the tested vehicle and the target low-voltage load output power of the tested vehicle.

Citation Information

Patent Citations

  • Vehicle power assembly test system

    CN111678710A

  • Indoor complete vehicle hardware-in-loop test device

    CN112014113A

  • In-loop test system for detecting edge scene of vehicle-mounted camera

    CN114979624A

  • Methods and systems for radar testing and development using hardware-in-the-loop with continuous integration

    US11714190B1